SlideShare a Scribd company logo
1
2
Quality Control (Q.C) – Checks
In QC department there are three sections to check the products staring from
the raw material used to produce the cable and during all various process of
production till the final stage to ensure the quality of the products and they are
confirming to the required specification before it shipped to customer
In Process Test Final Stage TestRaw Material
3
1st Stage – Raw Material Test
•All raw materials are brought into the stores “to be tested” area and placed into
the warehouse for QC to process and test according to materials book & work
instruction for each material. These are then reported on and either accepted or
rejected as below chart explains in detail.
2nd Stage – In Process Test
The purpose of the “In Process Checks” is to maintain production standards
and ensure the compliance of product under manufacture is falling within the
tolerances set out & manufacturing specification
4
Wires Drawing Process
Here following parameters have to be checked during this process to ensure a
quality wires are produced
1. Elongation test for 10 % of the drawn wires
2. Tensile Strength. for 10 % of the drawn wires
3. Wire Diameter for 10 % of the drawn wires
4. Ovality (roundness) for 10 % of the drawn
wires
5
Stranding Process
Here the tests carried out are to check both the actual cross section area of
particular size as specified by standard & customer requirements through.
1. Resistance measurement
2. Weight measuring: One meter sample of the stranded conductor
shall be taken from the end of every drum & weighing for cross
check purpose only.
6
Conductor (CU – AL )
Insulation (PVC – XLPE )
Metal Sheath ( Lead Alloy)
Inner Covering (PVC – XLPE)
Armoring
Outer Sheath (PVC – PE)
Insulation
Here a number of tests are carried out to measure the compliance of a
conductor’s insulation,
(1) Insulation thickness
(2) Spark Test
(3) Colour of Insulation
(4) Hot Set test for XLPE insulation
8
Conductor (CU – AL )
Insulation Tipple layer (XLPE )
Outer Sheath (PVC – PE)
Inner Covering (PVC – XLPE)
Copper Screen
Armouring
9
Medium Voltage (MV) & High Voltage (HV) Insulation
(1) Insulation Thickness
(2) Hot Set test
(3) Measuring the eccentricity of the insulation
(4) Measuring the Strippability of the insulation screen (for MV cables
only)
(2.5) check the transparent of the insulation (not required by the
standard)
Here a number of tests are carried out to measure the compliance of a
conductor’s insulation,
Insulation
Cu Tape
Screened Cable
11
there are two types of screening
(1) Copper Tape – thickness of tape and the % overlap of the tape
after being wound onto the cable.
(2) Copper Wire – actual number of wires and the diameter of
each copper strand
Screening
12
Assembling
here are again a number of tests carried out to measure the
following
1) Overall physical diameter of assembled cable
2) Assembling Lay length of the cores
3) Filler (Polypropylene) – area of the filler
Inner Sheath
This is to measure the physical dimensions of a cut sample taken from
a manufactured cable, prior to final acceptance.
1. The thickness of the inner sheath
Armouring
This deals with the physical (mechanical) protection of the cables, this is done
in three different methods. Here the physical properties of the armouring are
tested.
1. Steel Wire – actual number of strands of the wires armour and wires
diameter
2. Steel Tape – the physical thickness of the tape and % overlap of tape
3. Aluminium Wire – actual number of strands of the wire armour and diameter
of wire
Final Sheathing
Here the physical properties are measured to check compliance
1. Thickness of outer sheath
2. Cable marking (Embossing) or printing
3. Spark test (e.g. for every 1mm thickness, this relates to a 6kV
electrical charge)
4. Colour of outer sheath
5. Length marking – stamped physically onto every 1 meter of length
sequentially
*Hot Set test
This is a test comprising of the following procedure, to test the cross
linkable (or curing) properties of the XLPE insulation,
1. A sample is cut from cable under test
2. The insulation is then stripped from the cable (XLP part)
3. Shaved down into a set thickness (i.e. 0.8 – 1.7 mm thickness)
4. A “dumbbell” sample is stamped out for further testing.
5. Then a standard measured distance of 20 mm is marked off
6. When the total surface area is calculated and weight of 20N/cm2 is
selected
7. Then weighted load is attached to the sample and then placed in an
oven at 200’C for fifteen (15) minutes
8. Then the elongation (stretched) is measured and the elongation
percentage calculated a maximum of 175% is the maximum is allowed.
Note: For easy & fast procedures of performing the hot set test, loads for
all expecting thickness were calculated and prepared as weights pieces &
kept ready for using for this test as follows:
9.807Newton = 1000 g
1.000 Newton = 101.98 g
0.640 Newton = 65.26 g
CALCULATION OF LOAD FOR DUMBBELL TEST PIECES
Specified mechanical stress = 20 N/cm² according to
IEC 60811-2-1 clause 9 Width of the specimen = 4.0
Load
(Totally) (GR)
Actual Mechanical Stress
(Newton)
Area
(cm²)
Thickness
(mm)
Stress x 101.98 Area x 20 Thick. x Width Given
65.27 0.64 0.032 0.80
69.35 0.68 0.034 0.85
73.43 0.72 0.036 0.90
77.51 0.76 0.038 0.95
81.59 0.80 0.040 1.00
85.67 0.84 0.042 1.05
89.75 0.88 0.044 1.10
93.83 0.92 0.046 1.15
97.91 0.96 0.048 1.20
101.99 1.00 0.050 1.25
106.07 1.04 0.052 1.30
110.15 1.08 0.054 1.35
114.23 1.12 0.056 1.40
118.31 1.16 0.058 1.45
122.39 1.20 0.060 1.50
126.47 1.24 0.062 1.55
130.54 1.28 0.064 1.60
134.62 1.32 0.066 1.65
Size of Core
(mm²)
Outer Dia. of
Piece (mm)
(D)
Thick. of
Insulation
(mm)
Area of Cross
Section (mm²)
Area (cm²) (A) Actual Mech.
Stress (N)
Total
Load
(g)
1.5 2.96 0.70 4.97 0.0497 0.994 101.36
2.5 3.41 0.70 5.96 0.0596 1.192 121.55
4.0 3.95 0.70 7.14 0.0714 1.428 145.70
6.0 4.52 0.70 8.396 0.0840 1.68 171.30
Table # 2
CALCULATION OF LOAD FOR TUBULAR TEST PIECES
 
VOLTAGE TEST
PARTIAL DISCHARGE (FOR MV/HV CABLES)
CONDUCTOR RESISTANCE
TAN δ MEASUREMENT (FOR HV CABLES
MADE IN
EGYPT
18
3rd
Stage – Final test
19
)A) High Voltage Test 3500Volts )3.5kV) for 5 minutes
A voltage of 3500 volts is passed between a single conductor and the
neutral (or earth), for a period of 5 minutes respectively. A voltage of 6.2kV
is also passed between the phases to test the insulation between the
different phases respectively.
Low Voltage Cables
20
If this process of testing the individual core are successful passed and
there are no indication of any breakdown then the cable proceed to the
next test, which is
(B) Measuring the Conductors Resistance:
The conductor resistance of each cutting length on drum shall be
measured to verify the length of the cable as well as
1. HV test 3.5Uo voltage test is applied between the conductor & metallic
screen of each core for 5 minutes
2. Conductor resistance measurement (same as explained in LV cables)
3. Partial Discharge Test (PD test)
)B) Medium Voltage Cables
Partial Discharge test
The partial discharge phenomenon is known as a partial breakdown of
insulation. There are three type of PD which are:
1. Internal PD
2. Voids PD
3. Surface PD
The partial discharge is leakage charges from the conductor to the earth
through weak point in the insulation such as Voids, Contaminations in the
insulation, cavities in insulation or surface damage.
The purpose the PD test is to test if the minutist particles or voids are present
inside the XLPE insulation. This process is to measure the leakage of the
charge (Q) from the conductor to the metallic screen, through these weak
points. This test is measured in Pico-Column; the international standard is
anything ≤10 pC (10-12
Columns)
Conductor Insulation Insulation’s Screen
Prepared cable end length
C=
dt
dQ
Q = Charge t = time
For testing MV or HV cables electrically, cable terminals must be prepared as
shown in the above figure.
U is referred to any one of the following terms:
1.Line Voltage
2.Line to Line Voltage
3.Phase to Phase Voltage
U0 is referred to any one of the following terms:
1. Phase Voltage
2. Phase to neutral Voltage
3. Line to neutral Voltage
Voltage test for MV cables is 3.5 x U0, of the subject cables rated voltage
For example an 11kV cable, this means that U of this cable is 11kV,
therefore the U0
for this cable is:
3
11kV
=6.35kV
Thus the test voltage is 3.5x 6.35kV = 22kV test voltage rating to be applied for
5 minutes
S U M M A R Y
QUALITY CONTROL CHECKQUALITY CONTROL CHECK
PointPoint
IN-PROCESS PRODUCTIN-PROCESS PRODUCTIN-PROCESS PRODUCTIN-PROCESS PRODUCT
COPPER & ALUMINIUM WIRE DRAWINGCOPPER & ALUMINIUM WIRE DRAWING
 CONDUCTOR STRANDINGCONDUCTOR STRANDING
 INSULATION PROCESSINSULATION PROCESS
ELECTRICAL SCREENELECTRICAL SCREEN
 LAYING UP (ASSEMBLING)LAYING UP (ASSEMBLING)
FILLINGFILLING
ARMOURINGARMOURING
 OUTER SHEATHOUTER SHEATH
IN-PROCESS PRODUCT TESTIN-PROCESS PRODUCT TESTIN-PROCESS PRODUCT TESTIN-PROCESS PRODUCT TEST
SURFACE ( VISUAL )SURFACE ( VISUAL )
 DIMENSIONDIMENSION
 TENSILE STRENGTHTENSILE STRENGTH
 ELONGATIONELONGATION
 SPARK TEST ON INSULATION LINESPARK TEST ON INSULATION LINE
 HOT SET FOR XLPE INSULATIONHOT SET FOR XLPE INSULATION
 CABLE MARKINGCABLE MARKING
 PARTIAL DISCHARGEPARTIAL DISCHARGE
))For screened Cores of MV / HV CableFor screened Cores of MV / HV Cable
Function/Function/
DeptDept..
ProcessProcess ProcedureProcedure
Tech. Dept./ Prod.
Planning Dept.
According to spec. identified through
sales (contract review).
QC Engineer
Issue plan to QC supervisor/ Inspector.
QC Supervisor
For each manufacturing stage (as per
inspection & test plan).
Production
Supervisor
QC Inspector Attach tag to indicate status.
QC supervisor/
Inspector
- Sample frequency as specified in
In-Process Inspection.
- Continuous feedback about the trend
of the result to the operator.
QC Supervisor/
Inspector
- Identify rejected products as per
nonconformity procedure.
- Identify the accepted product.
QC Engineer
Quality Trends to be reviewed and
published in MRM and action plan to
be established to reduce
nonconformities.
IN-PROCESS INSPECTION & TESTINGIN-PROCESS INSPECTION & TESTING
CABLE FINAL TESTINGCABLE FINAL TESTING
11..ROUTINE TESTROUTINE TEST
Tests made on every finished length of cable or during
manufacture to ensure compliance with construction requirements
and demonstrate the integrity of the cable.
• Sampling criteria : 100 % of finished product
Tests made on samples of cable to represent production batches
and provide a periodic check on manufacturing consistency.
• Sampling criteria: 10% of total quantity order as per IEC 60502.
22..SAMPLE TESTSAMPLE TEST
33..TYPE TESTTYPE TEST
Tests made during the development of a new grade of cable design to
establish performance characteristics.
• Sampling criteria: 1 sample of new design product.
FINISHED PRODUCT ROUTNEFINISHED PRODUCT ROUTNE
TEST (100% TESTTEST (100% TEST((
FINISHED PRODUCT ROUTNEFINISHED PRODUCT ROUTNE
TEST (100% TESTTEST (100% TEST((
VISUAL INSPECTION OF CABLES DRUMSVISUAL INSPECTION OF CABLES DRUMS
CONDUCTOR RESISTANCECONDUCTOR RESISTANCE
 VOLTAGE TESTVOLTAGE TEST
 PARTIAL DISCHARGE FOR MV & HVPARTIAL DISCHARGE FOR MV & HV
CABLESCABLES
INSULATION RESISTANCE (IF REQUIRED)INSULATION RESISTANCE (IF REQUIRED)
TAN δ FOR HV CABLES (10 % OF CUTTINGTAN δ FOR HV CABLES (10 % OF CUTTING
LENGTH)LENGTH)
Function/Function/
Dept.Dept.
ProcessProcess ProcedureProcedure
QC Inspector
From production Department
Check cable marking/
embossing
According to applicable Test
instructions
According to work order no.
QC Lab Non- electrical tests.
QC Engineer Stamp
"Passed QC"
QC Manager
To be reviewed and published
in MRM
FINAL INSPECTION & TESTINGFINAL INSPECTION & TESTING
QUALITY CONTROL DEPARTMENT
QUALITY OBJECTIVEES (1)
Date of setting: 01-03-2006
Date of implementation: 9/03/2006
1)CONDUCTOR RESISTANCE:
A. COPPER CONDUCTORS:
•From 1.5 mm² to 6 mm² -1.5 % + 0.0% from the maximum
specified value
•From 10 mm² to 35 mm² -1.0 % + 0.0% from the maximum
specified value
•From 50 mm² to 630 mm² -0.8 % + 0.0% from the maximum
specified value
B. ALUMINUM CONDUCTORS:
•From 10 mm² to 35.0 mm² -1.50% + 0.0% from the
maximum specified value
•From 50 mm² to 630 mm² -1.00% + 0.0% from the
maximum specified value
2(INSULATION:
A( XLPE Insulation:
•From 0.0 mm to 1.0 mm, maximum allowed +8.0% from the
average required
•From 1.1 mm to 1.5 mm, maximum allowed +6.0% from the
average required
•From 1.6 mm to 2.5 mm, maximum allowed +5.0% from the
average required
•More than 2.50 mm, maximum allowed +4.0% from the
average required
B( NYA & Flex Insulation:
• From 1.5 to 16 MM² conductor sizes, maximum insulation thickness allowed
is +6% from the average required
• From 25 to 70 MM² conductor sizes, maximum insulation thickness allowed is
+5% from the average required
3(INNER SHEATH
Only the minimum value has to be achieved & the maximum value shall be
95% of the nominal value.
Unless otherwise for some special specification or agreement between the El
Sewedy & customer to achieve both value (average & minimum), so in this
case the maximum allowed value should be +6 % from the average required
4(OUTER SHEATH
A( Sheath over Armouring or Direct sheath:
Only the minimum value is required to be achieved & the maximum value
shall be 95% of the nominal one.
B. Sheath over smooth surface or sheath for flex cables:
The maximum allowed value should be +8.0 % from the average required
5(CCV LINE (MV & HV Cables(
Conductor screen: The maximum thickness allowed +10 % from the
average required
Insulation screen: The maximum thickness allowed +3 % from the
average required
Insulation: The maximum thickness allowed +4 % from the average
required
InsulationInsulationInsulationInsulation AssemblyAssemblyAssemblyAssembly Inner sheathingInner sheathingInner sheathingInner sheathing
StrandingStrandingStrandingStranding
DrawingDrawingDrawingDrawing
Lead SheathingLead SheathingLead SheathingLead Sheathing ArmouringArmouringArmouringArmouring
Outer SheathingOuter SheathingOuter SheathingOuter Sheathing
34
- CABLE COST
90 % MATERIAL COST
10% PRODUCTION COST
- MATERIAL COST
MATERIAL PRICE
MATERIAL CONSUMPTION
- MATERIAL PRICE
REDUCE
CABLE COST
REDUCE
CABLE COST
How you can reduce the Material Price?
Look always for additional supplier.
Replace the actual material with a cheaper solution
MATERIAL CONSUMPTION
IN PRODUCTION
IN DESIGN DEPARTMENT
IN PRODUCTION:
MATERIAL OVERUSAGE
* Look for the tolerance –range for each production step, also for different
machine. (Quality Department). If the tolerance-range is too high, look for
the reason (bad material, old machine, bad measurement-equipment…
and
“make it better”
* Reduce set-up-length
* It will be helpful, that all necessary process data are written down for the
personal at the machine.
* Reduce scrap.
IN DESIGN DEPARTMENT:
* Design department is one of the important departments to influence the
cable cost.
*The design engineer must create cheapest cable design solution in
accordance with the customer specification.
* Look for “gaps” in the specification, it means, what is not required in the
specification.
During our 2 weeks discussion with many colleagues from
Production, quality, technical, planning and financial,
We found many points you can change it.
80% of your orders are with 8 Types:
The last 2 days we have made a cable re-design with the designer colleagues in
accordance the new points, Also 2 offers for 220 kV-cables.
1) Reduce nominal thickness for inner and outer semiconductor layer.
2) Change the copper tape screening from 1 tape to 2 tapes.
3)Reduce the filler material in 3-core-cable with round conductor.
4)Fix the assembled cores with a tape as open helix.
5)In many specifications there is no average thickness required for bedding,
separation sheath. Therefore reduce the thickness.
6) Indicate in design sheet the different value: Nominal, Minimum, Average &
Practical Value.
7) Copper wire screen in mostly cheaper than copper tape screen.
8) Produce conductor for XLPE cable =10 kV only with dies.
9) Remove all fillers in 1 kV sector conductor – cables.
10) Reduce master batch colour in 1 kV cable with skin insulation
11)Manufacturing insulation for 1kV cable only in tube extrusion.
12) Try to use for 1kV cable as bedding a tape (instead extruded bedding).
13) Flat wire armouring is less in cost than round wire armouring. Check to
improve your armouring machine for flat wire.
14) Check your PVC- compound to increase the filler
It is really a great pleasure for me to work together with the very
friendly and well experience people in EL SEWEDY CABLES
THANKS
Eng’r. Mohsen Al Tandi
Quality Control Manager
Arab Cables Company

More Related Content

What's hot

Quality control and inspection
Quality control and inspectionQuality control and inspection
Quality control and inspection
Samiksha Sawant
 
Quality awareness
Quality awarenessQuality awareness
Quality awareness
smcci
 
Quiz on World Quality Day - 2017
Quiz on World Quality Day - 2017Quiz on World Quality Day - 2017
Quiz on World Quality Day - 2017
TCB Knowledge Factory
 
Seven QC Tools Training; Quiz
Seven QC Tools Training; QuizSeven QC Tools Training; Quiz
Seven QC Tools Training; Quiz
Shakehand with Life
 
The new ISO 9001:2015
The new ISO 9001:2015The new ISO 9001:2015
The new ISO 9001:2015
Reza Seifollahy
 
Problem solving thru qc circle (1)
Problem solving thru qc circle (1)Problem solving thru qc circle (1)
Problem solving thru qc circle (1)
Jitesh Gaurav
 
Instrumentation cables rev2
Instrumentation cables rev2Instrumentation cables rev2
Instrumentation cables rev2
GSS Srinivas
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Gensol Engineering Limited
 
Cost of-poor-quality - juran institute
Cost of-poor-quality - juran instituteCost of-poor-quality - juran institute
Cost of-poor-quality - juran institute
Manish Chaurasia
 
WHAT IS QUALITY | INTRODUCTION TO QUALITY | SETH SAFETY PRODUCTS.
WHAT IS QUALITY | INTRODUCTION TO QUALITY | SETH SAFETY PRODUCTS.WHAT IS QUALITY | INTRODUCTION TO QUALITY | SETH SAFETY PRODUCTS.
WHAT IS QUALITY | INTRODUCTION TO QUALITY | SETH SAFETY PRODUCTS.
Seth Medical and Safety Products (Pvt) Limited.
 
Iqc incoming quality control
Iqc incoming quality controlIqc incoming quality control
Iqc incoming quality control
AshutoshKumar1262
 
Quality definition
Quality  definitionQuality  definition
Quality definitionMohit Singla
 
Iatf 16949 training
Iatf 16949 trainingIatf 16949 training
Iatf 16949 training
dishashah4993
 
Quality control
Quality controlQuality control
Quality control
Nitin Shekapure
 
Piping sample report
Piping sample reportPiping sample report
Piping sample reportram111eg
 

What's hot (20)

C&I Cables Tests
C&I Cables TestsC&I Cables Tests
C&I Cables Tests
 
Quality control and inspection
Quality control and inspectionQuality control and inspection
Quality control and inspection
 
Cable
CableCable
Cable
 
Quality awareness
Quality awarenessQuality awareness
Quality awareness
 
Quiz on World Quality Day - 2017
Quiz on World Quality Day - 2017Quiz on World Quality Day - 2017
Quiz on World Quality Day - 2017
 
Quality Awareness Training
Quality Awareness TrainingQuality Awareness Training
Quality Awareness Training
 
Seven QC Tools Training; Quiz
Seven QC Tools Training; QuizSeven QC Tools Training; Quiz
Seven QC Tools Training; Quiz
 
The new ISO 9001:2015
The new ISO 9001:2015The new ISO 9001:2015
The new ISO 9001:2015
 
Problem solving thru qc circle (1)
Problem solving thru qc circle (1)Problem solving thru qc circle (1)
Problem solving thru qc circle (1)
 
Instrumentation cables rev2
Instrumentation cables rev2Instrumentation cables rev2
Instrumentation cables rev2
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
 
Cost of-poor-quality - juran institute
Cost of-poor-quality - juran instituteCost of-poor-quality - juran institute
Cost of-poor-quality - juran institute
 
WHAT IS QUALITY | INTRODUCTION TO QUALITY | SETH SAFETY PRODUCTS.
WHAT IS QUALITY | INTRODUCTION TO QUALITY | SETH SAFETY PRODUCTS.WHAT IS QUALITY | INTRODUCTION TO QUALITY | SETH SAFETY PRODUCTS.
WHAT IS QUALITY | INTRODUCTION TO QUALITY | SETH SAFETY PRODUCTS.
 
Iqc incoming quality control
Iqc incoming quality controlIqc incoming quality control
Iqc incoming quality control
 
Quality definition
Quality  definitionQuality  definition
Quality definition
 
Iatf 16949 training
Iatf 16949 trainingIatf 16949 training
Iatf 16949 training
 
Quality control
Quality controlQuality control
Quality control
 
Piping sample report
Piping sample reportPiping sample report
Piping sample report
 
Shell rolling procedure
Shell rolling procedureShell rolling procedure
Shell rolling procedure
 
Instrumentation Cable
Instrumentation CableInstrumentation Cable
Instrumentation Cable
 

Similar to Quality control (training course)

Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
Novia Putri
 
Module 6part1
Module 6part1Module 6part1
Module 6part1
Asha Anu Kurian
 
Craig Woolhouse - The Use of Pulsed DC Holiday Detectors for Field Testing Pi...
Craig Woolhouse - The Use of Pulsed DC Holiday Detectors for Field Testing Pi...Craig Woolhouse - The Use of Pulsed DC Holiday Detectors for Field Testing Pi...
Craig Woolhouse - The Use of Pulsed DC Holiday Detectors for Field Testing Pi...Ramy Saboungui
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
Nihal Shiroya
 
FESI Forth Road Bridge - Where Are We Today - P Roffey
FESI Forth Road Bridge - Where Are We Today - P RoffeyFESI Forth Road Bridge - Where Are We Today - P Roffey
FESI Forth Road Bridge - Where Are We Today - P RoffeyPaul Roffey
 
TENSILE TEST REPORT
TENSILE TEST REPORTTENSILE TEST REPORT
TENSILE TEST REPORT
musadoto
 
Electrical testing
Electrical testingElectrical testing
Electrical testing
Aarjun Singh Panesar
 
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Thorne & Derrick International
 
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Thorne & Derrick International
 
FAMECA Transmission Earthing Devices
FAMECA Transmission Earthing Devices FAMECA Transmission Earthing Devices
FAMECA Transmission Earthing Devices
Al Buraq Hardware & Tools L.L.C
 
Ellis Patents Cable Cleats Guide - Black Book
Ellis Patents Cable Cleats Guide - Black BookEllis Patents Cable Cleats Guide - Black Book
Ellis Patents Cable Cleats Guide - Black Book
Thorne & Derrick International
 
H046044147
H046044147H046044147
H046044147
IJERA Editor
 
Shorted Casing Study - Tim Sievert
Shorted Casing Study - Tim SievertShorted Casing Study - Tim Sievert
Shorted Casing Study - Tim Sievert
nacetwincities
 
ABB Low Voltage (LV) Bushings for Pad Mounted Distribution Transformers 600V
ABB Low Voltage (LV) Bushings for Pad Mounted Distribution Transformers 600VABB Low Voltage (LV) Bushings for Pad Mounted Distribution Transformers 600V
ABB Low Voltage (LV) Bushings for Pad Mounted Distribution Transformers 600V
Thorne & Derrick International
 
Impedance measurements
Impedance measurements Impedance measurements
Impedance measurements
justkabe
 
Four probe Method.pptx
Four probe Method.pptxFour probe Method.pptx
Four probe Method.pptx
JatinMahato1
 
pdfslide.net_iec-61439pptx.pptx
pdfslide.net_iec-61439pptx.pptxpdfslide.net_iec-61439pptx.pptx
pdfslide.net_iec-61439pptx.pptx
jiguparmar
 
1448442717.8628chap 4 ce 212
1448442717.8628chap 4 ce 2121448442717.8628chap 4 ce 212
1448442717.8628chap 4 ce 212
Jagajyoti Panda
 

Similar to Quality control (training course) (20)

Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
Testing
TestingTesting
Testing
 
Module 6part1
Module 6part1Module 6part1
Module 6part1
 
Craig Woolhouse - The Use of Pulsed DC Holiday Detectors for Field Testing Pi...
Craig Woolhouse - The Use of Pulsed DC Holiday Detectors for Field Testing Pi...Craig Woolhouse - The Use of Pulsed DC Holiday Detectors for Field Testing Pi...
Craig Woolhouse - The Use of Pulsed DC Holiday Detectors for Field Testing Pi...
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
 
FESI Forth Road Bridge - Where Are We Today - P Roffey
FESI Forth Road Bridge - Where Are We Today - P RoffeyFESI Forth Road Bridge - Where Are We Today - P Roffey
FESI Forth Road Bridge - Where Are We Today - P Roffey
 
TENSILE TEST REPORT
TENSILE TEST REPORTTENSILE TEST REPORT
TENSILE TEST REPORT
 
Electrical testing
Electrical testingElectrical testing
Electrical testing
 
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
 
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
 
FAMECA Transmission Earthing Devices
FAMECA Transmission Earthing Devices FAMECA Transmission Earthing Devices
FAMECA Transmission Earthing Devices
 
Ellis Patents Cable Cleats Guide - Black Book
Ellis Patents Cable Cleats Guide - Black BookEllis Patents Cable Cleats Guide - Black Book
Ellis Patents Cable Cleats Guide - Black Book
 
H046044147
H046044147H046044147
H046044147
 
Shorted Casing Study - Tim Sievert
Shorted Casing Study - Tim SievertShorted Casing Study - Tim Sievert
Shorted Casing Study - Tim Sievert
 
ABB Low Voltage (LV) Bushings for Pad Mounted Distribution Transformers 600V
ABB Low Voltage (LV) Bushings for Pad Mounted Distribution Transformers 600VABB Low Voltage (LV) Bushings for Pad Mounted Distribution Transformers 600V
ABB Low Voltage (LV) Bushings for Pad Mounted Distribution Transformers 600V
 
Impedance measurements
Impedance measurements Impedance measurements
Impedance measurements
 
Lightning arresters
Lightning arrestersLightning arresters
Lightning arresters
 
Four probe Method.pptx
Four probe Method.pptxFour probe Method.pptx
Four probe Method.pptx
 
pdfslide.net_iec-61439pptx.pptx
pdfslide.net_iec-61439pptx.pptxpdfslide.net_iec-61439pptx.pptx
pdfslide.net_iec-61439pptx.pptx
 
1448442717.8628chap 4 ce 212
1448442717.8628chap 4 ce 2121448442717.8628chap 4 ce 212
1448442717.8628chap 4 ce 212
 

Recently uploaded

SAR of Medicinal Chemistry 1st by dk.pdf
SAR of Medicinal Chemistry 1st by dk.pdfSAR of Medicinal Chemistry 1st by dk.pdf
SAR of Medicinal Chemistry 1st by dk.pdf
KrushnaDarade1
 
如何办理(uvic毕业证书)维多利亚大学毕业证本科学位证书原版一模一样
如何办理(uvic毕业证书)维多利亚大学毕业证本科学位证书原版一模一样如何办理(uvic毕业证书)维多利亚大学毕业证本科学位证书原版一模一样
如何办理(uvic毕业证书)维多利亚大学毕业证本科学位证书原版一模一样
yqqaatn0
 
What is greenhouse gasses and how many gasses are there to affect the Earth.
What is greenhouse gasses and how many gasses are there to affect the Earth.What is greenhouse gasses and how many gasses are there to affect the Earth.
What is greenhouse gasses and how many gasses are there to affect the Earth.
moosaasad1975
 
Chapter 12 - climate change and the energy crisis
Chapter 12 - climate change and the energy crisisChapter 12 - climate change and the energy crisis
Chapter 12 - climate change and the energy crisis
tonzsalvador2222
 
ESR spectroscopy in liquid food and beverages.pptx
ESR spectroscopy in liquid food and beverages.pptxESR spectroscopy in liquid food and beverages.pptx
ESR spectroscopy in liquid food and beverages.pptx
PRIYANKA PATEL
 
NuGOweek 2024 Ghent programme overview flyer
NuGOweek 2024 Ghent programme overview flyerNuGOweek 2024 Ghent programme overview flyer
NuGOweek 2024 Ghent programme overview flyer
pablovgd
 
In silico drugs analogue design: novobiocin analogues.pptx
In silico drugs analogue design: novobiocin analogues.pptxIn silico drugs analogue design: novobiocin analogues.pptx
In silico drugs analogue design: novobiocin analogues.pptx
AlaminAfendy1
 
ANAMOLOUS SECONDARY GROWTH IN DICOT ROOTS.pptx
ANAMOLOUS SECONDARY GROWTH IN DICOT ROOTS.pptxANAMOLOUS SECONDARY GROWTH IN DICOT ROOTS.pptx
ANAMOLOUS SECONDARY GROWTH IN DICOT ROOTS.pptx
RASHMI M G
 
Remote Sensing and Computational, Evolutionary, Supercomputing, and Intellige...
Remote Sensing and Computational, Evolutionary, Supercomputing, and Intellige...Remote Sensing and Computational, Evolutionary, Supercomputing, and Intellige...
Remote Sensing and Computational, Evolutionary, Supercomputing, and Intellige...
University of Maribor
 
原版制作(carleton毕业证书)卡尔顿大学毕业证硕士文凭原版一模一样
原版制作(carleton毕业证书)卡尔顿大学毕业证硕士文凭原版一模一样原版制作(carleton毕业证书)卡尔顿大学毕业证硕士文凭原版一模一样
原版制作(carleton毕业证书)卡尔顿大学毕业证硕士文凭原版一模一样
yqqaatn0
 
Shallowest Oil Discovery of Turkiye.pptx
Shallowest Oil Discovery of Turkiye.pptxShallowest Oil Discovery of Turkiye.pptx
Shallowest Oil Discovery of Turkiye.pptx
Gokturk Mehmet Dilci
 
ISI 2024: Application Form (Extended), Exam Date (Out), Eligibility
ISI 2024: Application Form (Extended), Exam Date (Out), EligibilityISI 2024: Application Form (Extended), Exam Date (Out), Eligibility
ISI 2024: Application Form (Extended), Exam Date (Out), Eligibility
SciAstra
 
Deep Software Variability and Frictionless Reproducibility
Deep Software Variability and Frictionless ReproducibilityDeep Software Variability and Frictionless Reproducibility
Deep Software Variability and Frictionless Reproducibility
University of Rennes, INSA Rennes, Inria/IRISA, CNRS
 
platelets_clotting_biogenesis.clot retractionpptx
platelets_clotting_biogenesis.clot retractionpptxplatelets_clotting_biogenesis.clot retractionpptx
platelets_clotting_biogenesis.clot retractionpptx
muralinath2
 
Observation of Io’s Resurfacing via Plume Deposition Using Ground-based Adapt...
Observation of Io’s Resurfacing via Plume Deposition Using Ground-based Adapt...Observation of Io’s Resurfacing via Plume Deposition Using Ground-based Adapt...
Observation of Io’s Resurfacing via Plume Deposition Using Ground-based Adapt...
Sérgio Sacani
 
PRESENTATION ABOUT PRINCIPLE OF COSMATIC EVALUATION
PRESENTATION ABOUT PRINCIPLE OF COSMATIC EVALUATIONPRESENTATION ABOUT PRINCIPLE OF COSMATIC EVALUATION
PRESENTATION ABOUT PRINCIPLE OF COSMATIC EVALUATION
ChetanK57
 
Earliest Galaxies in the JADES Origins Field: Luminosity Function and Cosmic ...
Earliest Galaxies in the JADES Origins Field: Luminosity Function and Cosmic ...Earliest Galaxies in the JADES Origins Field: Luminosity Function and Cosmic ...
Earliest Galaxies in the JADES Origins Field: Luminosity Function and Cosmic ...
Sérgio Sacani
 
Toxic effects of heavy metals : Lead and Arsenic
Toxic effects of heavy metals : Lead and ArsenicToxic effects of heavy metals : Lead and Arsenic
Toxic effects of heavy metals : Lead and Arsenic
sanjana502982
 
bordetella pertussis.................................ppt
bordetella pertussis.................................pptbordetella pertussis.................................ppt
bordetella pertussis.................................ppt
kejapriya1
 
Introduction to Mean Field Theory(MFT).pptx
Introduction to Mean Field Theory(MFT).pptxIntroduction to Mean Field Theory(MFT).pptx
Introduction to Mean Field Theory(MFT).pptx
zeex60
 

Recently uploaded (20)

SAR of Medicinal Chemistry 1st by dk.pdf
SAR of Medicinal Chemistry 1st by dk.pdfSAR of Medicinal Chemistry 1st by dk.pdf
SAR of Medicinal Chemistry 1st by dk.pdf
 
如何办理(uvic毕业证书)维多利亚大学毕业证本科学位证书原版一模一样
如何办理(uvic毕业证书)维多利亚大学毕业证本科学位证书原版一模一样如何办理(uvic毕业证书)维多利亚大学毕业证本科学位证书原版一模一样
如何办理(uvic毕业证书)维多利亚大学毕业证本科学位证书原版一模一样
 
What is greenhouse gasses and how many gasses are there to affect the Earth.
What is greenhouse gasses and how many gasses are there to affect the Earth.What is greenhouse gasses and how many gasses are there to affect the Earth.
What is greenhouse gasses and how many gasses are there to affect the Earth.
 
Chapter 12 - climate change and the energy crisis
Chapter 12 - climate change and the energy crisisChapter 12 - climate change and the energy crisis
Chapter 12 - climate change and the energy crisis
 
ESR spectroscopy in liquid food and beverages.pptx
ESR spectroscopy in liquid food and beverages.pptxESR spectroscopy in liquid food and beverages.pptx
ESR spectroscopy in liquid food and beverages.pptx
 
NuGOweek 2024 Ghent programme overview flyer
NuGOweek 2024 Ghent programme overview flyerNuGOweek 2024 Ghent programme overview flyer
NuGOweek 2024 Ghent programme overview flyer
 
In silico drugs analogue design: novobiocin analogues.pptx
In silico drugs analogue design: novobiocin analogues.pptxIn silico drugs analogue design: novobiocin analogues.pptx
In silico drugs analogue design: novobiocin analogues.pptx
 
ANAMOLOUS SECONDARY GROWTH IN DICOT ROOTS.pptx
ANAMOLOUS SECONDARY GROWTH IN DICOT ROOTS.pptxANAMOLOUS SECONDARY GROWTH IN DICOT ROOTS.pptx
ANAMOLOUS SECONDARY GROWTH IN DICOT ROOTS.pptx
 
Remote Sensing and Computational, Evolutionary, Supercomputing, and Intellige...
Remote Sensing and Computational, Evolutionary, Supercomputing, and Intellige...Remote Sensing and Computational, Evolutionary, Supercomputing, and Intellige...
Remote Sensing and Computational, Evolutionary, Supercomputing, and Intellige...
 
原版制作(carleton毕业证书)卡尔顿大学毕业证硕士文凭原版一模一样
原版制作(carleton毕业证书)卡尔顿大学毕业证硕士文凭原版一模一样原版制作(carleton毕业证书)卡尔顿大学毕业证硕士文凭原版一模一样
原版制作(carleton毕业证书)卡尔顿大学毕业证硕士文凭原版一模一样
 
Shallowest Oil Discovery of Turkiye.pptx
Shallowest Oil Discovery of Turkiye.pptxShallowest Oil Discovery of Turkiye.pptx
Shallowest Oil Discovery of Turkiye.pptx
 
ISI 2024: Application Form (Extended), Exam Date (Out), Eligibility
ISI 2024: Application Form (Extended), Exam Date (Out), EligibilityISI 2024: Application Form (Extended), Exam Date (Out), Eligibility
ISI 2024: Application Form (Extended), Exam Date (Out), Eligibility
 
Deep Software Variability and Frictionless Reproducibility
Deep Software Variability and Frictionless ReproducibilityDeep Software Variability and Frictionless Reproducibility
Deep Software Variability and Frictionless Reproducibility
 
platelets_clotting_biogenesis.clot retractionpptx
platelets_clotting_biogenesis.clot retractionpptxplatelets_clotting_biogenesis.clot retractionpptx
platelets_clotting_biogenesis.clot retractionpptx
 
Observation of Io’s Resurfacing via Plume Deposition Using Ground-based Adapt...
Observation of Io’s Resurfacing via Plume Deposition Using Ground-based Adapt...Observation of Io’s Resurfacing via Plume Deposition Using Ground-based Adapt...
Observation of Io’s Resurfacing via Plume Deposition Using Ground-based Adapt...
 
PRESENTATION ABOUT PRINCIPLE OF COSMATIC EVALUATION
PRESENTATION ABOUT PRINCIPLE OF COSMATIC EVALUATIONPRESENTATION ABOUT PRINCIPLE OF COSMATIC EVALUATION
PRESENTATION ABOUT PRINCIPLE OF COSMATIC EVALUATION
 
Earliest Galaxies in the JADES Origins Field: Luminosity Function and Cosmic ...
Earliest Galaxies in the JADES Origins Field: Luminosity Function and Cosmic ...Earliest Galaxies in the JADES Origins Field: Luminosity Function and Cosmic ...
Earliest Galaxies in the JADES Origins Field: Luminosity Function and Cosmic ...
 
Toxic effects of heavy metals : Lead and Arsenic
Toxic effects of heavy metals : Lead and ArsenicToxic effects of heavy metals : Lead and Arsenic
Toxic effects of heavy metals : Lead and Arsenic
 
bordetella pertussis.................................ppt
bordetella pertussis.................................pptbordetella pertussis.................................ppt
bordetella pertussis.................................ppt
 
Introduction to Mean Field Theory(MFT).pptx
Introduction to Mean Field Theory(MFT).pptxIntroduction to Mean Field Theory(MFT).pptx
Introduction to Mean Field Theory(MFT).pptx
 

Quality control (training course)

  • 1. 1
  • 2. 2 Quality Control (Q.C) – Checks In QC department there are three sections to check the products staring from the raw material used to produce the cable and during all various process of production till the final stage to ensure the quality of the products and they are confirming to the required specification before it shipped to customer In Process Test Final Stage TestRaw Material
  • 3. 3 1st Stage – Raw Material Test •All raw materials are brought into the stores “to be tested” area and placed into the warehouse for QC to process and test according to materials book & work instruction for each material. These are then reported on and either accepted or rejected as below chart explains in detail. 2nd Stage – In Process Test The purpose of the “In Process Checks” is to maintain production standards and ensure the compliance of product under manufacture is falling within the tolerances set out & manufacturing specification
  • 4. 4 Wires Drawing Process Here following parameters have to be checked during this process to ensure a quality wires are produced 1. Elongation test for 10 % of the drawn wires 2. Tensile Strength. for 10 % of the drawn wires 3. Wire Diameter for 10 % of the drawn wires 4. Ovality (roundness) for 10 % of the drawn wires
  • 5. 5 Stranding Process Here the tests carried out are to check both the actual cross section area of particular size as specified by standard & customer requirements through. 1. Resistance measurement 2. Weight measuring: One meter sample of the stranded conductor shall be taken from the end of every drum & weighing for cross check purpose only.
  • 6. 6 Conductor (CU – AL ) Insulation (PVC – XLPE ) Metal Sheath ( Lead Alloy) Inner Covering (PVC – XLPE) Armoring Outer Sheath (PVC – PE)
  • 7. Insulation Here a number of tests are carried out to measure the compliance of a conductor’s insulation, (1) Insulation thickness (2) Spark Test (3) Colour of Insulation (4) Hot Set test for XLPE insulation
  • 8. 8 Conductor (CU – AL ) Insulation Tipple layer (XLPE ) Outer Sheath (PVC – PE) Inner Covering (PVC – XLPE) Copper Screen Armouring
  • 9. 9
  • 10. Medium Voltage (MV) & High Voltage (HV) Insulation (1) Insulation Thickness (2) Hot Set test (3) Measuring the eccentricity of the insulation (4) Measuring the Strippability of the insulation screen (for MV cables only) (2.5) check the transparent of the insulation (not required by the standard) Here a number of tests are carried out to measure the compliance of a conductor’s insulation, Insulation
  • 11. Cu Tape Screened Cable 11 there are two types of screening (1) Copper Tape – thickness of tape and the % overlap of the tape after being wound onto the cable. (2) Copper Wire – actual number of wires and the diameter of each copper strand Screening
  • 12. 12 Assembling here are again a number of tests carried out to measure the following 1) Overall physical diameter of assembled cable 2) Assembling Lay length of the cores 3) Filler (Polypropylene) – area of the filler
  • 13. Inner Sheath This is to measure the physical dimensions of a cut sample taken from a manufactured cable, prior to final acceptance. 1. The thickness of the inner sheath Armouring This deals with the physical (mechanical) protection of the cables, this is done in three different methods. Here the physical properties of the armouring are tested. 1. Steel Wire – actual number of strands of the wires armour and wires diameter 2. Steel Tape – the physical thickness of the tape and % overlap of tape 3. Aluminium Wire – actual number of strands of the wire armour and diameter of wire
  • 14. Final Sheathing Here the physical properties are measured to check compliance 1. Thickness of outer sheath 2. Cable marking (Embossing) or printing 3. Spark test (e.g. for every 1mm thickness, this relates to a 6kV electrical charge) 4. Colour of outer sheath 5. Length marking – stamped physically onto every 1 meter of length sequentially *Hot Set test This is a test comprising of the following procedure, to test the cross linkable (or curing) properties of the XLPE insulation, 1. A sample is cut from cable under test 2. The insulation is then stripped from the cable (XLP part) 3. Shaved down into a set thickness (i.e. 0.8 – 1.7 mm thickness)
  • 15. 4. A “dumbbell” sample is stamped out for further testing. 5. Then a standard measured distance of 20 mm is marked off 6. When the total surface area is calculated and weight of 20N/cm2 is selected 7. Then weighted load is attached to the sample and then placed in an oven at 200’C for fifteen (15) minutes 8. Then the elongation (stretched) is measured and the elongation percentage calculated a maximum of 175% is the maximum is allowed. Note: For easy & fast procedures of performing the hot set test, loads for all expecting thickness were calculated and prepared as weights pieces & kept ready for using for this test as follows: 9.807Newton = 1000 g 1.000 Newton = 101.98 g 0.640 Newton = 65.26 g CALCULATION OF LOAD FOR DUMBBELL TEST PIECES
  • 16. Specified mechanical stress = 20 N/cm² according to IEC 60811-2-1 clause 9 Width of the specimen = 4.0 Load (Totally) (GR) Actual Mechanical Stress (Newton) Area (cm²) Thickness (mm) Stress x 101.98 Area x 20 Thick. x Width Given 65.27 0.64 0.032 0.80 69.35 0.68 0.034 0.85 73.43 0.72 0.036 0.90 77.51 0.76 0.038 0.95 81.59 0.80 0.040 1.00 85.67 0.84 0.042 1.05 89.75 0.88 0.044 1.10 93.83 0.92 0.046 1.15 97.91 0.96 0.048 1.20 101.99 1.00 0.050 1.25 106.07 1.04 0.052 1.30 110.15 1.08 0.054 1.35 114.23 1.12 0.056 1.40 118.31 1.16 0.058 1.45 122.39 1.20 0.060 1.50 126.47 1.24 0.062 1.55 130.54 1.28 0.064 1.60 134.62 1.32 0.066 1.65
  • 17. Size of Core (mm²) Outer Dia. of Piece (mm) (D) Thick. of Insulation (mm) Area of Cross Section (mm²) Area (cm²) (A) Actual Mech. Stress (N) Total Load (g) 1.5 2.96 0.70 4.97 0.0497 0.994 101.36 2.5 3.41 0.70 5.96 0.0596 1.192 121.55 4.0 3.95 0.70 7.14 0.0714 1.428 145.70 6.0 4.52 0.70 8.396 0.0840 1.68 171.30 Table # 2 CALCULATION OF LOAD FOR TUBULAR TEST PIECES
  • 18.   VOLTAGE TEST PARTIAL DISCHARGE (FOR MV/HV CABLES) CONDUCTOR RESISTANCE TAN δ MEASUREMENT (FOR HV CABLES MADE IN EGYPT 18 3rd Stage – Final test
  • 19. 19 )A) High Voltage Test 3500Volts )3.5kV) for 5 minutes A voltage of 3500 volts is passed between a single conductor and the neutral (or earth), for a period of 5 minutes respectively. A voltage of 6.2kV is also passed between the phases to test the insulation between the different phases respectively. Low Voltage Cables
  • 20. 20 If this process of testing the individual core are successful passed and there are no indication of any breakdown then the cable proceed to the next test, which is (B) Measuring the Conductors Resistance: The conductor resistance of each cutting length on drum shall be measured to verify the length of the cable as well as 1. HV test 3.5Uo voltage test is applied between the conductor & metallic screen of each core for 5 minutes 2. Conductor resistance measurement (same as explained in LV cables) 3. Partial Discharge Test (PD test) )B) Medium Voltage Cables
  • 21. Partial Discharge test The partial discharge phenomenon is known as a partial breakdown of insulation. There are three type of PD which are: 1. Internal PD 2. Voids PD 3. Surface PD The partial discharge is leakage charges from the conductor to the earth through weak point in the insulation such as Voids, Contaminations in the insulation, cavities in insulation or surface damage. The purpose the PD test is to test if the minutist particles or voids are present inside the XLPE insulation. This process is to measure the leakage of the charge (Q) from the conductor to the metallic screen, through these weak points. This test is measured in Pico-Column; the international standard is anything ≤10 pC (10-12 Columns)
  • 22. Conductor Insulation Insulation’s Screen Prepared cable end length C= dt dQ Q = Charge t = time For testing MV or HV cables electrically, cable terminals must be prepared as shown in the above figure.
  • 23. U is referred to any one of the following terms: 1.Line Voltage 2.Line to Line Voltage 3.Phase to Phase Voltage U0 is referred to any one of the following terms: 1. Phase Voltage 2. Phase to neutral Voltage 3. Line to neutral Voltage Voltage test for MV cables is 3.5 x U0, of the subject cables rated voltage For example an 11kV cable, this means that U of this cable is 11kV, therefore the U0 for this cable is: 3 11kV =6.35kV Thus the test voltage is 3.5x 6.35kV = 22kV test voltage rating to be applied for 5 minutes
  • 24. S U M M A R Y QUALITY CONTROL CHECKQUALITY CONTROL CHECK PointPoint
  • 25. IN-PROCESS PRODUCTIN-PROCESS PRODUCTIN-PROCESS PRODUCTIN-PROCESS PRODUCT COPPER & ALUMINIUM WIRE DRAWINGCOPPER & ALUMINIUM WIRE DRAWING  CONDUCTOR STRANDINGCONDUCTOR STRANDING  INSULATION PROCESSINSULATION PROCESS ELECTRICAL SCREENELECTRICAL SCREEN  LAYING UP (ASSEMBLING)LAYING UP (ASSEMBLING) FILLINGFILLING ARMOURINGARMOURING  OUTER SHEATHOUTER SHEATH IN-PROCESS PRODUCT TESTIN-PROCESS PRODUCT TESTIN-PROCESS PRODUCT TESTIN-PROCESS PRODUCT TEST SURFACE ( VISUAL )SURFACE ( VISUAL )  DIMENSIONDIMENSION  TENSILE STRENGTHTENSILE STRENGTH  ELONGATIONELONGATION  SPARK TEST ON INSULATION LINESPARK TEST ON INSULATION LINE  HOT SET FOR XLPE INSULATIONHOT SET FOR XLPE INSULATION  CABLE MARKINGCABLE MARKING  PARTIAL DISCHARGEPARTIAL DISCHARGE ))For screened Cores of MV / HV CableFor screened Cores of MV / HV Cable
  • 26. Function/Function/ DeptDept.. ProcessProcess ProcedureProcedure Tech. Dept./ Prod. Planning Dept. According to spec. identified through sales (contract review). QC Engineer Issue plan to QC supervisor/ Inspector. QC Supervisor For each manufacturing stage (as per inspection & test plan). Production Supervisor QC Inspector Attach tag to indicate status. QC supervisor/ Inspector - Sample frequency as specified in In-Process Inspection. - Continuous feedback about the trend of the result to the operator. QC Supervisor/ Inspector - Identify rejected products as per nonconformity procedure. - Identify the accepted product. QC Engineer Quality Trends to be reviewed and published in MRM and action plan to be established to reduce nonconformities. IN-PROCESS INSPECTION & TESTINGIN-PROCESS INSPECTION & TESTING
  • 27. CABLE FINAL TESTINGCABLE FINAL TESTING 11..ROUTINE TESTROUTINE TEST Tests made on every finished length of cable or during manufacture to ensure compliance with construction requirements and demonstrate the integrity of the cable. • Sampling criteria : 100 % of finished product Tests made on samples of cable to represent production batches and provide a periodic check on manufacturing consistency. • Sampling criteria: 10% of total quantity order as per IEC 60502. 22..SAMPLE TESTSAMPLE TEST
  • 28. 33..TYPE TESTTYPE TEST Tests made during the development of a new grade of cable design to establish performance characteristics. • Sampling criteria: 1 sample of new design product. FINISHED PRODUCT ROUTNEFINISHED PRODUCT ROUTNE TEST (100% TESTTEST (100% TEST(( FINISHED PRODUCT ROUTNEFINISHED PRODUCT ROUTNE TEST (100% TESTTEST (100% TEST(( VISUAL INSPECTION OF CABLES DRUMSVISUAL INSPECTION OF CABLES DRUMS CONDUCTOR RESISTANCECONDUCTOR RESISTANCE  VOLTAGE TESTVOLTAGE TEST  PARTIAL DISCHARGE FOR MV & HVPARTIAL DISCHARGE FOR MV & HV CABLESCABLES INSULATION RESISTANCE (IF REQUIRED)INSULATION RESISTANCE (IF REQUIRED) TAN δ FOR HV CABLES (10 % OF CUTTINGTAN δ FOR HV CABLES (10 % OF CUTTING LENGTH)LENGTH)
  • 29. Function/Function/ Dept.Dept. ProcessProcess ProcedureProcedure QC Inspector From production Department Check cable marking/ embossing According to applicable Test instructions According to work order no. QC Lab Non- electrical tests. QC Engineer Stamp "Passed QC" QC Manager To be reviewed and published in MRM FINAL INSPECTION & TESTINGFINAL INSPECTION & TESTING
  • 30. QUALITY CONTROL DEPARTMENT QUALITY OBJECTIVEES (1) Date of setting: 01-03-2006 Date of implementation: 9/03/2006 1)CONDUCTOR RESISTANCE: A. COPPER CONDUCTORS: •From 1.5 mm² to 6 mm² -1.5 % + 0.0% from the maximum specified value •From 10 mm² to 35 mm² -1.0 % + 0.0% from the maximum specified value •From 50 mm² to 630 mm² -0.8 % + 0.0% from the maximum specified value
  • 31. B. ALUMINUM CONDUCTORS: •From 10 mm² to 35.0 mm² -1.50% + 0.0% from the maximum specified value •From 50 mm² to 630 mm² -1.00% + 0.0% from the maximum specified value 2(INSULATION: A( XLPE Insulation: •From 0.0 mm to 1.0 mm, maximum allowed +8.0% from the average required •From 1.1 mm to 1.5 mm, maximum allowed +6.0% from the average required •From 1.6 mm to 2.5 mm, maximum allowed +5.0% from the average required •More than 2.50 mm, maximum allowed +4.0% from the average required
  • 32. B( NYA & Flex Insulation: • From 1.5 to 16 MM² conductor sizes, maximum insulation thickness allowed is +6% from the average required • From 25 to 70 MM² conductor sizes, maximum insulation thickness allowed is +5% from the average required 3(INNER SHEATH Only the minimum value has to be achieved & the maximum value shall be 95% of the nominal value. Unless otherwise for some special specification or agreement between the El Sewedy & customer to achieve both value (average & minimum), so in this case the maximum allowed value should be +6 % from the average required 4(OUTER SHEATH A( Sheath over Armouring or Direct sheath:
  • 33. Only the minimum value is required to be achieved & the maximum value shall be 95% of the nominal one. B. Sheath over smooth surface or sheath for flex cables: The maximum allowed value should be +8.0 % from the average required 5(CCV LINE (MV & HV Cables( Conductor screen: The maximum thickness allowed +10 % from the average required Insulation screen: The maximum thickness allowed +3 % from the average required Insulation: The maximum thickness allowed +4 % from the average required
  • 34. InsulationInsulationInsulationInsulation AssemblyAssemblyAssemblyAssembly Inner sheathingInner sheathingInner sheathingInner sheathing StrandingStrandingStrandingStranding DrawingDrawingDrawingDrawing Lead SheathingLead SheathingLead SheathingLead Sheathing ArmouringArmouringArmouringArmouring Outer SheathingOuter SheathingOuter SheathingOuter Sheathing 34
  • 35. - CABLE COST 90 % MATERIAL COST 10% PRODUCTION COST - MATERIAL COST MATERIAL PRICE MATERIAL CONSUMPTION - MATERIAL PRICE REDUCE CABLE COST REDUCE CABLE COST How you can reduce the Material Price? Look always for additional supplier. Replace the actual material with a cheaper solution MATERIAL CONSUMPTION IN PRODUCTION IN DESIGN DEPARTMENT
  • 36. IN PRODUCTION: MATERIAL OVERUSAGE * Look for the tolerance –range for each production step, also for different machine. (Quality Department). If the tolerance-range is too high, look for the reason (bad material, old machine, bad measurement-equipment… and “make it better” * Reduce set-up-length * It will be helpful, that all necessary process data are written down for the personal at the machine. * Reduce scrap.
  • 37. IN DESIGN DEPARTMENT: * Design department is one of the important departments to influence the cable cost. *The design engineer must create cheapest cable design solution in accordance with the customer specification. * Look for “gaps” in the specification, it means, what is not required in the specification. During our 2 weeks discussion with many colleagues from Production, quality, technical, planning and financial, We found many points you can change it. 80% of your orders are with 8 Types: The last 2 days we have made a cable re-design with the designer colleagues in accordance the new points, Also 2 offers for 220 kV-cables.
  • 38. 1) Reduce nominal thickness for inner and outer semiconductor layer. 2) Change the copper tape screening from 1 tape to 2 tapes. 3)Reduce the filler material in 3-core-cable with round conductor. 4)Fix the assembled cores with a tape as open helix. 5)In many specifications there is no average thickness required for bedding, separation sheath. Therefore reduce the thickness. 6) Indicate in design sheet the different value: Nominal, Minimum, Average & Practical Value. 7) Copper wire screen in mostly cheaper than copper tape screen. 8) Produce conductor for XLPE cable =10 kV only with dies. 9) Remove all fillers in 1 kV sector conductor – cables. 10) Reduce master batch colour in 1 kV cable with skin insulation 11)Manufacturing insulation for 1kV cable only in tube extrusion. 12) Try to use for 1kV cable as bedding a tape (instead extruded bedding). 13) Flat wire armouring is less in cost than round wire armouring. Check to improve your armouring machine for flat wire. 14) Check your PVC- compound to increase the filler
  • 39. It is really a great pleasure for me to work together with the very friendly and well experience people in EL SEWEDY CABLES THANKS Eng’r. Mohsen Al Tandi Quality Control Manager Arab Cables Company