SlideShare a Scribd company logo
1 of 54
Download to read offline
A Team Work ………
Presented by.
Md.Amzad, Hossain , ACE, PFG.
DUAL FILLING BUILDING
PLANT LIST
1. BLOWING SYSTEM.
a) HP Compressor, 40 BAR
b) Chiller Plant
c) SIDEL PET Blowing Plant.
2. Central Syrup & Blending
a) Central Syrup , 4 nosa) Central Syrup , 4 nos
b) Central Blending System
c) CIP Unit
3. Power & Utility
a) 1.5 MW Gas Generator & Gas use Reconciliation.
b) 4000 Amp substation in CAN Building.
c) 100 TPH WTP
d) 80 TPH RO Plant
3. Dual Filler Plant
Filler Name: DUAL FILLER
Location: New CAN Building
Capacity: 400 BPM
Filling system : Soft & Hot
Filling Control System : Flow meter controlling.
Filling Valve : Electro-pneumatic Valve.
Filler model : DQRS – 80 x 80 x 18.Filler model : DQRS – 80 x 80 x 18.
Type: Monoblock.
Total No of Nozzle : 80
CO2 Consumption : 180 Kg/hr.
Air Consumption : 24 M3/hr@6 Bar.
Required Chilling water temp:
a) Glycol water = -2 to -4 Deg C
b) Chilled water = 7 Deg C.
CSD Hot Fill
Carbo
mixer
Rinser Filler Capper Wrapper
(Packaging)
UHT
PET
Conveyor
Belt
Syrup
Homo
Syrup Juice
Mixing
Over head
conveyor
C
h
e
c
Warmer/
Cooling
tunnel
Conveyor
Blow
Dryer
Band-R
LabelerBlowing
PET
Bottle
Pre form Closure
Hopper
Caper
Rinser
FIG : PROCESS FLOW DIAGRAM (CSD & HOT FILL.)
Date
Coding
c
k
Cycle time : 35-40 Min
MACHINE NAME
UTILITY
CO2,
Kg/Hr.
LP
AIR,
CFM
Chilled
water,
M3/Hr
RO
Water,
M3/Hr
Fresh
Water,
M3/Hr
Steam,
Kg/Hr.
Power,
KW
CT
water
DUAL FILLER 90 32 NA 7 4 NA 31 NA
CARBO MIXER 90 21 40 15 3 NA 34 NA
HOMO NA 25 NA NA 2 NA 132 NA
WARMER NA 32 50 NA 1 400 34.9 80
LABELLER NA 45 NA NA NA NA 15 NA
WRAPPING NA 50 NA NA NA NA 78.5 NA
Band –Roll
inserter
NA 10 NA NA NA NA 27 NA
UHT NA 25 55 20 12 800 18 120
TOTAL 180 240 145 42 22 1000 363.4 200
1. Filler machine (Rainser + Filler + Capper), 80 x 80 x 18, Tech-long.
2. Carbo Mixer , 16 TPH Tech-Long, China.
3. Cooling Tunnel or Warmer , 4 Chambers, Tech-Long.
4. Air Blower / Dryer , Tech-Long
5. Date Coding Machine, Image Model: 9020.
6. Labeler, OPP, HF SSO-6000, Korean
7. Band-Roll Inserter, LEBAL TRADING CO, LTD.
8. Wrapping Machine: Automatic Shrink Film Wrapping system.
20-25 Min
8. Wrapping Machine: Automatic Shrink Film Wrapping system.
Capacity : 35 Boxes/Min, Model: WSD- LMB35T , China.
9. Homo : GEA, Max Pressure 25 MPa, Rated Flow : 1000 dm3/h,
VFD System, Italy.
10. UHT/Sterilizer : Type: Tabular, (Shell & Tube),
Heating Area = 88 M2 , Max temp = 1500 C
11. PHE : Total 5 nos.
12. Dosing Pump: Grundfos , 5 L/H, 6 Bar, 0.011 KW, 50 Hz.
13. Conveyor Lubrication system.
14. Cap Sterilization System: Cap: 32000 BPH, Pump = 4 Bar, 2 stage.
Carbon -Di-Oxide Tank
Installation date : 09:05:2014. C.Run :
Location : Beside CSD CO2 Tank.
Storage Capacity : 10 Cubic meter. y
Storage Condition: Liquid.
Vessel weight : 6500 kg
Operating & test pressure :Operating & test pressure :
Max = 22 Bar, Min: 10 Bar. Test Pr = 25 Bar
Dimension : Dia = 2020 mm , 3 Legs,(@ 70” & 120 deg)
Vaporizer capacity = 150 NM3/H.
Piping : 25 mm SS 40 schedule, with PRV, 8 Bar
Welding System : TIG with filler rod. Leak Test @ 12 Bar by
water only pipe line.
CO2 Process Flow Diagram
CO2 Tank Instruments:
1. Two pressure relief valve.
2. Operating pressure gauge.
3. Storage/capacity gauge.
4. High & Low level audible alarm.
Storage Pressure & Temp = 20.5 bar & -17 C.
CO2 Uses System:
1. During filling to storage tank use both hoses vapor and liquid to
displaced gas by liquid.
2. Use Non –return valve for Tanker & storage tank.
3. It is better to be safe than sorry , so use 0.01 micron polishing filter.
4. Use PRV after vaporizer. 15 Bar to 8 bar.
15% CO2 Losses in PET Bottle;
1. For 2 ltr = 12 weeks, 2. 500 ml = 9 weeks, 3. 250 ml = 7 weeks.
High Pressure Compressor.
Installation date : 24:05:2014.
Commissioning Date : 07:12:2014
Location : HP Compressor area.
Machine Specification :Brand: ABC , Spain
Model: 4HA-6TER- LT, SL# 24472. 4 stage, 6 cylinder, 280 KW
motor (Brazil) , 28 M3 / min. , 670 rpm, Wt : 13 tons. Mainmotor (Brazil) , 28 M3 / min. , 670 rpm, Wt : 13 tons. Main
Base dimension (mm) = 6800 x 2060.
Working Pressure : 35 Bar to 38 Bar
Power status:
Total Connected Load : 291.85 KW
Current at Load : 153-155-156 amp
Current at unload: 17 amp HP Comp#1
High Pressure Compressor.
Air drying system/Air Dryer:
Brand: Airsec,Model:FD-300-WH,Flow rate: 1768 M3/H
Type: Refrigeration, R-404A, (3.5 kg), DP = min 3 deg C.
Air input Temp max = @40 Bar,40 deg C. Compressor
Hermetic Type , 3.7 KW, 7A, Condenser water cooled.
Cooling system/Cooling Tower: Model : RMA -101 D, TEVA
Closed cycle , evaporative system with shell & tube .Its blower motor
HP Comp#2
Closed cycle , evaporative system with shell & tube .Its blower motor
permanently lubricated by bush bearing (2Z) , Motor = 3 nos. @ 1.1 Kw
Size : 680 x 1270 mm. Two parts wt = 800 + 1300 = 2100 Kgs.
Piping System :
Total length : 345 ft.
Size : 80 mm , 40 schedule , 40 BAR Grade : 304 L
Welding: V- shaped, SS filler rod .
MS 18” header with Grid system (by pass with HP # 1)
Hydraulic test : 55 Bar , Holding Time : 4 hours, by water.
Points / Aspects. ABC HP COMPRESSOR IR HP COMPRESSOR
1. Space Less More
2. Starting load Less (Due to LP air connected) More
3. Cooling system Good (Closed cycle) Poor, open
4. Dryness of air Good , 3 deg C Up to 8 deg C
5. Power consumption Less than IR, due to VLT drive
6. Air Filter 16000 hrs 8000 Hrs
Main Feature of ABC HP Compressor
6. Air Filter 16000 hrs 8000 Hrs
Main motor is 280 Kw, more than 10 Kw bigger than IR. Equipment
setup on base are more complex. Air cylinder also complex.
Plant Safety
1. PPE ( safety shoe, tight dresses)
2. SOP
3. CO2 Fire Extinguisher
4. Proper earthling 90 RM copper cable.
Re-Engineering for HP Air Compressor.
Description: As per design schedule we had to made a header by SS
18 inch pipe (40 schedule). So as per design we tried to collect it locally ,
but it was not in local market.12 inch SS pipe is available and market
price is 22,000 Tk per feet. Our demand was 20 feet , total price = 22000
x 20 = 44,0000 Tk.
KAIZEN WORK : We decided to make header by MS alloy pipe which
will be same as SS 40 schedule pipe. MS pipe price is 4000 Tk per feet.
HP Comp#3
will be same as SS 40 schedule pipe. MS pipe price is 4000 Tk per feet.
Here total cost = 80000 Tk.
Total save = 440000-80000 = 360,000 Tk.
So it is re-engineering to select metal.
Ammonia Plant
Installation Date: 27:12:2014
Commissioning Date: 05.01.15
Plant Origin : DCE Refrigeration Pvt Ltd, India.
Capacity: 676000 + 220000 = 896000 Kcal/Hr(296Ton)
As chilled water = 223.4 Ton, Glycol water = 72.7 Ton.As chilled water = 223.4 Ton, Glycol water = 72.7 Ton.
Chilled water temp = 7 deg C.
Glycol water temp = -4 to -2 deg C.
Total Connected Load:
Space Required : 25’-0” x 45’-0” x 22’ -0”.(LWH)
Type of Plant : Vapor Compression type.
NH3 # 1
Machinery & Equipment List of NH3 Plant
1. Refrigerant Compressor1. Refrigerant Compressor
2. Discharge valve
3. Non –return valve
4. Oil separator
5. Discharge header.
6. Condenser
7. Liquid receiver
8. Surge Drum
NH3 # 2
8. Surge Drum
9. Evaporator
10. Suction header
11. Cooling Tower
12. Tanks
13. Pumps
14. Controlling devices
15. Fittings
16. Panel board
FLOW DIAGRAM OF NH3 PLANT
NH3 # 2NH3 3
Machinery & Equipment List of NH3 Plant
Refrigerant Compressor: Brand: KIRLOSKER, Type: Reciprocating,Refrigerant Compressor: Brand: KIRLOSKER, Type: Reciprocating,
Model: KC-4, Single stage, 4 cylinder,
Operating system: Belt drive, Motor 90 KW, 1, 2 No cylinder direct
loading & 3 for 75% and 4 no cylinder 100% on load. Cylinder head
water cooling. Suction = 80 mm, Discharge = 65 mm.
Working pressure status:
a). Low oil pressure alarm = 1.5 Kg/cm2
b). Low suction pressure = 0.5 Kg/cm2
NH3 # 2
b). Low suction pressure = 0.5 Kg/cm2
c). High Discharge Pressure = 15 Kg/cm2
Power Status:
a) Amp at Load = 65 Amp @ 50 % Load.
b) Amp at unload = it is running always at 50% load.
It start at unloading condition, after oil pressure raise (2 Bar) , goes to
loading with 2 cylinder i.e. 50%. Then after load condition rest of
cylinder will open @ of load 75%(3 Cyl) and 100%.(4 cyl).
NH3 # 4
Machinery & Equipment List of NH3 Plant
Condenser:
Brand: LAVA, Type: PHE,
Model: MK15-144 PLTS, Capacity = 887770 Kcal / Hr
Qty = 1 No
Medium = Vapor NH3 and CT water.
Brand: LAVA, Type: PHE,
Model: MK10-82 PLTS, Capacity = 307274 Kcal / Hr
Qty = 1 No
NH3 # 5
Qty = 1 No
Medium = Vapor NH3 and CT water.
NH3 Liquid Receiver:
Metallic cylindrical , Design code: ASME SECT VIII DIV 1, ED 2007,ADD
Fluid : Ammonia, Design Pressure: 21 Bar, Working Pressure = 15 Bar, Wt
= 610 Kg, Wr. Wt = 750 kg. Fitting pipe = 40 Sch, Plate Thickness = 8
mm, Painting: a) Primer = 2 coats of red oxide, primer. 30 -40 micron
b) Intermediate = 2 coats
c) Final = 2 coats
Machinery & Equipment List of NH3 Plant
Evaporator:
Brand: LAVA, Type: PHE,
Model: MK15-136 PLTS, Capacity = 676000 Kcal / Hr
Qty = 1 No
Medium =
Brand: LAVA, Type: PHE,
Model: MK10-124 PLTS, Capacity = 222000 Kcal / Hr
Qty = 1 No
NH3 # 2
Qty = 1 No
Medium = Liquid NH3 and Hot Chilled water.
Surge Drum:
Machinery & Equipment List of NH3 Plant
Cooling TowerCooling Tower
Type: Evaporative , Counter Flow. Sprinkler speed = 3-5 RPM.
Capacity : 200 RT + 200 RT = 400 RT
IN/OUT Let : 6”
CT Fan motor = 4 Kw, Drive = Layer of fins = 2 , Fins Height , Dia =
CT Pump Motor Specification = 4 Nos Pump ( Stand by 2 Nos)
Power = 3 phase, 380 VAC, 15 KW.
Flow rate = 120 M3/Hr.
NH3 #7
Flow rate = 120 M3/Hr.
Head = 30 M
Inlet / Outlet = 5”
Type : Reciprocating, inline vertical.
Pipe line connection : GI Pipe, Grade B
Total No of CT = 2 Nos ,
Purpose: For NH3 Condenser.
Machinery & Equipment List of NH3 Plant
TANKS:
CHW = 1, Glycol = 1
Dimension : 1.5 x 3.0 x 1.0 (M), Metal: SS 304, Insulation :Rubber foam
75 mm thick with alu covering.
PUMPS:
NH3 # 8
Sensors & Instrument of NH3 Plant.
NH3 # 9
Name : PET Bottle Blowing Plant.
Capacity: 450 BPM.
Model : SBO 14, Sl # 11779.
System : SBO
Using Medium : High Air Pressure ,35 to 38 BAR1527 M3/Hr(1 Ltr)
LP Air Pressure : @7 Bar 190 M3/Hr
Features : Dual system , CSD & Hotfill
Purpose : For New Dual filler room.Purpose : For New Dual filler room.
Location : Ground Floor ,CAN Building.
Power Consumption : 324 KW+ 30 KW
Total Power = 480 KW
Chilled water = 12 deg C, 30 M3/Hr
4 Bar pressure
Origin : Sidel, France
At the start of the bottle blowing process, the perform is heated to about
90°C. At this stage it is critical that the neck finish is protected in the oven, as
the incorrect positioning of heat shields could result in distortion of the neck
finish which in turn will affect handling on any air conveyer system on route
to the filling and closure application affect filling. Once heated the perform is
transferred by the neck to the bottle mould. The perform is then initially
stretched with a metal rod to elongate the lengthwise so the tip of the perform
is located into the centre of the base section of the mould. Low pressure air at
ca. 7-8 bar is applied at the same time in order to form a balloon inside theca. 7-8 bar is applied at the same time in order to form a balloon inside the
mould and then finally high pressure air of up to 40bar is applied to stretch
the material sideways into the final shape of the bottle mould. These two
operations must be done sequentially in order to get maximum biaxial
orientation of the polymer chains.
Orientation is the process of aligning the polymer chains in an orderly fashion
by stretching, in biaxial orientation the amorphous polymer (the random
arrangement chains) is stretched in both longitudinal and transverse directions
simultaneously. Biaxial orientation improves both the tensile strength and the
stiffness of the PET bottle.
Preform specification
RESIN
CSD STILL PRODUCT PREFORM
I.V. (dl/g)intrensic 0.80 – 0.85 0.72 to 0.75 Maxi IV drop = 0.02dl/g
Preform : injection system at 275o C.
for blowing it hates 90 o C in oven,
NH3 # 2
I.V. (dl/g)intrensic
viscosity
0.80 – 0.85 0.72 to 0.75 Maxi IV drop = 0.02dl/g
A.A.Acidaldihide < 2ppm < 1ppm CSD / 5 to 6ppm
Mineral Water / 3 to 4ppm
MOISTURE PICK-UP After drying < 100ppm Just before blowing
≤ 2000 ppm recommended
2500ppm maxi
PET Bottle Specification
1. Bottle height : a) Mitutoyo height gauge (or equivalent)
b) Roch marble surface standard.
2. Bottle Diameter
a) Pi Tape
b) Caliper Gauge
3. Bottle metarials Distribution by Cutting & Weighting.
a) Hot wire bottle cutter (3 or 4 wires) supplied by SIDEL.
b) Digital laboratory scales (Mettler PR 8100 or équivalent).b) Digital laboratory scales (Mettler PR 8100 or équivalent).
4. Volume Mesurement
5. Vertical Compression Strenght.
6. Drop Test
7. Creeping test
8. Burst Test
9. Weight
Sidel blowing
NH3 # 2
Sidel blowing Cycle
Preblow
Nozzle
raising
Difference Between RIP Sidel & AMCL Sidel (SBO -14).
Points / Subject RIP SBO -14 AMCL SBO -14 Remarks
Model SBO Universal SBO Universal HR(
Heat Resistance)
PET Bottle Production
Type
1. CSD
2. Warm Filling PET.
(Filler Temp < 80 o C)
1. CSD
2. Hot Filling PET.
(Filler Temp > 80 o C)
HP air Cooling System
during blowing in
mould.
Nil. No system Available After blowing high
pressure air are
released by nozzle to
cold bottle and
mould.
Oven Lamp Infra Red ECO Lamp ECO is good.
Best For CSD CSD & Hot Fill
Difference Between Sidel &RJM
Aspects Sidel RJM(Tech-Long) Remarks
Oven Lamp ECO Lamp IR (Infra-red) Lamp ECO lamp takes low
current consumption.
No. of spindle 180 206 Maintenance costs high
for RJM
HP Air consumption Less High Sidel has HP air recoveryHP Air consumption Less High Sidel has HP air recovery
system.
Extra LP Air No need Need More utility need.
Efficiency 95% 75% 18000 BPH RJM machine
could not give 18000
BPH. Its maximum output
15000 BHP(incase of RJM-
10)
POWER (ELECTRICITY)POWER (ELECTRICITY)
SL # Machine Name ELECTRICAL CONSUMPTION,
KW
RUNNING LOAD, KW
1 DUAL FILLER PLANT 363.5 285
2 WTP 52 42
3 RO 125 125
4 Ammonia Plant 517.5 365
5 Blowing 480 4205 Blowing 480 420
6 HP Air Compressor 300 300
7 All CTs (Process) 80 50
8 All Chillers 40 40
9 Blending 190 175
10 CIP Unit 20 15
TOTAL (CONNECTED) = 2168 KW 1815 KW
GAS RUN
BOILER RUN GENERATOR RUN
PRESENT , CFH BEFORE , CFH PRESENT , CFH BEFORE, CFH
36240 45440
69555 60360
We have increased gas run for 1.5 MW Gas Generator by re-conciliation
of gas using machinery.
SubSub--StationStation
• To face the increasing demand we have installed a 1.5MW gas
generator.
SubSub--StationStation
• The LT panel has to modified to 7000Amp.
• Create provision for synchronous run for all generators.
Power TransmissionPower Transmission
• For the first time we are going to transmit 2.2MW power for
distribution to a separate building named canning building.
Cable Specification:
1 X 500 RM, 53 Nos Run.
Total = 12 Kilometer Cable.
It’s is the biggest cable
laying in our group by own
employee.
Control roomControl room
• The transmitted power will be distributed from the control
room located near to the lift on Ground Floor.
Fig : Verming Proof.Fig : New LT Panel, 4000 A.
Distribution BoardDistribution Board
• The power is distributed through the distribution board of
630A to the plant.
Cable InformationCable Information
SL # Machine Name Power Cable Grounding Cable
1 DUAL FILLER PLANT Cable 3x70sm/35rm Cable 1x25rm BYA
2 WTP Cable 3x35sm/16rm NYY Cable 1x16rm BYA
3 RO Cable 3x95sm/50rm NYY Cable 1x120rm BYA
4 Ammonia Plant Cable 1x300rm XLPE,
3x95sm/50rm
Cable 1x120rm BYA
3x95sm/50rm
5 Blowing Cable 1x300rm XLPE Cable 1x120rm BYA
6 HP Air Compressor Cable 1x150rm XLPE (D) Cable 1x120rm BYA
7 All CTs (Process) Cable 4x4rm NYY Cable 1x4rm BYA
8 All Chillers Cable 3x50sm/25rm XLPE Cable 1x16rm BYA
9 Blending Cable 3x70sm/35rm Cable 1x25rm BYA
10 CIP Unit Cable 3x25sm/16rm Cable 1x16rm BYA
Technical info for New Substation.Technical info for New Substation.
• LT panel 7000A for Synchronizing Generator
Sp. Incoming 6000A, ACB; outgoing 5000A, ACB one, two 2000AACB
• LT Panel 6000A for distribution
Sp. Incoming 5000A, ACB; outgoing one 2000A, ACB; twelve 630A
MCCB
• For transmission Cable used 15 run/phase & 10 run for Neutral;
sp. Aluminium Cable 1x500rm XLPE & Al Cable 1x400rm XLPE
• For Distribution cable used 2 run/phase & 1 run for Neutral;
Sp. Al Cable 1x300rm XLPE
Name : Water Treatment Plant.
Capacity : 100 Ton / Hr.
Treatment System : Softening system with ACF.(Activated Carbon
Filtering)
Vessel of Metal : SS 304 L
Purpose : For New 4 AMCL Lines.(Dual , Hot, PE & Alu CAN)
Features : It has sterilization system by LP steam to bacteria kill. Drive
regulated by Inverter.regulated by Inverter.
Location : North – West of CAN Building.
Electrical Power : 40 KW
Steam Consumption : @ 1 Bar, 100kg
Origin : CHINA.
Output Water parameter:
1. Ph = around 6.5 to 7.5
2. Hardness = 0 to 3 ppm
3. Iron = 0.1
4. Free from Bacteria.
Accessories & Required Materials
• Row water pump
• Chemical dosing device
• Dosing tank
• Mechanical filter
WTP pipe
• PLC
• Liquid level switch
• ACF
• Regenerator
• Salty water tank
• WTP valve
• Manual butterfly valve
• Cartridge
• Conductivity meter
• VFD
• Control cabinet
• Sand
• Resin
• Activated carbon
Name : RO Plant.
Capacity : 80 Ton / Hr.
Treatment System : RO Filtration.
Vessel of Metal : FRP, & 13 Nos.
Purpose : For New 4 AMCL Lines.
Features : Drive regulated system.
Location : Ground Floor of CAN Building.
Power : 125 KW
MEMBRANE
Size : 8” x 40”
2 Pass system.
Brand: FILMTECH, USA
Filter range: 0.0001 Micron.
Total Number: 78
Power : 125 KW
Origin : CHINA.
Water Network
Accessories Used for RO Plant
• RO unit
• High pressure pump
• VFD
• RO membrane
• Pressure meter
• Flow meter
• Pure water pump
• UV sterilizer
• Ozone pump
• Mixing tower
• Asepsis water tank
• Ozone generator• Flow meter
• Resin valve
• Rising device
• Rising tank
• CIP pump
• Pure water tank
• Breath filter
• Ozone generator
• RO pipe & fitting
• Flow rate adjusting valve
• Single direction valve
• Pure water tank
Name : Central Air-Conditioning System
Capacity: 50 TR
System : Vapor Compression system & AHU
Using Refrigerant: R-22
Total no of Chiller : 2
Purpose : For New Dual filler room.
Location : Roof of New Building.
Origin : TICA, China.
Cooling Coil Chamber
Origin : TICA, China.
Pre-filter chamber Bag-Filter Chamber HEFA Filter Chamber
CT OF DUAL FILLER
NH3 # 2
Central BlendingCentral Blending
1. 16 Ton per hour syrup process system for DUAL Filler.
2. 12 Ton per hour juice process system for HOTFILL.
3. 6 Ton per hour juice process system for ALU-CAN.
4. 5 Ton per hour Yogurt process system for PE-Lassi Line.
Blending ProcessBlending Process
Proper Clean In Place (CIP) & Sanitation Ensure
System Sterility
CIP Cycle Example:CIP Cycle Example:
Hot water (>60Hot water (>60°°°°°°°°C) circulated for 10 minutesC) circulated for 10 minutes
Hot caustic, 80Hot caustic, 80°°°°°°°°C circulated for 20 minutes (with an active alkalinity of atC circulated for 20 minutes (with an active alkalinity of at
least 2%)least 2%)
Rinse 5Rinse 5 -- 10 minutes with Hot water (>6010 minutes with Hot water (>60°°°°°°°°C) waterC) water
Hot Acid circulated for 20 minutes (with nitric acid of 0.6Hot Acid circulated for 20 minutes (with nitric acid of 0.6 -- 0.8 % v/v)0.8 % v/v)
Rinse 5Rinse 5 -- 10 minutes with Hot water (>6010 minutes with Hot water (>60°°°°°°°°C) waterC) waterRinse 5Rinse 5 -- 10 minutes with Hot water (>6010 minutes with Hot water (>60°°°°°°°°C) waterC) water
Rinse 5 minutes with treated waterRinse 5 minutes with treated water
Hot sanitation step must be performed prior toHot sanitation step must be performed prior to
production startproduction start--upup
An chlorinated water or acid sanitizer solutionAn chlorinated water or acid sanitizer solution
must be left in the system during downtimemust be left in the system during downtime
Merits & DeMerits & De--meritsmerits
1. A good team work.
2. Zero accident up to 5000 working hours.
3. Re-engineering.
4. 12 KM Cable laying by own-team.(Newly joint people)
1. GMP Space no consideration.
2. As per VUCA , need UV or Polishing filter for RO & CO2
delivery line.
3. Materials collection was not a good way.
Some Moments.
Fig: Support Fig: Unloading. Fig: MeetingFig: M/c Base
Fig: Set up
Fig:Tank setup Fig: m/c setup Fig: Unloading Fig: Pipe welding
Fig: Positioning Fig: Lifting. Fig: Gen Set.
THANKSTHANKSTHANKSTHANKS

More Related Content

What's hot

Water Gas Shift & Hydrogen Purification Section Flowsheet
Water Gas Shift & Hydrogen Purification Section FlowsheetWater Gas Shift & Hydrogen Purification Section Flowsheet
Water Gas Shift & Hydrogen Purification Section FlowsheetGerard B. Hawkins
 
Feb. 2016 webinar_condensate_return_piping
Feb. 2016 webinar_condensate_return_pipingFeb. 2016 webinar_condensate_return_piping
Feb. 2016 webinar_condensate_return_pipinglorenzo Monasca
 
Operation of urea fertilizers plant
Operation of urea fertilizers plantOperation of urea fertilizers plant
Operation of urea fertilizers plantPrem Baboo
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedureABVSAI
 
Incontri Formativi 17 marzo 2016 - P. Trevisan - BITZER
Incontri Formativi 17 marzo 2016 - P. Trevisan - BITZERIncontri Formativi 17 marzo 2016 - P. Trevisan - BITZER
Incontri Formativi 17 marzo 2016 - P. Trevisan - BITZERCentro Studi Galileo
 
Methanol Plant - Theory of Distillation
Methanol Plant - Theory of DistillationMethanol Plant - Theory of Distillation
Methanol Plant - Theory of DistillationGerard B. Hawkins
 
Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1Ray Beebe
 
Cb gf web in sep 2016, feeding chemicals to boilers sfc r3
Cb gf web in sep 2016, feeding chemicals to boilers sfc r3Cb gf web in sep 2016, feeding chemicals to boilers sfc r3
Cb gf web in sep 2016, feeding chemicals to boilers sfc r3lorenzo Monasca
 
Steam Reforming - Tube Design
Steam Reforming - Tube DesignSteam Reforming - Tube Design
Steam Reforming - Tube DesignGerard B. Hawkins
 
Principles of Pre-reforming Technology
Principles of Pre-reforming TechnologyPrinciples of Pre-reforming Technology
Principles of Pre-reforming TechnologyGerard B. Hawkins
 
Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Gerard B. Hawkins
 
Steam Reforming - Common Problems
Steam Reforming - Common ProblemsSteam Reforming - Common Problems
Steam Reforming - Common ProblemsGerard B. Hawkins
 
Hydrogen Plant - Normal Operations
Hydrogen Plant - Normal OperationsHydrogen Plant - Normal Operations
Hydrogen Plant - Normal OperationsGerard B. Hawkins
 
Paper 5 iven li Energy Efficiency Improvement and Cost-Saving for Oilseeds p...
Paper 5 iven li  Energy Efficiency Improvement and Cost-Saving for Oilseeds p...Paper 5 iven li  Energy Efficiency Improvement and Cost-Saving for Oilseeds p...
Paper 5 iven li Energy Efficiency Improvement and Cost-Saving for Oilseeds p...pakistanoilseeds
 
Normal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen PlantsNormal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen PlantsGerard B. Hawkins
 
Methanol Plant Safety - A Historical Perspective
Methanol Plant Safety - A Historical PerspectiveMethanol Plant Safety - A Historical Perspective
Methanol Plant Safety - A Historical PerspectiveGerard B. Hawkins
 

What's hot (20)

Water Gas Shift & Hydrogen Purification Section Flowsheet
Water Gas Shift & Hydrogen Purification Section FlowsheetWater Gas Shift & Hydrogen Purification Section Flowsheet
Water Gas Shift & Hydrogen Purification Section Flowsheet
 
Feb. 2016 webinar_condensate_return_piping
Feb. 2016 webinar_condensate_return_pipingFeb. 2016 webinar_condensate_return_piping
Feb. 2016 webinar_condensate_return_piping
 
Operation of urea fertilizers plant
Operation of urea fertilizers plantOperation of urea fertilizers plant
Operation of urea fertilizers plant
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedure
 
Reformer Catalyst Report
Reformer Catalyst ReportReformer Catalyst Report
Reformer Catalyst Report
 
Final Year Project Presentation
Final Year Project PresentationFinal Year Project Presentation
Final Year Project Presentation
 
Incontri Formativi 17 marzo 2016 - P. Trevisan - BITZER
Incontri Formativi 17 marzo 2016 - P. Trevisan - BITZERIncontri Formativi 17 marzo 2016 - P. Trevisan - BITZER
Incontri Formativi 17 marzo 2016 - P. Trevisan - BITZER
 
Methanol Plant - Theory of Distillation
Methanol Plant - Theory of DistillationMethanol Plant - Theory of Distillation
Methanol Plant - Theory of Distillation
 
Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1Beebe steam turbines cm apr2016 r1
Beebe steam turbines cm apr2016 r1
 
Cb gf web in sep 2016, feeding chemicals to boilers sfc r3
Cb gf web in sep 2016, feeding chemicals to boilers sfc r3Cb gf web in sep 2016, feeding chemicals to boilers sfc r3
Cb gf web in sep 2016, feeding chemicals to boilers sfc r3
 
Steam Reforming - Tube Design
Steam Reforming - Tube DesignSteam Reforming - Tube Design
Steam Reforming - Tube Design
 
Principles of Pre-reforming Technology
Principles of Pre-reforming TechnologyPrinciples of Pre-reforming Technology
Principles of Pre-reforming Technology
 
Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers -
 
Steam Reforming - Common Problems
Steam Reforming - Common ProblemsSteam Reforming - Common Problems
Steam Reforming - Common Problems
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
Hydrogen Plant - Normal Operations
Hydrogen Plant - Normal OperationsHydrogen Plant - Normal Operations
Hydrogen Plant - Normal Operations
 
Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2Gross turbine cycle_heat_rate_ch-8.2
Gross turbine cycle_heat_rate_ch-8.2
 
Paper 5 iven li Energy Efficiency Improvement and Cost-Saving for Oilseeds p...
Paper 5 iven li  Energy Efficiency Improvement and Cost-Saving for Oilseeds p...Paper 5 iven li  Energy Efficiency Improvement and Cost-Saving for Oilseeds p...
Paper 5 iven li Energy Efficiency Improvement and Cost-Saving for Oilseeds p...
 
Normal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen PlantsNormal Operation of Steam Reformers on Hydrogen Plants
Normal Operation of Steam Reformers on Hydrogen Plants
 
Methanol Plant Safety - A Historical Perspective
Methanol Plant Safety - A Historical PerspectiveMethanol Plant Safety - A Historical Perspective
Methanol Plant Safety - A Historical Perspective
 

Similar to Microsoft PowerPoint - DEV of Dual Filling

Report on Industrial Training
Report on Industrial TrainingReport on Industrial Training
Report on Industrial TrainingNashiyat Fyza
 
Combined Cycle power Plant IFFCO Aonla
Combined Cycle power Plant IFFCO AonlaCombined Cycle power Plant IFFCO Aonla
Combined Cycle power Plant IFFCO AonlaANUP SRIVASTAV
 
Hvac - presentation (Air conditioning presentation)
Hvac - presentation (Air conditioning presentation) Hvac - presentation (Air conditioning presentation)
Hvac - presentation (Air conditioning presentation) SYED KHURSHID ALAM ARZOO
 
Adiabatic cooling tower v3 08.08
Adiabatic cooling tower v3 08.08Adiabatic cooling tower v3 08.08
Adiabatic cooling tower v3 08.08Er Ramgarhia
 
Deyab a. aspen hysys 2013 workbook
Deyab a.  aspen hysys 2013   workbookDeyab a.  aspen hysys 2013   workbook
Deyab a. aspen hysys 2013 workbookLito Aguirre
 
Hydraulic ppt.pptx
Hydraulic ppt.pptxHydraulic ppt.pptx
Hydraulic ppt.pptxnikuk1
 
CESC SGS project report
CESC SGS project reportCESC SGS project report
CESC SGS project reportSayanSarkar55
 
Introduction to ppe
Introduction to ppeIntroduction to ppe
Introduction to ppeYash Shah
 
Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Ray Beebe
 
Inplant training report
Inplant training reportInplant training report
Inplant training reportapplesam8
 
660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliariesAshvani Shukla
 
Aph operation and emergency handling
Aph operation and emergency handlingAph operation and emergency handling
Aph operation and emergency handlingParag Agrawal
 
Opportunities of climate and energy efficiency co benefits
Opportunities of climate and energy efficiency co benefits Opportunities of climate and energy efficiency co benefits
Opportunities of climate and energy efficiency co benefits UNEP OzonAction
 
engineering and utilities report
engineering and utilities reportengineering and utilities report
engineering and utilities reportHassan Bilal
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]Amardeep Jadeja
 
BE Chemical Engineering Design Project Production Of Propylene Oxide
BE Chemical Engineering Design Project   Production Of Propylene OxideBE Chemical Engineering Design Project   Production Of Propylene Oxide
BE Chemical Engineering Design Project Production Of Propylene Oxidepatrickconneran
 

Similar to Microsoft PowerPoint - DEV of Dual Filling (20)

Report on Industrial Training
Report on Industrial TrainingReport on Industrial Training
Report on Industrial Training
 
Combined Cycle power Plant IFFCO Aonla
Combined Cycle power Plant IFFCO AonlaCombined Cycle power Plant IFFCO Aonla
Combined Cycle power Plant IFFCO Aonla
 
Hvac - presentation (Air conditioning presentation)
Hvac - presentation (Air conditioning presentation) Hvac - presentation (Air conditioning presentation)
Hvac - presentation (Air conditioning presentation)
 
Adiabatic cooling tower v3 08.08
Adiabatic cooling tower v3 08.08Adiabatic cooling tower v3 08.08
Adiabatic cooling tower v3 08.08
 
Deyab a. aspen hysys 2013 workbook
Deyab a.  aspen hysys 2013   workbookDeyab a.  aspen hysys 2013   workbook
Deyab a. aspen hysys 2013 workbook
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
Hydraulic ppt.pptx
Hydraulic ppt.pptxHydraulic ppt.pptx
Hydraulic ppt.pptx
 
CESC SGS project report
CESC SGS project reportCESC SGS project report
CESC SGS project report
 
Introduction to ppe
Introduction to ppeIntroduction to ppe
Introduction to ppe
 
CRAP PRESENTATION
CRAP PRESENTATIONCRAP PRESENTATION
CRAP PRESENTATION
 
Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014
 
training report
training reporttraining report
training report
 
Inplant training report
Inplant training reportInplant training report
Inplant training report
 
660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries
 
Presentation On Boiler Analysis
Presentation On Boiler AnalysisPresentation On Boiler Analysis
Presentation On Boiler Analysis
 
Aph operation and emergency handling
Aph operation and emergency handlingAph operation and emergency handling
Aph operation and emergency handling
 
Opportunities of climate and energy efficiency co benefits
Opportunities of climate and energy efficiency co benefits Opportunities of climate and energy efficiency co benefits
Opportunities of climate and energy efficiency co benefits
 
engineering and utilities report
engineering and utilities reportengineering and utilities report
engineering and utilities report
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]
 
BE Chemical Engineering Design Project Production Of Propylene Oxide
BE Chemical Engineering Design Project   Production Of Propylene OxideBE Chemical Engineering Design Project   Production Of Propylene Oxide
BE Chemical Engineering Design Project Production Of Propylene Oxide
 

More from PRAN-RFL Group

More from PRAN-RFL Group (9)

Bangladesh All Mobile operators query short code.
Bangladesh All Mobile operators query short code.Bangladesh All Mobile operators query short code.
Bangladesh All Mobile operators query short code.
 
Ramadan management
Ramadan managementRamadan management
Ramadan management
 
PRAN AMCL COMPRESSED AIR SYSTEM
PRAN AMCL COMPRESSED AIR SYSTEMPRAN AMCL COMPRESSED AIR SYSTEM
PRAN AMCL COMPRESSED AIR SYSTEM
 
Word order
Word orderWord order
Word order
 
Noun verses Verb
Noun verses Verb  Noun verses Verb
Noun verses Verb
 
N vs v
N vs vN vs v
N vs v
 
Fork lift training on 21th sep 13
Fork lift training on 21th sep 13Fork lift training on 21th sep 13
Fork lift training on 21th sep 13
 
Forklift training
Forklift trainingForklift training
Forklift training
 
Tpm 02
Tpm 02Tpm 02
Tpm 02
 

Microsoft PowerPoint - DEV of Dual Filling

  • 1. A Team Work ……… Presented by. Md.Amzad, Hossain , ACE, PFG.
  • 3. PLANT LIST 1. BLOWING SYSTEM. a) HP Compressor, 40 BAR b) Chiller Plant c) SIDEL PET Blowing Plant. 2. Central Syrup & Blending a) Central Syrup , 4 nosa) Central Syrup , 4 nos b) Central Blending System c) CIP Unit 3. Power & Utility a) 1.5 MW Gas Generator & Gas use Reconciliation. b) 4000 Amp substation in CAN Building. c) 100 TPH WTP d) 80 TPH RO Plant 3. Dual Filler Plant
  • 4. Filler Name: DUAL FILLER Location: New CAN Building Capacity: 400 BPM Filling system : Soft & Hot Filling Control System : Flow meter controlling. Filling Valve : Electro-pneumatic Valve. Filler model : DQRS – 80 x 80 x 18.Filler model : DQRS – 80 x 80 x 18. Type: Monoblock. Total No of Nozzle : 80 CO2 Consumption : 180 Kg/hr. Air Consumption : 24 M3/hr@6 Bar. Required Chilling water temp: a) Glycol water = -2 to -4 Deg C b) Chilled water = 7 Deg C.
  • 5.
  • 6.
  • 7. CSD Hot Fill Carbo mixer Rinser Filler Capper Wrapper (Packaging) UHT PET Conveyor Belt Syrup Homo Syrup Juice Mixing Over head conveyor C h e c Warmer/ Cooling tunnel Conveyor Blow Dryer Band-R LabelerBlowing PET Bottle Pre form Closure Hopper Caper Rinser FIG : PROCESS FLOW DIAGRAM (CSD & HOT FILL.) Date Coding c k Cycle time : 35-40 Min
  • 8. MACHINE NAME UTILITY CO2, Kg/Hr. LP AIR, CFM Chilled water, M3/Hr RO Water, M3/Hr Fresh Water, M3/Hr Steam, Kg/Hr. Power, KW CT water DUAL FILLER 90 32 NA 7 4 NA 31 NA CARBO MIXER 90 21 40 15 3 NA 34 NA HOMO NA 25 NA NA 2 NA 132 NA WARMER NA 32 50 NA 1 400 34.9 80 LABELLER NA 45 NA NA NA NA 15 NA WRAPPING NA 50 NA NA NA NA 78.5 NA Band –Roll inserter NA 10 NA NA NA NA 27 NA UHT NA 25 55 20 12 800 18 120 TOTAL 180 240 145 42 22 1000 363.4 200
  • 9. 1. Filler machine (Rainser + Filler + Capper), 80 x 80 x 18, Tech-long. 2. Carbo Mixer , 16 TPH Tech-Long, China. 3. Cooling Tunnel or Warmer , 4 Chambers, Tech-Long. 4. Air Blower / Dryer , Tech-Long 5. Date Coding Machine, Image Model: 9020. 6. Labeler, OPP, HF SSO-6000, Korean 7. Band-Roll Inserter, LEBAL TRADING CO, LTD. 8. Wrapping Machine: Automatic Shrink Film Wrapping system. 20-25 Min 8. Wrapping Machine: Automatic Shrink Film Wrapping system. Capacity : 35 Boxes/Min, Model: WSD- LMB35T , China. 9. Homo : GEA, Max Pressure 25 MPa, Rated Flow : 1000 dm3/h, VFD System, Italy. 10. UHT/Sterilizer : Type: Tabular, (Shell & Tube), Heating Area = 88 M2 , Max temp = 1500 C 11. PHE : Total 5 nos. 12. Dosing Pump: Grundfos , 5 L/H, 6 Bar, 0.011 KW, 50 Hz. 13. Conveyor Lubrication system. 14. Cap Sterilization System: Cap: 32000 BPH, Pump = 4 Bar, 2 stage.
  • 10. Carbon -Di-Oxide Tank Installation date : 09:05:2014. C.Run : Location : Beside CSD CO2 Tank. Storage Capacity : 10 Cubic meter. y Storage Condition: Liquid. Vessel weight : 6500 kg Operating & test pressure :Operating & test pressure : Max = 22 Bar, Min: 10 Bar. Test Pr = 25 Bar Dimension : Dia = 2020 mm , 3 Legs,(@ 70” & 120 deg) Vaporizer capacity = 150 NM3/H. Piping : 25 mm SS 40 schedule, with PRV, 8 Bar Welding System : TIG with filler rod. Leak Test @ 12 Bar by water only pipe line.
  • 11. CO2 Process Flow Diagram CO2 Tank Instruments: 1. Two pressure relief valve. 2. Operating pressure gauge. 3. Storage/capacity gauge. 4. High & Low level audible alarm. Storage Pressure & Temp = 20.5 bar & -17 C. CO2 Uses System: 1. During filling to storage tank use both hoses vapor and liquid to displaced gas by liquid. 2. Use Non –return valve for Tanker & storage tank. 3. It is better to be safe than sorry , so use 0.01 micron polishing filter. 4. Use PRV after vaporizer. 15 Bar to 8 bar. 15% CO2 Losses in PET Bottle; 1. For 2 ltr = 12 weeks, 2. 500 ml = 9 weeks, 3. 250 ml = 7 weeks.
  • 12. High Pressure Compressor. Installation date : 24:05:2014. Commissioning Date : 07:12:2014 Location : HP Compressor area. Machine Specification :Brand: ABC , Spain Model: 4HA-6TER- LT, SL# 24472. 4 stage, 6 cylinder, 280 KW motor (Brazil) , 28 M3 / min. , 670 rpm, Wt : 13 tons. Mainmotor (Brazil) , 28 M3 / min. , 670 rpm, Wt : 13 tons. Main Base dimension (mm) = 6800 x 2060. Working Pressure : 35 Bar to 38 Bar Power status: Total Connected Load : 291.85 KW Current at Load : 153-155-156 amp Current at unload: 17 amp HP Comp#1
  • 13. High Pressure Compressor. Air drying system/Air Dryer: Brand: Airsec,Model:FD-300-WH,Flow rate: 1768 M3/H Type: Refrigeration, R-404A, (3.5 kg), DP = min 3 deg C. Air input Temp max = @40 Bar,40 deg C. Compressor Hermetic Type , 3.7 KW, 7A, Condenser water cooled. Cooling system/Cooling Tower: Model : RMA -101 D, TEVA Closed cycle , evaporative system with shell & tube .Its blower motor HP Comp#2 Closed cycle , evaporative system with shell & tube .Its blower motor permanently lubricated by bush bearing (2Z) , Motor = 3 nos. @ 1.1 Kw Size : 680 x 1270 mm. Two parts wt = 800 + 1300 = 2100 Kgs. Piping System : Total length : 345 ft. Size : 80 mm , 40 schedule , 40 BAR Grade : 304 L Welding: V- shaped, SS filler rod . MS 18” header with Grid system (by pass with HP # 1) Hydraulic test : 55 Bar , Holding Time : 4 hours, by water.
  • 14. Points / Aspects. ABC HP COMPRESSOR IR HP COMPRESSOR 1. Space Less More 2. Starting load Less (Due to LP air connected) More 3. Cooling system Good (Closed cycle) Poor, open 4. Dryness of air Good , 3 deg C Up to 8 deg C 5. Power consumption Less than IR, due to VLT drive 6. Air Filter 16000 hrs 8000 Hrs Main Feature of ABC HP Compressor 6. Air Filter 16000 hrs 8000 Hrs Main motor is 280 Kw, more than 10 Kw bigger than IR. Equipment setup on base are more complex. Air cylinder also complex. Plant Safety 1. PPE ( safety shoe, tight dresses) 2. SOP 3. CO2 Fire Extinguisher 4. Proper earthling 90 RM copper cable.
  • 15. Re-Engineering for HP Air Compressor. Description: As per design schedule we had to made a header by SS 18 inch pipe (40 schedule). So as per design we tried to collect it locally , but it was not in local market.12 inch SS pipe is available and market price is 22,000 Tk per feet. Our demand was 20 feet , total price = 22000 x 20 = 44,0000 Tk. KAIZEN WORK : We decided to make header by MS alloy pipe which will be same as SS 40 schedule pipe. MS pipe price is 4000 Tk per feet. HP Comp#3 will be same as SS 40 schedule pipe. MS pipe price is 4000 Tk per feet. Here total cost = 80000 Tk. Total save = 440000-80000 = 360,000 Tk. So it is re-engineering to select metal.
  • 16. Ammonia Plant Installation Date: 27:12:2014 Commissioning Date: 05.01.15 Plant Origin : DCE Refrigeration Pvt Ltd, India. Capacity: 676000 + 220000 = 896000 Kcal/Hr(296Ton) As chilled water = 223.4 Ton, Glycol water = 72.7 Ton.As chilled water = 223.4 Ton, Glycol water = 72.7 Ton. Chilled water temp = 7 deg C. Glycol water temp = -4 to -2 deg C. Total Connected Load: Space Required : 25’-0” x 45’-0” x 22’ -0”.(LWH) Type of Plant : Vapor Compression type. NH3 # 1
  • 17. Machinery & Equipment List of NH3 Plant 1. Refrigerant Compressor1. Refrigerant Compressor 2. Discharge valve 3. Non –return valve 4. Oil separator 5. Discharge header. 6. Condenser 7. Liquid receiver 8. Surge Drum NH3 # 2 8. Surge Drum 9. Evaporator 10. Suction header 11. Cooling Tower 12. Tanks 13. Pumps 14. Controlling devices 15. Fittings 16. Panel board
  • 18. FLOW DIAGRAM OF NH3 PLANT NH3 # 2NH3 3
  • 19. Machinery & Equipment List of NH3 Plant Refrigerant Compressor: Brand: KIRLOSKER, Type: Reciprocating,Refrigerant Compressor: Brand: KIRLOSKER, Type: Reciprocating, Model: KC-4, Single stage, 4 cylinder, Operating system: Belt drive, Motor 90 KW, 1, 2 No cylinder direct loading & 3 for 75% and 4 no cylinder 100% on load. Cylinder head water cooling. Suction = 80 mm, Discharge = 65 mm. Working pressure status: a). Low oil pressure alarm = 1.5 Kg/cm2 b). Low suction pressure = 0.5 Kg/cm2 NH3 # 2 b). Low suction pressure = 0.5 Kg/cm2 c). High Discharge Pressure = 15 Kg/cm2 Power Status: a) Amp at Load = 65 Amp @ 50 % Load. b) Amp at unload = it is running always at 50% load. It start at unloading condition, after oil pressure raise (2 Bar) , goes to loading with 2 cylinder i.e. 50%. Then after load condition rest of cylinder will open @ of load 75%(3 Cyl) and 100%.(4 cyl). NH3 # 4
  • 20. Machinery & Equipment List of NH3 Plant Condenser: Brand: LAVA, Type: PHE, Model: MK15-144 PLTS, Capacity = 887770 Kcal / Hr Qty = 1 No Medium = Vapor NH3 and CT water. Brand: LAVA, Type: PHE, Model: MK10-82 PLTS, Capacity = 307274 Kcal / Hr Qty = 1 No NH3 # 5 Qty = 1 No Medium = Vapor NH3 and CT water. NH3 Liquid Receiver: Metallic cylindrical , Design code: ASME SECT VIII DIV 1, ED 2007,ADD Fluid : Ammonia, Design Pressure: 21 Bar, Working Pressure = 15 Bar, Wt = 610 Kg, Wr. Wt = 750 kg. Fitting pipe = 40 Sch, Plate Thickness = 8 mm, Painting: a) Primer = 2 coats of red oxide, primer. 30 -40 micron b) Intermediate = 2 coats c) Final = 2 coats
  • 21. Machinery & Equipment List of NH3 Plant Evaporator: Brand: LAVA, Type: PHE, Model: MK15-136 PLTS, Capacity = 676000 Kcal / Hr Qty = 1 No Medium = Brand: LAVA, Type: PHE, Model: MK10-124 PLTS, Capacity = 222000 Kcal / Hr Qty = 1 No NH3 # 2 Qty = 1 No Medium = Liquid NH3 and Hot Chilled water. Surge Drum:
  • 22. Machinery & Equipment List of NH3 Plant Cooling TowerCooling Tower Type: Evaporative , Counter Flow. Sprinkler speed = 3-5 RPM. Capacity : 200 RT + 200 RT = 400 RT IN/OUT Let : 6” CT Fan motor = 4 Kw, Drive = Layer of fins = 2 , Fins Height , Dia = CT Pump Motor Specification = 4 Nos Pump ( Stand by 2 Nos) Power = 3 phase, 380 VAC, 15 KW. Flow rate = 120 M3/Hr. NH3 #7 Flow rate = 120 M3/Hr. Head = 30 M Inlet / Outlet = 5” Type : Reciprocating, inline vertical. Pipe line connection : GI Pipe, Grade B Total No of CT = 2 Nos , Purpose: For NH3 Condenser.
  • 23. Machinery & Equipment List of NH3 Plant TANKS: CHW = 1, Glycol = 1 Dimension : 1.5 x 3.0 x 1.0 (M), Metal: SS 304, Insulation :Rubber foam 75 mm thick with alu covering. PUMPS: NH3 # 8
  • 24. Sensors & Instrument of NH3 Plant. NH3 # 9
  • 25. Name : PET Bottle Blowing Plant. Capacity: 450 BPM. Model : SBO 14, Sl # 11779. System : SBO Using Medium : High Air Pressure ,35 to 38 BAR1527 M3/Hr(1 Ltr) LP Air Pressure : @7 Bar 190 M3/Hr Features : Dual system , CSD & Hotfill Purpose : For New Dual filler room.Purpose : For New Dual filler room. Location : Ground Floor ,CAN Building. Power Consumption : 324 KW+ 30 KW Total Power = 480 KW Chilled water = 12 deg C, 30 M3/Hr 4 Bar pressure Origin : Sidel, France
  • 26. At the start of the bottle blowing process, the perform is heated to about 90°C. At this stage it is critical that the neck finish is protected in the oven, as the incorrect positioning of heat shields could result in distortion of the neck finish which in turn will affect handling on any air conveyer system on route to the filling and closure application affect filling. Once heated the perform is transferred by the neck to the bottle mould. The perform is then initially stretched with a metal rod to elongate the lengthwise so the tip of the perform is located into the centre of the base section of the mould. Low pressure air at ca. 7-8 bar is applied at the same time in order to form a balloon inside theca. 7-8 bar is applied at the same time in order to form a balloon inside the mould and then finally high pressure air of up to 40bar is applied to stretch the material sideways into the final shape of the bottle mould. These two operations must be done sequentially in order to get maximum biaxial orientation of the polymer chains. Orientation is the process of aligning the polymer chains in an orderly fashion by stretching, in biaxial orientation the amorphous polymer (the random arrangement chains) is stretched in both longitudinal and transverse directions simultaneously. Biaxial orientation improves both the tensile strength and the stiffness of the PET bottle.
  • 27. Preform specification RESIN CSD STILL PRODUCT PREFORM I.V. (dl/g)intrensic 0.80 – 0.85 0.72 to 0.75 Maxi IV drop = 0.02dl/g Preform : injection system at 275o C. for blowing it hates 90 o C in oven, NH3 # 2 I.V. (dl/g)intrensic viscosity 0.80 – 0.85 0.72 to 0.75 Maxi IV drop = 0.02dl/g A.A.Acidaldihide < 2ppm < 1ppm CSD / 5 to 6ppm Mineral Water / 3 to 4ppm MOISTURE PICK-UP After drying < 100ppm Just before blowing ≤ 2000 ppm recommended 2500ppm maxi
  • 28. PET Bottle Specification 1. Bottle height : a) Mitutoyo height gauge (or equivalent) b) Roch marble surface standard. 2. Bottle Diameter a) Pi Tape b) Caliper Gauge 3. Bottle metarials Distribution by Cutting & Weighting. a) Hot wire bottle cutter (3 or 4 wires) supplied by SIDEL. b) Digital laboratory scales (Mettler PR 8100 or équivalent).b) Digital laboratory scales (Mettler PR 8100 or équivalent). 4. Volume Mesurement 5. Vertical Compression Strenght. 6. Drop Test 7. Creeping test 8. Burst Test 9. Weight
  • 31. Difference Between RIP Sidel & AMCL Sidel (SBO -14). Points / Subject RIP SBO -14 AMCL SBO -14 Remarks Model SBO Universal SBO Universal HR( Heat Resistance) PET Bottle Production Type 1. CSD 2. Warm Filling PET. (Filler Temp < 80 o C) 1. CSD 2. Hot Filling PET. (Filler Temp > 80 o C) HP air Cooling System during blowing in mould. Nil. No system Available After blowing high pressure air are released by nozzle to cold bottle and mould. Oven Lamp Infra Red ECO Lamp ECO is good. Best For CSD CSD & Hot Fill
  • 32. Difference Between Sidel &RJM Aspects Sidel RJM(Tech-Long) Remarks Oven Lamp ECO Lamp IR (Infra-red) Lamp ECO lamp takes low current consumption. No. of spindle 180 206 Maintenance costs high for RJM HP Air consumption Less High Sidel has HP air recoveryHP Air consumption Less High Sidel has HP air recovery system. Extra LP Air No need Need More utility need. Efficiency 95% 75% 18000 BPH RJM machine could not give 18000 BPH. Its maximum output 15000 BHP(incase of RJM- 10)
  • 33. POWER (ELECTRICITY)POWER (ELECTRICITY) SL # Machine Name ELECTRICAL CONSUMPTION, KW RUNNING LOAD, KW 1 DUAL FILLER PLANT 363.5 285 2 WTP 52 42 3 RO 125 125 4 Ammonia Plant 517.5 365 5 Blowing 480 4205 Blowing 480 420 6 HP Air Compressor 300 300 7 All CTs (Process) 80 50 8 All Chillers 40 40 9 Blending 190 175 10 CIP Unit 20 15 TOTAL (CONNECTED) = 2168 KW 1815 KW
  • 34. GAS RUN BOILER RUN GENERATOR RUN PRESENT , CFH BEFORE , CFH PRESENT , CFH BEFORE, CFH 36240 45440 69555 60360 We have increased gas run for 1.5 MW Gas Generator by re-conciliation of gas using machinery.
  • 35. SubSub--StationStation • To face the increasing demand we have installed a 1.5MW gas generator.
  • 36. SubSub--StationStation • The LT panel has to modified to 7000Amp. • Create provision for synchronous run for all generators.
  • 37. Power TransmissionPower Transmission • For the first time we are going to transmit 2.2MW power for distribution to a separate building named canning building. Cable Specification: 1 X 500 RM, 53 Nos Run. Total = 12 Kilometer Cable. It’s is the biggest cable laying in our group by own employee.
  • 38. Control roomControl room • The transmitted power will be distributed from the control room located near to the lift on Ground Floor. Fig : Verming Proof.Fig : New LT Panel, 4000 A.
  • 39. Distribution BoardDistribution Board • The power is distributed through the distribution board of 630A to the plant.
  • 40. Cable InformationCable Information SL # Machine Name Power Cable Grounding Cable 1 DUAL FILLER PLANT Cable 3x70sm/35rm Cable 1x25rm BYA 2 WTP Cable 3x35sm/16rm NYY Cable 1x16rm BYA 3 RO Cable 3x95sm/50rm NYY Cable 1x120rm BYA 4 Ammonia Plant Cable 1x300rm XLPE, 3x95sm/50rm Cable 1x120rm BYA 3x95sm/50rm 5 Blowing Cable 1x300rm XLPE Cable 1x120rm BYA 6 HP Air Compressor Cable 1x150rm XLPE (D) Cable 1x120rm BYA 7 All CTs (Process) Cable 4x4rm NYY Cable 1x4rm BYA 8 All Chillers Cable 3x50sm/25rm XLPE Cable 1x16rm BYA 9 Blending Cable 3x70sm/35rm Cable 1x25rm BYA 10 CIP Unit Cable 3x25sm/16rm Cable 1x16rm BYA
  • 41. Technical info for New Substation.Technical info for New Substation. • LT panel 7000A for Synchronizing Generator Sp. Incoming 6000A, ACB; outgoing 5000A, ACB one, two 2000AACB • LT Panel 6000A for distribution Sp. Incoming 5000A, ACB; outgoing one 2000A, ACB; twelve 630A MCCB • For transmission Cable used 15 run/phase & 10 run for Neutral; sp. Aluminium Cable 1x500rm XLPE & Al Cable 1x400rm XLPE • For Distribution cable used 2 run/phase & 1 run for Neutral; Sp. Al Cable 1x300rm XLPE
  • 42. Name : Water Treatment Plant. Capacity : 100 Ton / Hr. Treatment System : Softening system with ACF.(Activated Carbon Filtering) Vessel of Metal : SS 304 L Purpose : For New 4 AMCL Lines.(Dual , Hot, PE & Alu CAN) Features : It has sterilization system by LP steam to bacteria kill. Drive regulated by Inverter.regulated by Inverter. Location : North – West of CAN Building. Electrical Power : 40 KW Steam Consumption : @ 1 Bar, 100kg Origin : CHINA. Output Water parameter: 1. Ph = around 6.5 to 7.5 2. Hardness = 0 to 3 ppm 3. Iron = 0.1 4. Free from Bacteria.
  • 43. Accessories & Required Materials • Row water pump • Chemical dosing device • Dosing tank • Mechanical filter WTP pipe • PLC • Liquid level switch • ACF • Regenerator • Salty water tank • WTP valve • Manual butterfly valve • Cartridge • Conductivity meter • VFD • Control cabinet • Sand • Resin • Activated carbon
  • 44. Name : RO Plant. Capacity : 80 Ton / Hr. Treatment System : RO Filtration. Vessel of Metal : FRP, & 13 Nos. Purpose : For New 4 AMCL Lines. Features : Drive regulated system. Location : Ground Floor of CAN Building. Power : 125 KW MEMBRANE Size : 8” x 40” 2 Pass system. Brand: FILMTECH, USA Filter range: 0.0001 Micron. Total Number: 78 Power : 125 KW Origin : CHINA.
  • 46. Accessories Used for RO Plant • RO unit • High pressure pump • VFD • RO membrane • Pressure meter • Flow meter • Pure water pump • UV sterilizer • Ozone pump • Mixing tower • Asepsis water tank • Ozone generator• Flow meter • Resin valve • Rising device • Rising tank • CIP pump • Pure water tank • Breath filter • Ozone generator • RO pipe & fitting • Flow rate adjusting valve • Single direction valve • Pure water tank
  • 47. Name : Central Air-Conditioning System Capacity: 50 TR System : Vapor Compression system & AHU Using Refrigerant: R-22 Total no of Chiller : 2 Purpose : For New Dual filler room. Location : Roof of New Building. Origin : TICA, China. Cooling Coil Chamber Origin : TICA, China. Pre-filter chamber Bag-Filter Chamber HEFA Filter Chamber
  • 48. CT OF DUAL FILLER NH3 # 2
  • 49. Central BlendingCentral Blending 1. 16 Ton per hour syrup process system for DUAL Filler. 2. 12 Ton per hour juice process system for HOTFILL. 3. 6 Ton per hour juice process system for ALU-CAN. 4. 5 Ton per hour Yogurt process system for PE-Lassi Line.
  • 51. Proper Clean In Place (CIP) & Sanitation Ensure System Sterility CIP Cycle Example:CIP Cycle Example: Hot water (>60Hot water (>60°°°°°°°°C) circulated for 10 minutesC) circulated for 10 minutes Hot caustic, 80Hot caustic, 80°°°°°°°°C circulated for 20 minutes (with an active alkalinity of atC circulated for 20 minutes (with an active alkalinity of at least 2%)least 2%) Rinse 5Rinse 5 -- 10 minutes with Hot water (>6010 minutes with Hot water (>60°°°°°°°°C) waterC) water Hot Acid circulated for 20 minutes (with nitric acid of 0.6Hot Acid circulated for 20 minutes (with nitric acid of 0.6 -- 0.8 % v/v)0.8 % v/v) Rinse 5Rinse 5 -- 10 minutes with Hot water (>6010 minutes with Hot water (>60°°°°°°°°C) waterC) waterRinse 5Rinse 5 -- 10 minutes with Hot water (>6010 minutes with Hot water (>60°°°°°°°°C) waterC) water Rinse 5 minutes with treated waterRinse 5 minutes with treated water Hot sanitation step must be performed prior toHot sanitation step must be performed prior to production startproduction start--upup An chlorinated water or acid sanitizer solutionAn chlorinated water or acid sanitizer solution must be left in the system during downtimemust be left in the system during downtime
  • 52. Merits & DeMerits & De--meritsmerits 1. A good team work. 2. Zero accident up to 5000 working hours. 3. Re-engineering. 4. 12 KM Cable laying by own-team.(Newly joint people) 1. GMP Space no consideration. 2. As per VUCA , need UV or Polishing filter for RO & CO2 delivery line. 3. Materials collection was not a good way.
  • 53. Some Moments. Fig: Support Fig: Unloading. Fig: MeetingFig: M/c Base Fig: Set up Fig:Tank setup Fig: m/c setup Fig: Unloading Fig: Pipe welding Fig: Positioning Fig: Lifting. Fig: Gen Set.