1. Connection of electric traction substations on the
principle of input-output
2. Electric traction substation connected to the
nearby electric power plant
Connection of electric traction on the principle of input-output with two
transmission feeders equipped with three-poles switches, three-phase
busbar disconnectors and a three-pole disconnectors with earthing
blades
Electric traction substation connected to the
nearby electric power plant
There are two transformers, two transmission feeders, the two bus feeders
(high voltage and low voltage), two transformer feeders.
Each transformer has its own voltage regulator. Each feeder is fitted in same way.
The number of redundant paths, redundant equipment and devices is a basic
feature of this concept and schemes shown at figures 1 and 2. A variety of spare
delivery paths (which would be used in the case of virtually unimaginable
coincidences failures of the left feeder, right switch and transformer left) and
lots of devices make electric traction substations very complicated.
The solution of this problem is
illustrated by applying auxiliary bus
Saving three measuring transformers of 110 kV (decrease the total cost,
including installation, footages and required space).
The result: more reliable and simpler substation
Based on long time researching and studies, as well as broad international survey
conducted by the Committee A 50 Office for Research and testing (Office de
Recherrches et d'Essais), International Union of Railways, in singlephase
substations, surge arresters are not applied anymore.
This method of protection when the electric traction substation was built near
already protected buses of a power plant is assessed as dangerous for operational
reliability and plant staff and removed from the substations in developed
countries
The result: transfersally feeders are not necessary on the 110 kV side .
Scheme of electric traction substations connected via a three-phase transmission line
Transformers that are shown in the picture are without voltage regulators, which
are weak spots subjected to failures.
Result: increased plant reliability.
The next step of substation simplification is transformer feeder 110 kV and 25
kV feeder lacks and giving to circuit breaker in 110 kV feeder functions of
protection of transformer , as it shown in the previous figure.
In this case energy measurement is in 25 kV because there are required current
and voltage transformers for the protection.
So it is necessary to add kWh meters for measuring losses.
-using drawable circuit breakers in 25 kV feeders instead circuit breakers
and disconnectors which are elements of wrong manipulations;
- the application of switch-disconnectors instead circuit breakers in 25 kV
transformer feeders;
-aplication of combined instrument transformers (CT and VT in one
element) in all feeders;
Bypassing neutral section in separating substations with neutral section and
designing electeric traction substations with single transformer - parallel
connection of electric traction substations
Thyristor voltage adjustor is required to make identical voltages in catenary
in this case.
Distance between electric traction substations increase from
40 - 50 km to 80 - 90 km.
Peak power reduction wherein speed of trains do not decrease.
There are necessity for selectivity and accuracy of catenary distant relays with
power direction relay in separating substations, because two substations deliver
power to electric vehicle and ground fault.
Selectivity of catenary distant relays is acquired with time grading in
three zone toward sources.
Equivalent circuit of electric traction system 25 kV; 50 Hz for parallel
connected electric traction substations
Short circuit current:
𝑰 𝑲𝑺 =
𝑼
𝟐 ∙ 𝒁 𝑴 + 𝒁 𝑻 + 𝒁 𝒆𝒌𝒗
′
∙ 𝒍
𝑨
𝒁 𝑴 - impedance of electric network operator for two pole short circuit on
𝟏𝟏𝟎 𝒌𝑽 busbars in electric traction substation reduced on catenary voltage,
𝒁 𝑻 - impedance of single phase transformer of electric traction substations,
𝒁 𝒆𝒌𝒗
′
- equivalent impedance per unit of length of catenary
𝒁 𝑴 = 𝒋 ∙
𝟏,𝟎𝟓∙𝑼 𝟐
𝑺 𝒌
𝜴
U–voltage of catenary 𝑽 ,
𝑺 𝒌 – two phase fault power on electric traction substation busbar 𝑽𝑨
𝒁 𝑻 = 𝒋 ∙
𝒖 𝒌(%)
𝟏𝟎𝟎
𝑼 𝟐
𝑺 𝑻
𝜴 ,
where: 𝒖 𝒌(%) – relative short circuit voltage % ,
𝑺 𝑻 – nominal power of transformer 𝑽𝑨
𝒁 𝒆𝒌𝒗
′
= 𝒁 𝒗
′ − 𝜺𝒁 𝒎
′ +
𝟏−𝒆−𝒌∙𝒍
𝒌∙𝒍
𝟏 − 𝜺 𝟐 𝒁Š𝑰
′ 𝜴
𝒌𝒎
Carson-Pollaczek formulaes:
𝒁 𝒆𝒌𝒗
′
= 𝒁 𝒗
′
− 𝜺𝒁 𝒎
′
+
𝟏 − 𝒆−𝒌∙𝒍
𝒌 ∙ 𝒍
𝟏 − 𝜺 𝟐
𝒁Š𝑰
′ 𝜴
𝒌𝒎
𝒁 𝑽
′
– impedance per unit of length of catenary
𝜴
𝒌𝒎
,
𝒁Š𝑰
′
–impedance per unit of length of returning current circuit
𝜴
𝒌𝒎
,
𝒍 – distance to electrica traction substation 𝒌𝒎 ,
𝒁 𝒎
′
– mutual impedance per unit of length catenary- returning current circuit
𝜴
𝒌𝒎
,
𝜺 =
𝒁 𝒎
′
𝒁Š𝑰
′ ,
where: 𝒌 = 𝒁Š𝑰
′
∙ 𝒈 𝒌𝒎−𝟏 - propagation coefficient of gauge
𝒈- admittance per unit of length of gauge
𝑺
𝒌𝒎
Impedance per unit of length of returning current circuit with two rails: 𝒁Š𝑰
′
=
𝟎, 𝟓 𝒓Š𝒂 + 𝒋 𝒙′ + 𝒙′′ + 𝝎𝑴 𝟏,𝟐
′ 𝜴
𝒌𝒎
,
where: 𝒓Š𝒂 –resistance of rails
𝜴
𝒌𝒎
,
𝒙′
- interior reactance per unit of length of rail otpor
𝜴
𝒌𝒎
,
𝒙′′
- external rail reactance per unit of length
𝜴
𝒌𝒎
,
𝝎 = 𝟐𝝅𝒇 𝒔−𝟏
- circle frequency
Internal reactance pwr unit of length of S-49 rail: 𝒙′
= 𝟎, 𝟕𝟓 ∙ 𝒓Š𝒂
External rail reactance per unit of length:
𝒋𝒙′′
= 𝟎, 𝟎𝟒𝟗𝟑 − 𝒋𝟎, 𝟏𝟒𝟒𝟔 𝟏, 𝟓𝟑 + 𝒍𝒐𝒈 𝑹Š
𝟐
∙ 𝜸
𝜴
𝒌𝒎
𝑹Š - radius of equivalent conductor: 𝑹Š =
𝑷
𝟐𝝅
𝒄𝒎 ,
where P is rail perimeter 𝒄𝒎 .
Mutual rails impedance per unit of length: 𝒋𝝎𝑴 𝟏,𝟐
′
= 𝟎, 𝟎𝟒𝟗𝟑 − 𝒋𝟎, 𝟏𝟒𝟒𝟔 𝟏, 𝟓𝟑 +
Dependance of catenary impedance
per unit of length on distance
for S-49 and UIC 60 rails
Dependance of catenary impedance arguments on
distance for S-49 and UIC 60 rails
Short circuit current of a single truck
Overall short circuit current on place of fault is addition of currents from
two electrical traction substations.
Dependance of impedance on distance
measured by distant relay
Short circuit impedance measured by impedance relays in separating substations
(R-X diagram)
CONCLUSION
The existing designs of electric traction substations in exploitation proved to be
expensive, overcomplicated and unnecessary. Consequences are too large costs of
construction and maintenance, overcomplicated facilities, lack of diagrams
clearness and problems during maintenance.
In this paper, we proposed new ways of substations designing and changes in
designs of exploited substations when the reconstruction is needed. It reduces
costs, economizes controlling, makes maintenance simplified and improves
clearness of electrical traction substations. Availability and safety of substations
remains high. Parallel connected traction substations could reduce peak power
costs and measurements of energy consumption are simpler. This paper provides
electrical calculations for protective relay adjustments in traction systems.
Calculations of impedances and short circuit currents are performed using the
Wolfram Mathematica program.

More Related Content

What's hot

33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-system
babu yadav
 
Vishwas jain
Vishwas jainVishwas jain
Vishwas jain
Vishwas Jain
 
Electric traction ankit
Electric traction ankitElectric traction ankit
Electric traction ankit
Ankit Verma
 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-systemMasterhead Jack
 
Power electronics transformer(pet) based railway traction system
Power electronics transformer(pet) based railway traction systemPower electronics transformer(pet) based railway traction system
Power electronics transformer(pet) based railway traction system
Rajat Keshari
 
Electric traction on railways
Electric traction on railwaysElectric traction on railways
Electric traction on railways
Parvez Pathan
 
Distribution of power supply in indian railway
Distribution of power supply in indian railwayDistribution of power supply in indian railway
Distribution of power supply in indian railway
Surajit Mondal
 
Electric Traction
Electric Traction Electric Traction
Electric Traction
ZunAib Ali
 
Eletric traction
Eletric tractionEletric traction
Eletric traction
abhinav singh baghel
 
NWR summer training ppt
NWR summer training pptNWR summer training ppt
NWR summer training ppt
Kaushu Deshwal
 
SEMINAR-2015 (abhishek)
SEMINAR-2015 (abhishek)SEMINAR-2015 (abhishek)
SEMINAR-2015 (abhishek)Abhishek Karan
 
Ppt on Kharagpur railway
Ppt on Kharagpur railwayPpt on Kharagpur railway
Ppt on Kharagpur railway
SURAJBHAKTA4
 
Electric traction
Electric tractionElectric traction
Electric traction
Manish Sahu
 
Electric traction system and motors used in Electric traction system
Electric traction system and motors used in Electric traction systemElectric traction system and motors used in Electric traction system
Electric traction system and motors used in Electric traction system
abrar younas
 
Modern electric trends in electric drives
Modern electric trends in electric drivesModern electric trends in electric drives
Modern electric trends in electric drivesSurinder Kumar
 
Electric traction (Part 1)
Electric traction (Part 1)Electric traction (Part 1)
Electric traction (Part 1)
vishalwadkar9
 
Electric Traction
Electric TractionElectric Traction
Electric Traction
Nawaz Nz
 
Pantograph I - Analysis on Pantographs & Traction Control
Pantograph I - Analysis on Pantographs & Traction ControlPantograph I - Analysis on Pantographs & Traction Control
Pantograph I - Analysis on Pantographs & Traction Control
Kelvin Lam
 
ELECTRIC RAILWAY(ELECTRIC TRACTION)
ELECTRIC RAILWAY(ELECTRIC TRACTION)ELECTRIC RAILWAY(ELECTRIC TRACTION)
ELECTRIC RAILWAY(ELECTRIC TRACTION)
Arshad Hussain
 

What's hot (20)

33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-system
 
Vishwas jain
Vishwas jainVishwas jain
Vishwas jain
 
Electric traction ankit
Electric traction ankitElectric traction ankit
Electric traction ankit
 
33016052 electric-traction-system
33016052 electric-traction-system33016052 electric-traction-system
33016052 electric-traction-system
 
Power electronics transformer(pet) based railway traction system
Power electronics transformer(pet) based railway traction systemPower electronics transformer(pet) based railway traction system
Power electronics transformer(pet) based railway traction system
 
Electric traction on railways
Electric traction on railwaysElectric traction on railways
Electric traction on railways
 
Electric traction
Electric tractionElectric traction
Electric traction
 
Distribution of power supply in indian railway
Distribution of power supply in indian railwayDistribution of power supply in indian railway
Distribution of power supply in indian railway
 
Electric Traction
Electric Traction Electric Traction
Electric Traction
 
Eletric traction
Eletric tractionEletric traction
Eletric traction
 
NWR summer training ppt
NWR summer training pptNWR summer training ppt
NWR summer training ppt
 
SEMINAR-2015 (abhishek)
SEMINAR-2015 (abhishek)SEMINAR-2015 (abhishek)
SEMINAR-2015 (abhishek)
 
Ppt on Kharagpur railway
Ppt on Kharagpur railwayPpt on Kharagpur railway
Ppt on Kharagpur railway
 
Electric traction
Electric tractionElectric traction
Electric traction
 
Electric traction system and motors used in Electric traction system
Electric traction system and motors used in Electric traction systemElectric traction system and motors used in Electric traction system
Electric traction system and motors used in Electric traction system
 
Modern electric trends in electric drives
Modern electric trends in electric drivesModern electric trends in electric drives
Modern electric trends in electric drives
 
Electric traction (Part 1)
Electric traction (Part 1)Electric traction (Part 1)
Electric traction (Part 1)
 
Electric Traction
Electric TractionElectric Traction
Electric Traction
 
Pantograph I - Analysis on Pantographs & Traction Control
Pantograph I - Analysis on Pantographs & Traction ControlPantograph I - Analysis on Pantographs & Traction Control
Pantograph I - Analysis on Pantographs & Traction Control
 
ELECTRIC RAILWAY(ELECTRIC TRACTION)
ELECTRIC RAILWAY(ELECTRIC TRACTION)ELECTRIC RAILWAY(ELECTRIC TRACTION)
ELECTRIC RAILWAY(ELECTRIC TRACTION)
 

Viewers also liked

CALCULATION OF MAGNETIC AND ELECTRIC FIELDS OF A SINGLE RAIL TRACK AND INFLUE...
CALCULATION OF MAGNETIC AND ELECTRIC FIELDS OF A SINGLE RAIL TRACK AND INFLUE...CALCULATION OF MAGNETIC AND ELECTRIC FIELDS OF A SINGLE RAIL TRACK AND INFLUE...
CALCULATION OF MAGNETIC AND ELECTRIC FIELDS OF A SINGLE RAIL TRACK AND INFLUE...Dženan Ćelić
 
USAGE AND ADJUSTMENT OF AUTOMATICS AND PROTECTIVE RELAYS ON RAILWAYS
USAGE AND ADJUSTMENT OF AUTOMATICS AND PROTECTIVE RELAYS ON RAILWAYSUSAGE AND ADJUSTMENT OF AUTOMATICS AND PROTECTIVE RELAYS ON RAILWAYS
USAGE AND ADJUSTMENT OF AUTOMATICS AND PROTECTIVE RELAYS ON RAILWAYSDženan Ćelić
 
Kablovi i električne instalacije
Kablovi i električne instalacijeKablovi i električne instalacije
Kablovi i električne instalacije
gworks
 
“Principles of designing electrical installations in business and residential...
“Principles of designing electrical installations in business and residential...“Principles of designing electrical installations in business and residential...
“Principles of designing electrical installations in business and residential...Faris Karić
 
Projekat el postrojenja
Projekat el postrojenjaProjekat el postrojenja
Projekat el postrojenja
Zvonko Gašparović
 
Komenzacija reaktivne elektricne energije
Komenzacija reaktivne elektricne energijeKomenzacija reaktivne elektricne energije
Komenzacija reaktivne elektricne energijezornik
 
12687eir ppei 0809
12687eir ppei 080912687eir ppei 0809
12687eir ppei 0809Samir Salman
 
10 gromobranska zastita
10 gromobranska zastita10 gromobranska zastita
10 gromobranska zastitaWizard TM
 
заштита од струен удар
заштита од струен ударзаштита од струен удар
заштита од струен ударJovanka Ivanova
 
Journal Entries
Journal EntriesJournal Entries
Journal Entriesinnli
 
Standardni instalacioni elementi
Standardni instalacioni elementiStandardni instalacioni elementi
Standardni instalacioni elementiSlavka Čičak
 
Shashank1
Shashank1Shashank1
Design T&D of city
Design T&D of cityDesign T&D of city
Design T&D of city
Gaurav Singh
 
Baterijski sistem paljenje
Baterijski sistem paljenjeBaterijski sistem paljenje
Baterijski sistem paljenje
igoriv
 
Električne instalacije i signalni uredjaji
Električne instalacije i signalni uredjajiElektrične instalacije i signalni uredjaji
Električne instalacije i signalni uredjaji
igoriv
 

Viewers also liked (20)

CALCULATION OF MAGNETIC AND ELECTRIC FIELDS OF A SINGLE RAIL TRACK AND INFLUE...
CALCULATION OF MAGNETIC AND ELECTRIC FIELDS OF A SINGLE RAIL TRACK AND INFLUE...CALCULATION OF MAGNETIC AND ELECTRIC FIELDS OF A SINGLE RAIL TRACK AND INFLUE...
CALCULATION OF MAGNETIC AND ELECTRIC FIELDS OF A SINGLE RAIL TRACK AND INFLUE...
 
USAGE AND ADJUSTMENT OF AUTOMATICS AND PROTECTIVE RELAYS ON RAILWAYS
USAGE AND ADJUSTMENT OF AUTOMATICS AND PROTECTIVE RELAYS ON RAILWAYSUSAGE AND ADJUSTMENT OF AUTOMATICS AND PROTECTIVE RELAYS ON RAILWAYS
USAGE AND ADJUSTMENT OF AUTOMATICS AND PROTECTIVE RELAYS ON RAILWAYS
 
Kablovi i električne instalacije
Kablovi i električne instalacijeKablovi i električne instalacije
Kablovi i električne instalacije
 
struja
strujastruja
struja
 
“Principles of designing electrical installations in business and residential...
“Principles of designing electrical installations in business and residential...“Principles of designing electrical installations in business and residential...
“Principles of designing electrical installations in business and residential...
 
Dalibor nenadic
Dalibor nenadicDalibor nenadic
Dalibor nenadic
 
Instalacije u stanu
Instalacije u stanuInstalacije u stanu
Instalacije u stanu
 
Projekat el postrojenja
Projekat el postrojenjaProjekat el postrojenja
Projekat el postrojenja
 
Komenzacija reaktivne elektricne energije
Komenzacija reaktivne elektricne energijeKomenzacija reaktivne elektricne energije
Komenzacija reaktivne elektricne energije
 
12687eir ppei 0809
12687eir ppei 080912687eir ppei 0809
12687eir ppei 0809
 
10 gromobranska zastita
10 gromobranska zastita10 gromobranska zastita
10 gromobranska zastita
 
заштита од струен удар
заштита од струен ударзаштита од струен удар
заштита од струен удар
 
28 cas sastavljanje strujnih kola
28 cas sastavljanje strujnih kola28 cas sastavljanje strujnih kola
28 cas sastavljanje strujnih kola
 
Journal Entries
Journal EntriesJournal Entries
Journal Entries
 
Standardni instalacioni elementi
Standardni instalacioni elementiStandardni instalacioni elementi
Standardni instalacioni elementi
 
Shashank1
Shashank1Shashank1
Shashank1
 
Design T&D of city
Design T&D of cityDesign T&D of city
Design T&D of city
 
Rad i snaga_str-17
Rad i snaga_str-17Rad i snaga_str-17
Rad i snaga_str-17
 
Baterijski sistem paljenje
Baterijski sistem paljenjeBaterijski sistem paljenje
Baterijski sistem paljenje
 
Električne instalacije i signalni uredjaji
Električne instalacije i signalni uredjajiElektrične instalacije i signalni uredjaji
Električne instalacije i signalni uredjaji
 

Similar to NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS

RGPV EX7102 unit I
RGPV EX7102 unit IRGPV EX7102 unit I
RGPV EX7102 unit I
Mani Deep Dutt
 
HVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission LinesHVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
Rajaram Meena
 
Principles Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC SchemesPrinciples Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC Schemes
Power System Operation
 
Hvdc dad
Hvdc dadHvdc dad
Hvdc dad
dharmesh dabhi
 
Modelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway SystemModelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway System
Bérengère VIGNAUX
 
Control of kV and mA in x-ray tube.pptx
Control of kV and mA in x-ray tube.pptxControl of kV and mA in x-ray tube.pptx
Control of kV and mA in x-ray tube.pptx
Sagar Chaulagain
 
overvoltage in distribution network
overvoltage in distribution networkovervoltage in distribution network
overvoltage in distribution network
megala venkatesan
 
POWER SYSTEMS – II chapter 1 transmission line modelling.pptx
POWER SYSTEMS – II chapter 1 transmission line modelling.pptxPOWER SYSTEMS – II chapter 1 transmission line modelling.pptx
POWER SYSTEMS – II chapter 1 transmission line modelling.pptx
MaipaliJyoshnaDevi
 
A New Filtering Method and a Novel Converter Transformer for HVDC System.
A New Filtering Method and a Novel Converter Transformer for HVDC System.A New Filtering Method and a Novel Converter Transformer for HVDC System.
A New Filtering Method and a Novel Converter Transformer for HVDC System.
IOSR Journals
 
Reactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcomReactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcom
Hussain Ali
 
Unit 2 Reactive Power Management
Unit 2 Reactive Power ManagementUnit 2 Reactive Power Management
Unit 2 Reactive Power Management
SANTOSH GADEKAR
 
An Improved Single Phase Transformer less Inverter Topology for Cost Effecti...
An Improved Single Phase Transformer less Inverter Topology  for Cost Effecti...An Improved Single Phase Transformer less Inverter Topology  for Cost Effecti...
An Improved Single Phase Transformer less Inverter Topology for Cost Effecti...
IJMER
 
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt Reactor
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt ReactorTransients Caused by Switching of 420 kV Three-Phase Variable Shunt Reactor
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt Reactor
Bérengère VIGNAUX
 
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptx
ssuser99d6551
 
GENERATION OF HVDC 17.8.16 (2).ppt
GENERATION OF HVDC  17.8.16 (2).pptGENERATION OF HVDC  17.8.16 (2).ppt
GENERATION OF HVDC 17.8.16 (2).ppt
ssuser4b87fd
 
Power electronics and its applications.pptx
Power electronics and its applications.pptxPower electronics and its applications.pptx
Power electronics and its applications.pptx
SHIVANICHAUUHAN1
 
"high tension generator", "high tension","tension generator", "generator", ...
"high tension generator",  "high tension","tension generator",  "generator", ..."high tension generator",  "high tension","tension generator",  "generator", ...
"high tension generator", "high tension","tension generator", "generator", ...Prem Murti
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )
AnandMohan271812
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
IJERD Editor
 

Similar to NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS (20)

RGPV EX7102 unit I
RGPV EX7102 unit IRGPV EX7102 unit I
RGPV EX7102 unit I
 
HVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission LinesHVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
 
RAJARAM PPT
RAJARAM PPTRAJARAM PPT
RAJARAM PPT
 
Principles Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC SchemesPrinciples Control & Protection of HVDC Schemes
Principles Control & Protection of HVDC Schemes
 
Hvdc dad
Hvdc dadHvdc dad
Hvdc dad
 
Modelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway SystemModelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway System
 
Control of kV and mA in x-ray tube.pptx
Control of kV and mA in x-ray tube.pptxControl of kV and mA in x-ray tube.pptx
Control of kV and mA in x-ray tube.pptx
 
overvoltage in distribution network
overvoltage in distribution networkovervoltage in distribution network
overvoltage in distribution network
 
POWER SYSTEMS – II chapter 1 transmission line modelling.pptx
POWER SYSTEMS – II chapter 1 transmission line modelling.pptxPOWER SYSTEMS – II chapter 1 transmission line modelling.pptx
POWER SYSTEMS – II chapter 1 transmission line modelling.pptx
 
A New Filtering Method and a Novel Converter Transformer for HVDC System.
A New Filtering Method and a Novel Converter Transformer for HVDC System.A New Filtering Method and a Novel Converter Transformer for HVDC System.
A New Filtering Method and a Novel Converter Transformer for HVDC System.
 
Reactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcomReactive power management and voltage control by using statcom
Reactive power management and voltage control by using statcom
 
Unit 2 Reactive Power Management
Unit 2 Reactive Power ManagementUnit 2 Reactive Power Management
Unit 2 Reactive Power Management
 
An Improved Single Phase Transformer less Inverter Topology for Cost Effecti...
An Improved Single Phase Transformer less Inverter Topology  for Cost Effecti...An Improved Single Phase Transformer less Inverter Topology  for Cost Effecti...
An Improved Single Phase Transformer less Inverter Topology for Cost Effecti...
 
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt Reactor
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt ReactorTransients Caused by Switching of 420 kV Three-Phase Variable Shunt Reactor
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt Reactor
 
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptx
 
GENERATION OF HVDC 17.8.16 (2).ppt
GENERATION OF HVDC  17.8.16 (2).pptGENERATION OF HVDC  17.8.16 (2).ppt
GENERATION OF HVDC 17.8.16 (2).ppt
 
Power electronics and its applications.pptx
Power electronics and its applications.pptxPower electronics and its applications.pptx
Power electronics and its applications.pptx
 
"high tension generator", "high tension","tension generator", "generator", ...
"high tension generator",  "high tension","tension generator",  "generator", ..."high tension generator",  "high tension","tension generator",  "generator", ...
"high tension generator", "high tension","tension generator", "generator", ...
 
NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )NMRC Summer Tanning/Internship PPT(Anand Mohan )
NMRC Summer Tanning/Internship PPT(Anand Mohan )
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 

Recently uploaded

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 

Recently uploaded (20)

block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 

NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS

  • 1.
  • 2. 1. Connection of electric traction substations on the principle of input-output 2. Electric traction substation connected to the nearby electric power plant
  • 3. Connection of electric traction on the principle of input-output with two transmission feeders equipped with three-poles switches, three-phase busbar disconnectors and a three-pole disconnectors with earthing blades
  • 4. Electric traction substation connected to the nearby electric power plant
  • 5. There are two transformers, two transmission feeders, the two bus feeders (high voltage and low voltage), two transformer feeders. Each transformer has its own voltage regulator. Each feeder is fitted in same way. The number of redundant paths, redundant equipment and devices is a basic feature of this concept and schemes shown at figures 1 and 2. A variety of spare delivery paths (which would be used in the case of virtually unimaginable coincidences failures of the left feeder, right switch and transformer left) and lots of devices make electric traction substations very complicated.
  • 6. The solution of this problem is illustrated by applying auxiliary bus
  • 7. Saving three measuring transformers of 110 kV (decrease the total cost, including installation, footages and required space). The result: more reliable and simpler substation
  • 8. Based on long time researching and studies, as well as broad international survey conducted by the Committee A 50 Office for Research and testing (Office de Recherrches et d'Essais), International Union of Railways, in singlephase substations, surge arresters are not applied anymore. This method of protection when the electric traction substation was built near already protected buses of a power plant is assessed as dangerous for operational reliability and plant staff and removed from the substations in developed countries
  • 9. The result: transfersally feeders are not necessary on the 110 kV side . Scheme of electric traction substations connected via a three-phase transmission line Transformers that are shown in the picture are without voltage regulators, which are weak spots subjected to failures. Result: increased plant reliability.
  • 10. The next step of substation simplification is transformer feeder 110 kV and 25 kV feeder lacks and giving to circuit breaker in 110 kV feeder functions of protection of transformer , as it shown in the previous figure. In this case energy measurement is in 25 kV because there are required current and voltage transformers for the protection. So it is necessary to add kWh meters for measuring losses.
  • 11. -using drawable circuit breakers in 25 kV feeders instead circuit breakers and disconnectors which are elements of wrong manipulations; - the application of switch-disconnectors instead circuit breakers in 25 kV transformer feeders; -aplication of combined instrument transformers (CT and VT in one element) in all feeders;
  • 12. Bypassing neutral section in separating substations with neutral section and designing electeric traction substations with single transformer - parallel connection of electric traction substations
  • 13. Thyristor voltage adjustor is required to make identical voltages in catenary in this case.
  • 14. Distance between electric traction substations increase from 40 - 50 km to 80 - 90 km. Peak power reduction wherein speed of trains do not decrease.
  • 15. There are necessity for selectivity and accuracy of catenary distant relays with power direction relay in separating substations, because two substations deliver power to electric vehicle and ground fault.
  • 16. Selectivity of catenary distant relays is acquired with time grading in three zone toward sources.
  • 17. Equivalent circuit of electric traction system 25 kV; 50 Hz for parallel connected electric traction substations Short circuit current: 𝑰 𝑲𝑺 = 𝑼 𝟐 ∙ 𝒁 𝑴 + 𝒁 𝑻 + 𝒁 𝒆𝒌𝒗 ′ ∙ 𝒍 𝑨 𝒁 𝑴 - impedance of electric network operator for two pole short circuit on 𝟏𝟏𝟎 𝒌𝑽 busbars in electric traction substation reduced on catenary voltage, 𝒁 𝑻 - impedance of single phase transformer of electric traction substations, 𝒁 𝒆𝒌𝒗 ′ - equivalent impedance per unit of length of catenary
  • 18. 𝒁 𝑴 = 𝒋 ∙ 𝟏,𝟎𝟓∙𝑼 𝟐 𝑺 𝒌 𝜴 U–voltage of catenary 𝑽 , 𝑺 𝒌 – two phase fault power on electric traction substation busbar 𝑽𝑨 𝒁 𝑻 = 𝒋 ∙ 𝒖 𝒌(%) 𝟏𝟎𝟎 𝑼 𝟐 𝑺 𝑻 𝜴 , where: 𝒖 𝒌(%) – relative short circuit voltage % , 𝑺 𝑻 – nominal power of transformer 𝑽𝑨 𝒁 𝒆𝒌𝒗 ′ = 𝒁 𝒗 ′ − 𝜺𝒁 𝒎 ′ + 𝟏−𝒆−𝒌∙𝒍 𝒌∙𝒍 𝟏 − 𝜺 𝟐 𝒁Š𝑰 ′ 𝜴 𝒌𝒎
  • 19. Carson-Pollaczek formulaes: 𝒁 𝒆𝒌𝒗 ′ = 𝒁 𝒗 ′ − 𝜺𝒁 𝒎 ′ + 𝟏 − 𝒆−𝒌∙𝒍 𝒌 ∙ 𝒍 𝟏 − 𝜺 𝟐 𝒁Š𝑰 ′ 𝜴 𝒌𝒎 𝒁 𝑽 ′ – impedance per unit of length of catenary 𝜴 𝒌𝒎 , 𝒁Š𝑰 ′ –impedance per unit of length of returning current circuit 𝜴 𝒌𝒎 , 𝒍 – distance to electrica traction substation 𝒌𝒎 , 𝒁 𝒎 ′ – mutual impedance per unit of length catenary- returning current circuit 𝜴 𝒌𝒎 , 𝜺 = 𝒁 𝒎 ′ 𝒁Š𝑰 ′ , where: 𝒌 = 𝒁Š𝑰 ′ ∙ 𝒈 𝒌𝒎−𝟏 - propagation coefficient of gauge 𝒈- admittance per unit of length of gauge 𝑺 𝒌𝒎
  • 20. Impedance per unit of length of returning current circuit with two rails: 𝒁Š𝑰 ′ = 𝟎, 𝟓 𝒓Š𝒂 + 𝒋 𝒙′ + 𝒙′′ + 𝝎𝑴 𝟏,𝟐 ′ 𝜴 𝒌𝒎 , where: 𝒓Š𝒂 –resistance of rails 𝜴 𝒌𝒎 , 𝒙′ - interior reactance per unit of length of rail otpor 𝜴 𝒌𝒎 , 𝒙′′ - external rail reactance per unit of length 𝜴 𝒌𝒎 , 𝝎 = 𝟐𝝅𝒇 𝒔−𝟏 - circle frequency Internal reactance pwr unit of length of S-49 rail: 𝒙′ = 𝟎, 𝟕𝟓 ∙ 𝒓Š𝒂 External rail reactance per unit of length: 𝒋𝒙′′ = 𝟎, 𝟎𝟒𝟗𝟑 − 𝒋𝟎, 𝟏𝟒𝟒𝟔 𝟏, 𝟓𝟑 + 𝒍𝒐𝒈 𝑹Š 𝟐 ∙ 𝜸 𝜴 𝒌𝒎 𝑹Š - radius of equivalent conductor: 𝑹Š = 𝑷 𝟐𝝅 𝒄𝒎 , where P is rail perimeter 𝒄𝒎 . Mutual rails impedance per unit of length: 𝒋𝝎𝑴 𝟏,𝟐 ′ = 𝟎, 𝟎𝟒𝟗𝟑 − 𝒋𝟎, 𝟏𝟒𝟒𝟔 𝟏, 𝟓𝟑 +
  • 21. Dependance of catenary impedance per unit of length on distance for S-49 and UIC 60 rails
  • 22. Dependance of catenary impedance arguments on distance for S-49 and UIC 60 rails
  • 23. Short circuit current of a single truck Overall short circuit current on place of fault is addition of currents from two electrical traction substations.
  • 24. Dependance of impedance on distance measured by distant relay
  • 25. Short circuit impedance measured by impedance relays in separating substations (R-X diagram)
  • 26. CONCLUSION The existing designs of electric traction substations in exploitation proved to be expensive, overcomplicated and unnecessary. Consequences are too large costs of construction and maintenance, overcomplicated facilities, lack of diagrams clearness and problems during maintenance. In this paper, we proposed new ways of substations designing and changes in designs of exploited substations when the reconstruction is needed. It reduces costs, economizes controlling, makes maintenance simplified and improves clearness of electrical traction substations. Availability and safety of substations remains high. Parallel connected traction substations could reduce peak power costs and measurements of energy consumption are simpler. This paper provides electrical calculations for protective relay adjustments in traction systems. Calculations of impedances and short circuit currents are performed using the Wolfram Mathematica program.