SlideShare a Scribd company logo
Session 6-7
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
1
Process Analysis
Process & Capacity Analysis
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
2
 Process: Is any part of an organization that takes
inputs and transforms them into outputs
 Decisions taken with respect to
 The amount of capacity that an operating unit has
 The manner in which the existing capacity is put to use
will lead to loss of productivity & overall reduction in
the profitability of the operating system
 Examples:
 Excessive delay and waiting in service systems such as a
teller counter in a bank
 Some factories working with near 100 percent utilization
of their resources
Issues in Process Analysis
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
3
 Do I have adequate number of resources to meet
the demand
 If I need to add some extra resources where
should I add?
 What is the utilization of my resources?
 If I need to increase the capacity of my system how
should I modify the process?
 Should I add some more resources?
 What will the cost of my operation?
 One can find answers to the above questions by
process analysis
Process Flow Charting
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
4
 Design & Analysis of process begins with identification
of
 activities that constitute the process
 time taken for each of the activity
 nature of flow of materials/information in the process.
 A pictorial representation of all these information could
be developed using process flow charting.
 Process flow charting employs a set of standard
symbols and graphical tools to represent all the
information pertaining to the process
 The symbols used are
 A step in the Process
 Transportation (Move)
 Storage or Inventory
Process flow chart for Shirt
Manufacturing
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
5
Process Strategy
(Example of PIZZA)
Planning Premises in Process Design
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
7
 Three generic planning premises are in use in
operations management
 Make-to-Stock (MTS): more amenable for systems with
fewer product varieties and high production volume as
in the case of continuous and streamlined flow systems
 Assemble-to-order (ATO): useful for intermittent flow
systems catering to the mid-volume mid- variety
situations
 Make-to-order (MTO): organizations typically belong
to manufacturer of high product variety (jumbled flow
process systems) use this planning methodology
Process Analysis issues for MTS
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
8
 From a process and capacity analysis perspective
MTS is related to mass production systems.
Therefore the relevant questions for process and
capacity analysis are:
 What is the productive capacity of my process per
shift or per day?
 Where is the bottleneck for this process?
 If I need to increase the capacity of the process at
which stage of the process should I invest?
 Can I improve the productive capacity by other
means than investing in new resources?
Process Analysis: Performance
Metrics
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
9
 Throughput time: Throughput time (TPUT) is the
elapsed time from the first stage of the process to the
last stage of the process. It is also known as lead time.
 Cycle Time: Cycle time is the elapsed time between
two successive output from a process that is
continuously operating in a given period of time.
 Bottleneck: That stage of the process that dictates the
output of a process is the bottleneck.
 TPUT is a relevant measure for MTO systems.
 Measures such as Cycle Time and Bottleneck are
relevant in the case of MTS systems.
Process Analysis Example:
Toy Manufacturing
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
10
Prepare
8 minutes
Pre‐treat
12
minutes
Inspect &
Pack
5 minutes
Paint
20
minutes
Dry
10
minutes
Find
• Throughput time for the process
• The bottleneck in the process
• Cycle time
Graphical Representation
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
11
Example
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
12
 Ram runs a small roti shop. People can place their
order over the phone and come and collect the roti.
Orders are taken for a standard pack of 5 rotis. The
entire process is done in batches of 5 rotis only. Roti
making and delivery has five steps. Preparing the
dough (3 minutes), rolling (5 minutes), heating (4
minutes), packing (2 minutes), billing and cash (1
minute). Given this process, answer the following:
 Prepare a process flow chart and identify the bottleneck for
the shop.
 If Ram keeps his shop open for 4 hours, how many roti can
he hope to make?
 What is the utilization of each activity in the process?
Example
Dr. Lokesh Vijayvargy, Jaipuria Jaipur
13
 A product is manufactured in a shop using a five-stage
process. The first step in the process is to cut the sheet metal
to required shapes and sizes using a shearing process. After
the shearing process, the components are subjected to
pressing operations to alter the shape of the flat sheet as per
the design. In the third stage of the process welding is done to
join the components. The next step in the process is a
painting operation. After painting, the components are packed
and kept ready for dispatch.
 The time take for each of these operations are 20, 30, 15, 12 and
6 minutes respectively.
 Presently, each stage has only one machine for operation.
 Map the process and analyses the capacity with respect to
the following scenarios:
 If the shop works for an 8-hour shift with an effective available
time of 450 minutes, what is the production capacity of the shop?
 Where is the bottleneck in the system? If we want to add one
machine, where should we make the investment?
 Identify the additional capacity required for a daily production
Pg. 353; Problem 16
Pg. 353, Question 16
Pg. 353, Question 16 (Continued)
Solution (a)
Company WWW takes order from their customers and
delivers it on the next day.
The entire processes is divided into:
1. Take the order of a customer
2. Pick the order
3. Pack the order for shipping
Workstations Capacity per hour Capacity per day
(7 AM - 7PM) = 12 Hours
Take order 100 customers/hour 1200 customers
Pick orders 80 customers/hour 960 customers
Pack orders 60 customers/hour 720 customers
Solution (a)
Bottleneck
Thus, the maximum output is the bottleneck
capacity which is 720 units per day
Solution (b)
Maximum Capacity of Order Taker : 1200
customers/day
Picking capacity is 80 customers/hour
Picking Order Station (No. of Working Hours) =
𝑫𝒆𝒎𝒂𝒏𝒅
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟
=
1200
80
= 15
Hours
Solution (b) (Continued)
Maximum Capacity of Order Taker : 1200
customers/day
Packing capacity is 60 customers/hour
Picking Order Station (No. of Working Hours) =
𝑫𝒆𝒎𝒂𝒏𝒅
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟
=
1200
60
= 20
Hours
Solution (b)
Take Orders
(12 hours)
Pick Orders
(15 hours)
Pack Orders
(20 hours)
3 Hours 5 Hours
Workstations Capacity per hour Capacity per day
(7 AM - 7PM) = 12 Hours
Take order 100 customers/hour 1200 customers
Pick orders 80 customers/hour 960 customers
Pack orders 120 customers/hour 1440 customers
Solution (e)
Bottleneck
Thus, the maximum output is the bottleneck
capacity which is 960 units per day
Packing capacity is doubled from 60 customers/hour to 120 customers/hour
Solution (e)
Impact on Solution(b)
Maximum Capacity of Order Taker : 1200
customers/day
Packing capacity is 120 customers/hour
Picking Order Station (No. of Working Hours) =
𝑫𝒆𝒎𝒂𝒏𝒅
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟
=
1200
120
= 10
Hours
Solution (e)
Impact on Solution(b)
3 Hours 0 Hours
Take Orders
(12 hours)
100
customers
/hour
Pick Orders
(15 hours)
80 customers
/hour
Pack Orders
(10 hours)
120
customers
/hour
Pg. 353 Problem 17
Pg. 353 Problem 17
Solution 17 (a)
T1
Service
Time
5 Mins
T2
Service
Time
5 Mins
T3
Service
Time
5 Mins
T4
Service
Time
5 Mins
T5
Service
Time
5 Mins
T6
Service
Time
5 Mins
T7
Service
Time
5 Mins
T8
Service
Time
5 Mins
Capacity of Each Station =
12 customer/hour
Maximum O/P Capacity (Per Hour) = 12 customer × 8
stations
Time Customer
Arriving
4:00 – 4:05 2
4:05 – 4:10 5
4:10 – 4:15 6
4:15 – 4:20 8
4:20 – 4:25 10
4:25 – 4:30 12
4:30 – 4:35 16
4:35 – 4:40 12
4:40 – 4:45 10
4:45 – 4:50 6
4:50 – 4:55 4
4:55 – 5:00 2
5:00 – 5:05 0
Solution 17 (b)
Time Customer
Arriving
+
Waiting in
Queue
Tellers
Station
Used
(Max 8)
Customer
Waiting
4:00 – 4:05 2 2 0
4:05 – 4:10 5 5 0
4:10 – 4:15 6 6 0
4:15 – 4:20 8 8 0
4:20 – 4:25 10 8 2
4:25 – 4:30 12 + 2 8 6
4:30 – 4:35 16 + 6 8 14
4:35 – 4:40 12 + 14 8 18
4:40 – 4:45 10 + 18 8 20
4:45 – 4:50 6 + 20 8 18
4:50 – 4:55 4 + 18 8 14
4:55 – 5:00 2 + 14 8 8
5:00 – 5:05 0 + 8 8 0
Solution 17 (b)
8 customers
are waiting by
5.00 Pm
But all
customers
would be
handled by
5.05PM
Waiting time is customer waiting
Waiting Time (Each Customer) =
𝑆𝑒𝑟𝑣𝑖𝑐𝑒 𝑇𝑖𝑚𝑒 𝑜𝑓 𝐸𝑎𝑐ℎ 𝐶𝑢𝑠𝑡𝑜𝑚𝑒𝑟
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑆𝑡𝑎𝑡𝑖𝑜𝑛𝑠
=
5 𝑚𝑖𝑛𝑢𝑡𝑒 𝑠𝑒𝑟𝑣𝑖𝑐𝑒
8 𝑇𝑒𝑙𝑙𝑒𝑟𝑠
= 0.625 minutes
Solution 17 (c)
Time Customer
Arriving
+
Waiting in
Queue
Tellers
Station
Used
(Max 8)
Customer
Waiting
(x)
Expected
Waiting Time
x × 0.625 mins
4:00 – 4:05 2 2 0 0
4:05 – 4:10 5 5 0 0
4:10 – 4:15 6 6 0 0
4:15 – 4:20 8 8 0 0
4:20 – 4:25 10 8 2 1.25
4:25 – 4:30 12 + 2 8 6 3.75
4:30 – 4:35 16 + 6 8 14 8.75
4:35 – 4:40 12 + 14 8 18 11.25
4:40 – 4:45 10 + 18 8 20 12.50
4:45 – 4:50 6 + 20 8 18 11.25
4:50 – 4:55 4 + 18 8 14 8.75
4:55 – 5:00 2 + 14 8 8 5.00
5:00 – 5:05 0 + 8 8 0 0
Solution 17 (c)

More Related Content

What's hot

Lean Process Improvement Techniques
Lean Process Improvement TechniquesLean Process Improvement Techniques
Lean Process Improvement Techniques
Jeremy Jay V. Lim, MBB, PMP
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
Deepesh Singh
 
Process And Layout Strategies
Process And Layout StrategiesProcess And Layout Strategies
Process And Layout Strategies
Joanmaines
 
SMED-Observation Training
SMED-Observation TrainingSMED-Observation Training
SMED-Observation Training
Harold Philbrick
 
Top 25 lean tools
Top 25 lean toolsTop 25 lean tools
Top 25 lean tools
GarrettBittner
 
Line balancing and heuristics
Line balancing and heuristicsLine balancing and heuristics
Line balancing and heuristics
Abrity Bhattacharya
 
Process planning SMED and VSM: Single minute exchange of die and Value stream...
Process planning SMED and VSM: Single minute exchange of die and Value stream...Process planning SMED and VSM: Single minute exchange of die and Value stream...
Process planning SMED and VSM: Single minute exchange of die and Value stream...
Yatinkumar Patel
 
Lean Tools
Lean ToolsLean Tools
Lean Tools
Anand Subramaniam
 
Product layout in Food Industry and Line Balancing
Product layout in Food Industry and Line BalancingProduct layout in Food Industry and Line Balancing
Product layout in Food Industry and Line Balancing
Abhishek Thakur
 
APO-Productivity Tools & Techniques (Basic)_Module-1.pdf
APO-Productivity Tools & Techniques (Basic)_Module-1.pdfAPO-Productivity Tools & Techniques (Basic)_Module-1.pdf
APO-Productivity Tools & Techniques (Basic)_Module-1.pdf
TariqulBari2
 
Learning to see (VSM)
Learning to see (VSM)Learning to see (VSM)
Learning to see (VSM)
Mohamed Effat
 
5S Training Presentation.pptx
5S Training Presentation.pptx5S Training Presentation.pptx
5S Training Presentation.pptx
S.H. Fahad Fiaz
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
avijit biswas
 
Lean Kanban Systems Training Module
Lean Kanban Systems Training ModuleLean Kanban Systems Training Module
Lean Kanban Systems Training Module
Frank-G. Adler
 
8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides 8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides
SlideTeam
 
A Quick Guide to Production Department
A Quick Guide to Production DepartmentA Quick Guide to Production Department
A Quick Guide to Production Department
Ananth Palaniappan
 
Identify 7 Wastes
Identify 7 WastesIdentify 7 Wastes
Identify 7 Wastes
Lean for U
 
Single Minute Exchange of Dies
Single Minute Exchange of DiesSingle Minute Exchange of Dies
Single Minute Exchange of Dies
Md. Nazmul Hasan Dipu
 
Improving SMT Equipment Utilization
Improving SMT Equipment UtilizationImproving SMT Equipment Utilization
Improving SMT Equipment Utilization
imdiven
 
Lean manufacturing overview
Lean manufacturing overviewLean manufacturing overview
Lean manufacturing overview
Pruek Pinyo
 

What's hot (20)

Lean Process Improvement Techniques
Lean Process Improvement TechniquesLean Process Improvement Techniques
Lean Process Improvement Techniques
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
Process And Layout Strategies
Process And Layout StrategiesProcess And Layout Strategies
Process And Layout Strategies
 
SMED-Observation Training
SMED-Observation TrainingSMED-Observation Training
SMED-Observation Training
 
Top 25 lean tools
Top 25 lean toolsTop 25 lean tools
Top 25 lean tools
 
Line balancing and heuristics
Line balancing and heuristicsLine balancing and heuristics
Line balancing and heuristics
 
Process planning SMED and VSM: Single minute exchange of die and Value stream...
Process planning SMED and VSM: Single minute exchange of die and Value stream...Process planning SMED and VSM: Single minute exchange of die and Value stream...
Process planning SMED and VSM: Single minute exchange of die and Value stream...
 
Lean Tools
Lean ToolsLean Tools
Lean Tools
 
Product layout in Food Industry and Line Balancing
Product layout in Food Industry and Line BalancingProduct layout in Food Industry and Line Balancing
Product layout in Food Industry and Line Balancing
 
APO-Productivity Tools & Techniques (Basic)_Module-1.pdf
APO-Productivity Tools & Techniques (Basic)_Module-1.pdfAPO-Productivity Tools & Techniques (Basic)_Module-1.pdf
APO-Productivity Tools & Techniques (Basic)_Module-1.pdf
 
Learning to see (VSM)
Learning to see (VSM)Learning to see (VSM)
Learning to see (VSM)
 
5S Training Presentation.pptx
5S Training Presentation.pptx5S Training Presentation.pptx
5S Training Presentation.pptx
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
 
Lean Kanban Systems Training Module
Lean Kanban Systems Training ModuleLean Kanban Systems Training Module
Lean Kanban Systems Training Module
 
8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides 8 Lean Wastes PowerPoint Presentation Slides
8 Lean Wastes PowerPoint Presentation Slides
 
A Quick Guide to Production Department
A Quick Guide to Production DepartmentA Quick Guide to Production Department
A Quick Guide to Production Department
 
Identify 7 Wastes
Identify 7 WastesIdentify 7 Wastes
Identify 7 Wastes
 
Single Minute Exchange of Dies
Single Minute Exchange of DiesSingle Minute Exchange of Dies
Single Minute Exchange of Dies
 
Improving SMT Equipment Utilization
Improving SMT Equipment UtilizationImproving SMT Equipment Utilization
Improving SMT Equipment Utilization
 
Lean manufacturing overview
Lean manufacturing overviewLean manufacturing overview
Lean manufacturing overview
 

Similar to Process analysis

Mba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1sMba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1s
Chainon
 
Constraint Management, operations management.ppt
Constraint Management, operations management.pptConstraint Management, operations management.ppt
Constraint Management, operations management.ppt
PratyushKumar908783
 
OPS 571 GENIUS You can do it--ops571genius.com
OPS 571 GENIUS You can do it--ops571genius.comOPS 571 GENIUS You can do it--ops571genius.com
OPS 571 GENIUS You can do it--ops571genius.com
agathachristie218
 
OPS 571 HELP You can do it--ops571help.com
OPS 571 HELP You can do it--ops571help.comOPS 571 HELP You can do it--ops571help.com
OPS 571 HELP You can do it--ops571help.com
agathachristie218
 
1 and 2 pojjejwjwkwiwiwiwiwiwiwjwjkwjejwm.ppt
1 and 2 pojjejwjwkwiwiwiwiwiwiwjwjkwjejwm.ppt1 and 2 pojjejwjwkwiwiwiwiwiwiwjwjkwjejwm.ppt
1 and 2 pojjejwjwkwiwiwiwiwiwiwjwjkwjejwm.ppt
doremonlovers365
 
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
37020766 jit-and-lean-manufacturing-by-sashi-prabhu37020766 jit-and-lean-manufacturing-by-sashi-prabhu
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
sashi prabhu
 
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
37020766 jit-and-lean-manufacturing-by-sashi-prabhu37020766 jit-and-lean-manufacturing-by-sashi-prabhu
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
sashi prabhu
 
Process analysis
Process analysisProcess analysis
Process analysis
Arun Kandukuri
 
Generic Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherGeneric Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S Desrocher
Alan Desrocher
 
Lean, Just-in-time, and Toyota Production System
Lean, Just-in-time,and Toyota Production SystemLean, Just-in-time,and Toyota Production System
Lean, Just-in-time, and Toyota Production System
jasonhian
 
13.jajajajajajajajjajajajqjajqjajqjajjaajppt
13.jajajajajajajajjajajajqjajqjajqjajjaajppt13.jajajajajajajajjajajajqjajqjajqjajjaajppt
13.jajajajajajajajjajajajqjajqjajqjajjaajppt
doremonlovers365
 
UOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.comUOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.com
agathachristie218
 
A company must perform a maintenance project consisting
A company must perform a maintenance project consistingA company must perform a maintenance project consisting
A company must perform a maintenance project consisting
johann11369
 
From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...
johann11371
 
Operations Research & Methodology project report
Operations Research & Methodology  project reportOperations Research & Methodology  project report
Operations Research & Methodology project report
Pankaj Kumar Dwivedi
 
A simple project listing of five activities and their respective time
A simple project listing of five activities and their respective timeA simple project listing of five activities and their respective time
A simple project listing of five activities and their respective time
johann11370
 
In hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chainsIn hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chains
johann11371
 
OPS 571 Massive Success / snaptutorial...com
OPS 571 Massive Success / snaptutorial...comOPS 571 Massive Success / snaptutorial...com
OPS 571 Massive Success / snaptutorial...com
donaldzs25
 
OPS 571 Massive Success / snaptutorial.com
OPS 571 Massive Success / snaptutorial.comOPS 571 Massive Success / snaptutorial.com
OPS 571 Massive Success / snaptutorial.com
donaldzs17
 
A company has actual unit demand for three consecutive years
A company has actual unit demand for three consecutive yearsA company has actual unit demand for three consecutive years
A company has actual unit demand for three consecutive years
johann11369
 

Similar to Process analysis (20)

Mba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1sMba 505 business_processes_operations_productivity_strategy_tutorial1s
Mba 505 business_processes_operations_productivity_strategy_tutorial1s
 
Constraint Management, operations management.ppt
Constraint Management, operations management.pptConstraint Management, operations management.ppt
Constraint Management, operations management.ppt
 
OPS 571 GENIUS You can do it--ops571genius.com
OPS 571 GENIUS You can do it--ops571genius.comOPS 571 GENIUS You can do it--ops571genius.com
OPS 571 GENIUS You can do it--ops571genius.com
 
OPS 571 HELP You can do it--ops571help.com
OPS 571 HELP You can do it--ops571help.comOPS 571 HELP You can do it--ops571help.com
OPS 571 HELP You can do it--ops571help.com
 
1 and 2 pojjejwjwkwiwiwiwiwiwiwjwjkwjejwm.ppt
1 and 2 pojjejwjwkwiwiwiwiwiwiwjwjkwjejwm.ppt1 and 2 pojjejwjwkwiwiwiwiwiwiwjwjkwjejwm.ppt
1 and 2 pojjejwjwkwiwiwiwiwiwiwjwjkwjejwm.ppt
 
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
37020766 jit-and-lean-manufacturing-by-sashi-prabhu37020766 jit-and-lean-manufacturing-by-sashi-prabhu
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
 
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
37020766 jit-and-lean-manufacturing-by-sashi-prabhu37020766 jit-and-lean-manufacturing-by-sashi-prabhu
37020766 jit-and-lean-manufacturing-by-sashi-prabhu
 
Process analysis
Process analysisProcess analysis
Process analysis
 
Generic Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherGeneric Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S Desrocher
 
Lean, Just-in-time, and Toyota Production System
Lean, Just-in-time,and Toyota Production SystemLean, Just-in-time,and Toyota Production System
Lean, Just-in-time, and Toyota Production System
 
13.jajajajajajajajjajajajqjajqjajqjajjaajppt
13.jajajajajajajajjajajajqjajqjajqjajjaajppt13.jajajajajajajajjajajajqjajqjajqjajjaajppt
13.jajajajajajajajjajajajqjajqjajqjajjaajppt
 
UOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.comUOPOPS571 You can do it--uopops571.com
UOPOPS571 You can do it--uopops571.com
 
A company must perform a maintenance project consisting
A company must perform a maintenance project consistingA company must perform a maintenance project consisting
A company must perform a maintenance project consisting
 
From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...From an operational perspective, yield management is most effective under whi...
From an operational perspective, yield management is most effective under whi...
 
Operations Research & Methodology project report
Operations Research & Methodology  project reportOperations Research & Methodology  project report
Operations Research & Methodology project report
 
A simple project listing of five activities and their respective time
A simple project listing of five activities and their respective timeA simple project listing of five activities and their respective time
A simple project listing of five activities and their respective time
 
In hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chainsIn hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chains
 
OPS 571 Massive Success / snaptutorial...com
OPS 571 Massive Success / snaptutorial...comOPS 571 Massive Success / snaptutorial...com
OPS 571 Massive Success / snaptutorial...com
 
OPS 571 Massive Success / snaptutorial.com
OPS 571 Massive Success / snaptutorial.comOPS 571 Massive Success / snaptutorial.com
OPS 571 Massive Success / snaptutorial.com
 
A company has actual unit demand for three consecutive years
A company has actual unit demand for three consecutive yearsA company has actual unit demand for three consecutive years
A company has actual unit demand for three consecutive years
 

Recently uploaded

HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdfHOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
46adnanshahzad
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
AnnySerafinaLove
 
list of states and organizations .pdf
list of  states  and  organizations .pdflist of  states  and  organizations .pdf
list of states and organizations .pdf
Rbc Rbcua
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
taqyea
 
2022 Vintage Roman Numerals Men Rings
2022 Vintage Roman  Numerals  Men  Rings2022 Vintage Roman  Numerals  Men  Rings
2022 Vintage Roman Numerals Men Rings
aragme
 
TIMES BPO: Business Plan For Startup Industry
TIMES BPO: Business Plan For Startup IndustryTIMES BPO: Business Plan For Startup Industry
TIMES BPO: Business Plan For Startup Industry
timesbpobusiness
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
CA Dr. Prithvi Ranjan Parhi
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
APCO
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
The Most Inspiring Entrepreneurs to Follow in 2024.pdf
The Most Inspiring Entrepreneurs to Follow in 2024.pdfThe Most Inspiring Entrepreneurs to Follow in 2024.pdf
The Most Inspiring Entrepreneurs to Follow in 2024.pdf
thesiliconleaders
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdfRegistered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
dazzjoker
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
Alexandra Fulford
 
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
Stephen Cashman
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
JoeYangGreatMachiner
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
ecamare2
 
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Stone Art Hub
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
hartfordclub1
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
MJ Global
 

Recently uploaded (20)

HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdfHOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
 
list of states and organizations .pdf
list of  states  and  organizations .pdflist of  states  and  organizations .pdf
list of states and organizations .pdf
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
 
2022 Vintage Roman Numerals Men Rings
2022 Vintage Roman  Numerals  Men  Rings2022 Vintage Roman  Numerals  Men  Rings
2022 Vintage Roman Numerals Men Rings
 
TIMES BPO: Business Plan For Startup Industry
TIMES BPO: Business Plan For Startup IndustryTIMES BPO: Business Plan For Startup Industry
TIMES BPO: Business Plan For Startup Industry
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
 
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
 
The Most Inspiring Entrepreneurs to Follow in 2024.pdf
The Most Inspiring Entrepreneurs to Follow in 2024.pdfThe Most Inspiring Entrepreneurs to Follow in 2024.pdf
The Most Inspiring Entrepreneurs to Follow in 2024.pdf
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian Matka
 
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdfRegistered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
 
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
 
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
 

Process analysis

  • 1. Session 6-7 Dr. Lokesh Vijayvargy, Jaipuria Jaipur 1 Process Analysis
  • 2. Process & Capacity Analysis Dr. Lokesh Vijayvargy, Jaipuria Jaipur 2  Process: Is any part of an organization that takes inputs and transforms them into outputs  Decisions taken with respect to  The amount of capacity that an operating unit has  The manner in which the existing capacity is put to use will lead to loss of productivity & overall reduction in the profitability of the operating system  Examples:  Excessive delay and waiting in service systems such as a teller counter in a bank  Some factories working with near 100 percent utilization of their resources
  • 3. Issues in Process Analysis Dr. Lokesh Vijayvargy, Jaipuria Jaipur 3  Do I have adequate number of resources to meet the demand  If I need to add some extra resources where should I add?  What is the utilization of my resources?  If I need to increase the capacity of my system how should I modify the process?  Should I add some more resources?  What will the cost of my operation?  One can find answers to the above questions by process analysis
  • 4. Process Flow Charting Dr. Lokesh Vijayvargy, Jaipuria Jaipur 4  Design & Analysis of process begins with identification of  activities that constitute the process  time taken for each of the activity  nature of flow of materials/information in the process.  A pictorial representation of all these information could be developed using process flow charting.  Process flow charting employs a set of standard symbols and graphical tools to represent all the information pertaining to the process  The symbols used are  A step in the Process  Transportation (Move)  Storage or Inventory
  • 5. Process flow chart for Shirt Manufacturing Dr. Lokesh Vijayvargy, Jaipuria Jaipur 5
  • 7. Planning Premises in Process Design Dr. Lokesh Vijayvargy, Jaipuria Jaipur 7  Three generic planning premises are in use in operations management  Make-to-Stock (MTS): more amenable for systems with fewer product varieties and high production volume as in the case of continuous and streamlined flow systems  Assemble-to-order (ATO): useful for intermittent flow systems catering to the mid-volume mid- variety situations  Make-to-order (MTO): organizations typically belong to manufacturer of high product variety (jumbled flow process systems) use this planning methodology
  • 8. Process Analysis issues for MTS Dr. Lokesh Vijayvargy, Jaipuria Jaipur 8  From a process and capacity analysis perspective MTS is related to mass production systems. Therefore the relevant questions for process and capacity analysis are:  What is the productive capacity of my process per shift or per day?  Where is the bottleneck for this process?  If I need to increase the capacity of the process at which stage of the process should I invest?  Can I improve the productive capacity by other means than investing in new resources?
  • 9. Process Analysis: Performance Metrics Dr. Lokesh Vijayvargy, Jaipuria Jaipur 9  Throughput time: Throughput time (TPUT) is the elapsed time from the first stage of the process to the last stage of the process. It is also known as lead time.  Cycle Time: Cycle time is the elapsed time between two successive output from a process that is continuously operating in a given period of time.  Bottleneck: That stage of the process that dictates the output of a process is the bottleneck.  TPUT is a relevant measure for MTO systems.  Measures such as Cycle Time and Bottleneck are relevant in the case of MTS systems.
  • 10. Process Analysis Example: Toy Manufacturing Dr. Lokesh Vijayvargy, Jaipuria Jaipur 10 Prepare 8 minutes Pre‐treat 12 minutes Inspect & Pack 5 minutes Paint 20 minutes Dry 10 minutes Find • Throughput time for the process • The bottleneck in the process • Cycle time
  • 11. Graphical Representation Dr. Lokesh Vijayvargy, Jaipuria Jaipur 11
  • 12. Example Dr. Lokesh Vijayvargy, Jaipuria Jaipur 12  Ram runs a small roti shop. People can place their order over the phone and come and collect the roti. Orders are taken for a standard pack of 5 rotis. The entire process is done in batches of 5 rotis only. Roti making and delivery has five steps. Preparing the dough (3 minutes), rolling (5 minutes), heating (4 minutes), packing (2 minutes), billing and cash (1 minute). Given this process, answer the following:  Prepare a process flow chart and identify the bottleneck for the shop.  If Ram keeps his shop open for 4 hours, how many roti can he hope to make?  What is the utilization of each activity in the process?
  • 13. Example Dr. Lokesh Vijayvargy, Jaipuria Jaipur 13  A product is manufactured in a shop using a five-stage process. The first step in the process is to cut the sheet metal to required shapes and sizes using a shearing process. After the shearing process, the components are subjected to pressing operations to alter the shape of the flat sheet as per the design. In the third stage of the process welding is done to join the components. The next step in the process is a painting operation. After painting, the components are packed and kept ready for dispatch.  The time take for each of these operations are 20, 30, 15, 12 and 6 minutes respectively.  Presently, each stage has only one machine for operation.  Map the process and analyses the capacity with respect to the following scenarios:  If the shop works for an 8-hour shift with an effective available time of 450 minutes, what is the production capacity of the shop?  Where is the bottleneck in the system? If we want to add one machine, where should we make the investment?  Identify the additional capacity required for a daily production
  • 16. Pg. 353, Question 16 (Continued)
  • 17. Solution (a) Company WWW takes order from their customers and delivers it on the next day. The entire processes is divided into: 1. Take the order of a customer 2. Pick the order 3. Pack the order for shipping
  • 18. Workstations Capacity per hour Capacity per day (7 AM - 7PM) = 12 Hours Take order 100 customers/hour 1200 customers Pick orders 80 customers/hour 960 customers Pack orders 60 customers/hour 720 customers Solution (a) Bottleneck Thus, the maximum output is the bottleneck capacity which is 720 units per day
  • 19. Solution (b) Maximum Capacity of Order Taker : 1200 customers/day Picking capacity is 80 customers/hour Picking Order Station (No. of Working Hours) = 𝑫𝒆𝒎𝒂𝒏𝒅 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟 = 1200 80 = 15 Hours
  • 20. Solution (b) (Continued) Maximum Capacity of Order Taker : 1200 customers/day Packing capacity is 60 customers/hour Picking Order Station (No. of Working Hours) = 𝑫𝒆𝒎𝒂𝒏𝒅 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟 = 1200 60 = 20 Hours
  • 21. Solution (b) Take Orders (12 hours) Pick Orders (15 hours) Pack Orders (20 hours) 3 Hours 5 Hours
  • 22. Workstations Capacity per hour Capacity per day (7 AM - 7PM) = 12 Hours Take order 100 customers/hour 1200 customers Pick orders 80 customers/hour 960 customers Pack orders 120 customers/hour 1440 customers Solution (e) Bottleneck Thus, the maximum output is the bottleneck capacity which is 960 units per day Packing capacity is doubled from 60 customers/hour to 120 customers/hour
  • 23. Solution (e) Impact on Solution(b) Maximum Capacity of Order Taker : 1200 customers/day Packing capacity is 120 customers/hour Picking Order Station (No. of Working Hours) = 𝑫𝒆𝒎𝒂𝒏𝒅 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟 = 1200 120 = 10 Hours
  • 24. Solution (e) Impact on Solution(b) 3 Hours 0 Hours Take Orders (12 hours) 100 customers /hour Pick Orders (15 hours) 80 customers /hour Pack Orders (10 hours) 120 customers /hour
  • 27. Solution 17 (a) T1 Service Time 5 Mins T2 Service Time 5 Mins T3 Service Time 5 Mins T4 Service Time 5 Mins T5 Service Time 5 Mins T6 Service Time 5 Mins T7 Service Time 5 Mins T8 Service Time 5 Mins Capacity of Each Station = 12 customer/hour Maximum O/P Capacity (Per Hour) = 12 customer × 8 stations
  • 28. Time Customer Arriving 4:00 – 4:05 2 4:05 – 4:10 5 4:10 – 4:15 6 4:15 – 4:20 8 4:20 – 4:25 10 4:25 – 4:30 12 4:30 – 4:35 16 4:35 – 4:40 12 4:40 – 4:45 10 4:45 – 4:50 6 4:50 – 4:55 4 4:55 – 5:00 2 5:00 – 5:05 0 Solution 17 (b)
  • 29. Time Customer Arriving + Waiting in Queue Tellers Station Used (Max 8) Customer Waiting 4:00 – 4:05 2 2 0 4:05 – 4:10 5 5 0 4:10 – 4:15 6 6 0 4:15 – 4:20 8 8 0 4:20 – 4:25 10 8 2 4:25 – 4:30 12 + 2 8 6 4:30 – 4:35 16 + 6 8 14 4:35 – 4:40 12 + 14 8 18 4:40 – 4:45 10 + 18 8 20 4:45 – 4:50 6 + 20 8 18 4:50 – 4:55 4 + 18 8 14 4:55 – 5:00 2 + 14 8 8 5:00 – 5:05 0 + 8 8 0 Solution 17 (b) 8 customers are waiting by 5.00 Pm But all customers would be handled by 5.05PM
  • 30. Waiting time is customer waiting Waiting Time (Each Customer) = 𝑆𝑒𝑟𝑣𝑖𝑐𝑒 𝑇𝑖𝑚𝑒 𝑜𝑓 𝐸𝑎𝑐ℎ 𝐶𝑢𝑠𝑡𝑜𝑚𝑒𝑟 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑆𝑡𝑎𝑡𝑖𝑜𝑛𝑠 = 5 𝑚𝑖𝑛𝑢𝑡𝑒 𝑠𝑒𝑟𝑣𝑖𝑐𝑒 8 𝑇𝑒𝑙𝑙𝑒𝑟𝑠 = 0.625 minutes Solution 17 (c)
  • 31. Time Customer Arriving + Waiting in Queue Tellers Station Used (Max 8) Customer Waiting (x) Expected Waiting Time x × 0.625 mins 4:00 – 4:05 2 2 0 0 4:05 – 4:10 5 5 0 0 4:10 – 4:15 6 6 0 0 4:15 – 4:20 8 8 0 0 4:20 – 4:25 10 8 2 1.25 4:25 – 4:30 12 + 2 8 6 3.75 4:30 – 4:35 16 + 6 8 14 8.75 4:35 – 4:40 12 + 14 8 18 11.25 4:40 – 4:45 10 + 18 8 20 12.50 4:45 – 4:50 6 + 20 8 18 11.25 4:50 – 4:55 4 + 18 8 14 8.75 4:55 – 5:00 2 + 14 8 8 5.00 5:00 – 5:05 0 + 8 8 0 0 Solution 17 (c)

Editor's Notes

  1. MAKE to Stock: AMUL FROZEN PIZZA ASSEMBLE TO ORDER : WILLIAM JONES PIZZA MAKE TO ORDER STRATEGY : DOMINOES PIZZA