The Temple Mills Bridge in London was reconstructed from 2004-2006. The original 1963 bridge had deteriorated due to water ingress and reinforcement corrosion. The reconstruction involved demolishing the old bridge down to the existing foundations and riverbed, then constructing new piers, abutments, and a precast concrete deck. Environmental considerations like flood risk, habitat creation, and noise/pollution mitigation played a key role. Careful planning and risk management were needed due to the bridge's strategic location and need to maintain traffic flow during construction. The reconstruction secured this important transport link in advance of nearby Olympic development works.
Transport Scotland requested that Scottish Water relocate their long sea outfall infrastructure to accommodate construction of a new pier for the Forth Replacement Crossing project. Grontmij was hired to design and oversee construction of a replacement outfall. They determined that using HDPE piping instead of the original expensive armored piping, along with changing from a twin pipe to single pipe design and simplifying the diffuser, would reduce costs and health and safety risks. The redesigned outfall was constructed on schedule by September 2010 through conventional barge techniques. The project demonstrated that thorough understanding of historical context and value engineering can produce substantial savings.
The document discusses the design of concrete gravity dams for hydropower generation. It covers topics such as the various types of dams, forces acting on gravity dams, factors in site selection, general design considerations, construction materials, the procedure for building a dam, modes of failure and stability criteria, construction problems, and a field visit experience to Tilaiya Dam in Jharkhand. Concrete gravity dams are designed to withstand water pressure, uplift pressure, seismic forces, and other pressures through their massive weight and shape, which provides stability without any additional reinforcement.
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...Michal Krzeminski
This document summarizes a case study of ground improvement using controlled modulus columns (CMCs) for a bridge project in Victoria, Australia. Soft and compressible soils up to 6 meters thick at the site required ground improvement to reduce long-term settlements. CMCs were installed in a grid pattern to a depth of 6-9 meters to transfer loads through the soft soils to a denser layer below. Numerical modeling predicted total settlements of less than 50 mm after construction. Monitoring of settlements and performance is ongoing.
The document provides a preliminary brief for a flood alleviation project along the Clontarf Promenade between Alfie Byrne Road and the Wooden Bridge in Dublin. It summarizes discussions from a Joint Working Group regarding flood protection options and outlines a proposed dual defence system using the existing seawall and a new secondary wall near the road. The consultant is asked to review flood risk levels, calculate required defence heights, produce preliminary designs and cost estimates, and advise on planning and development of the Promenade going forward while minimizing visual impacts. The goal is to finalize a preliminary plan for the flood protection scheme and Promenade redevelopment.
The document discusses dams and hydraulic structures. It provides an overview of different types of dams including embankment, gravity, buttress, and arch dams. It emphasizes the importance of regular inspections and monitoring of dams to identify any signs of distress or changes in conditions. The document also discusses causes of dam failures, noting that embankment dams and older dams are more likely to fail than other types. Embankment dams from 1900 had around a 10% probability of failure while modern dams constructed after 1950 have less than a 0.04% chance.
Over 25% of US bridges are structurally deficient or functionally obsolete, and funding for infrastructure maintenance is decreasing while needs are increasing. Structurally deficient bridges have safety issues while functionally obsolete bridges no longer meet current design standards. Deciding whether to rehabilitate or replace a bridge involves considering its structural condition, costs, impacts, regulations, and remaining lifespan, though no single algorithm can account for all factors. Bridge owners must prioritize options based on their goals, and rehabilitation is often more challenging but cheaper than replacement.
This document provides an overview of dam engineering and the history of dam construction. It discusses that dams were first constructed over 8,000 years ago for irrigation purposes. The 20th century saw a rapid increase in large dam construction, with over 45,000 large dams built globally by the end of the century. China alone has built around 22,000 large dams, accounting for nearly half of the world's total. Dams were promoted as a means to meet water and energy needs and foster regional development. Factors governing dam type selection include valley topography, geology and foundation conditions, availability of construction materials, and environmental and cost considerations.
This document provides information on Farrans, a UK-based building and civil engineering contractor. It summarizes some of Farrans' marine portfolio projects, including the construction of a new deep water berth and quay wall at Belfast Harbour, widening of the Seaforth Passage in Liverpool, repairs to a cooling water outfall structure in Heysham, construction of a new harbour wall in Granton, redevelopment of berthing areas and construction of a new quay wall at Montrose Deep Water Berth, construction of Pointhouse Quay in Glasgow, and renewal of Berth 6 in Montrose.
Transport Scotland requested that Scottish Water relocate their long sea outfall infrastructure to accommodate construction of a new pier for the Forth Replacement Crossing project. Grontmij was hired to design and oversee construction of a replacement outfall. They determined that using HDPE piping instead of the original expensive armored piping, along with changing from a twin pipe to single pipe design and simplifying the diffuser, would reduce costs and health and safety risks. The redesigned outfall was constructed on schedule by September 2010 through conventional barge techniques. The project demonstrated that thorough understanding of historical context and value engineering can produce substantial savings.
The document discusses the design of concrete gravity dams for hydropower generation. It covers topics such as the various types of dams, forces acting on gravity dams, factors in site selection, general design considerations, construction materials, the procedure for building a dam, modes of failure and stability criteria, construction problems, and a field visit experience to Tilaiya Dam in Jharkhand. Concrete gravity dams are designed to withstand water pressure, uplift pressure, seismic forces, and other pressures through their massive weight and shape, which provides stability without any additional reinforcement.
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...Michal Krzeminski
This document summarizes a case study of ground improvement using controlled modulus columns (CMCs) for a bridge project in Victoria, Australia. Soft and compressible soils up to 6 meters thick at the site required ground improvement to reduce long-term settlements. CMCs were installed in a grid pattern to a depth of 6-9 meters to transfer loads through the soft soils to a denser layer below. Numerical modeling predicted total settlements of less than 50 mm after construction. Monitoring of settlements and performance is ongoing.
The document provides a preliminary brief for a flood alleviation project along the Clontarf Promenade between Alfie Byrne Road and the Wooden Bridge in Dublin. It summarizes discussions from a Joint Working Group regarding flood protection options and outlines a proposed dual defence system using the existing seawall and a new secondary wall near the road. The consultant is asked to review flood risk levels, calculate required defence heights, produce preliminary designs and cost estimates, and advise on planning and development of the Promenade going forward while minimizing visual impacts. The goal is to finalize a preliminary plan for the flood protection scheme and Promenade redevelopment.
The document discusses dams and hydraulic structures. It provides an overview of different types of dams including embankment, gravity, buttress, and arch dams. It emphasizes the importance of regular inspections and monitoring of dams to identify any signs of distress or changes in conditions. The document also discusses causes of dam failures, noting that embankment dams and older dams are more likely to fail than other types. Embankment dams from 1900 had around a 10% probability of failure while modern dams constructed after 1950 have less than a 0.04% chance.
Over 25% of US bridges are structurally deficient or functionally obsolete, and funding for infrastructure maintenance is decreasing while needs are increasing. Structurally deficient bridges have safety issues while functionally obsolete bridges no longer meet current design standards. Deciding whether to rehabilitate or replace a bridge involves considering its structural condition, costs, impacts, regulations, and remaining lifespan, though no single algorithm can account for all factors. Bridge owners must prioritize options based on their goals, and rehabilitation is often more challenging but cheaper than replacement.
This document provides an overview of dam engineering and the history of dam construction. It discusses that dams were first constructed over 8,000 years ago for irrigation purposes. The 20th century saw a rapid increase in large dam construction, with over 45,000 large dams built globally by the end of the century. China alone has built around 22,000 large dams, accounting for nearly half of the world's total. Dams were promoted as a means to meet water and energy needs and foster regional development. Factors governing dam type selection include valley topography, geology and foundation conditions, availability of construction materials, and environmental and cost considerations.
This document provides information on Farrans, a UK-based building and civil engineering contractor. It summarizes some of Farrans' marine portfolio projects, including the construction of a new deep water berth and quay wall at Belfast Harbour, widening of the Seaforth Passage in Liverpool, repairs to a cooling water outfall structure in Heysham, construction of a new harbour wall in Granton, redevelopment of berthing areas and construction of a new quay wall at Montrose Deep Water Berth, construction of Pointhouse Quay in Glasgow, and renewal of Berth 6 in Montrose.
This document discusses the foundation design processes for two major bridge projects - the Vasco da Gama Bridge in Lisbon, Portugal and the Rion-Antirion Bridge in Greece. For the Vasco da Gama Bridge, the foundations consisted of vertical large diameter bored concrete piles due to favorable soil conditions and design requirements. For the Rion-Antirion Bridge, the soil conditions were less favorable so an innovative foundation concept was developed and implemented, which allowed for some permanent displacement under seismic loading. The additional time for design of the Rion-Antirion Bridge was crucial to developing and validating this new foundation solution.
The document summarizes a conference on sustainable bridge design, planning, and construction to be held in Abu Dhabi, UAE from October 25-27, 2010. It provides information on workshops, speakers, sponsors, and registration. A case study is presented on the planning, design, and construction of the Mafraq Interchange project in Abu Dhabi, including traffic analysis, structural design considerations, and construction techniques used to complete the project on schedule while incorporating sustainability measures.
Geophysical surveys were conducted along the 17th Street Canal flood wall in New Orleans to determine the depth of steel sheet piles after Hurricane Katrina. Parallel seismic tests indicated the sheet pile tips were 5 to 7 feet shorter than specifications, but direct measurements after removing the concrete wall found the sheet piles were the required length. This highlighted both the capabilities and limitations of geophysical methods, and the need for further research in their application.
Martin Jacobs is a senior civil engineer with almost 30 years of experience in civil engineering consultancy in Australia, New Zealand, Hong Kong, and the UK. He has worked on a wide range of infrastructure projects from small domestic developments to multi-billion dollar projects. Martin is skilled in drainage design, project management, and providing technical leadership to teams. He has extensive experience designing drainage systems for major highway, airport, and urban development projects. Martin is a registered professional engineer and maintains active membership in several engineering institutions.
The document provides details on the design of a new diversion dam project at the Tarbela Dam in Pakistan. It discusses selecting the site, conducting site studies and subsurface explorations, selecting an earth-fill dam type, and considerations for the embankment, foundation geology, reservoir investigations, test fills, flood hydrology, engineering design aspects like capacity and power calculations, penstock selection and construction details. Foundation conditions, causes of dam failures, and administrative requirements are also outlined.
The Balangero asbestos open pit mine, located 35km NW of Torino (Italy), was the largest operation of this kind in Western Europe. The dry tailings were lifted by a conveyor belt from the mill and dumped over a natural slope with an approximate angle of 25 degrees, progressively reaching a maximum thickness estimated at 80 m.
By the '80s the dump was deeply scarred by various local and large scale instabilities, to the point that houses located at the toe, on the opposite side of the valley, were evacuated.
The award winning restoration project used a multidisciplinary approach including hydraulics, geotechnical, pedological and risk engineering to yield a well balanced and sustainable solution. This paper illustrates the Risk Based Decision Making (RBDM) process used through the feasibility, design and construction follow-up of the environmental restoration of the 60 Mm3 dry Balangero asbestos tailings dump.
The slopes were hit by storm Quinn and Medicane Rolf and came out unscathed. That was after surviving heavy summer storms in 2010 and 2011.
The document summarizes a project to rehabilitate Virginia Beach in Durban, South Africa. It began as a project to extend a stormwater culvert to address flooding issues. It was expanded to also rehabilitate the beach access road, repair ablution facilities, and develop recreational areas. The expanded works approach enhanced infrastructure value for the local community by displacing negative activities and developing the area into a prime recreational site through community participation. The project showed how municipal infrastructure projects can achieve additional social and economic benefits with minimal added costs.
This document provides guidelines for designing flood resistant bridges in Papua New Guinea. It discusses design considerations for bridge abutments, superstructures, piers, and foundations to withstand flooding and scour. It also covers estimating scour depths, designing for structural stability, afflux, and providing scour protection. The goal is to develop low-cost, practical solutions to improve flood resilience of bridges and reduce damage.
The Busan-Geoje Fixed Link project in South Korea consists of an 8.2 km long immersed tunnel and cable-stayed bridges that connect the cities of Busan and Geoje Island. The tunnel is 3.2km long and 18 tunnel elements that are 180m long were constructed using immersed tube tunneling. Two cable-stayed bridges with pylons up to 156m tall were also built, with caisson foundations in seas up to 30m deep. The $1.8 billion project improves transportation between Busan and Geoje Island and was designed to withstand earthquakes, typhoons, and ship impacts for at least 100 years.
This document discusses the disadvantages of using a blanket factor of safety approach when designing remedial measures for railway earthworks. It argues that seeking only to improve the factor of safety can lead to overly conservative and expensive remedial designs. Instead, it proposes a new approach where performance requirements of the track are the key design criteria, and remedial works specifically target the key causes of poor performance in a more cost-effective manner. An example project is described to illustrate how this new approach was applied.
In these slides, we talk about infrastructure.
First tells that what is infrastructure. Secondly, its importance. At last, types of infrastructure.
Hope you enjoy our slides.
Thanks.
This document discusses flood resistant bridge design in Papua New Guinea. It notes that over 280 bridges in PNG have been damaged by flooding in the last 5 years. The damage is mainly to bridge foundations, with flooding washing away abutments or scouring piers. The study aims to conduct fieldwork on flooded bridges in PNG and Japan, and provide recommended flood resilient bridge design guidelines for PNG. The guidelines will consider constructability and cost issues to provide practical, economical and sustainable solutions for bridge design in PNG.
This document summarizes a project to replace aging water and sewer lines under a busy road in Fort Collins, Colorado. An alternative project delivery system was used bringing together utilities, engineers, and contractors. Trenchless installation methods like pipe bursting and horizontal directional drilling were chosen to install new fusible PVC pipes to minimize impacts to traffic. This allowed replacement of over 5,800 feet of waterline and 400 feet of sewer line in a shorter time frame compared to traditional open cut methods.
A Review of Previous Work on an Approach to Design and Construction of Low He...IRJET Journal
This document reviews previous work on the design and construction of low height gravity dams. It discusses several past studies on related topics. Researchers have refined criteria for designing earth dams to resist piping and erosion. Construction of dams is needed on rivers carrying large rainwater flows. For the specific context of Lucknow, India, a dam needs to be built on the Gomti River without diverting the flowing water. Previous literature suggests constructing such a dam using geo bags, boulders, piling and earth over a period of 3 to 5 years. The stability and safety of earth dams against issues like overturning, sliding and piping has been explored in depth by other scholars.
Civil Engineering Technical Project for an existing T intersection needing to be updated. Plans submitted to NCDOT, City of Asheville, and to Wilbur Smith Engineering company over the Wilma Dykeman Riverway Project in Asheville North Carolina. This was submitted by the Senior Project Class Spring 2011
A case study on Coastal protection structure failure. Quay failure in Port of Barcelona. The presentation describes the failure of harbour walls which occurred at Barcelona on 1st January 2007, associated with an inadequate consideration of the ground conditions in the light of the marine environment. At Barcelona, the construction of the quay wall proceeded at a faster rate than the breakwater. In this case the wharf backfill was placed rapidly on the soft muds, progressing from the inland side. The paper discusses the importance of an overview including the ground investigation, engineering design, construction method and speed of construction. KeywordsBearing capacity–Caissons–Shallow foundations–Failure modes–Study cases
The document summarizes an environmental impact assessment of the Jamuna Bridge project in Bangladesh. Key points:
- The project involved constructing a 5.63km long road-rail-power bridge over the Jamuna River, along with approach roads and infrastructure.
- Potential environmental impacts identified included loss of fisheries habitat, disruption of wildlife, erosion, drainage issues, and flooding impacts.
- The assessment evaluated these impacts and proposed mitigation measures like constructing fish hatcheries, managing erosion, ensuring adequate drainage, and avoiding construction perpendicular to flood plains.
- Public consultation and environmental monitoring were recommended to minimize impacts and ensure a sustainable project.
The document discusses the economic impacts and evaluation of port projects. It notes that ports offer economic and social benefits but also environmental constraints. Significant increases in throughput have required developing new infrastructure and ports. Ports are capital-intensive and closely linked to trade and economic development. Their economic impacts and benefits can be difficult to accurately assess or forecast. The document also discusses the environmental impacts of port activities, including air and water pollution, climate risks, and health disparities faced by neighboring communities.
Case study on underwater pipieline leaks and its environmental impactsssuser8fec94
Underwater pipelines can leak and damage the environment. A document analyzed causes of underwater pipeline leakage and environmental impacts. It discussed inspection and repair management practices. Pipeline failures are often due to corrosion, scouring, or mechanical damage. Quickly resolving the causes of leaks in muddy water can be difficult with current tools. The document reviewed literature on various topics like pipeline location decisions, corrosion problems and solutions, and sensor network architectures for pipeline monitoring.
SENTENZA sul ricorso numero di registro generale 7690 del 2015, proposto dalla signora Patrizia Borgarello, contro
la Regione Piemonte, rappresentata e difesa dagli avv. Giovanna Scollo
e Giuseppe Piccarreta, con domicilio eletto presso l’avv. Alfredo
Codacci Pisanelli in Roma, Via Claudio Monteverdi 26;
nei confronti di
i signori Sergio Chiamparino, Silvana Accossato, Paolo Allemano,
Andrea Appiano, Francesco Balocco, Vittorio Barazzotto, Enrica
Baricco, Antonino Boeti, Valentina Giuseppina Caputo, Monica Cerutti,
Nadia Conticelli, Giovanni Corgnati, Augusto Ferrari, Antonio
Ferrentino, Giorgio Ferrero, Raffaele Gallo, Davide Gariglio, Mario
Giaccone, Marco Grimaldi, Gabriele Molinari, Angela Motta,
Domenico Valter Ottria, Giovanna Pentenero, Domenico Ravetti, Aldo
Reschigna, Domenico Rossi, rappresentati e difesi dagli avv. Massimo
Luciani, Mario Contaldi, Gianluca Contaldi, Vittorio Barosio e Fabio
Dell'Anna, con domicilio eletto presso l’avv. Mario Contaldi in Roma,
Via Pierluigi da Palestrina 63;
i signori Elvio Rostagno e Daniele Valle, rappresentati e difesi dagli avv.
Massimo Luciani, Mario Contaldi, Vittorio Barosio, Gianluca Contaldi e
Fabio Dell'Anna, con domicilio eletto presso l’avv. Mario Contaldi in
Roma, Via Pierluigi da Palestrina 63;
i signori Zicarelli Stefania, Mastrodicasa Fabiana, Vito Massimiliano
Bucci, Mina Lucetta, Alberto Moro, Pierluigi Ubezio, Clarissa Cacici,
Gianpaolo Andrissi, Stefania Batzella, Alessandro Manuel Benvenuto,
Giorgio Bertola, Massimo Berutti, Davide Bono, Mauro Willem Campo,
Maria Carla Chiapello, Francesca Frediani, Gianna Gancia, Francesco
Graglia, Mauro Antonio Donato Laus, Maurizio Raffaello Vincenzo
Marrone, Paolo Domenico Mighetti, Alfredo Monaco, Claudia
Porchietto, Daniela Ruffino, Diego Sozzani, Federico Valetti, Alberto
Valmaggia, Gian Luca Vignale, Lorenza Morello, Emanuele Rivoira,
Giovanni Maria Ferraris, Gilberto Pichetto Fratin;
sul ricorso numero di registro generale 8218 del 2015, proposto dai
signori Sara Franchino, Sebastiano Strazzeri, Onorato Passarelli, Davide
Betti, Rosanna Borsa, Antonio Del Buono, Sabrina Margherita Giovine,
Jessica Molino, Salvatore Calogero Piccicuto e Sebastiana Trigila,
rappresentati e difesi dall'avv. Giorgio Strambi, con domicilio eletto
presso il Consiglio di Stato – Segreteria in Roma, piazza Capo di Ferro
13;
contro
la signora Patrizia Borgarello;
Las herramientas web son sitios que facilitan el compartir información y la colaboración entre usuarios. Permiten que los usuarios interactúen y creen contenido en lugar de limitarse a observar pasivamente. Algunos ejemplos son comunidades web, redes sociales, wikis y blogs. Estas herramientas aprovechan la inteligencia colectiva y permiten compartir recursos digitales creados por los usuarios.
This document discusses the foundation design processes for two major bridge projects - the Vasco da Gama Bridge in Lisbon, Portugal and the Rion-Antirion Bridge in Greece. For the Vasco da Gama Bridge, the foundations consisted of vertical large diameter bored concrete piles due to favorable soil conditions and design requirements. For the Rion-Antirion Bridge, the soil conditions were less favorable so an innovative foundation concept was developed and implemented, which allowed for some permanent displacement under seismic loading. The additional time for design of the Rion-Antirion Bridge was crucial to developing and validating this new foundation solution.
The document summarizes a conference on sustainable bridge design, planning, and construction to be held in Abu Dhabi, UAE from October 25-27, 2010. It provides information on workshops, speakers, sponsors, and registration. A case study is presented on the planning, design, and construction of the Mafraq Interchange project in Abu Dhabi, including traffic analysis, structural design considerations, and construction techniques used to complete the project on schedule while incorporating sustainability measures.
Geophysical surveys were conducted along the 17th Street Canal flood wall in New Orleans to determine the depth of steel sheet piles after Hurricane Katrina. Parallel seismic tests indicated the sheet pile tips were 5 to 7 feet shorter than specifications, but direct measurements after removing the concrete wall found the sheet piles were the required length. This highlighted both the capabilities and limitations of geophysical methods, and the need for further research in their application.
Martin Jacobs is a senior civil engineer with almost 30 years of experience in civil engineering consultancy in Australia, New Zealand, Hong Kong, and the UK. He has worked on a wide range of infrastructure projects from small domestic developments to multi-billion dollar projects. Martin is skilled in drainage design, project management, and providing technical leadership to teams. He has extensive experience designing drainage systems for major highway, airport, and urban development projects. Martin is a registered professional engineer and maintains active membership in several engineering institutions.
The document provides details on the design of a new diversion dam project at the Tarbela Dam in Pakistan. It discusses selecting the site, conducting site studies and subsurface explorations, selecting an earth-fill dam type, and considerations for the embankment, foundation geology, reservoir investigations, test fills, flood hydrology, engineering design aspects like capacity and power calculations, penstock selection and construction details. Foundation conditions, causes of dam failures, and administrative requirements are also outlined.
The Balangero asbestos open pit mine, located 35km NW of Torino (Italy), was the largest operation of this kind in Western Europe. The dry tailings were lifted by a conveyor belt from the mill and dumped over a natural slope with an approximate angle of 25 degrees, progressively reaching a maximum thickness estimated at 80 m.
By the '80s the dump was deeply scarred by various local and large scale instabilities, to the point that houses located at the toe, on the opposite side of the valley, were evacuated.
The award winning restoration project used a multidisciplinary approach including hydraulics, geotechnical, pedological and risk engineering to yield a well balanced and sustainable solution. This paper illustrates the Risk Based Decision Making (RBDM) process used through the feasibility, design and construction follow-up of the environmental restoration of the 60 Mm3 dry Balangero asbestos tailings dump.
The slopes were hit by storm Quinn and Medicane Rolf and came out unscathed. That was after surviving heavy summer storms in 2010 and 2011.
The document summarizes a project to rehabilitate Virginia Beach in Durban, South Africa. It began as a project to extend a stormwater culvert to address flooding issues. It was expanded to also rehabilitate the beach access road, repair ablution facilities, and develop recreational areas. The expanded works approach enhanced infrastructure value for the local community by displacing negative activities and developing the area into a prime recreational site through community participation. The project showed how municipal infrastructure projects can achieve additional social and economic benefits with minimal added costs.
This document provides guidelines for designing flood resistant bridges in Papua New Guinea. It discusses design considerations for bridge abutments, superstructures, piers, and foundations to withstand flooding and scour. It also covers estimating scour depths, designing for structural stability, afflux, and providing scour protection. The goal is to develop low-cost, practical solutions to improve flood resilience of bridges and reduce damage.
The Busan-Geoje Fixed Link project in South Korea consists of an 8.2 km long immersed tunnel and cable-stayed bridges that connect the cities of Busan and Geoje Island. The tunnel is 3.2km long and 18 tunnel elements that are 180m long were constructed using immersed tube tunneling. Two cable-stayed bridges with pylons up to 156m tall were also built, with caisson foundations in seas up to 30m deep. The $1.8 billion project improves transportation between Busan and Geoje Island and was designed to withstand earthquakes, typhoons, and ship impacts for at least 100 years.
This document discusses the disadvantages of using a blanket factor of safety approach when designing remedial measures for railway earthworks. It argues that seeking only to improve the factor of safety can lead to overly conservative and expensive remedial designs. Instead, it proposes a new approach where performance requirements of the track are the key design criteria, and remedial works specifically target the key causes of poor performance in a more cost-effective manner. An example project is described to illustrate how this new approach was applied.
In these slides, we talk about infrastructure.
First tells that what is infrastructure. Secondly, its importance. At last, types of infrastructure.
Hope you enjoy our slides.
Thanks.
This document discusses flood resistant bridge design in Papua New Guinea. It notes that over 280 bridges in PNG have been damaged by flooding in the last 5 years. The damage is mainly to bridge foundations, with flooding washing away abutments or scouring piers. The study aims to conduct fieldwork on flooded bridges in PNG and Japan, and provide recommended flood resilient bridge design guidelines for PNG. The guidelines will consider constructability and cost issues to provide practical, economical and sustainable solutions for bridge design in PNG.
This document summarizes a project to replace aging water and sewer lines under a busy road in Fort Collins, Colorado. An alternative project delivery system was used bringing together utilities, engineers, and contractors. Trenchless installation methods like pipe bursting and horizontal directional drilling were chosen to install new fusible PVC pipes to minimize impacts to traffic. This allowed replacement of over 5,800 feet of waterline and 400 feet of sewer line in a shorter time frame compared to traditional open cut methods.
A Review of Previous Work on an Approach to Design and Construction of Low He...IRJET Journal
This document reviews previous work on the design and construction of low height gravity dams. It discusses several past studies on related topics. Researchers have refined criteria for designing earth dams to resist piping and erosion. Construction of dams is needed on rivers carrying large rainwater flows. For the specific context of Lucknow, India, a dam needs to be built on the Gomti River without diverting the flowing water. Previous literature suggests constructing such a dam using geo bags, boulders, piling and earth over a period of 3 to 5 years. The stability and safety of earth dams against issues like overturning, sliding and piping has been explored in depth by other scholars.
Civil Engineering Technical Project for an existing T intersection needing to be updated. Plans submitted to NCDOT, City of Asheville, and to Wilbur Smith Engineering company over the Wilma Dykeman Riverway Project in Asheville North Carolina. This was submitted by the Senior Project Class Spring 2011
A case study on Coastal protection structure failure. Quay failure in Port of Barcelona. The presentation describes the failure of harbour walls which occurred at Barcelona on 1st January 2007, associated with an inadequate consideration of the ground conditions in the light of the marine environment. At Barcelona, the construction of the quay wall proceeded at a faster rate than the breakwater. In this case the wharf backfill was placed rapidly on the soft muds, progressing from the inland side. The paper discusses the importance of an overview including the ground investigation, engineering design, construction method and speed of construction. KeywordsBearing capacity–Caissons–Shallow foundations–Failure modes–Study cases
The document summarizes an environmental impact assessment of the Jamuna Bridge project in Bangladesh. Key points:
- The project involved constructing a 5.63km long road-rail-power bridge over the Jamuna River, along with approach roads and infrastructure.
- Potential environmental impacts identified included loss of fisheries habitat, disruption of wildlife, erosion, drainage issues, and flooding impacts.
- The assessment evaluated these impacts and proposed mitigation measures like constructing fish hatcheries, managing erosion, ensuring adequate drainage, and avoiding construction perpendicular to flood plains.
- Public consultation and environmental monitoring were recommended to minimize impacts and ensure a sustainable project.
The document discusses the economic impacts and evaluation of port projects. It notes that ports offer economic and social benefits but also environmental constraints. Significant increases in throughput have required developing new infrastructure and ports. Ports are capital-intensive and closely linked to trade and economic development. Their economic impacts and benefits can be difficult to accurately assess or forecast. The document also discusses the environmental impacts of port activities, including air and water pollution, climate risks, and health disparities faced by neighboring communities.
Case study on underwater pipieline leaks and its environmental impactsssuser8fec94
Underwater pipelines can leak and damage the environment. A document analyzed causes of underwater pipeline leakage and environmental impacts. It discussed inspection and repair management practices. Pipeline failures are often due to corrosion, scouring, or mechanical damage. Quickly resolving the causes of leaks in muddy water can be difficult with current tools. The document reviewed literature on various topics like pipeline location decisions, corrosion problems and solutions, and sensor network architectures for pipeline monitoring.
SENTENZA sul ricorso numero di registro generale 7690 del 2015, proposto dalla signora Patrizia Borgarello, contro
la Regione Piemonte, rappresentata e difesa dagli avv. Giovanna Scollo
e Giuseppe Piccarreta, con domicilio eletto presso l’avv. Alfredo
Codacci Pisanelli in Roma, Via Claudio Monteverdi 26;
nei confronti di
i signori Sergio Chiamparino, Silvana Accossato, Paolo Allemano,
Andrea Appiano, Francesco Balocco, Vittorio Barazzotto, Enrica
Baricco, Antonino Boeti, Valentina Giuseppina Caputo, Monica Cerutti,
Nadia Conticelli, Giovanni Corgnati, Augusto Ferrari, Antonio
Ferrentino, Giorgio Ferrero, Raffaele Gallo, Davide Gariglio, Mario
Giaccone, Marco Grimaldi, Gabriele Molinari, Angela Motta,
Domenico Valter Ottria, Giovanna Pentenero, Domenico Ravetti, Aldo
Reschigna, Domenico Rossi, rappresentati e difesi dagli avv. Massimo
Luciani, Mario Contaldi, Gianluca Contaldi, Vittorio Barosio e Fabio
Dell'Anna, con domicilio eletto presso l’avv. Mario Contaldi in Roma,
Via Pierluigi da Palestrina 63;
i signori Elvio Rostagno e Daniele Valle, rappresentati e difesi dagli avv.
Massimo Luciani, Mario Contaldi, Vittorio Barosio, Gianluca Contaldi e
Fabio Dell'Anna, con domicilio eletto presso l’avv. Mario Contaldi in
Roma, Via Pierluigi da Palestrina 63;
i signori Zicarelli Stefania, Mastrodicasa Fabiana, Vito Massimiliano
Bucci, Mina Lucetta, Alberto Moro, Pierluigi Ubezio, Clarissa Cacici,
Gianpaolo Andrissi, Stefania Batzella, Alessandro Manuel Benvenuto,
Giorgio Bertola, Massimo Berutti, Davide Bono, Mauro Willem Campo,
Maria Carla Chiapello, Francesca Frediani, Gianna Gancia, Francesco
Graglia, Mauro Antonio Donato Laus, Maurizio Raffaello Vincenzo
Marrone, Paolo Domenico Mighetti, Alfredo Monaco, Claudia
Porchietto, Daniela Ruffino, Diego Sozzani, Federico Valetti, Alberto
Valmaggia, Gian Luca Vignale, Lorenza Morello, Emanuele Rivoira,
Giovanni Maria Ferraris, Gilberto Pichetto Fratin;
sul ricorso numero di registro generale 8218 del 2015, proposto dai
signori Sara Franchino, Sebastiano Strazzeri, Onorato Passarelli, Davide
Betti, Rosanna Borsa, Antonio Del Buono, Sabrina Margherita Giovine,
Jessica Molino, Salvatore Calogero Piccicuto e Sebastiana Trigila,
rappresentati e difesi dall'avv. Giorgio Strambi, con domicilio eletto
presso il Consiglio di Stato – Segreteria in Roma, piazza Capo di Ferro
13;
contro
la signora Patrizia Borgarello;
Las herramientas web son sitios que facilitan el compartir información y la colaboración entre usuarios. Permiten que los usuarios interactúen y creen contenido en lugar de limitarse a observar pasivamente. Algunos ejemplos son comunidades web, redes sociales, wikis y blogs. Estas herramientas aprovechan la inteligencia colectiva y permiten compartir recursos digitales creados por los usuarios.
Este documento presenta los ganadores y finalistas de la XII edición del Premio Luis Valtueña de fotografía humanitaria organizado por Médicos del Mundo. Entre los ganadores se encuentran fotógrafos de países como Chile, España, Bélgica, Dinamarca, Italia, Portugal y Argentina, cuyas obras documentan diversas crisis humanitarias como desastres naturales, conflictos, pobreza, enfermedades y migración en regiones de Latinoamérica, África, Asia y Medio Oriente. El primer premio recayó en
The document announces a public meeting of the City Council of San Angelo, Texas to take place on April 5, 2011. The agenda includes opening procedures, consideration of proclamations and recognitions, public comment, and a consent agenda with various items for approval. The regular agenda includes an executive session to discuss economic development and a public hearing on adopting a resolution.
An overview of the scientific, technological and engineering achievements of Lawrence Livermore National Laboratory researchers from January to March 2014. For more Science and Technology Updates, visit https://st.llnl.gov/showcase/st-update.
This document summarizes a student's research on the effects of goat manure on the growth and yield of corn in Liberia. The student aims to fulfill requirements for a Bachelor of Science degree. The introduction provides background on corn as a major crop in Liberia and how organic or inorganic fertilizers influence yield. The specific objectives are to determine the rate of goat manure application and its effects on vegetative growth and yield. The significance is that the research will provide farmers guidance on fertilizer use to improve yields. The methodology, results and conclusion will be discussed in subsequent chapters.
En mi condición de Gerente del Departamento de Comunicaciones y Relaciones, de la Central de Cooperativas Cafetaleras de Honduras, coordiné la elaboración de un documento de análisis de los impactos de la crisis en los productores afiliados a La Central, planteando también la tesis sobre la oportunidad que ofrecía la crisis cafetalera para los pequeños y medianos productores organizados en cooperativas e integrados en La Central.
This document outlines Jose L. Martinez's professional achievements and work samples. It lists four awards he received between 2014-2015, including Best of New York State in 2014, Digital Government Achievement National Award in 2014, Best of New York City in 2014, and Igniting Innovation National Award in 2015. It also provides details on the NYCStreets Permit Management System project for New York City DOT from 2012-2016, including team building, marketing, and Agile/Scrum artifacts.
The document discusses the rehabilitation of aging bridges through innovative engineering techniques. It focuses on the rehabilitation of the Angus L. Macdonald Bridge in Halifax, Nova Scotia. The rehabilitation involved replacing the entire suspended structure of the bridge in segments over 10.5-hour nightly closures. This allowed for a brand new suspended structure with increased service life and reduced maintenance costs. The rehabilitation also improved traffic flow and increased shipping clearances under the bridge. Through continuous development of innovative rehabilitation techniques, owners can address aging infrastructure issues and provide long-term solutions.
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...Lucas de Brito Nascimento
The document analyzes two viaduct rehabilitation projects in the US. It describes the Interstate 91 Viaduct Rehabilitation Project in Massachusetts, which aims to replace the deteriorating bridge deck through accelerated bridge construction techniques to minimize costs and disruption. It also outlines the North Spring Street Viaduct Widening Project in California, which intends to address geometric deficiencies, seismic issues, and improve bicycle and pedestrian access. The document then compares the two projects.
This document discusses water intrusion in the I-93 tunnels in Boston and efforts to seal leaks. It notes that some water intrusion is normal during tunnel construction and leaks are typically sealed through pressure grouting of cracks in the concrete. While the tunnels experience more leaks currently than completed tunnels, the amount of leakage is within industry norms. Efforts to seal leaks through grouting are standard practice and will continue through project completion to further reduce water intrusion.
The document discusses the design and construction challenges of the Deh Cho Bridge in the Northwest Territories of Canada. Some key points:
- The bridge crosses the Mackenzie River and connects Yellowknife to Highway 1, replacing a ferry. Its remote northern location and extreme winter conditions of -40°C posed challenges.
- An innovative extradosed bridge design was used with a 1045m continuous superstructure and expansion joints only at the abutments.
- Construction methods like incremental launching and extensive prefabrication were employed to minimize field work during the short construction season.
- Rigorous shop trial assembly and quality control processes were required given the remote site and need to minimize repairs.
Review on studies and research on widening of existing concrete bridgesIRJET Journal
This document summarizes several studies that have been conducted on widening existing concrete bridges. It describes a study from China that examined load distribution factors for a bridge widened with composite steel-concrete girders. It also outlines challenges and solutions for widening a bridge in the UAE, including replacing bearings and stitching the new and existing structures. Additionally, it discusses two bridge widening projects in New Zealand that involved adding precast beams and stitching to connect structures. Finally, safety measures and challenges for strengthening a historic bridge in Switzerland under live traffic are presented.
Walton Boulevard Reconstruction, APWA Project of the YearOHM Advisors
http://www.ohm-advisors.com. An APWA award-winning project, reconstructing Walton Boulevard, in the City of Auburn Hills, was no easy task. Start with 1.5 miles of road, an old bridge over a major freeway, and three government owners. Then, throw in high priority federal and state funding deadlines and a five month schedule to complete. No problem. If you're OHM, and you're committed to Advancing Communities!
This document provides details about the Samuel Beckett Bridge in Dublin, Ireland. It is a cable-stayed steel structure with a 123m main span across the River Liffey. The bridge rotates 90 degrees to allow ship traffic. It has an asymmetric shape influenced by maintaining the navigable river channel. The bridge structure transfers loads through a box girder deck, cable stays in tension, and a curved pylon foundation. Live loads include traffic and wind. Value engineering identified cost savings such as using steel blocks instead of lead shot for ballast.
This document provides details about the planning and design of a reinforced concrete bridge at Challathadi, Aivarnadu. A team of civil engineering students conducted surveys of the site, designed a T-beam bridge using limit state methods, and created drawings, estimates, and a model. They reviewed literature on bridge design and failure factors. The objective was to plan, analyze, and design an RCC bridge to connect local villages. The methodology included site visits, surveys, fixation of dimensions, AutoCAD drawings, manual design, estimation, and model making. The work was carried out from December to March under the guidance of a professor.
The Downtown Crossing bridge project in Louisville, Kentucky is progressing ahead of schedule. Steel work is expected to be completed by late October 2015 and the bridge is scheduled to open to traffic in January 2016. The 642m, $860 million cable-stayed bridge will connect Louisville to Covington, Indiana, doubling traffic capacity across the Ohio River. Its design incorporates measures like flexible tower foundations and a three-tower arrangement to allow for movement, as well as aesthetic elements like unobstructed tower views. Service life modeling was used to design the bridge to last 100 years with minimal maintenance.
This document summarizes research presented at the 2015 Transportation Research Board meeting regarding new approaches to bridge construction.
Researchers at LSU developed a new approach slab system using precast deck slabs paired with geotextile-reinforced embankments to eliminate differential settlement issues that cause "end bumps" at bridge approaches in Louisiana. Field testing over two years showed the new system had better performance than traditional methods.
Additional research showed that connections and grouts used in precast deck panels are critical to their long-term performance. Tests identified best practices for surface preparation, grout selection, and design considerations to ensure durability of the connections under loading.
Other research presented testing of a hybrid jacketing
Case study: Widening an existing bridge structure Challenges and solutionsIRJET Journal
This document summarizes the process of widening an existing bridge in the UAE. It faced several challenges, including replacing deteriorated bearings, repairing cracks and defects found after removing pavement, constructing approach slabs where there were none previously, addressing differences in cross-slope between the existing and new structures, protecting the deck from chemicals, and strengthening an existing pier with carbon fiber reinforced polymer sheets. These challenges were addressed through methods like jacking the bridge to replace bearings, repairing cracks, constructing new approach slabs, using leveling concrete to create uniform cross-slope, applying waterproofing, and installing CFRP sheets to strengthen the pier according to product specifications. The widening resulted in two bridges with four
The Detail Project Report is an essential building block for any construction project. The DPR is to be prepared carefully and with sufficient details to ensure appraisal, approval, and subsequent implementation in a timely and efficient manner. The detailed project report gives us the clear idea about the existing site conditions and improvements needed to be accomplished. The DPR survey has been done for construction of a high level bridge on road pertaining @ km 6/2 (R&B) road to Kadapa district. The bridge crosses the river in normal crossing. It has total span of 50.80mts.This work has been executed under MNREGS scheme. The bridge has 3 vents of 6.37m effective span. The bridge is constructed across the stream to provide transportation facilities to people of Proddatur to various places of Kadapa District. This stream has an adequate discharge of 97.00 cusecs and it increases more during in rainy season. Traffic studies have been conducted on this road and the outcome was 120cvpd. The maximum flood level of this stream is 99.830.The linear water way is 18.00m. The design drawings and plans were given by MORT&H for execution of work. To calculate the discharge levels has been surveyed around 300mts both upstream and down streams. Funding for this project has been given by the government of A.P. The work has to be completed in a period of one year. The total estimate amount of the project is said to be 69.50 Lakhs.
1) The concrete durability strategy for the Rion-Antirion Bridge project focused on controlling corrosion of embedded steel by reducing chloride penetration through proper definition of exposure zones, concrete covers, and characterization of concrete mixes.
2) Specific tests were performed on concrete mixes to evaluate durability parameters such as rapid chloride penetration, water penetration, chloride diffusion coefficient, and oxygen permeability.
3) Strict quality assurance/quality control procedures were followed during construction to ensure the in-situ concrete quality matched specifications and laboratory results.
This document provides a method statement for repair works to existing river walls and installation of a new secant pile wall to support the widening of an access road for the North Blyth Renewable Energy Project. The existing river walls are in poor condition with sections that have collapsed or are subsiding. The selected design option is to install an interlocking bored secant pile wall approximately 4-4.5m landward of the existing walls. This will provide support for the widened road without requiring excavation of contaminated fill materials or causing loss of intertidal mudflat habitat, while reducing noise and vibration impacts compared to other options.
Jamie Tousignant has over 25 years of experience as a project superintendent on a variety of public and private infrastructure projects. He has experience managing both civil works and structural projects, including those with environmental components. Some of the key projects he oversaw included the $30 million Mile 36 Alaska Highway infrastructure project, the $15 million Keeyask Dam site buildings project in Manitoba, and the $3 million South Surrey Park and Ride expansion. Throughout his career, he has successfully delivered projects on time and on budget while maintaining safety and cooperation between stakeholders.
The M8 Footbridge in Harthill, Scotland was designed using an innovative helical truss design made of circular hollow steel sections to provide a pedestrian crossing over one of Scotland's busiest motorways. Steel was chosen as the primary construction material due to its strength, aesthetic qualities, and ability to be prefabricated off-site for improved safety and construction time. The complex steel structure was fabricated in sections off-site and erected over a single evening closure of the motorway to minimize disruption.
Innovative solutions for complex geotechnical and tunnelling projects, april ...Dr Mazin Alhamrany
Dr Mazin Alhamrany has experience of more than 25 years in the field of Geotechnical and Tunneling Engineering. Dr Mazin is specialist in the field of applications of Finite Element Method for tackling soil-structure interaction problems. He is a highly experienced in 2D and 3D Finite Element Modelling, using advanced soil models, to simulate construction staging and soil-structure interaction to produce buildable economic designs and to assess the impact of carrying out engineering activities such as deep excavations on existing adjacent structures. We have a solid reputation in finding innovative solutions for complex geotechnical and tunneling projects.
Innovative solutions for complex geotechnical and tunnelling projects, april ...Dr Mazin Alhamrany
Dr Mazin Alhamrany has experience of more than 25 years in the field of Geotechnical and Tunneling Engineering. Dr Mazin is specialist in the field of applications of Finite Element Method for tackling complex soil-structure interaction problems.
Neville Bryant is a retired Australian civil engineer with over 50 years of experience in the oil and gas industry. He has extensive expertise in LNG plant construction, having worked on 6 LNG trains. His areas of specialty include cryogenic and hot insulation, marine infrastructure like LNG jetties, dredging over 25 million cubic meters, and managing large capital projects. Since retiring from Woodside Energy in 2014, he has consulted part-time in the oil and gas industry.
Nicolas Theodor is a senior bridge engineer with over 30 years of experience working for the Ministry of Transportation of Ontario in progressively more responsible positions. He has extensive experience designing all types of bridges using Canadian and American design codes. Throughout his career he has managed large, complex bridge projects and has saved millions through value engineering efforts. Currently he works as a senior bridge engineer for Amec Foster Wheeler, where he provides expertise on bridge design, code interpretation, and project management.
Similar to 060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar (20)
This presentation summarizes two case studies of upgrading urban interchanges in a sustainable manner while addressing existing constraints. In the first case study, an existing elevated roundabout was replaced with a signalized junction (SPUI) to avoid constructing a costly three-level interchange. Precast elements and spread foundations reduced costs. The second case study describes widening an existing two-cell underpass by 3.5 meters using precast deck extensions, instead of the originally proposed 20 meter extensions, to minimize traffic disruptions. Both case studies emphasized jointless construction and natural ventilation to reduce maintenance needs and avoid tunnel effects.
Zambezi River Crossing Feasibility StudyJavad Akhtar
The Zambezi River Crossing Feasibility Study investigated alternative crossings of the Zambezi River in Mozambique for the client DNEP, including upgrading an existing ferry and designs for pontoon, Bailey bridge, and ferry berthing ramp structures. Hydrological studies were conducted to analyze river flows and flood behavior to inform the most cost-effective crossing design.
Mott MacDonald has designed and constructed sign and signal gantries for highways and railways throughout the UK since 1995. They have contributed to gantry design on many major projects, including for the Medway Tunnel, Channel Tunnel Terminal, Birmingham-Nottingham-M25 route, and Croydon Tramlink. More recently, Mott MacDonald designed an improved modular aluminum gantry for emergency situations and developed computerized design methods for sign gantries used at the Channel Tunnel Terminal and Medway Crossing.
The Overseas Development Administration (now DFID) commissioned a review of its Bailey bridge construction program in Mozambique's Zambezia Province, which had been initiated after the civil war to open routes for aid agencies. The review involved visiting bridge sites, inspecting structures, and discussing the program with relevant agencies. It concluded by producing a report proposing an extension project to transfer technology, develop self-reliance, repair existing assets, improve facilities, and generate an ability to maintain roads and bridges going forward.
Bridges on Kapchorwa – Suam Road_UgandaJavad Akhtar
This document summarizes a feasibility study and design work for bridges along the Kapchorwa – Suam Road in Uganda. The study evaluated upgrading the deteriorated mud track road, which passes through a national park, to an all-weather route. Due to limited traffic and funds, a strategy was adopted to rehabilitate suitable existing bridges and replace severely deficient structures. Typical modifications to the 6 existing bridges included re-kerbing, reconstructing parapets and resurfacing. Some steel beam bridges were converted to composite steel-concrete structures. Replacement bridges used reinforced concrete box or beam and slab designs to facilitate simple local construction.
Mott MacDonald has provided expertise to Nepal's Ministry of Water Resources for the Rajapur Irrigation Project since 1998. A key part of the project is crossing the Geruwa River at Kothiyaghat with a pontoon bridge, as a permanent bridge would be too expensive given the river's unpredictable flooding. Mott MacDonald conducted feasibility studies and developed a design-and-construct contract for the pontoon bridge and associated works, advising during the contract award process and reviewing the contractor's developed design for construction.
The document discusses innovations for cantilever sign foundations used on highways. It describes the components of the MS3 cantilever sign structure, including the enclosure, arm, main post, and head design arrangement. It also outlines considerations for siting signs, the design procedure, and provides examples of possible foundation types including concrete pile foundations and steel pile or cable stay foundations.
The document discusses approaches to bridge refurbishment projects. It outlines the challenges in identifying problems, agreeing on solutions, and implementing repairs. Examples are provided of construction defects, issues arising over time from changes in use or hazards, and solutions implemented including strengthening elements and protecting against deterioration. The process of investigating causes, devising and convincing others of solutions, monitoring implementation, and tracking the structure long-term is described.
Isambard Kingdom Brunel was an influential British engineer in the 19th century best known for designing numerous important bridges and railways. One of his earliest bridges was the 1838-39 Paddington Canal Bridge, which was recently discovered to be the first cast iron bridge designed by Brunel. The bridge was carefully dismantled and preserved during the Paddington LTVA bridge project, which replaced an existing bridge over 15 rail tracks and a canal near Paddington station in London. The project involved raising the existing bowstring arch bridge, constructing new support structures, and launching a new rail bridge deck between 2004-2006 while minimizing disruption.
The document summarizes a conference on tunnels and underground construction in the Middle East. It provides details on the conference location, dates, speakers, and topics to be discussed. The conference will take place March 14-15, 2011 in Abu Dhabi, UAE and will focus on design, construction, operation, and projects related to tunnels and underground structures in the region. Over 30 speakers will provide insights on completed, current, and future projects to help attendees deliver projects on time and on budget.
This document discusses maintenance management of bridges and underpasses. It outlines threats like environmental factors, material deterioration, traffic usage, and human/terrorist threats. Specific threats in the Middle East include extreme temperatures and salty soil deteriorating concrete. The document recommends establishing routine maintenance, condition inspections, load assessments, and long-term asset management to ensure bridge safety. This includes data collection, preventative maintenance, and planned refurbishment/replacement.
1. School of
Engineering and Design
First International Conference on
Advances in Bridge Engineering
Bridges - Past,
Present and Future
co-sponsored by
“Celebrating the 200th Birth
Anniversary of Isambard
Kingdom Brunel”
www.brunel.ac.uk/about/acad/sed/bec2006
to be held at Brunel University, West London
26-28th June 2006
2. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Temple Mills Bridge Reconstruction
Javad Akhtar
Hyder Consulting (UK) Ltd.
Abstract
Temple Mills Bridge built in 1963, carries the A106, over the River Lea in five spans.
The original bridge decks of 50m overall length, consist of precast, prestressed
concrete beams with in situ concrete infill, supported on piled reinforced concrete
piers and abutments. Extensive chloride contamination and difficult maintenance
issues led to the decision to replace the structure. A number of alternative deck
replacement solutions were examined – including complete “encapsulation” within
new precast concrete arches.
Careful risk management played an important part in being able to develop the most
economical solution within the framework of a design and build contract under NEC
Option C conditions of contract. Review of geotechnical data and concrete testing
concluded that the existing foundations were acceptable for re-use. The replacement
adopted a similar span arrangement, but with a deck of semi-integral construction,
bearings only being provided at the abutments. The original piers were demolished
down to river foundation level and new ones built up with epoxy coated reinforcement
below river level. The abutments were extended to form a series of plinths for the
bearing shelf with existing faces encased in a 100mm thick skin of new concrete. piers.
A wide range of Environmental mitigation measures were undertaken, including
hydraulic design to cater for future “Global Warming”. The design allows for the
passage of small mammals along the river-banks and bat roosting facilities. The
environmental management plan included a range of measures to mitigate noise and
pollution threats.
Keywords: Bridge Reconstruction, Rehabilitation, Concrete Repair, precast prestressed, foundations,
environmental, traffic management, GGBFS, PFA, DPS, epoxy coated reinforcement.
3. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
1.0 Background
Temple Mills Bridge is sited an Olympic champion’s stone’s throw from the site of the main Olympic Park
in Stratford. The bridge, built in 1963, carries one of the area’s major routes, the A106, over the River Lea.
The existing bridge consists of two nearly identical structures, 50 metres long, each carrying a three lane
carriageway, a footway/cycleway and a central paved verge. The bridge decks are separated by a 3.66 metre
gap and consist of precast, prestressed concrete beams with in situ concrete infill. Each five-span bridge
structure is supported on reinforced concrete piers and abutments supported on piles. Unusually, the piers are
articulated by means of bearings halfway up the pier, with a concrete ‘hinge’ detail at the top. Whilst many
parts of the structure were judged beyond economic repair, the river foundations and the abutment supports
were re-used.
Due to the high traffic volumes in the area, the replacement took place in two parts with traffic diverted
initially all to the south carriageway while demolition and reconstruction of the North Carriageway was
undertaken. By careful re-assessment of the existing deck four lanes were maintained for traffic, and services
diverted to the other side.
2.0 Defects in original structure
Most of the problems with the bridge stem from inadequate waterproofing at the time of construction. The
bridge was built just before the Highways Agency (HA) introduced specific requirements for waterproofing.
The bitumen impregnated jute used at the time has failed to prevent water ingress, to the point that stalactites
had formed on extensive areas at the underside of the bridge deck. The water ingress had also caused the
sliding bearings of the abutments to seize to a point where they were beyond repair.
Previous investigations had also revealed that reinforcement corrosion due to chloride attack in the insitu
concrete “stitch” over the piers had progressed to the point that the deck could no longer sustain the applied
hogging moment over the piers due to vehicle loading on the continuous deck.
Fortunately, the original contractor had designed beams to cater for simply supported loading conditions,
rather than attempt to refine the design to suit the actual complex continuous frame system. Thus, although
the bridge is currently not supporting the applied loading in the manner intended by the designer, the reserve
of strength in the beams has saved it from a more imminent demise.
A further concern with the structure was that a “mechanism” type failure mode of the piers was possible
due to the presence of bearings at the lower part of the piers and the loss of moment restraint due to corrosion
of reinforcement in the insitu concrete stitch at the top of the pier. This failure mode was only prevented by
the restraint provided by the abutment curtain wall and the seized abutment bearings. Furthermore parapets
did not conform to current standards.
These concerns over long-term structural behaviour and the whole life costs of a growing programme of
investigation, monitoring and repair led to Hackney Council’s decision to replace the structure.
3 Project/Risk Management
Hyder Consulting was appointed by the London Borough of Hackney in 2003 as Project Managers to
review and consolidate the findings of previous studies, to develop the options for the crossing and to
supervise the detailed bridge design and construction phases. In February 2004, contractor Norwest Holst
with Designers Mouchel Parkman started the £2 million, 18 month design and build project to replace the
existing bridge.
4. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
3.1 Pre-contract Planning
Prior to letting the design and construction contract, the following steps were undertaken:
• Scheme, program & procurement strategy review with LB Hackney
• Stakeholder Consultation
• Technical Investigations and Studies (Hydraulic Flow Modelling, Traffic Counts, Traffic Modelling,
Site Investigations, Planning Review, Environmental Appraisal, Contaminated Land investigation etc.
• Design performance criteria and specifications
• Preparation of reference designs
• Contract Documents
• CDM Risk Assessment and Pre-Tender Health & Safety Plan
These processes are illustrated on the figure 1.
3.2 Contract Strategy
The “ideal” form of construction contract was initially considered as NEC Form A for simplicity of
administration and price certainty. However this was changed to NEC Option C to meet LBH accelerated
program and to allow early letting of the design and construct contract prior to completion of the various
investigations and studies. Tender documents were issued Oct 03 (two months after Hyder appointment).
Tender evaluation was based on a 60:40 Quality: Price weighting.
3.3 Risk Management
The key risks identified at project planning stage are given in Table 1 below, with a brief indication of
mitigation measures. During construction a much more extensive Risk Register was developed based on
contractual “Early Warnings”.
Table 1 Perceived Risks and Proposed Mitigation Measures
Risk Comment/Mitigation
Travellers not moving Two separate Traveller Community encampments were present adjacent
to the site. Sensitive discussion and liaison resulted in peaceful
relocation of these communities.
Geotechnical - Lack of Information/ reuse of
existing foundations (abutment & river
piles/pedestals)
An extensive amount of Ground Investigation data was obtained from
Transport for London (TfL) archives relating to the A12 Project. Further
Site Investigations were instigated during the course of the contract.
Construction unknowns Dealt with through contractual “Early Warning” register.
Environment Agency (EA) requirements &
timing of responses
Maintained close contact with relevant responsible officers within EA.
Extensive hydraulic and environmental studies undertaken.
Potential Traffic Problems Traffic studies undertaken and flows modelled to prove feasibility.
Close liaison with Police, TfL, Buses and transport operators.
Public Objection Extensive consultations and publicity.
Identification of key stakeholders and planning to minimise impacts.
Control of Construction Costs and planning
of Funding
Administration of contract to limit instructed variations and close liaison
with funding authorities, including raising risk awareness and provision
of cash-flow forecasts.
Statutory Undertakers (SU’s) requirements
and information issue
Early development of plans with SU’s and close liaison.
Major Sewers (syphon+Chambers) under
bridge at river bed level
Close liaison with Thames Water Utilities. Provision of protective
measures.
5. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
4 Alternatives Considered
One of the options considered during project planning stage was the propping and encapsulation of the
existing structure on precast concrete arches launched from the existing river foundations. While this option
would have avoided demolition with the associated requirements for traffic and services diversions, it was
ruled out in conjunction with the Environment Agency because of worries over the hydraulic and ecological
effects on the River Lea. Indeed, environmental issues are to the forefront generally because of the bridge’s
location on the fringes of the Lea Valley Regional Park.
5 Environmental Considerations
One consequence is that the deck of the new bridge will be 0.5 metre higher than the original. This again
takes into account some Environment Agency (EA) concerns about a 1 in 100 year flood event with a further
20% allowance for “Global Warming”. Hydraulic studies were scoped and commissioned by Hyder from
external consultants – Halcrow, in order to re-assure the EA that the results were indeed independent from the
construction team.
The “hard” revetments adjacent to the riverbank have been lined with “Geoweb” plastic mesh infilled with
granular material in order to aid soil retention, vegetation growth and habitat creation. A minor surface bank
slip adjacent to the structure has been stabilised by willow stakes.
The design of the new structure will also allow for the easier passage of small mammals along the river-
banks and will provide for bat roosting facilities. The construction team liaised closely with Hackney Council
and the Environment Agency to mitigate potential noise and pollution threats.
5.1 Traffic Modelling
Due to the critical location of the structure, Hackney were anxious to ensure that traffic flows were catered
for with minimal disruption. Hyder therefore undertook advance traffic-modelling studies and developed an
outline Traffic Management Scheme in liaison with Hackney, Transport for London, emergency services,
transport operators and other stakeholders. The planned construction phasing allowed for services diversions,
with the new structure also providing spare capacity to cater for future services.
6 Aspects of Design of Replacement Structure
6.4 Structural Form and Deck
Refer to figures 6 and 7 for deck details (from drawings by Messrs Mouchel Parkman). An infilled precast
prestressed deck was adopted, continuous and integral over intermediate pier transoms, supported by
laminated rubber bearings at abutments. This semi-continuous form minimised any additional lateral loads
on the existing concrete bored piled abutments.
6.2 Materials
In order to improve longer term durability, the new bridge was constructed using a Ground Granulated
Blast Furnace Slag (GGBFS) concrete mix. This in turn was subject to a two part spray waterproofing.
To prevent environmental pollution of the watercourse, impregnation of the concrete was undertaken using
“Deep Penetrating Sealant” rather than Silane. This forms a permanent protective “glass” coating to the outer
pores of the concrete that does not require renewal. DPS whilst having a history of use in Norway and other
countries, does not previously appear to have been used in the UK.
6. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
6.3 Foundations
The existing 1.5m diameter, 6m deep cylindrical reinforced concrete “Pedestal” foundations were
geotechnically appraised for upper and lower bound geotechnical parameters and judged capable of taking the
loads from the new structure (which in any case were lower than pre-existing loads).
Contingency risk-management planning was undertaken in case the concrete condition (which would only
be apparent once the existing piers were damaged and cofferdams installed) was found to be poor. However
in the event the pedestals were found to be in good condition.
Whilst the effects of the enlarged tops of concrete pedestals have been hydraulically modelled and shown to
have little impact on the flow of the River Lea, large pieces of concrete from the deck demolition will be
placed around the pile cap to mitigate the possibility of scour on the pile caps below the water level. This is
being done as a precaution against possible eddy currents under and around the lips of the enlarged pedestals.
Refer to figure 5 New Piers Founded on Existing "Pedestal" Foundations.
7 Construction
Demolition of the original bridge started with the northern carriageway. This initially required the
stabilisation of the existing bridge piers and the positioning of pontoons underneath the bridge deck.
Hydraulic breakers then moved in to break up the deck, with the debris being scooped up from the pontoons
below using small robotic excavators refer to figure 8 Deck Demolition on Pontoons.
As the deck is removed temporary struts were put up to support the piers before removal of these down to
river floor level. This was undertaken in two stages, firstly down to the level of the pier bearings, followed by
removal of the stubs below the waterline down to the level of the top of the “Pedestal” foundations.
In order to begin the construction of the new piers, precast concrete rings were first embedded around the
existing pile caps. As well as creating enlarged pedestals, these served as coffer-dams during the river level
works and provided shuttering moulds for the concrete pour of the new piers. Prior to the pour, new epoxy
coated reinforcement bars were drilled and resin anchored in to the existing pedestal.
While tests on the loading capabilities of the abutments showed good performance with core test results of
60 KPa, there was evidence of some corrosion of non-structural steel reinforcement in the abutment face due
to water leaking in from the top and side of the expansion joints. Mouchel-Parkman, who carried out the
detailed design for Norwest Holst, proposed that, the top of the existing abutments be scabbled down and new
reinforcement bars resin anchored in at close centres. The abutments were then extended to form a series of
plinths for the bearing shelf with existing faces encased in a 100mm thick skin of new concrete.
The buried faces of the abutments were tested and found to have negligible chloride contamination,
however due to the uneven concrete finish it was decided to extend the “encapsulation” concrete skin to the
rear face of the abutment also.
In the river itself, particular care was required working around the three 1 metre diameter sewage pipes
which run longitudinally through the middle of the bridge just below the river floor. In the first stage the
pontoons protected these pipes. However it was found that the pontoons grounded easily and would actually
obstruct the river in the event of an unforeseen flood event. For demolition of the southern half of the deck
the pontoons were omitted and a crash-deck provided - comprising a 300 mm thick granular pad over two
layers of steel sheet piles laid flat on the bed (spanning the pipes).
7. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Precast beam erection was undertaken using a mobile crane sited just behind the abutments (refer to figure
9). Difficulties were encountered at the junction between previously erected North Deck and the South deck
due to the need to “mesh” into the 3 dimensional reinforcement cage provided out of the cross-head and
continuity reinforcement from the pre-erected deck. These were overcome by use of reinforcement couplers.
8 Conclusion
Completion of this bridge in March 2006 secured this important local transport link and marks the first
project to cross the finish line at the start of the major developments on the adjacent Olympic site.
Acknowledgements
The author, whose role was as Project Manager, wishes to acknowledge the assistance and support of….
Client Manager Joe Figurado London Borough of Hackney
Supervisor Richard Williams Hyder Consulting (UK) Ltd.
Contractor Mark McGleenon Norwest Holst Construction Ltd
Contractor’s Designer Andrew Foster Mouchel-Parkman Ltd
Figure 1 Pre-Construction Contract Project Management Processes
Figure 2 Existing Bridge
8. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Figure 3 Installation of Phase 1 Traffic Management
9. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Figure 4 Scheme Options Considered
Figure 5 New Piers Founded on Existing "Pedestal" Foundations
(Note details slightly modified during construction)
Figure 6 Deck Cross-section at Central Reserve
10. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Figure 7 Deck Long-section at Abutment and Abutment “Encapsulation” Detail
Figure 8 Deck Long-section at Abutment and Abutment “Encapsulation” Detail
Figure 8 Deck Demolition
11. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Figure 9 Precast Beam Erection
12. Call for papers
The theme of the conference will be ‘Bridges - past,
present and future’. Papers can be presented on
any aspect of the development of knowledge,
techniques, innovations, control, monitoring and
management processes which may represent an
advancement in the field of bridge engineering. A
special session on Historical Bridges, with particular
emphasis on Brunel’s work, is planned to celebrate his
200th birth anniversary.
Invited Speakers
The following have indicated acceptance of
invitations to make Keynote Presentations:
Mr Steven Brindle
English Heritage, UK
Prof Jean Armand Calgaro
ENPC and GCPC, Paris, France
Prof Jacques Heyman
Cambridge University, UK
Mr Makoto Kitagawa
Honshu Bridge Authority, Japan
Mr Brian Pritchard
Consultant, formerly Atkins, UK
Prof Santiago Huerta
University of Madrid, Spain
Prof Michael Collins
Toronto University, Canada
Requirements and dates
Authors wishing to present a paper should submit an
abstract (300 words approx.). Abstracts and Papers
must be in English and should clearly indicate the
contact author details (affiliation, address, telephone,
FAX and e-mail). The abstracts may be submitted by
post (Bridge Conference 2006, Research Office,
School of Engineering and Design, Brunel University,
Uxbridge, UB8 3PH, UK) or e-mail
(bridgeconf.2006@brunel.ac.uk)
Target dates
Submission of Abstracts 30 December 2005
Acceptance of Abstracts 6 January 2006
Submission of full Manuscripts 28 February 2006
Final acceptance will be based on peer-review of the
full manuscript.
Final Manuscripts should be no more than
8 pages in length and must comply with the
'Instructions for Preparing a Paper' available at
www.brunel.ac.uk/about/acad/sed/bec2006
Manuscripts should be submitted via e-mail or
the electronic submission form at the conference
website. In exceptional circumstances, full
manuscripts may be submitted for consideration as
paper hard copy. In all circumstances, a paper hard
copy and an electronic CD-ROM version of the final
manuscript of the paper must be provided for the
publication process by the due date.
First International Conference on
Advances in Bridge Engineering
www.brunel.ac.uk/about/
acad/sed/bec2006
Isambard Kingdom Brunel was a visionary and amongst the most influential engineers of the last millennium.
His wide-ranging works, his aesthetic sense and legacy have withstood the test of time and have been a
constant inspiration to generations of engineers. He was a tunnelling engineer, a railway engineer, a
transportation engineer, a buildings engineer, a marine engineer but above all he was a bridge engineer. Even
the general public who have no special knowledge of engineering matters tend to automatically warm to the
inherent beauty and merit of his works and contribution, recognising the genius he was. The splendid Clifton
Suspension Bridge of his design is an example of this artistry. The University is proud to be named after this
great engineer and following his footsteps shall endeavour to advance the frontiers of knowledge and
engineering for the future.
13. Exhibition
There will be an associated exhibition of selected
equipment, instrumentation, software and
information relating to bridge engineering, providing
delegates an opportunity for exchange of ideas and
information on topics of current interest in the field.
Organisations interested in exhibiting their products
or services should contact the Conference
Administrator for terms and conditions.
Venue
Howell Theatre, Brunel University, Uxbridge,
Middlesex UB8 3PH.
Booking Conditions
i) Early booking is recommended; places will be
reserved on first come first served basis.
ii) Reserved places can be reassigned to another
person by prior written request.
v) Delegates are encouraged to travel by public
transport. A limited number of car parking permits
will be available for parking at the University.
vi)All rights reserved with the University.
Application Form:
First International Conference on Advances in Bridge Engineering on 26-28 June 2006
For reserving a place, please either register online at www.brunel.ac.uk/about/acad/sed/bec2006 or complete this
application form with Conference fee (cheque or transfers made payable to Brunel University) or address for
invoicing to:
Mrs Carole Carr [e-mail: bridgeconf.2006@brunel.ac.uk]
Research Office Manager
Bridge Engineering Centre
School of Engineering and Design
Brunel University
Uxbridge
Middlesex UB8 3PH Tel: 01895 266 962 Fax: 01895 269 797
¡
Registration Fee
The registration fees for the various categories of participants at the conference, which include a copy of the
proceedings, a reception, buffet lunches and refreshments for the 3 days of the conference, are as follows:
Fee received: Before 1 March 2006 From 1 March 2006
Delegates £495 €740 £545 €815
Authors £445 €665 N/A
Students (proof required) £295 €440 £325 €485
Day rate delegates/authors £245 €365 £275 €410
14. SCHOOL OF ENGINEERING AND DESIGN
102240 0106
Conference Organising Committee
Prof Arvind Kumar Kumar Associates & Brunel University
Mr Chris Brown Brunel University
Prof Luiz Wrobel Brunel University
Conference Administrator
Mrs Carole Carr Brunel University
Conference Advisory Committee
Prof Ben Barr Cardiff University & Institution of Civil Engineers
Mr Robert Benaim Robert Benaim & Associates, UK
Mr Steven Brindle English Heritage, UK
Prof Jean Armand Calgaro ENPC and GCPC, Paris, France
Mr Michael Chubb Atkins, UK
Prof Michael Collins Toronto University, Canada
Mr Patrick Dallard Arup, UK
Dr Stuart Davis Mott MacDonald, UK
Prof Christopher Earls Pittsburgh University, USA
Mr Ian Firth Flint & Neil Partnership, UK
Prof Bill Harvey Bill Harvey Associates, UK
Prof Paulo Helene Sao Paulo University, Brazil
Prof Jacques Heyman Cambridge University, UK
Mr Makoto Kitagawa Honshu Bridge Authority, Japan
Prof Paulo Laurenco Minho University, Portugal
Mr Angus Low Arup, UK
Prof Jianming Lu Research Institute of Highways, China
Prof Claudio Modena Padua University, Italy
Mr Graham Nicholson Tony Gee & Partners, UK
Mr Brian Pritchard Consultant formerly Atkins, UK
Mr Nigel Ricketts Network Rail, UK
Prof Charles Roeder Washington University, USA
Mr Benjamin Sadka Highways Agency, UK
Prof Berthold Schlecht Technical University Dresden, Germany
Prof Fernando Stucchi Sao Paulo University, Brazil
Mr Keith Wilson Faber Maunsell, UK
Dr Richard Woodward Transport Research Laboratory, UK
Surname
First Names
Organisation
Position
Address
City
Post Code
Tel
Fax
Date
Fee cheque enclosed
£Or Invoicing Address (UK only)
¡