Advertisement
Advertisement

More Related Content

Advertisement
Advertisement

A case study presentation on Dabhol Power Plant

  1. Group Members 0006/50 ABHISHEK KATIYAR 0071/50 ANUJ SOOD 0106/50 BHARAT JAIN 0169/50 KOUSTOOV DUTTA 0225/50 NISHANT SOMYA 0275/50 RAHUL MITTAL 0311/50 SANTANU SHYAM 4018/20 ASHUTOSH SINGH IIM Calcutta A case study on Dabhol Power Plant
  2. Indian Power Sector - Characteristics • Huge energy demand outpacing supply India's Power Generating Capacity Central Govt. 31% State Govt. 65% Private 4% • Projected shortage of over 5,800 MW in Maharashtra only by 2001-2002 and around 50,000 MW nationwide • Estimate of overall 3.1 % loss in industrial production • Most SEBs close to insolvency: Average cost recovery of only 78% • Different Tariffs for Industrial(High) and Agricultural(very low, waive offs) consumers • High Transmission and Distribution losses Dominated by Public Sector
  3. Reforms • Invitations to private sector companies allowing 100% foreign equity • Protection against adverse exchange rate fluctuations • Import of equipment was permitted • Single window clearance mechanism was introduced • Foreign Investment Promotion Board(FIPB) was created to negotiate and approve investments Opening up of Indian Power sector for Foreign Investment
  4. Enron’s Global Strategy • Vision - “to become world’s leading energy company-creating innovative and efficient energy solutions for growing economies and a better environment worldwide” • Focus on every aspect of natural gas – exploration, production, transportation, processing, marketing • EDC offered complete energy solutions – generating addition opportunities for other Enron business units • Introduce concept of PPP in energy industry • All undertakings are Project Financed with long term contracts and appropriate measures for Economic, Financial risks etc.. • Usage of Natural gas to take care of environmental concerns Positioning in India • India, being a growing economy with huge energy needs fit well with Enron’s vision • By contracting the middle east for fuel supply, EDC ensured stake of EPP in Dabhol Project • With reforms just coming in, India was welcoming private investment in Power sector • Indian Govt. and MSEB providing for Currency risk, commercial feasibility etc. • India’s coal considered environmentally unfriendly
  5. Risk factors for Enron • Political instability • Lack of experience(In terms of foreign investments in India) • Fuel wasn’t locally available • Local opposition(because of environmental risks, displacing people) • Technical risks • Financial risks • Transparency/corruption related issues • Penalty payments on not meeting the targets • World bank report: labeled Dabhol project as a liability
  6. Potential benefits for Enron • Huge untapped market • Buying guarantee from MSEB • High tariff rates • Shielding from currency fluctuations (MSEB) • First mover advantage • Successful project completion would lead to future growth opportunities
  7. Potential benefits for India/Maharashtra • Growth of Indian power sector • Development of sectors dependent on energy(Industry & Transport) • Ability to satisfy growing demand • Huge foreign Investments in India • Local Infrastructure and social development • Opening up to foreign investments in other sectors • Employment generation
  8. Risk factors for India/Maharashtra • High project costs as compared to other similar projects • Liability to pay in case of default • Commitment to purchase 90% of the generated power • Civil unrest • Environmental concerns • No prior FDI experience • Project failure might result in loosing out on future FDI opportunities • World bank report: Liability on the state
  9. Enron Entry Strategy Why Dabhol  State board was profitable and this reduced the revenue risk - the state board could pay Enron for power generated  A large demand for power existed in the state  Maharashtra already generated close to 10,000MW (12% of India’s generation capacity)  Location was close to a port making it easy to transport fuel for the power plant.  Maharashtra was one of India’s more developed states – institutional risks were comparatively lesser In Dabhol  IAS officer in charge held talks with Enron  Enron officials spoke to MSEB who were open to entering into an agreement  Enron proposed a phased 2000 MW LNG plant. MSEB agreed to this.  Phased plan was drawn out to first test the concept, and then to develop the complete facility:  695 MW was to be developed in Phase 1  1320 MW was to be developed in Phase 2
  10. Bank of America - $150 million Overseas Pvt. Inv. Corp. - $100 million IDBI + other Indian banks - $95 million Exim Bank of USA - $298 million Lenders Purchase contracts Raw materials Suppliers Purchasers Dabhol Project Debt repayment Debt funds Equity investors Returns to investors Equity funds Output Supply contracts Phase 1 Enron Power Corp. - $223 million (80%) / $182 million (65%) Bechtel Inc. - $28 million (10%) General Electric - $28 million (10%) MSEB - $42 million (15%) PPA based on Capacity Payments and Energy Payments Enron - Rs. 2.40/KwH (initial) Rs. 2.03/KwH (revised) Ministerial Committee – Rs. 5/KwH (distribution + inflation accounted) 695 MW (initial) 826 MW (revised) Cost: Rs. 4.49 crore per MW (overall) Rs. 3.65 crore per MW (core) Total cost: $920 million out of $2.8 billion Proposed: 26.52% Revised: 25.22% Proposed: Distillate fuel (Diesel) sourced locally; later switch to LNG Revised: Naphtha
  11. To be worked out Lenders Purchase contracts Raw materials Suppliers Purchasers Dabhol Project Debt repayment Debt funds Equity investors Returns to investors Equity funds Output Supply contracts Phase 2 Forward Contracts with Qatar Govt. for LNG To be worked out PPA based on Capacity Payments and Energy Payments Enron - Rs. 2.40/KwH (initial) Rs. 1.86/KwH (revised) Ministerial Committee – Rs. 5/KwH (distribution + inflation accounted) 1320 MW (initial) 1624 MW (revised) Cost: Rs. 4.49 crore per MW (overall) Rs. 3.65 crore per MW (core) Total cost: $1.88 billion out of $2.8 billion Proposed: 26.52% Revised: 25.22% LNG
  12. Strengths of market entry strategy • Maharashtra was one of the developed states and one of the 2 states which had a positive return on their fixed assets, thus revenue risk was relatively lower in Maharashtra than in other states • Dabhol was a good location for the power plant to close proximity to a deep-water port which would require less dredging and save costs • Dispute resolution clause in the PPA through international arbitration mitigated some of the local judicial risk in case of any disputes • Enron had structured the project as a PPP very carefully, building in guarantees into the contract. Signing PPAs ensured that atleast 90% of the power generated would be bought and thus, ensured a constant demand throughout the operation of the plant • The tariff structure mitigated all currency risk, inflationary risk and fuel price risk for DPC and was borne by MSEB/GoM/GoI • They had partnered with firms like GE and Bechtel who could provide them sound technical expertise • They undertook the investment in two stages. This was a good step as any problems noted in the first phase of the project could be rectified in the second phase • They had a strong financial backing for their project, through the strength of Enron’s own balance sheet and by the support of well know credible global lenders.
  13. Weaknesses of market entry strategy • They didn’t have a transparent bidding process for their contracts • Enron didn’t consider the impact of the project on the local communities and the actual consumers of the power they supply. • The possible repercussions of the high cost of power compared to other projects were not considered by Enron • The MoU was drafted in a very short span of time and it was highly one sided, favouring DPC on most occasions. • Such an MoU was bound to fail as when the new government actually realized that it would cause MSEB huge amount of losses if they went ahead with the project and honoured all the terms of the contract • No EIA (Environmental Impact Assessment) was carried out • Proposed use of LPG as compared to cheaper alternative indigenous fuels greatly increased the cost of the energy supplied to MSEB • The return to equity of 25.22% was still a very high number compared to other previous power projects • A lot of responsibility and risk was on MSEB and GoM, in such a scenario it was only fair that Enron gave MSEB an equity stake in their project which they failed to do in the first agreement • Enron didn’t take political risk into account. • A changing political environment, inefficient, slow moving administration constant re-examination of projects and disputes over the approved contracts. All these factors actually end up causing major hindrances for Dabhol down the line
  14. The Aftermath • With the Enron bankruptcy, Enron's stake in DPC was bought out by GE and Bechtel. • In 2005, it was taken over and revived by the RGPPL (Ratnagiri Gas and Power Private Limited), a company owned by the Government of India • The power plant Phase I which was renamed Ratnagiri Gas and Power Pvt. Ltd (RGPPL) started operation in May 2006, after a hiatus of over 5 years. However, the Dabhol plant ran into further problems, with RGPPL shutting down the plant on 4 July 2006 due to a lack of naphtha supply. The Qatar based company RasGas Company Ltd. started supplying LNG to the plant in April 2007. • The power station had resumed operations at 100% of its installed capacity of 1967 MW in 2010. • The 1,980MW plant had closed down last March, but even when gas becomes available, the cost of power from the plant will be over Rs 5.50 per unit, which is far higher than other sources of power for MSEDCL. There is no incentive for MSEDCL to buy this power, since it is power surplus and is selling power to others. • It seems the project is en route to becoming another non-performing asset (NPA).
  15. Thank You!
Advertisement