SlideShare a Scribd company logo
School of
Engineering and Design
First International Conference on
Advances in Bridge Engineering
Bridges - Past,
Present and Future
co-sponsored by
“Celebrating the 200th Birth
Anniversary of Isambard
Kingdom Brunel”
www.brunel.ac.uk/about/acad/sed/bec2006
to be held at Brunel University, West London
26-28th June 2006
Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Temple Mills Bridge Reconstruction
Javad Akhtar
Hyder Consulting (UK) Ltd.
Abstract
Temple Mills Bridge built in 1963, carries the A106, over the River Lea in five spans.
The original bridge decks of 50m overall length, consist of precast, prestressed
concrete beams with in situ concrete infill, supported on piled reinforced concrete
piers and abutments. Extensive chloride contamination and difficult maintenance
issues led to the decision to replace the structure. A number of alternative deck
replacement solutions were examined – including complete “encapsulation” within
new precast concrete arches.
Careful risk management played an important part in being able to develop the most
economical solution within the framework of a design and build contract under NEC
Option C conditions of contract. Review of geotechnical data and concrete testing
concluded that the existing foundations were acceptable for re-use. The replacement
adopted a similar span arrangement, but with a deck of semi-integral construction,
bearings only being provided at the abutments. The original piers were demolished
down to river foundation level and new ones built up with epoxy coated reinforcement
below river level. The abutments were extended to form a series of plinths for the
bearing shelf with existing faces encased in a 100mm thick skin of new concrete. piers.
A wide range of Environmental mitigation measures were undertaken, including
hydraulic design to cater for future “Global Warming”. The design allows for the
passage of small mammals along the river-banks and bat roosting facilities. The
environmental management plan included a range of measures to mitigate noise and
pollution threats.
Keywords: Bridge Reconstruction, Rehabilitation, Concrete Repair, precast prestressed, foundations,
environmental, traffic management, GGBFS, PFA, DPS, epoxy coated reinforcement.
Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
1.0 Background
Temple Mills Bridge is sited an Olympic champion’s stone’s throw from the site of the main Olympic Park
in Stratford. The bridge, built in 1963, carries one of the area’s major routes, the A106, over the River Lea.
The existing bridge consists of two nearly identical structures, 50 metres long, each carrying a three lane
carriageway, a footway/cycleway and a central paved verge. The bridge decks are separated by a 3.66 metre
gap and consist of precast, prestressed concrete beams with in situ concrete infill. Each five-span bridge
structure is supported on reinforced concrete piers and abutments supported on piles. Unusually, the piers are
articulated by means of bearings halfway up the pier, with a concrete ‘hinge’ detail at the top. Whilst many
parts of the structure were judged beyond economic repair, the river foundations and the abutment supports
were re-used.
Due to the high traffic volumes in the area, the replacement took place in two parts with traffic diverted
initially all to the south carriageway while demolition and reconstruction of the North Carriageway was
undertaken. By careful re-assessment of the existing deck four lanes were maintained for traffic, and services
diverted to the other side.
2.0 Defects in original structure
Most of the problems with the bridge stem from inadequate waterproofing at the time of construction. The
bridge was built just before the Highways Agency (HA) introduced specific requirements for waterproofing.
The bitumen impregnated jute used at the time has failed to prevent water ingress, to the point that stalactites
had formed on extensive areas at the underside of the bridge deck. The water ingress had also caused the
sliding bearings of the abutments to seize to a point where they were beyond repair.
Previous investigations had also revealed that reinforcement corrosion due to chloride attack in the insitu
concrete “stitch” over the piers had progressed to the point that the deck could no longer sustain the applied
hogging moment over the piers due to vehicle loading on the continuous deck.
Fortunately, the original contractor had designed beams to cater for simply supported loading conditions,
rather than attempt to refine the design to suit the actual complex continuous frame system. Thus, although
the bridge is currently not supporting the applied loading in the manner intended by the designer, the reserve
of strength in the beams has saved it from a more imminent demise.
A further concern with the structure was that a “mechanism” type failure mode of the piers was possible
due to the presence of bearings at the lower part of the piers and the loss of moment restraint due to corrosion
of reinforcement in the insitu concrete stitch at the top of the pier. This failure mode was only prevented by
the restraint provided by the abutment curtain wall and the seized abutment bearings. Furthermore parapets
did not conform to current standards.
These concerns over long-term structural behaviour and the whole life costs of a growing programme of
investigation, monitoring and repair led to Hackney Council’s decision to replace the structure.
3 Project/Risk Management
Hyder Consulting was appointed by the London Borough of Hackney in 2003 as Project Managers to
review and consolidate the findings of previous studies, to develop the options for the crossing and to
supervise the detailed bridge design and construction phases. In February 2004, contractor Norwest Holst
with Designers Mouchel Parkman started the £2 million, 18 month design and build project to replace the
existing bridge.
Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
3.1 Pre-contract Planning
Prior to letting the design and construction contract, the following steps were undertaken:
• Scheme, program & procurement strategy review with LB Hackney
• Stakeholder Consultation
• Technical Investigations and Studies (Hydraulic Flow Modelling, Traffic Counts, Traffic Modelling,
Site Investigations, Planning Review, Environmental Appraisal, Contaminated Land investigation etc.
• Design performance criteria and specifications
• Preparation of reference designs
• Contract Documents
• CDM Risk Assessment and Pre-Tender Health & Safety Plan
These processes are illustrated on the figure 1.
3.2 Contract Strategy
The “ideal” form of construction contract was initially considered as NEC Form A for simplicity of
administration and price certainty. However this was changed to NEC Option C to meet LBH accelerated
program and to allow early letting of the design and construct contract prior to completion of the various
investigations and studies. Tender documents were issued Oct 03 (two months after Hyder appointment).
Tender evaluation was based on a 60:40 Quality: Price weighting.
3.3 Risk Management
The key risks identified at project planning stage are given in Table 1 below, with a brief indication of
mitigation measures. During construction a much more extensive Risk Register was developed based on
contractual “Early Warnings”.
Table 1 Perceived Risks and Proposed Mitigation Measures
Risk Comment/Mitigation
Travellers not moving Two separate Traveller Community encampments were present adjacent
to the site. Sensitive discussion and liaison resulted in peaceful
relocation of these communities.
Geotechnical - Lack of Information/ reuse of
existing foundations (abutment & river
piles/pedestals)
An extensive amount of Ground Investigation data was obtained from
Transport for London (TfL) archives relating to the A12 Project. Further
Site Investigations were instigated during the course of the contract.
Construction unknowns Dealt with through contractual “Early Warning” register.
Environment Agency (EA) requirements &
timing of responses
Maintained close contact with relevant responsible officers within EA.
Extensive hydraulic and environmental studies undertaken.
Potential Traffic Problems Traffic studies undertaken and flows modelled to prove feasibility.
Close liaison with Police, TfL, Buses and transport operators.
Public Objection Extensive consultations and publicity.
Identification of key stakeholders and planning to minimise impacts.
Control of Construction Costs and planning
of Funding
Administration of contract to limit instructed variations and close liaison
with funding authorities, including raising risk awareness and provision
of cash-flow forecasts.
Statutory Undertakers (SU’s) requirements
and information issue
Early development of plans with SU’s and close liaison.
Major Sewers (syphon+Chambers) under
bridge at river bed level
Close liaison with Thames Water Utilities. Provision of protective
measures.
Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
4 Alternatives Considered
One of the options considered during project planning stage was the propping and encapsulation of the
existing structure on precast concrete arches launched from the existing river foundations. While this option
would have avoided demolition with the associated requirements for traffic and services diversions, it was
ruled out in conjunction with the Environment Agency because of worries over the hydraulic and ecological
effects on the River Lea. Indeed, environmental issues are to the forefront generally because of the bridge’s
location on the fringes of the Lea Valley Regional Park.
5 Environmental Considerations
One consequence is that the deck of the new bridge will be 0.5 metre higher than the original. This again
takes into account some Environment Agency (EA) concerns about a 1 in 100 year flood event with a further
20% allowance for “Global Warming”. Hydraulic studies were scoped and commissioned by Hyder from
external consultants – Halcrow, in order to re-assure the EA that the results were indeed independent from the
construction team.
The “hard” revetments adjacent to the riverbank have been lined with “Geoweb” plastic mesh infilled with
granular material in order to aid soil retention, vegetation growth and habitat creation. A minor surface bank
slip adjacent to the structure has been stabilised by willow stakes.
The design of the new structure will also allow for the easier passage of small mammals along the river-
banks and will provide for bat roosting facilities. The construction team liaised closely with Hackney Council
and the Environment Agency to mitigate potential noise and pollution threats.
5.1 Traffic Modelling
Due to the critical location of the structure, Hackney were anxious to ensure that traffic flows were catered
for with minimal disruption. Hyder therefore undertook advance traffic-modelling studies and developed an
outline Traffic Management Scheme in liaison with Hackney, Transport for London, emergency services,
transport operators and other stakeholders. The planned construction phasing allowed for services diversions,
with the new structure also providing spare capacity to cater for future services.
6 Aspects of Design of Replacement Structure
6.4 Structural Form and Deck
Refer to figures 6 and 7 for deck details (from drawings by Messrs Mouchel Parkman). An infilled precast
prestressed deck was adopted, continuous and integral over intermediate pier transoms, supported by
laminated rubber bearings at abutments. This semi-continuous form minimised any additional lateral loads
on the existing concrete bored piled abutments.
6.2 Materials
In order to improve longer term durability, the new bridge was constructed using a Ground Granulated
Blast Furnace Slag (GGBFS) concrete mix. This in turn was subject to a two part spray waterproofing.
To prevent environmental pollution of the watercourse, impregnation of the concrete was undertaken using
“Deep Penetrating Sealant” rather than Silane. This forms a permanent protective “glass” coating to the outer
pores of the concrete that does not require renewal. DPS whilst having a history of use in Norway and other
countries, does not previously appear to have been used in the UK.
Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
6.3 Foundations
The existing 1.5m diameter, 6m deep cylindrical reinforced concrete “Pedestal” foundations were
geotechnically appraised for upper and lower bound geotechnical parameters and judged capable of taking the
loads from the new structure (which in any case were lower than pre-existing loads).
Contingency risk-management planning was undertaken in case the concrete condition (which would only
be apparent once the existing piers were damaged and cofferdams installed) was found to be poor. However
in the event the pedestals were found to be in good condition.
Whilst the effects of the enlarged tops of concrete pedestals have been hydraulically modelled and shown to
have little impact on the flow of the River Lea, large pieces of concrete from the deck demolition will be
placed around the pile cap to mitigate the possibility of scour on the pile caps below the water level. This is
being done as a precaution against possible eddy currents under and around the lips of the enlarged pedestals.
Refer to figure 5 New Piers Founded on Existing "Pedestal" Foundations.
7 Construction
Demolition of the original bridge started with the northern carriageway. This initially required the
stabilisation of the existing bridge piers and the positioning of pontoons underneath the bridge deck.
Hydraulic breakers then moved in to break up the deck, with the debris being scooped up from the pontoons
below using small robotic excavators refer to figure 8 Deck Demolition on Pontoons.
As the deck is removed temporary struts were put up to support the piers before removal of these down to
river floor level. This was undertaken in two stages, firstly down to the level of the pier bearings, followed by
removal of the stubs below the waterline down to the level of the top of the “Pedestal” foundations.
In order to begin the construction of the new piers, precast concrete rings were first embedded around the
existing pile caps. As well as creating enlarged pedestals, these served as coffer-dams during the river level
works and provided shuttering moulds for the concrete pour of the new piers. Prior to the pour, new epoxy
coated reinforcement bars were drilled and resin anchored in to the existing pedestal.
While tests on the loading capabilities of the abutments showed good performance with core test results of
60 KPa, there was evidence of some corrosion of non-structural steel reinforcement in the abutment face due
to water leaking in from the top and side of the expansion joints. Mouchel-Parkman, who carried out the
detailed design for Norwest Holst, proposed that, the top of the existing abutments be scabbled down and new
reinforcement bars resin anchored in at close centres. The abutments were then extended to form a series of
plinths for the bearing shelf with existing faces encased in a 100mm thick skin of new concrete.
The buried faces of the abutments were tested and found to have negligible chloride contamination,
however due to the uneven concrete finish it was decided to extend the “encapsulation” concrete skin to the
rear face of the abutment also.
In the river itself, particular care was required working around the three 1 metre diameter sewage pipes
which run longitudinally through the middle of the bridge just below the river floor. In the first stage the
pontoons protected these pipes. However it was found that the pontoons grounded easily and would actually
obstruct the river in the event of an unforeseen flood event. For demolition of the southern half of the deck
the pontoons were omitted and a crash-deck provided - comprising a 300 mm thick granular pad over two
layers of steel sheet piles laid flat on the bed (spanning the pipes).
Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Precast beam erection was undertaken using a mobile crane sited just behind the abutments (refer to figure
9). Difficulties were encountered at the junction between previously erected North Deck and the South deck
due to the need to “mesh” into the 3 dimensional reinforcement cage provided out of the cross-head and
continuity reinforcement from the pre-erected deck. These were overcome by use of reinforcement couplers.
8 Conclusion
Completion of this bridge in March 2006 secured this important local transport link and marks the first
project to cross the finish line at the start of the major developments on the adjacent Olympic site.
Acknowledgements
The author, whose role was as Project Manager, wishes to acknowledge the assistance and support of….
Client Manager Joe Figurado London Borough of Hackney
Supervisor Richard Williams Hyder Consulting (UK) Ltd.
Contractor Mark McGleenon Norwest Holst Construction Ltd
Contractor’s Designer Andrew Foster Mouchel-Parkman Ltd
Figure 1 Pre-Construction Contract Project Management Processes
Figure 2 Existing Bridge
Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Figure 3 Installation of Phase 1 Traffic Management
Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Figure 4 Scheme Options Considered
Figure 5 New Piers Founded on Existing "Pedestal" Foundations
(Note details slightly modified during construction)
Figure 6 Deck Cross-section at Central Reserve
Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Figure 7 Deck Long-section at Abutment and Abutment “Encapsulation” Detail
Figure 8 Deck Long-section at Abutment and Abutment “Encapsulation” Detail
Figure 8 Deck Demolition
Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006
TEMPLE MILLS BRIDGE RECONSTRUCTION
Figure 9 Precast Beam Erection
Call for papers
The theme of the conference will be ‘Bridges - past,
present and future’. Papers can be presented on
any aspect of the development of knowledge,
techniques, innovations, control, monitoring and
management processes which may represent an
advancement in the field of bridge engineering. A
special session on Historical Bridges, with particular
emphasis on Brunel’s work, is planned to celebrate his
200th birth anniversary.
Invited Speakers
The following have indicated acceptance of
invitations to make Keynote Presentations:
Mr Steven Brindle
English Heritage, UK
Prof Jean Armand Calgaro
ENPC and GCPC, Paris, France
Prof Jacques Heyman
Cambridge University, UK
Mr Makoto Kitagawa
Honshu Bridge Authority, Japan
Mr Brian Pritchard
Consultant, formerly Atkins, UK
Prof Santiago Huerta
University of Madrid, Spain
Prof Michael Collins
Toronto University, Canada
Requirements and dates
Authors wishing to present a paper should submit an
abstract (300 words approx.). Abstracts and Papers
must be in English and should clearly indicate the
contact author details (affiliation, address, telephone,
FAX and e-mail). The abstracts may be submitted by
post (Bridge Conference 2006, Research Office,
School of Engineering and Design, Brunel University,
Uxbridge, UB8 3PH, UK) or e-mail
(bridgeconf.2006@brunel.ac.uk)
Target dates
Submission of Abstracts 30 December 2005
Acceptance of Abstracts 6 January 2006
Submission of full Manuscripts 28 February 2006
Final acceptance will be based on peer-review of the
full manuscript.
Final Manuscripts should be no more than
8 pages in length and must comply with the
'Instructions for Preparing a Paper' available at
www.brunel.ac.uk/about/acad/sed/bec2006
Manuscripts should be submitted via e-mail or
the electronic submission form at the conference
website. In exceptional circumstances, full
manuscripts may be submitted for consideration as
paper hard copy. In all circumstances, a paper hard
copy and an electronic CD-ROM version of the final
manuscript of the paper must be provided for the
publication process by the due date.
First International Conference on
Advances in Bridge Engineering
www.brunel.ac.uk/about/
acad/sed/bec2006
Isambard Kingdom Brunel was a visionary and amongst the most influential engineers of the last millennium.
His wide-ranging works, his aesthetic sense and legacy have withstood the test of time and have been a
constant inspiration to generations of engineers. He was a tunnelling engineer, a railway engineer, a
transportation engineer, a buildings engineer, a marine engineer but above all he was a bridge engineer. Even
the general public who have no special knowledge of engineering matters tend to automatically warm to the
inherent beauty and merit of his works and contribution, recognising the genius he was. The splendid Clifton
Suspension Bridge of his design is an example of this artistry. The University is proud to be named after this
great engineer and following his footsteps shall endeavour to advance the frontiers of knowledge and
engineering for the future.
Exhibition
There will be an associated exhibition of selected
equipment, instrumentation, software and
information relating to bridge engineering, providing
delegates an opportunity for exchange of ideas and
information on topics of current interest in the field.
Organisations interested in exhibiting their products
or services should contact the Conference
Administrator for terms and conditions.
Venue
Howell Theatre, Brunel University, Uxbridge,
Middlesex UB8 3PH.
Booking Conditions
i) Early booking is recommended; places will be
reserved on first come first served basis.
ii) Reserved places can be reassigned to another
person by prior written request.
v) Delegates are encouraged to travel by public
transport. A limited number of car parking permits
will be available for parking at the University.
vi)All rights reserved with the University.
Application Form:
First International Conference on Advances in Bridge Engineering on 26-28 June 2006
For reserving a place, please either register online at www.brunel.ac.uk/about/acad/sed/bec2006 or complete this
application form with Conference fee (cheque or transfers made payable to Brunel University) or address for
invoicing to:
Mrs Carole Carr [e-mail: bridgeconf.2006@brunel.ac.uk]
Research Office Manager
Bridge Engineering Centre
School of Engineering and Design
Brunel University
Uxbridge
Middlesex UB8 3PH Tel: 01895 266 962 Fax: 01895 269 797
¡
Registration Fee
The registration fees for the various categories of participants at the conference, which include a copy of the
proceedings, a reception, buffet lunches and refreshments for the 3 days of the conference, are as follows:
Fee received: Before 1 March 2006 From 1 March 2006
Delegates £495 €740 £545 €815
Authors £445 €665 N/A
Students (proof required) £295 €440 £325 €485
Day rate delegates/authors £245 €365 £275 €410
SCHOOL OF ENGINEERING AND DESIGN
102240 0106
Conference Organising Committee
Prof Arvind Kumar Kumar Associates & Brunel University
Mr Chris Brown Brunel University
Prof Luiz Wrobel Brunel University
Conference Administrator
Mrs Carole Carr Brunel University
Conference Advisory Committee
Prof Ben Barr Cardiff University & Institution of Civil Engineers
Mr Robert Benaim Robert Benaim & Associates, UK
Mr Steven Brindle English Heritage, UK
Prof Jean Armand Calgaro ENPC and GCPC, Paris, France
Mr Michael Chubb Atkins, UK
Prof Michael Collins Toronto University, Canada
Mr Patrick Dallard Arup, UK
Dr Stuart Davis Mott MacDonald, UK
Prof Christopher Earls Pittsburgh University, USA
Mr Ian Firth Flint & Neil Partnership, UK
Prof Bill Harvey Bill Harvey Associates, UK
Prof Paulo Helene Sao Paulo University, Brazil
Prof Jacques Heyman Cambridge University, UK
Mr Makoto Kitagawa Honshu Bridge Authority, Japan
Prof Paulo Laurenco Minho University, Portugal
Mr Angus Low Arup, UK
Prof Jianming Lu Research Institute of Highways, China
Prof Claudio Modena Padua University, Italy
Mr Graham Nicholson Tony Gee & Partners, UK
Mr Brian Pritchard Consultant formerly Atkins, UK
Mr Nigel Ricketts Network Rail, UK
Prof Charles Roeder Washington University, USA
Mr Benjamin Sadka Highways Agency, UK
Prof Berthold Schlecht Technical University Dresden, Germany
Prof Fernando Stucchi Sao Paulo University, Brazil
Mr Keith Wilson Faber Maunsell, UK
Dr Richard Woodward Transport Research Laboratory, UK
Surname
First Names
Organisation
Position
Address
City
Post Code
Tel
Fax
Date
Fee cheque enclosed
£Or Invoicing Address (UK only)
¡

More Related Content

What's hot

Pecker aci2003
Pecker aci2003Pecker aci2003
Pecker aci2003
gefyra-rion
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
Javad Akhtar
 
putnam engineering geophysics 2007
putnam engineering geophysics 2007putnam engineering geophysics 2007
putnam engineering geophysics 2007
Niklas Putnam, PhD, PG
 
2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs
Martin Jacobs
 
OK
OKOK
Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Oboni Riskope Associates Inc.
 
Virginia
VirginiaVirginia
Virginia
Brad Harburn
 
General Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design GuidelinesGeneral Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design Guidelines
Gibson Ali Holemba
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
Vicky Matwan
 
"The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety""The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety"
Remedy Geotechnics Ltd
 
Lane ave bridge report
Lane ave bridge reportLane ave bridge report
Lane ave bridge report
John Mangini
 
Advancement in infrastructure
Advancement in infrastructureAdvancement in infrastructure
Advancement in infrastructure
Hassan Mahar
 
Flood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draftFlood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draft
Gibson Ali Holemba
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
Mark Oberschmidt
 
A Review of Previous Work on an Approach to Design and Construction of Low He...
A Review of Previous Work on an Approach to Design and Construction of Low He...A Review of Previous Work on an Approach to Design and Construction of Low He...
A Review of Previous Work on an Approach to Design and Construction of Low He...
IRJET Journal
 
Wilma Dykeman Riverway Road Intersection Re-modernization
Wilma Dykeman Riverway  Road Intersection Re-modernizationWilma Dykeman Riverway  Road Intersection Re-modernization
Wilma Dykeman Riverway Road Intersection Re-modernization
MsplcdYkee69
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
FHRahman1
 
Jamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptxJamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptx
Md. Mahmudor Rahman
 
8. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 31706238. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 3170623
VATSAL PATEL
 
Case study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impactsCase study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impacts
ssuser8fec94
 

What's hot (20)

Pecker aci2003
Pecker aci2003Pecker aci2003
Pecker aci2003
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
putnam engineering geophysics 2007
putnam engineering geophysics 2007putnam engineering geophysics 2007
putnam engineering geophysics 2007
 
2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs
 
OK
OKOK
OK
 
Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...Balangero asbestos mine dumps restoration a few years after, in the aftermath...
Balangero asbestos mine dumps restoration a few years after, in the aftermath...
 
Virginia
VirginiaVirginia
Virginia
 
General Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design GuidelinesGeneral Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design Guidelines
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
"The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety""The Disadvantages of Designing to a Blanket Factor of Safety"
"The Disadvantages of Designing to a Blanket Factor of Safety"
 
Lane ave bridge report
Lane ave bridge reportLane ave bridge report
Lane ave bridge report
 
Advancement in infrastructure
Advancement in infrastructureAdvancement in infrastructure
Advancement in infrastructure
 
Flood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draftFlood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draft
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
 
A Review of Previous Work on an Approach to Design and Construction of Low He...
A Review of Previous Work on an Approach to Design and Construction of Low He...A Review of Previous Work on an Approach to Design and Construction of Low He...
A Review of Previous Work on an Approach to Design and Construction of Low He...
 
Wilma Dykeman Riverway Road Intersection Re-modernization
Wilma Dykeman Riverway  Road Intersection Re-modernizationWilma Dykeman Riverway  Road Intersection Re-modernization
Wilma Dykeman Riverway Road Intersection Re-modernization
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
 
Jamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptxJamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptx
 
8. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 31706238. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 3170623
 
Case study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impactsCase study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impacts
 

Viewers also liked

Sentenza sul ricorso Borgarello vs Chiamparino
Sentenza sul ricorso Borgarello vs ChiamparinoSentenza sul ricorso Borgarello vs Chiamparino
Sentenza sul ricorso Borgarello vs Chiamparino
Quotidiano Piemontese
 
Herramientas web barreto
Herramientas web  barretoHerramientas web  barreto
Herramientas web barreto
dbarretoespinosagemora
 
Fotos humanitarias
Fotos humanitariasFotos humanitarias
Fotos humanitarias
ileanajuarroz
 
City Council April 5, 2011 Agenda Packet
City Council April 5, 2011 Agenda PacketCity Council April 5, 2011 Agenda Packet
City Council April 5, 2011 Agenda Packet
City of San Angelo Texas
 
Science and Technology Update - March 2014
Science and Technology Update - March 2014Science and Technology Update - March 2014
Science and Technology Update - March 2014
Lawrence Livermore National Laboratory
 
James Stewart Thesis Draft
James Stewart Thesis DraftJames Stewart Thesis Draft
James Stewart Thesis Draft
James Stewart
 
La crisis del café en Honduras: Los productores generan riqueza y administran...
La crisis del café en Honduras: Los productores generan riqueza y administran...La crisis del café en Honduras: Los productores generan riqueza y administran...
La crisis del café en Honduras: Los productores generan riqueza y administran...
Francisco José Tomás Moratalla
 
Jose L Martinez- LinkedIn NYC DOT Portfolio - Jan 2016`
Jose L Martinez- LinkedIn NYC DOT Portfolio - Jan 2016`Jose L Martinez- LinkedIn NYC DOT Portfolio - Jan 2016`
Jose L Martinez- LinkedIn NYC DOT Portfolio - Jan 2016`
Jose L Martinez, MBA / PMP / CSM
 

Viewers also liked (8)

Sentenza sul ricorso Borgarello vs Chiamparino
Sentenza sul ricorso Borgarello vs ChiamparinoSentenza sul ricorso Borgarello vs Chiamparino
Sentenza sul ricorso Borgarello vs Chiamparino
 
Herramientas web barreto
Herramientas web  barretoHerramientas web  barreto
Herramientas web barreto
 
Fotos humanitarias
Fotos humanitariasFotos humanitarias
Fotos humanitarias
 
City Council April 5, 2011 Agenda Packet
City Council April 5, 2011 Agenda PacketCity Council April 5, 2011 Agenda Packet
City Council April 5, 2011 Agenda Packet
 
Science and Technology Update - March 2014
Science and Technology Update - March 2014Science and Technology Update - March 2014
Science and Technology Update - March 2014
 
James Stewart Thesis Draft
James Stewart Thesis DraftJames Stewart Thesis Draft
James Stewart Thesis Draft
 
La crisis del café en Honduras: Los productores generan riqueza y administran...
La crisis del café en Honduras: Los productores generan riqueza y administran...La crisis del café en Honduras: Los productores generan riqueza y administran...
La crisis del café en Honduras: Los productores generan riqueza y administran...
 
Jose L Martinez- LinkedIn NYC DOT Portfolio - Jan 2016`
Jose L Martinez- LinkedIn NYC DOT Portfolio - Jan 2016`Jose L Martinez- LinkedIn NYC DOT Portfolio - Jan 2016`
Jose L Martinez- LinkedIn NYC DOT Portfolio - Jan 2016`
 

Similar to 060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar

CB_SeptOct_2015_bridges
CB_SeptOct_2015_bridgesCB_SeptOct_2015_bridges
CB_SeptOct_2015_bridges
Rebecca Abel
 
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
Lucas de Brito Nascimento
 
Water_Intrusion
Water_IntrusionWater_Intrusion
Water_Intrusion
Jonathan Marshall
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
Matthias Schueller
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
Walton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the YearWalton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the Year
OHM Advisors
 
Assignment 2
Assignment 2Assignment 2
Assignment 2
Lisa Cain
 
project-1.pptx
project-1.pptxproject-1.pptx
project-1.pptx
Spidra1
 
BDE80_p10
BDE80_p10BDE80_p10
BDE80_p10
Rebecca Abel
 
EQUIP-WORLD-RS-MAY-2015-FINAL
EQUIP-WORLD-RS-MAY-2015-FINALEQUIP-WORLD-RS-MAY-2015-FINAL
EQUIP-WORLD-RS-MAY-2015-FINAL
Mostafa Fakharifar
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutions
IRJET Journal
 
Construction of a High Level Bridge
Construction of a High Level BridgeConstruction of a High Level Bridge
Construction of a High Level Bridge
IJSRD
 
Fib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_aFib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_a
gefyra-rion
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
NECB
 
Jamie Resume
Jamie ResumeJamie Resume
Jamie Resume
Jamie Tousignant
 
Harthill footbridge
Harthill footbridgeHarthill footbridge
Harthill footbridge
Glenn Corewyn
 
Innovative solutions for complex geotechnical and tunnelling projects, april ...
Innovative solutions for complex geotechnical and tunnelling projects, april ...Innovative solutions for complex geotechnical and tunnelling projects, april ...
Innovative solutions for complex geotechnical and tunnelling projects, april ...
Dr Mazin Alhamrany
 
Innovative solutions for complex geotechnical and tunnelling projects, april ...
Innovative solutions for complex geotechnical and tunnelling projects, april ...Innovative solutions for complex geotechnical and tunnelling projects, april ...
Innovative solutions for complex geotechnical and tunnelling projects, april ...
Dr Mazin Alhamrany
 
Curricula Vitae - NVB
Curricula Vitae - NVBCurricula Vitae - NVB
Curricula Vitae - NVB
Neville Bryant
 
Theodor Nicolas Master
Theodor Nicolas MasterTheodor Nicolas Master
Theodor Nicolas Master
Nicolas Theodor
 

Similar to 060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar (20)

CB_SeptOct_2015_bridges
CB_SeptOct_2015_bridgesCB_SeptOct_2015_bridges
CB_SeptOct_2015_bridges
 
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
 
Water_Intrusion
Water_IntrusionWater_Intrusion
Water_Intrusion
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
Walton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the YearWalton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the Year
 
Assignment 2
Assignment 2Assignment 2
Assignment 2
 
project-1.pptx
project-1.pptxproject-1.pptx
project-1.pptx
 
BDE80_p10
BDE80_p10BDE80_p10
BDE80_p10
 
EQUIP-WORLD-RS-MAY-2015-FINAL
EQUIP-WORLD-RS-MAY-2015-FINALEQUIP-WORLD-RS-MAY-2015-FINAL
EQUIP-WORLD-RS-MAY-2015-FINAL
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutions
 
Construction of a High Level Bridge
Construction of a High Level BridgeConstruction of a High Level Bridge
Construction of a High Level Bridge
 
Fib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_aFib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_a
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
 
Jamie Resume
Jamie ResumeJamie Resume
Jamie Resume
 
Harthill footbridge
Harthill footbridgeHarthill footbridge
Harthill footbridge
 
Innovative solutions for complex geotechnical and tunnelling projects, april ...
Innovative solutions for complex geotechnical and tunnelling projects, april ...Innovative solutions for complex geotechnical and tunnelling projects, april ...
Innovative solutions for complex geotechnical and tunnelling projects, april ...
 
Innovative solutions for complex geotechnical and tunnelling projects, april ...
Innovative solutions for complex geotechnical and tunnelling projects, april ...Innovative solutions for complex geotechnical and tunnelling projects, april ...
Innovative solutions for complex geotechnical and tunnelling projects, april ...
 
Curricula Vitae - NVB
Curricula Vitae - NVBCurricula Vitae - NVB
Curricula Vitae - NVB
 
Theodor Nicolas Master
Theodor Nicolas MasterTheodor Nicolas Master
Theodor Nicolas Master
 

More from Javad Akhtar

150525_IQPS_Bridges_Dubai_2015_Javad
150525_IQPS_Bridges_Dubai_2015_Javad150525_IQPS_Bridges_Dubai_2015_Javad
150525_IQPS_Bridges_Dubai_2015_Javad
Javad Akhtar
 
Zambezi River Crossing Feasibility Study
Zambezi River Crossing Feasibility StudyZambezi River Crossing Feasibility Study
Zambezi River Crossing Feasibility Study
Javad Akhtar
 
UK-Gantries
UK-GantriesUK-Gantries
UK-Gantries
Javad Akhtar
 
ODA-SCF_Bridges_Mozambique
ODA-SCF_Bridges_MozambiqueODA-SCF_Bridges_Mozambique
ODA-SCF_Bridges_Mozambique
Javad Akhtar
 
Bridges on Kapchorwa – Suam Road_Uganda
Bridges on Kapchorwa – Suam Road_UgandaBridges on Kapchorwa – Suam Road_Uganda
Bridges on Kapchorwa – Suam Road_Uganda
Javad Akhtar
 
BG4-KOTHIYAGHAT-Pontoon_Nepal
BG4-KOTHIYAGHAT-Pontoon_NepalBG4-KOTHIYAGHAT-Pontoon_Nepal
BG4-KOTHIYAGHAT-Pontoon_Nepal
Javad Akhtar
 
000301_Ms3_Gantry_Foundations_Javad_Akhtar
000301_Ms3_Gantry_Foundations_Javad_Akhtar000301_Ms3_Gantry_Foundations_Javad_Akhtar
000301_Ms3_Gantry_Foundations_Javad_Akhtar
Javad Akhtar
 
0011_Bridge_Refurbishment_Javad_Akhtar
0011_Bridge_Refurbishment_Javad_Akhtar0011_Bridge_Refurbishment_Javad_Akhtar
0011_Bridge_Refurbishment_Javad_Akhtar
Javad Akhtar
 
0410_Paddington-Brunel LoBEG-Oct04-Presentation_Javad_Akhtar
0410_Paddington-Brunel LoBEG-Oct04-Presentation_Javad_Akhtar0410_Paddington-Brunel LoBEG-Oct04-Presentation_Javad_Akhtar
0410_Paddington-Brunel LoBEG-Oct04-Presentation_Javad_Akhtar
Javad Akhtar
 
110314_Tunnel_VE-Javad_Akhtar
110314_Tunnel_VE-Javad_Akhtar110314_Tunnel_VE-Javad_Akhtar
110314_Tunnel_VE-Javad_Akhtar
Javad Akhtar
 
091115_Bridge Maintenance_Javad_Akhtar
091115_Bridge Maintenance_Javad_Akhtar091115_Bridge Maintenance_Javad_Akhtar
091115_Bridge Maintenance_Javad_Akhtar
Javad Akhtar
 

More from Javad Akhtar (11)

150525_IQPS_Bridges_Dubai_2015_Javad
150525_IQPS_Bridges_Dubai_2015_Javad150525_IQPS_Bridges_Dubai_2015_Javad
150525_IQPS_Bridges_Dubai_2015_Javad
 
Zambezi River Crossing Feasibility Study
Zambezi River Crossing Feasibility StudyZambezi River Crossing Feasibility Study
Zambezi River Crossing Feasibility Study
 
UK-Gantries
UK-GantriesUK-Gantries
UK-Gantries
 
ODA-SCF_Bridges_Mozambique
ODA-SCF_Bridges_MozambiqueODA-SCF_Bridges_Mozambique
ODA-SCF_Bridges_Mozambique
 
Bridges on Kapchorwa – Suam Road_Uganda
Bridges on Kapchorwa – Suam Road_UgandaBridges on Kapchorwa – Suam Road_Uganda
Bridges on Kapchorwa – Suam Road_Uganda
 
BG4-KOTHIYAGHAT-Pontoon_Nepal
BG4-KOTHIYAGHAT-Pontoon_NepalBG4-KOTHIYAGHAT-Pontoon_Nepal
BG4-KOTHIYAGHAT-Pontoon_Nepal
 
000301_Ms3_Gantry_Foundations_Javad_Akhtar
000301_Ms3_Gantry_Foundations_Javad_Akhtar000301_Ms3_Gantry_Foundations_Javad_Akhtar
000301_Ms3_Gantry_Foundations_Javad_Akhtar
 
0011_Bridge_Refurbishment_Javad_Akhtar
0011_Bridge_Refurbishment_Javad_Akhtar0011_Bridge_Refurbishment_Javad_Akhtar
0011_Bridge_Refurbishment_Javad_Akhtar
 
0410_Paddington-Brunel LoBEG-Oct04-Presentation_Javad_Akhtar
0410_Paddington-Brunel LoBEG-Oct04-Presentation_Javad_Akhtar0410_Paddington-Brunel LoBEG-Oct04-Presentation_Javad_Akhtar
0410_Paddington-Brunel LoBEG-Oct04-Presentation_Javad_Akhtar
 
110314_Tunnel_VE-Javad_Akhtar
110314_Tunnel_VE-Javad_Akhtar110314_Tunnel_VE-Javad_Akhtar
110314_Tunnel_VE-Javad_Akhtar
 
091115_Bridge Maintenance_Javad_Akhtar
091115_Bridge Maintenance_Javad_Akhtar091115_Bridge Maintenance_Javad_Akhtar
091115_Bridge Maintenance_Javad_Akhtar
 

060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar

  • 1. School of Engineering and Design First International Conference on Advances in Bridge Engineering Bridges - Past, Present and Future co-sponsored by “Celebrating the 200th Birth Anniversary of Isambard Kingdom Brunel” www.brunel.ac.uk/about/acad/sed/bec2006 to be held at Brunel University, West London 26-28th June 2006
  • 2. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006 TEMPLE MILLS BRIDGE RECONSTRUCTION Temple Mills Bridge Reconstruction Javad Akhtar Hyder Consulting (UK) Ltd. Abstract Temple Mills Bridge built in 1963, carries the A106, over the River Lea in five spans. The original bridge decks of 50m overall length, consist of precast, prestressed concrete beams with in situ concrete infill, supported on piled reinforced concrete piers and abutments. Extensive chloride contamination and difficult maintenance issues led to the decision to replace the structure. A number of alternative deck replacement solutions were examined – including complete “encapsulation” within new precast concrete arches. Careful risk management played an important part in being able to develop the most economical solution within the framework of a design and build contract under NEC Option C conditions of contract. Review of geotechnical data and concrete testing concluded that the existing foundations were acceptable for re-use. The replacement adopted a similar span arrangement, but with a deck of semi-integral construction, bearings only being provided at the abutments. The original piers were demolished down to river foundation level and new ones built up with epoxy coated reinforcement below river level. The abutments were extended to form a series of plinths for the bearing shelf with existing faces encased in a 100mm thick skin of new concrete. piers. A wide range of Environmental mitigation measures were undertaken, including hydraulic design to cater for future “Global Warming”. The design allows for the passage of small mammals along the river-banks and bat roosting facilities. The environmental management plan included a range of measures to mitigate noise and pollution threats. Keywords: Bridge Reconstruction, Rehabilitation, Concrete Repair, precast prestressed, foundations, environmental, traffic management, GGBFS, PFA, DPS, epoxy coated reinforcement.
  • 3. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006 TEMPLE MILLS BRIDGE RECONSTRUCTION 1.0 Background Temple Mills Bridge is sited an Olympic champion’s stone’s throw from the site of the main Olympic Park in Stratford. The bridge, built in 1963, carries one of the area’s major routes, the A106, over the River Lea. The existing bridge consists of two nearly identical structures, 50 metres long, each carrying a three lane carriageway, a footway/cycleway and a central paved verge. The bridge decks are separated by a 3.66 metre gap and consist of precast, prestressed concrete beams with in situ concrete infill. Each five-span bridge structure is supported on reinforced concrete piers and abutments supported on piles. Unusually, the piers are articulated by means of bearings halfway up the pier, with a concrete ‘hinge’ detail at the top. Whilst many parts of the structure were judged beyond economic repair, the river foundations and the abutment supports were re-used. Due to the high traffic volumes in the area, the replacement took place in two parts with traffic diverted initially all to the south carriageway while demolition and reconstruction of the North Carriageway was undertaken. By careful re-assessment of the existing deck four lanes were maintained for traffic, and services diverted to the other side. 2.0 Defects in original structure Most of the problems with the bridge stem from inadequate waterproofing at the time of construction. The bridge was built just before the Highways Agency (HA) introduced specific requirements for waterproofing. The bitumen impregnated jute used at the time has failed to prevent water ingress, to the point that stalactites had formed on extensive areas at the underside of the bridge deck. The water ingress had also caused the sliding bearings of the abutments to seize to a point where they were beyond repair. Previous investigations had also revealed that reinforcement corrosion due to chloride attack in the insitu concrete “stitch” over the piers had progressed to the point that the deck could no longer sustain the applied hogging moment over the piers due to vehicle loading on the continuous deck. Fortunately, the original contractor had designed beams to cater for simply supported loading conditions, rather than attempt to refine the design to suit the actual complex continuous frame system. Thus, although the bridge is currently not supporting the applied loading in the manner intended by the designer, the reserve of strength in the beams has saved it from a more imminent demise. A further concern with the structure was that a “mechanism” type failure mode of the piers was possible due to the presence of bearings at the lower part of the piers and the loss of moment restraint due to corrosion of reinforcement in the insitu concrete stitch at the top of the pier. This failure mode was only prevented by the restraint provided by the abutment curtain wall and the seized abutment bearings. Furthermore parapets did not conform to current standards. These concerns over long-term structural behaviour and the whole life costs of a growing programme of investigation, monitoring and repair led to Hackney Council’s decision to replace the structure. 3 Project/Risk Management Hyder Consulting was appointed by the London Borough of Hackney in 2003 as Project Managers to review and consolidate the findings of previous studies, to develop the options for the crossing and to supervise the detailed bridge design and construction phases. In February 2004, contractor Norwest Holst with Designers Mouchel Parkman started the £2 million, 18 month design and build project to replace the existing bridge.
  • 4. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006 TEMPLE MILLS BRIDGE RECONSTRUCTION 3.1 Pre-contract Planning Prior to letting the design and construction contract, the following steps were undertaken: • Scheme, program & procurement strategy review with LB Hackney • Stakeholder Consultation • Technical Investigations and Studies (Hydraulic Flow Modelling, Traffic Counts, Traffic Modelling, Site Investigations, Planning Review, Environmental Appraisal, Contaminated Land investigation etc. • Design performance criteria and specifications • Preparation of reference designs • Contract Documents • CDM Risk Assessment and Pre-Tender Health & Safety Plan These processes are illustrated on the figure 1. 3.2 Contract Strategy The “ideal” form of construction contract was initially considered as NEC Form A for simplicity of administration and price certainty. However this was changed to NEC Option C to meet LBH accelerated program and to allow early letting of the design and construct contract prior to completion of the various investigations and studies. Tender documents were issued Oct 03 (two months after Hyder appointment). Tender evaluation was based on a 60:40 Quality: Price weighting. 3.3 Risk Management The key risks identified at project planning stage are given in Table 1 below, with a brief indication of mitigation measures. During construction a much more extensive Risk Register was developed based on contractual “Early Warnings”. Table 1 Perceived Risks and Proposed Mitigation Measures Risk Comment/Mitigation Travellers not moving Two separate Traveller Community encampments were present adjacent to the site. Sensitive discussion and liaison resulted in peaceful relocation of these communities. Geotechnical - Lack of Information/ reuse of existing foundations (abutment & river piles/pedestals) An extensive amount of Ground Investigation data was obtained from Transport for London (TfL) archives relating to the A12 Project. Further Site Investigations were instigated during the course of the contract. Construction unknowns Dealt with through contractual “Early Warning” register. Environment Agency (EA) requirements & timing of responses Maintained close contact with relevant responsible officers within EA. Extensive hydraulic and environmental studies undertaken. Potential Traffic Problems Traffic studies undertaken and flows modelled to prove feasibility. Close liaison with Police, TfL, Buses and transport operators. Public Objection Extensive consultations and publicity. Identification of key stakeholders and planning to minimise impacts. Control of Construction Costs and planning of Funding Administration of contract to limit instructed variations and close liaison with funding authorities, including raising risk awareness and provision of cash-flow forecasts. Statutory Undertakers (SU’s) requirements and information issue Early development of plans with SU’s and close liaison. Major Sewers (syphon+Chambers) under bridge at river bed level Close liaison with Thames Water Utilities. Provision of protective measures.
  • 5. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006 TEMPLE MILLS BRIDGE RECONSTRUCTION 4 Alternatives Considered One of the options considered during project planning stage was the propping and encapsulation of the existing structure on precast concrete arches launched from the existing river foundations. While this option would have avoided demolition with the associated requirements for traffic and services diversions, it was ruled out in conjunction with the Environment Agency because of worries over the hydraulic and ecological effects on the River Lea. Indeed, environmental issues are to the forefront generally because of the bridge’s location on the fringes of the Lea Valley Regional Park. 5 Environmental Considerations One consequence is that the deck of the new bridge will be 0.5 metre higher than the original. This again takes into account some Environment Agency (EA) concerns about a 1 in 100 year flood event with a further 20% allowance for “Global Warming”. Hydraulic studies were scoped and commissioned by Hyder from external consultants – Halcrow, in order to re-assure the EA that the results were indeed independent from the construction team. The “hard” revetments adjacent to the riverbank have been lined with “Geoweb” plastic mesh infilled with granular material in order to aid soil retention, vegetation growth and habitat creation. A minor surface bank slip adjacent to the structure has been stabilised by willow stakes. The design of the new structure will also allow for the easier passage of small mammals along the river- banks and will provide for bat roosting facilities. The construction team liaised closely with Hackney Council and the Environment Agency to mitigate potential noise and pollution threats. 5.1 Traffic Modelling Due to the critical location of the structure, Hackney were anxious to ensure that traffic flows were catered for with minimal disruption. Hyder therefore undertook advance traffic-modelling studies and developed an outline Traffic Management Scheme in liaison with Hackney, Transport for London, emergency services, transport operators and other stakeholders. The planned construction phasing allowed for services diversions, with the new structure also providing spare capacity to cater for future services. 6 Aspects of Design of Replacement Structure 6.4 Structural Form and Deck Refer to figures 6 and 7 for deck details (from drawings by Messrs Mouchel Parkman). An infilled precast prestressed deck was adopted, continuous and integral over intermediate pier transoms, supported by laminated rubber bearings at abutments. This semi-continuous form minimised any additional lateral loads on the existing concrete bored piled abutments. 6.2 Materials In order to improve longer term durability, the new bridge was constructed using a Ground Granulated Blast Furnace Slag (GGBFS) concrete mix. This in turn was subject to a two part spray waterproofing. To prevent environmental pollution of the watercourse, impregnation of the concrete was undertaken using “Deep Penetrating Sealant” rather than Silane. This forms a permanent protective “glass” coating to the outer pores of the concrete that does not require renewal. DPS whilst having a history of use in Norway and other countries, does not previously appear to have been used in the UK.
  • 6. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006 TEMPLE MILLS BRIDGE RECONSTRUCTION 6.3 Foundations The existing 1.5m diameter, 6m deep cylindrical reinforced concrete “Pedestal” foundations were geotechnically appraised for upper and lower bound geotechnical parameters and judged capable of taking the loads from the new structure (which in any case were lower than pre-existing loads). Contingency risk-management planning was undertaken in case the concrete condition (which would only be apparent once the existing piers were damaged and cofferdams installed) was found to be poor. However in the event the pedestals were found to be in good condition. Whilst the effects of the enlarged tops of concrete pedestals have been hydraulically modelled and shown to have little impact on the flow of the River Lea, large pieces of concrete from the deck demolition will be placed around the pile cap to mitigate the possibility of scour on the pile caps below the water level. This is being done as a precaution against possible eddy currents under and around the lips of the enlarged pedestals. Refer to figure 5 New Piers Founded on Existing "Pedestal" Foundations. 7 Construction Demolition of the original bridge started with the northern carriageway. This initially required the stabilisation of the existing bridge piers and the positioning of pontoons underneath the bridge deck. Hydraulic breakers then moved in to break up the deck, with the debris being scooped up from the pontoons below using small robotic excavators refer to figure 8 Deck Demolition on Pontoons. As the deck is removed temporary struts were put up to support the piers before removal of these down to river floor level. This was undertaken in two stages, firstly down to the level of the pier bearings, followed by removal of the stubs below the waterline down to the level of the top of the “Pedestal” foundations. In order to begin the construction of the new piers, precast concrete rings were first embedded around the existing pile caps. As well as creating enlarged pedestals, these served as coffer-dams during the river level works and provided shuttering moulds for the concrete pour of the new piers. Prior to the pour, new epoxy coated reinforcement bars were drilled and resin anchored in to the existing pedestal. While tests on the loading capabilities of the abutments showed good performance with core test results of 60 KPa, there was evidence of some corrosion of non-structural steel reinforcement in the abutment face due to water leaking in from the top and side of the expansion joints. Mouchel-Parkman, who carried out the detailed design for Norwest Holst, proposed that, the top of the existing abutments be scabbled down and new reinforcement bars resin anchored in at close centres. The abutments were then extended to form a series of plinths for the bearing shelf with existing faces encased in a 100mm thick skin of new concrete. The buried faces of the abutments were tested and found to have negligible chloride contamination, however due to the uneven concrete finish it was decided to extend the “encapsulation” concrete skin to the rear face of the abutment also. In the river itself, particular care was required working around the three 1 metre diameter sewage pipes which run longitudinally through the middle of the bridge just below the river floor. In the first stage the pontoons protected these pipes. However it was found that the pontoons grounded easily and would actually obstruct the river in the event of an unforeseen flood event. For demolition of the southern half of the deck the pontoons were omitted and a crash-deck provided - comprising a 300 mm thick granular pad over two layers of steel sheet piles laid flat on the bed (spanning the pipes).
  • 7. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006 TEMPLE MILLS BRIDGE RECONSTRUCTION Precast beam erection was undertaken using a mobile crane sited just behind the abutments (refer to figure 9). Difficulties were encountered at the junction between previously erected North Deck and the South deck due to the need to “mesh” into the 3 dimensional reinforcement cage provided out of the cross-head and continuity reinforcement from the pre-erected deck. These were overcome by use of reinforcement couplers. 8 Conclusion Completion of this bridge in March 2006 secured this important local transport link and marks the first project to cross the finish line at the start of the major developments on the adjacent Olympic site. Acknowledgements The author, whose role was as Project Manager, wishes to acknowledge the assistance and support of…. Client Manager Joe Figurado London Borough of Hackney Supervisor Richard Williams Hyder Consulting (UK) Ltd. Contractor Mark McGleenon Norwest Holst Construction Ltd Contractor’s Designer Andrew Foster Mouchel-Parkman Ltd Figure 1 Pre-Construction Contract Project Management Processes Figure 2 Existing Bridge
  • 8. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006 TEMPLE MILLS BRIDGE RECONSTRUCTION Figure 3 Installation of Phase 1 Traffic Management
  • 9. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006 TEMPLE MILLS BRIDGE RECONSTRUCTION Figure 4 Scheme Options Considered Figure 5 New Piers Founded on Existing "Pedestal" Foundations (Note details slightly modified during construction) Figure 6 Deck Cross-section at Central Reserve
  • 10. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006 TEMPLE MILLS BRIDGE RECONSTRUCTION Figure 7 Deck Long-section at Abutment and Abutment “Encapsulation” Detail Figure 8 Deck Long-section at Abutment and Abutment “Encapsulation” Detail Figure 8 Deck Demolition
  • 11. Proceedings of the First International Conference on Advances in Bridge Engineering 26 - 28 June 2006 TEMPLE MILLS BRIDGE RECONSTRUCTION Figure 9 Precast Beam Erection
  • 12. Call for papers The theme of the conference will be ‘Bridges - past, present and future’. Papers can be presented on any aspect of the development of knowledge, techniques, innovations, control, monitoring and management processes which may represent an advancement in the field of bridge engineering. A special session on Historical Bridges, with particular emphasis on Brunel’s work, is planned to celebrate his 200th birth anniversary. Invited Speakers The following have indicated acceptance of invitations to make Keynote Presentations: Mr Steven Brindle English Heritage, UK Prof Jean Armand Calgaro ENPC and GCPC, Paris, France Prof Jacques Heyman Cambridge University, UK Mr Makoto Kitagawa Honshu Bridge Authority, Japan Mr Brian Pritchard Consultant, formerly Atkins, UK Prof Santiago Huerta University of Madrid, Spain Prof Michael Collins Toronto University, Canada Requirements and dates Authors wishing to present a paper should submit an abstract (300 words approx.). Abstracts and Papers must be in English and should clearly indicate the contact author details (affiliation, address, telephone, FAX and e-mail). The abstracts may be submitted by post (Bridge Conference 2006, Research Office, School of Engineering and Design, Brunel University, Uxbridge, UB8 3PH, UK) or e-mail (bridgeconf.2006@brunel.ac.uk) Target dates Submission of Abstracts 30 December 2005 Acceptance of Abstracts 6 January 2006 Submission of full Manuscripts 28 February 2006 Final acceptance will be based on peer-review of the full manuscript. Final Manuscripts should be no more than 8 pages in length and must comply with the 'Instructions for Preparing a Paper' available at www.brunel.ac.uk/about/acad/sed/bec2006 Manuscripts should be submitted via e-mail or the electronic submission form at the conference website. In exceptional circumstances, full manuscripts may be submitted for consideration as paper hard copy. In all circumstances, a paper hard copy and an electronic CD-ROM version of the final manuscript of the paper must be provided for the publication process by the due date. First International Conference on Advances in Bridge Engineering www.brunel.ac.uk/about/ acad/sed/bec2006 Isambard Kingdom Brunel was a visionary and amongst the most influential engineers of the last millennium. His wide-ranging works, his aesthetic sense and legacy have withstood the test of time and have been a constant inspiration to generations of engineers. He was a tunnelling engineer, a railway engineer, a transportation engineer, a buildings engineer, a marine engineer but above all he was a bridge engineer. Even the general public who have no special knowledge of engineering matters tend to automatically warm to the inherent beauty and merit of his works and contribution, recognising the genius he was. The splendid Clifton Suspension Bridge of his design is an example of this artistry. The University is proud to be named after this great engineer and following his footsteps shall endeavour to advance the frontiers of knowledge and engineering for the future.
  • 13. Exhibition There will be an associated exhibition of selected equipment, instrumentation, software and information relating to bridge engineering, providing delegates an opportunity for exchange of ideas and information on topics of current interest in the field. Organisations interested in exhibiting their products or services should contact the Conference Administrator for terms and conditions. Venue Howell Theatre, Brunel University, Uxbridge, Middlesex UB8 3PH. Booking Conditions i) Early booking is recommended; places will be reserved on first come first served basis. ii) Reserved places can be reassigned to another person by prior written request. v) Delegates are encouraged to travel by public transport. A limited number of car parking permits will be available for parking at the University. vi)All rights reserved with the University. Application Form: First International Conference on Advances in Bridge Engineering on 26-28 June 2006 For reserving a place, please either register online at www.brunel.ac.uk/about/acad/sed/bec2006 or complete this application form with Conference fee (cheque or transfers made payable to Brunel University) or address for invoicing to: Mrs Carole Carr [e-mail: bridgeconf.2006@brunel.ac.uk] Research Office Manager Bridge Engineering Centre School of Engineering and Design Brunel University Uxbridge Middlesex UB8 3PH Tel: 01895 266 962 Fax: 01895 269 797 ¡ Registration Fee The registration fees for the various categories of participants at the conference, which include a copy of the proceedings, a reception, buffet lunches and refreshments for the 3 days of the conference, are as follows: Fee received: Before 1 March 2006 From 1 March 2006 Delegates £495 €740 £545 €815 Authors £445 €665 N/A Students (proof required) £295 €440 £325 €485 Day rate delegates/authors £245 €365 £275 €410
  • 14. SCHOOL OF ENGINEERING AND DESIGN 102240 0106 Conference Organising Committee Prof Arvind Kumar Kumar Associates & Brunel University Mr Chris Brown Brunel University Prof Luiz Wrobel Brunel University Conference Administrator Mrs Carole Carr Brunel University Conference Advisory Committee Prof Ben Barr Cardiff University & Institution of Civil Engineers Mr Robert Benaim Robert Benaim & Associates, UK Mr Steven Brindle English Heritage, UK Prof Jean Armand Calgaro ENPC and GCPC, Paris, France Mr Michael Chubb Atkins, UK Prof Michael Collins Toronto University, Canada Mr Patrick Dallard Arup, UK Dr Stuart Davis Mott MacDonald, UK Prof Christopher Earls Pittsburgh University, USA Mr Ian Firth Flint & Neil Partnership, UK Prof Bill Harvey Bill Harvey Associates, UK Prof Paulo Helene Sao Paulo University, Brazil Prof Jacques Heyman Cambridge University, UK Mr Makoto Kitagawa Honshu Bridge Authority, Japan Prof Paulo Laurenco Minho University, Portugal Mr Angus Low Arup, UK Prof Jianming Lu Research Institute of Highways, China Prof Claudio Modena Padua University, Italy Mr Graham Nicholson Tony Gee & Partners, UK Mr Brian Pritchard Consultant formerly Atkins, UK Mr Nigel Ricketts Network Rail, UK Prof Charles Roeder Washington University, USA Mr Benjamin Sadka Highways Agency, UK Prof Berthold Schlecht Technical University Dresden, Germany Prof Fernando Stucchi Sao Paulo University, Brazil Mr Keith Wilson Faber Maunsell, UK Dr Richard Woodward Transport Research Laboratory, UK Surname First Names Organisation Position Address City Post Code Tel Fax Date Fee cheque enclosed £Or Invoicing Address (UK only) ¡