SlideShare a Scribd company logo
Lecture P4
Rights of Setting-Off by Employer
(8-12,Q3)
Rights of contractor
When contractor received the
set-off calculation from the QS
To accept the amount within 28 days
of notices of setting off
To dispute the amount within 21 days
of receipt of written notice of set-off
+ state reasons from disagreement
+ own evaluation with supporting
documents and calculation
Rights of employer
When employer received the
contractor’s written notice of dispute
To accept the contractor’s disagreement &
agree on the disputed amount within 21 days
after receipt of contractor’s response
Employer and contractor mutually come to
an agreement on the amount as set-off
Eg: Both parties pay half / Give discount
Employer and contractor unable to agree, either
party may refer the dispute to adjudication
Adjudication (Clause 34.1)
Employer can only set-off the amount
decided by the adjudicator.
If any parties disputes with the decision by
the adjudicator, he must still comply and be
bound by the decision until CPC.
“Pay Now Argues Later” (Rough Justice) =
enables the works on site to proceed with a
temporary decision on the dispute.
APPEAL
Procedure to refer the disputed decision to
an Arbitration :
Give written notice within 6 weeks from
the date of adjudicator’s decision.
After 6 weeks, the adjudicator’s decision is
final.
Restriction on Employer’s rights to set off
• Limitation on the employer’s rights to set-off:
1. The dispute arises before CPC
2. The dispute must within Clause 30.4
• Employer can only set-off when:
1. The contractor has expressly agreed to the amount
2. The disputes has gone to adjudication & the adjudicator has issued decision
Liquidated Damages (LD)
• LD are not stated in Clause 30.4 and 22.1
o Clause 30.4 – Matters subjects to an appropriate set-off
o Clause 22.1 – The imposition of LD by the Employer shall not be taken into account by the
Architect in the issuance of payment certificates and Final certificates, and is not subject to
the set-off procedures under Clause 30.4 and adjudication.
• LD is the only item that are not subject to set-off procedure and it
has to be resolved separately between employer and contractor.
• The reasons for this exemption from set-off:
o LD are often subject to disputes
o Up to the Employer’s discretion to deduct the LD from any money due to the contractor
Questions
Q3.
3a. Why are set-off and Liquidated Damages taken
up by the Employer separately and is not stated in
Interim Certificate?
3b. Can the Employer refer a set-off dispute to
arbitration during the construction period?
• Set-off and Liquidated Damages are taken up by the Employer
separately and are not stated in Interim Certificate.
• This is because Interim Certificate is to certify the works that have
been properly carried out but Set-off and Liquidated Damages are
not work done.
• They are matters between the employer and the contractor. They
are up to the employer whether to deduct or not. However, as a
professional QS, we have to highlight the rights to the employer.
Answer for 3a:
• Clause 34.1 states that any dispute under Clause 30.4 after the date of
Practical Completion shall be referred to arbitration under Clause 34.5.
• However, employer can refer a set-off dispute to arbitration during the
construction period.
• Clause 34.10 states that unless with the written agreement of the
Employer and Contractor, such arbitration proceedings shall not
commence until after Practical Completion or alleged Practical
Completion of the Works or determination or alleged determination of
the Contractor’s employment under the Contract or abandonment of
the Works except on Clause 34.10 (a)-(d).
Answer for 3b:
Q6.
What are the main differences between
Adjudication and Arbitration?
Adjudication Arbitration
Faster process  Cheaper
• Adjudicator can straight away make decision by
documents (Quick Decision)
Longer process  More expensive
• Arbitration is like court case and have more
procedures
• Eg : need witness to prove/ need to check the
documents correct or not
Dispute after CPC not going to Adjudication anymore. Dispute after CPC need to go to Arbitration.
(Clause 34.1)
After the adjudicator make decision, we must still
comply and be bound by the decision until CPC.
However, we can still appeal the decision to
Arbitration upon CPC.
Once Arbitrator make decision, we cannot challenge
or appeal.
Mainly for set-off dispute. For other dispute.

More Related Content

What's hot

M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3
Project Controls Expo
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction Contracts
Francis Ho
 
Contract costing
Contract costingContract costing
Contract costing
Prince Sagoo
 
Construction contract
Construction contractConstruction contract
Construction contract
Aqsa Shafique
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
Rai University
 
Site possession
Site possessionSite possession
Site possession
Amir Ibrahim
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
Yee Len Wan
 
Construction contract
Construction contractConstruction contract
Construction contract
Delhi Technological University
 
Contract Costing
Contract CostingContract Costing
Contract Costing
Md. Shamsur Rahman Heera
 
Unit-3_Measurement and payment
Unit-3_Measurement and paymentUnit-3_Measurement and payment
Unit-3_Measurement and payment
Akash Bharti
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
Avinash Kumar Gupta
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
SHKLaw
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
Akash Bharti
 
Contract costing
Contract costingContract costing
Contract costing
Mahesh Chandra Sharma
 
Cl compilation
Cl compilationCl compilation
Cl compilation
Jessyca Than
 
Contracts & tenders
Contracts & tendersContracts & tenders
Contracts & tenders
Swamy Vanapalli
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
srinivas2036
 

What's hot (20)

M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction Contracts
 
Site Possession
Site PossessionSite Possession
Site Possession
 
Contract costing
Contract costingContract costing
Contract costing
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
 
Site possession
Site possessionSite possession
Site possession
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Contract Costing
Contract CostingContract Costing
Contract Costing
 
Unit-3_Measurement and payment
Unit-3_Measurement and paymentUnit-3_Measurement and payment
Unit-3_Measurement and payment
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
 
Contract costing
Contract costingContract costing
Contract costing
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Contracts & tenders
Contracts & tendersContracts & tenders
Contracts & tenders
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
work_contract_tax
work_contract_taxwork_contract_tax
work_contract_tax
 
contract procedure
contract procedurecontract procedure
contract procedure
 

Similar to Seminar

Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
Shze Hwa Lee
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
ahmong4
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
Lin Hui
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
Kheng Hoe Advocates
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
seenyeeyong
 
CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021
Ir Albert YEU FCIArb MICE
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
Delhi Technological University
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
Delhi Technological University
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-payment
Arthur Wilson
 
CIPAA presentation
CIPAA presentationCIPAA presentation
CIPAA presentation
Doreen Yeo
 
Cl compilation updated
Cl compilation updatedCl compilation updated
Cl compilation updated
Yong Sy
 
CL Seminar
CL SeminarCL Seminar
CL Seminar
kohwenqi
 
UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021
Ir Albert YEU FCIArb MICE
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
Kai Yun Pang
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
Farah Sham
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
Farah Sham
 
Cc 2
Cc 2Cc 2
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the Contract
SHKLaw
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
ashleyyeap
 

Similar to Seminar (20)

Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 
CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-payment
 
CIPAA presentation
CIPAA presentationCIPAA presentation
CIPAA presentation
 
Cl compilation updated
Cl compilation updatedCl compilation updated
Cl compilation updated
 
CL Seminar
CL SeminarCL Seminar
CL Seminar
 
UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
 
Cc 2
Cc 2Cc 2
Cc 2
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the Contract
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
 

More from kohwenqi

VM Presentation
VM PresentationVM Presentation
VM Presentation
kohwenqi
 
PM Presentation
PM PresentationPM Presentation
PM Presentation
kohwenqi
 
BE Assignment
BE AssignmentBE Assignment
BE Assignment
kohwenqi
 
Measurement4
Measurement4Measurement4
Measurement4
kohwenqi
 
Software Application
Software ApplicationSoftware Application
Software Application
kohwenqi
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
kohwenqi
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
kohwenqi
 
Management science
Management scienceManagement science
Management science
kohwenqi
 
Group 5 sustainable stormwater management(building services1)
Group 5   sustainable stormwater management(building services1)Group 5   sustainable stormwater management(building services1)
Group 5 sustainable stormwater management(building services1)
kohwenqi
 
Site visit
Site visitSite visit
Site visit
kohwenqi
 
Mid valley finale
Mid valley finaleMid valley finale
Mid valley finale
kohwenqi
 

More from kohwenqi (11)

VM Presentation
VM PresentationVM Presentation
VM Presentation
 
PM Presentation
PM PresentationPM Presentation
PM Presentation
 
BE Assignment
BE AssignmentBE Assignment
BE Assignment
 
Measurement4
Measurement4Measurement4
Measurement4
 
Software Application
Software ApplicationSoftware Application
Software Application
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Management science
Management scienceManagement science
Management science
 
Group 5 sustainable stormwater management(building services1)
Group 5   sustainable stormwater management(building services1)Group 5   sustainable stormwater management(building services1)
Group 5 sustainable stormwater management(building services1)
 
Site visit
Site visitSite visit
Site visit
 
Mid valley finale
Mid valley finaleMid valley finale
Mid valley finale
 

Recently uploaded

Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
ArianaBusciglio
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
Kartik Tiwari
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
kimdan468
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
Mohammed Sikander
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Atul Kumar Singh
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
chanes7
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 

Recently uploaded (20)

Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 

Seminar

  • 1. Lecture P4 Rights of Setting-Off by Employer (8-12,Q3)
  • 2. Rights of contractor When contractor received the set-off calculation from the QS To accept the amount within 28 days of notices of setting off To dispute the amount within 21 days of receipt of written notice of set-off + state reasons from disagreement + own evaluation with supporting documents and calculation
  • 3. Rights of employer When employer received the contractor’s written notice of dispute To accept the contractor’s disagreement & agree on the disputed amount within 21 days after receipt of contractor’s response Employer and contractor mutually come to an agreement on the amount as set-off Eg: Both parties pay half / Give discount Employer and contractor unable to agree, either party may refer the dispute to adjudication
  • 4. Adjudication (Clause 34.1) Employer can only set-off the amount decided by the adjudicator. If any parties disputes with the decision by the adjudicator, he must still comply and be bound by the decision until CPC. “Pay Now Argues Later” (Rough Justice) = enables the works on site to proceed with a temporary decision on the dispute. APPEAL Procedure to refer the disputed decision to an Arbitration : Give written notice within 6 weeks from the date of adjudicator’s decision. After 6 weeks, the adjudicator’s decision is final.
  • 5. Restriction on Employer’s rights to set off • Limitation on the employer’s rights to set-off: 1. The dispute arises before CPC 2. The dispute must within Clause 30.4 • Employer can only set-off when: 1. The contractor has expressly agreed to the amount 2. The disputes has gone to adjudication & the adjudicator has issued decision
  • 6. Liquidated Damages (LD) • LD are not stated in Clause 30.4 and 22.1 o Clause 30.4 – Matters subjects to an appropriate set-off o Clause 22.1 – The imposition of LD by the Employer shall not be taken into account by the Architect in the issuance of payment certificates and Final certificates, and is not subject to the set-off procedures under Clause 30.4 and adjudication. • LD is the only item that are not subject to set-off procedure and it has to be resolved separately between employer and contractor. • The reasons for this exemption from set-off: o LD are often subject to disputes o Up to the Employer’s discretion to deduct the LD from any money due to the contractor
  • 8. Q3. 3a. Why are set-off and Liquidated Damages taken up by the Employer separately and is not stated in Interim Certificate? 3b. Can the Employer refer a set-off dispute to arbitration during the construction period?
  • 9. • Set-off and Liquidated Damages are taken up by the Employer separately and are not stated in Interim Certificate. • This is because Interim Certificate is to certify the works that have been properly carried out but Set-off and Liquidated Damages are not work done. • They are matters between the employer and the contractor. They are up to the employer whether to deduct or not. However, as a professional QS, we have to highlight the rights to the employer. Answer for 3a:
  • 10. • Clause 34.1 states that any dispute under Clause 30.4 after the date of Practical Completion shall be referred to arbitration under Clause 34.5. • However, employer can refer a set-off dispute to arbitration during the construction period. • Clause 34.10 states that unless with the written agreement of the Employer and Contractor, such arbitration proceedings shall not commence until after Practical Completion or alleged Practical Completion of the Works or determination or alleged determination of the Contractor’s employment under the Contract or abandonment of the Works except on Clause 34.10 (a)-(d). Answer for 3b:
  • 11. Q6. What are the main differences between Adjudication and Arbitration?
  • 12. Adjudication Arbitration Faster process  Cheaper • Adjudicator can straight away make decision by documents (Quick Decision) Longer process  More expensive • Arbitration is like court case and have more procedures • Eg : need witness to prove/ need to check the documents correct or not Dispute after CPC not going to Adjudication anymore. Dispute after CPC need to go to Arbitration. (Clause 34.1) After the adjudicator make decision, we must still comply and be bound by the decision until CPC. However, we can still appeal the decision to Arbitration upon CPC. Once Arbitrator make decision, we cannot challenge or appeal. Mainly for set-off dispute. For other dispute.