SlideShare a Scribd company logo
1 of 33
Professional Practice 2 - P7
Partial Possession by Employer
Louise Fong (0322815)
Muhd Fareez Sham (0322961)
Chan Wei Lun (0326117)
● Used part of the building before practical completion
● Clause 16.0: Employer wishes to take possession of certain sections of the works
before the whole Works is completed.
What is partial possession?
Why partial possession?
● Business Pressure- Current demand and price is good so they need to start business or
production
● Commercial reasons- Works has been delayed so the need to complete early, thus
partial possession for some sections.
How to take partial possession?
● Under clause 16.0 employer must give a written notice of intention to take partial
possession to contractor, so that contractor can prepare himself and focus the part of
employer want to occupy.
1. Partial possession occur before practical completion.
2. The employer to identify part to be taken over.
3. The contractor have given his consent
● Contractor cannot unreasonably delay or withhold such consent
Contractor consent for partial possession
● Clause 16.1 prohibits the Contractor from unreasonably withholding or delaying
consent. However, the Contractor is not bound to give consent for partial possession.
● Reasons :
1. Health and Safety Issue
2. Disturb the progress of work
3. Non-payment issue for work done
Certificate of partial completion
● Clause 16.1(a): Architect must issue Certificate of Partial Completion within 14 days
of taking partial possession of the Occupied Parts.
● Certificate of Partial Completion must include date of partial possession. Layout plan
is a must to identify or demarcate the occupied part and estimated value of the
occupied part
Contractual effects of partial completion
• Practical Completion: Practical completion of the Occupied Part shall be deemed to have
occurred on the date of taking over the Occupied Part.
• Defects Liability Period (DLP): Commenced on the date of practical completion of the
Occupied Part by the Employer.
• Liquidated Damages (clause 16.1©): Liquidated damages shall be reduced by the ratio of
the estimated value of occupied part to the contract sum.
Example of calculation
• If Occupy part is RM2 Mil. Contract sum RM10 Mil. Liquidated Damages RM1000/day
• New liquidated damage = 1000-(2/10x1000)
= 1000-200 = RM800 per day
• Liquidated damages of RM800 per day shall apply to the remaining works
Retention sum
• Clause 16.1 (d): Architect must issue a payment certificate to release the first
moiety of the retention fund in the ratio of the estimated value of the
occupied part and must issue payment certificate within 14 days after the
issuance of the certificate of partial completion.
• Formula for retention sum: RP = VOP/CS x R
● RP= the amount of retention to be released
● VOP= estimated value of Occupied Part
● CS= Contract Sum
● R= Maximum Retention
Example
• Retention sum (max) is RM500,000. Value of Occupied Part is RM2,000,000.
Contract Sum is RM10,000,000.
• Value of retention sum for Occupied Part is 2/10 x 500,000= 100,000/2 =
RM50,000
• 1 st moiety to be released = 100,000/2 = RM50,000
Certificate of making good defects (CMGD)
• Clause 16.1(e): All defects in the Occupied Parts have been made good, the Architect
shall issue a CMGD
Release of second moiety of retention
• 16.1 (f), the Architect shall issue a certificate for the release of the remaining retention
fund (second moiety) for the Occupied Part within 14 days after the issue of CMGD of the
same Occupied Part.
Items not affected by partial possession
Work Insurance
• Clause 20.A.1: Contractor shall keep such works so insured notwithstanding any
arrangement for partial possession.
• Total sum insured of the above provision is that the parties insurance obligations remain
unaffected.
• Respective parties remain obliged to insure and keep the works insured to the full value ,
there being no reduction for the value of the Occupied Part.
Items not affected by partial possession
Performance Bond and Final Certificate.
• Clause 30.6 for Performance Bond does not indicate any deduction or reduction of the
bond value after partial possession.
• Clause 30.0 for Final Certificate are not affected by the partial possession since there is
only one Final Certificate issued.
• Hence, it can be inferred that both the Performance Bond and the Final Certificate are to
remain unaffected by the issuance of Certificate of Partial Completion.
Partial possession by employer (without consent)
• The employer may trigger breach of contract
• Restrictions on employer right to take possession without consent
• Clause 16.2: A provision which caters for the common practice where the Employer
does, or is forced to take over parts of the works before practical completion without the
Contractor’s consent.
Restrictions on employer rights to take partial possession
without consent
• Employer has no absolute rights.
• Clause 16.2(a) may take partial possession provided three preconditions are met:
i) The completion of Works have been delayed
ii) A Certificate of Non-Completion has been issued by Architect under clause 22.1
iii) Partial possession do not unreasonably disturb the regular and remaining work
Employer’s rights limited by the contract
• Clause 16.2 “without prejudice to any other rights and remedies which he
may possess under the contract”
• Limit employer right to those under contract only
Procedures following partial possession (with or without
consent)
• Clause 16.3: Govern the Contractor’s duties following partial possession by the
Employer, whether with or without contractor’s consent.
i) Contractor shall remove all facilities and equipments from the occupied part upon the
receipt of AI
ii) Architect shall prescribe the time for removal from occupied part
iii) However contract silence on consequences of non compliance by contractor and
remedies of employer
iv) It is also silent on remedies available to employer for such non-compliance by the
Contractor.
TUTORIAL QUESTIONS
Q1:Explain the differences between Sectional Completion and Partial
Possession in PAM 2006.
Sectional completion Partial completion
Clause 21.3 Clause 16.1
Stated in contract documents (different
sectional commencement date and different
sectional completion date)
Not stated in contract documents
Architect to issue the Certificate of Partial
Completion within 14 days of taking partial
possession of the Occupied Parts
Architect to issue the Certificate of Sectional
Completion when the sections of Works are
Practically Completed.
Happened before Signage of Contract Happened after Signage of Contract
Answer :
Q2: Under what circumstance can the Employer take partial possession of the site?
Please explain for both partial possession with and without consent from the
Contractor.
● Under Clause 16.0, the employer must comply with the following:-
1. To give written notice of intention to take partial possession to contractor
2. The partial possession occurs before practical completion.
3. The employer to identify part to be taken over.
4. That the contractor has given his consent.
Answer:
Partial possession with consent from the Contractor:
● Under clause 16.1, the contractor cannot unreasonably delay or withhold such consent.
Partial possession without consent from the Contractor:
● Under clause 16.2, the Employer may take partial possession provided three pre-conditions are
met:-
a) The completion of Works have been delayed
b) A Certificate of Non-Completion has been issued by Architect under clause 22.1
c) Such entry and partial possession of the Occupied Part do not unreasonably disturb the regular
progress of the Contractor’s remaining works or adversely affect the safety and health issues.
Q3: Explain the contractual implications of partial possession and the
items not affected by it.
1. Work insurance
- Under clauses 20.A.1,20.B.1, 20.C.1 are stated that the parties’ insurance
obligation remain unaffected by the partial possession situation; the value
insured is full value and so that there is no reduction can be made.
Q3: Explain the contractual implications of partial possession and the
items not affected by it.
2. Performance Bond & Final Certificate
- Under Clause 37, it stated that for performance bond does not indicate
any deduction or reduction of the bond value after partial possession.
- Under Clause 30.0, it stated that for Final Certificate are not affected by
the partial possession since there is only one Final Certificate issued.
- Therefore, it can be inferred that both the Performance Bond and the
Final Certificate are to remain unaffected by the issuance of Certificate of
Partial Completion.
QUESTIONS
Question 1:
How many percent (%) of retention sum that the employer need to release to the
contractor after the partial possession is completed and hand over to the
employer?
Answer For Q1:
Any part for which partial possession is given is deemed to have achieved
practical completion. Therefore, 50% of the retention for that part must be
released. And the balance of 50% will be released after the issuance of certificate
of making goods defect (CMGD) by the architect.
Question 2:
• Architect shall issue the Certificate of Partial Completion within
how many days and under which clause?
Answer For Q2:
Within 14 days of taking partial possession of the Occupied Parts. Clause 16.1(a)
Question 3:
Whats should the contractor do if the employer takes possession of the
Occupied Part, whether with or without contractor’s consent?
Answer For Q3:
Under clause 16.3 govern the Contractor’s duties following partial possession by the
Employer, whether with or without contractor’s consent.
1) Contractor to remove his site facilities, equipments, plants, materials, etc from
Occupied Part upon receipt of Architect’s written instruction.
2) It is implied that the Architect must prescribe a definite time for removal from the
Occupied Part and this should be a reasonable time frame
Thank You!!!

More Related Content

What's hot

DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
Anep Botak
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
ahmong4
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
DarrenTofu
 

What's hot (20)

Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
Construction plan
Construction planConstruction plan
Construction plan
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
 
Construction law cl3 (completed)
Construction law cl3 (completed)Construction law cl3 (completed)
Construction law cl3 (completed)
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
Cl report final
Cl report finalCl report final
Cl report final
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
 
Kandil_Sameh_AR50360
Kandil_Sameh_AR50360Kandil_Sameh_AR50360
Kandil_Sameh_AR50360
 

Similar to Pp2 p7

Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
seenyeeyong
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
Farah Sham
 

Similar to Pp2 p7 (20)

Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptxCONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
CONTRACTS AND CLAIMS MANAGEMENT PPT.pptx
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignment
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group Assignment
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 

More from fareezsham (20)

Building economics tutorial 1
Building economics  tutorial 1Building economics  tutorial 1
Building economics tutorial 1
 
Poster
PosterPoster
Poster
 
Il poster
Il posterIl poster
Il poster
 
Hubungan etnik
Hubungan etnik  Hubungan etnik
Hubungan etnik
 
Structural assignment
Structural assignmentStructural assignment
Structural assignment
 
Strategic mgmt present
Strategic mgmt presentStrategic mgmt present
Strategic mgmt present
 
Strategic mgmt group
Strategic mgmt groupStrategic mgmt group
Strategic mgmt group
 
Strategic management
Strategic managementStrategic management
Strategic management
 
Professional practice 1 tut 2
Professional practice 1   tut 2Professional practice 1   tut 2
Professional practice 1 tut 2
 
Pp1 group presentation
Pp1 group presentation Pp1 group presentation
Pp1 group presentation
 
Elemental cost analysis
Elemental cost analysisElemental cost analysis
Elemental cost analysis
 
Measurement 4
Measurement 4Measurement 4
Measurement 4
 
Little things make big days
Little things make big daysLittle things make big days
Little things make big days
 
2 nd report
2 nd report2 nd report
2 nd report
 
1 st report
1 st report1 st report
1 st report
 
Building services 2
Building services 2Building services 2
Building services 2
 
Building services 2 final (final)
Building services 2 final (final)Building services 2 final (final)
Building services 2 final (final)
 
Ct block work system.docx
Ct block work system.docxCt block work system.docx
Ct block work system.docx
 
Latest ct3
Latest ct3Latest ct3
Latest ct3
 
Biodiversity
BiodiversityBiodiversity
Biodiversity
 

Recently uploaded

The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

Recently uploaded (20)

INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 

Pp2 p7

  • 1. Professional Practice 2 - P7 Partial Possession by Employer Louise Fong (0322815) Muhd Fareez Sham (0322961) Chan Wei Lun (0326117)
  • 2. ● Used part of the building before practical completion ● Clause 16.0: Employer wishes to take possession of certain sections of the works before the whole Works is completed. What is partial possession?
  • 3. Why partial possession? ● Business Pressure- Current demand and price is good so they need to start business or production ● Commercial reasons- Works has been delayed so the need to complete early, thus partial possession for some sections.
  • 4. How to take partial possession? ● Under clause 16.0 employer must give a written notice of intention to take partial possession to contractor, so that contractor can prepare himself and focus the part of employer want to occupy. 1. Partial possession occur before practical completion. 2. The employer to identify part to be taken over. 3. The contractor have given his consent ● Contractor cannot unreasonably delay or withhold such consent
  • 5. Contractor consent for partial possession ● Clause 16.1 prohibits the Contractor from unreasonably withholding or delaying consent. However, the Contractor is not bound to give consent for partial possession. ● Reasons : 1. Health and Safety Issue 2. Disturb the progress of work 3. Non-payment issue for work done
  • 6. Certificate of partial completion ● Clause 16.1(a): Architect must issue Certificate of Partial Completion within 14 days of taking partial possession of the Occupied Parts. ● Certificate of Partial Completion must include date of partial possession. Layout plan is a must to identify or demarcate the occupied part and estimated value of the occupied part
  • 7. Contractual effects of partial completion • Practical Completion: Practical completion of the Occupied Part shall be deemed to have occurred on the date of taking over the Occupied Part. • Defects Liability Period (DLP): Commenced on the date of practical completion of the Occupied Part by the Employer. • Liquidated Damages (clause 16.1©): Liquidated damages shall be reduced by the ratio of the estimated value of occupied part to the contract sum.
  • 8. Example of calculation • If Occupy part is RM2 Mil. Contract sum RM10 Mil. Liquidated Damages RM1000/day • New liquidated damage = 1000-(2/10x1000) = 1000-200 = RM800 per day • Liquidated damages of RM800 per day shall apply to the remaining works
  • 9. Retention sum • Clause 16.1 (d): Architect must issue a payment certificate to release the first moiety of the retention fund in the ratio of the estimated value of the occupied part and must issue payment certificate within 14 days after the issuance of the certificate of partial completion. • Formula for retention sum: RP = VOP/CS x R ● RP= the amount of retention to be released ● VOP= estimated value of Occupied Part ● CS= Contract Sum ● R= Maximum Retention
  • 10. Example • Retention sum (max) is RM500,000. Value of Occupied Part is RM2,000,000. Contract Sum is RM10,000,000. • Value of retention sum for Occupied Part is 2/10 x 500,000= 100,000/2 = RM50,000 • 1 st moiety to be released = 100,000/2 = RM50,000
  • 11. Certificate of making good defects (CMGD) • Clause 16.1(e): All defects in the Occupied Parts have been made good, the Architect shall issue a CMGD
  • 12. Release of second moiety of retention • 16.1 (f), the Architect shall issue a certificate for the release of the remaining retention fund (second moiety) for the Occupied Part within 14 days after the issue of CMGD of the same Occupied Part.
  • 13. Items not affected by partial possession Work Insurance • Clause 20.A.1: Contractor shall keep such works so insured notwithstanding any arrangement for partial possession. • Total sum insured of the above provision is that the parties insurance obligations remain unaffected. • Respective parties remain obliged to insure and keep the works insured to the full value , there being no reduction for the value of the Occupied Part.
  • 14. Items not affected by partial possession Performance Bond and Final Certificate. • Clause 30.6 for Performance Bond does not indicate any deduction or reduction of the bond value after partial possession. • Clause 30.0 for Final Certificate are not affected by the partial possession since there is only one Final Certificate issued. • Hence, it can be inferred that both the Performance Bond and the Final Certificate are to remain unaffected by the issuance of Certificate of Partial Completion.
  • 15. Partial possession by employer (without consent) • The employer may trigger breach of contract • Restrictions on employer right to take possession without consent • Clause 16.2: A provision which caters for the common practice where the Employer does, or is forced to take over parts of the works before practical completion without the Contractor’s consent.
  • 16. Restrictions on employer rights to take partial possession without consent • Employer has no absolute rights. • Clause 16.2(a) may take partial possession provided three preconditions are met: i) The completion of Works have been delayed ii) A Certificate of Non-Completion has been issued by Architect under clause 22.1 iii) Partial possession do not unreasonably disturb the regular and remaining work
  • 17. Employer’s rights limited by the contract • Clause 16.2 “without prejudice to any other rights and remedies which he may possess under the contract” • Limit employer right to those under contract only
  • 18. Procedures following partial possession (with or without consent) • Clause 16.3: Govern the Contractor’s duties following partial possession by the Employer, whether with or without contractor’s consent. i) Contractor shall remove all facilities and equipments from the occupied part upon the receipt of AI ii) Architect shall prescribe the time for removal from occupied part iii) However contract silence on consequences of non compliance by contractor and remedies of employer iv) It is also silent on remedies available to employer for such non-compliance by the Contractor.
  • 20. Q1:Explain the differences between Sectional Completion and Partial Possession in PAM 2006. Sectional completion Partial completion Clause 21.3 Clause 16.1 Stated in contract documents (different sectional commencement date and different sectional completion date) Not stated in contract documents Architect to issue the Certificate of Partial Completion within 14 days of taking partial possession of the Occupied Parts Architect to issue the Certificate of Sectional Completion when the sections of Works are Practically Completed. Happened before Signage of Contract Happened after Signage of Contract
  • 22. Q2: Under what circumstance can the Employer take partial possession of the site? Please explain for both partial possession with and without consent from the Contractor. ● Under Clause 16.0, the employer must comply with the following:- 1. To give written notice of intention to take partial possession to contractor 2. The partial possession occurs before practical completion. 3. The employer to identify part to be taken over. 4. That the contractor has given his consent.
  • 23. Answer: Partial possession with consent from the Contractor: ● Under clause 16.1, the contractor cannot unreasonably delay or withhold such consent. Partial possession without consent from the Contractor: ● Under clause 16.2, the Employer may take partial possession provided three pre-conditions are met:- a) The completion of Works have been delayed b) A Certificate of Non-Completion has been issued by Architect under clause 22.1 c) Such entry and partial possession of the Occupied Part do not unreasonably disturb the regular progress of the Contractor’s remaining works or adversely affect the safety and health issues.
  • 24. Q3: Explain the contractual implications of partial possession and the items not affected by it. 1. Work insurance - Under clauses 20.A.1,20.B.1, 20.C.1 are stated that the parties’ insurance obligation remain unaffected by the partial possession situation; the value insured is full value and so that there is no reduction can be made.
  • 25. Q3: Explain the contractual implications of partial possession and the items not affected by it. 2. Performance Bond & Final Certificate - Under Clause 37, it stated that for performance bond does not indicate any deduction or reduction of the bond value after partial possession. - Under Clause 30.0, it stated that for Final Certificate are not affected by the partial possession since there is only one Final Certificate issued. - Therefore, it can be inferred that both the Performance Bond and the Final Certificate are to remain unaffected by the issuance of Certificate of Partial Completion.
  • 27. Question 1: How many percent (%) of retention sum that the employer need to release to the contractor after the partial possession is completed and hand over to the employer?
  • 28. Answer For Q1: Any part for which partial possession is given is deemed to have achieved practical completion. Therefore, 50% of the retention for that part must be released. And the balance of 50% will be released after the issuance of certificate of making goods defect (CMGD) by the architect.
  • 29. Question 2: • Architect shall issue the Certificate of Partial Completion within how many days and under which clause?
  • 30. Answer For Q2: Within 14 days of taking partial possession of the Occupied Parts. Clause 16.1(a)
  • 31. Question 3: Whats should the contractor do if the employer takes possession of the Occupied Part, whether with or without contractor’s consent?
  • 32. Answer For Q3: Under clause 16.3 govern the Contractor’s duties following partial possession by the Employer, whether with or without contractor’s consent. 1) Contractor to remove his site facilities, equipments, plants, materials, etc from Occupied Part upon receipt of Architect’s written instruction. 2) It is implied that the Architect must prescribe a definite time for removal from the Occupied Part and this should be a reasonable time frame