SlideShare a Scribd company logo
CONSTRUCTION PROJECT MANAGEMENT
By-
Er. Priyanka Kale
Planning Engineer (Roads and Highway)
DIFFERENT STAGES & PROFILES IN
CONSTRUCTION PROJECT
1. Initiation
• Project Manager
• Construction
Manager
• Planning Manager
• Project Document
Controller
• Contract manager
2. Planning and
Design
• Planning engineer
• Design Manager
• Project Co-
ordinator
• Design Engineer
• Quantity Surveyor
• Estimator
• Chartered
Accountant
3. Procurement
and Execution
• Procurement
Manager
• Suppliers
• Warehouse
Manager
4. Monitoring and
Controlling
• Field Engineer
• Project Engineer
• Quality assurance
and control
manager
• Safety Engineer
5. Closing
Chartered Accountant
Initiation of Project
Planning and Design
 Schematic Design
 Design Development
 Construction Document and
Permitting
 Construction Plans and
Specifications
 Communication Plan
 Stakeholder Integration Plan
 Risk Management
 Planning engineer
 Quantity surveyor
 Project manager
Procurement and Execution
 Processing steps and time is defined
 Budget Approval
 Quotation Requests
 Negotiation and Contracts
 Receive Good/Services
 Three way matching
 Invoice Approval Payment
 Record Keeping
Monitoring and Controlling
 Keep track of scope
 Project Engineer
 Quality assurance and control manager
 Monitoring change in scope
 Control cost, schedule and quality
 Facilitate stakeholder communication
 Corrective actions
 Risk Mitigation
 Monitoring Resources
Closing Phase
 Handing over the project deliverables to the client
 Confirm the project completion
 Review all contracts and documentations
 Release resources
 Conduct most-mortem
 Archive documentation
10 Management knowledge areas
Integration Management
Scope Management
Time management
Cost Management
Quality Management
Resource Management
Communication Management
Risk Management
Procurement Management
Stakeholder Management
Project Integration Management
1. Develop Project Charter
2. Develop Project Management Plan
3. Direct and Manage Project Work
4. Manage Project Knowledge
5. Monitor and Control Project Work
6. Perform Integrated Change Control
7. Close Project or Phase
Project Scope Management
• Details all the boundaries of the project while also establishing the responsibilities
of the team,
• Defines all the procedures that need to be followed for verifying and approving the
finished work, and,
• Gives team members a definitive guideline for making project-related decisions.
• Ensure to create a Work Breakdown Structure (WBS) as it will provide a
breakdown of the scope statement into smaller, more manageable parcels.
• To avoid unnecessary work and stress, avoid ambiguity in your scope. Define it as
clearly as possible.
• Make the process of defining scope a collaborative process to prevent
misinterpretations of requirements.
Project Time Management
 Defining Activities
 Sequencing Activities
 Resource Estimating for Activities
 Duration and Effort Estimation
 Development of the Schedule
 Schedule Control
Project Cost Management
 Cost Management
 Resource planning
 Cost estimation-Cost aggregation, Reserve analysis, Historical data, Funding
limit reconciliation
 Cost budget- Earned value management
 Cost control- Earned value management, Forecasting, To-complete
performance index (TCPI), Variance analysis, Performance reviews
Project Quality Management
Quality planning
Quality assurance
Quality control
Affinity diagrams
Process decision program charts
Interrelationship diagrams
Prioritization matrices
Network diagrams
Matrix diagrams
Project Resource Management
Resource
Allocation
• Labor Consumables & materials Equipment & Tools Facilities
Finance
Resource
Levelling
• A technique in which start and finish dates are adjusted based on
resource constraints with the goal of balancing demand for resources
with the available supply
Resource
Forecasting
• Project scope and client requirements can change anytime during the
project lifecycle. Therefore, continuously monitoring and controlling
procedures ensure that you have a skilled workforce ready
Communication Management
1. Collection and analysis of data
2. Creation of messages for communication
3. Transmission or distribution of communications
4. Storage of any communication reports, files, or documents
5. Retrieval of any stored communications
6. Disposal of any old communications upon project closure or a set date
Risk Management
• Risk Identification
• Risk Analysis
• Risk Assessment
• Risk Monitoring
Procurement Management
• RFP forms
• Vendor selection criteria
• Statements of work
• Documented make-or-buy decisions
• Change request forms or process documentation
• Any noted risks added to the risk register and risk management plan
Project Stakeholder Management
 Identify Stakeholders- Project Charter, Procurement Documents, Enterprise
Environmental Factors, Organizational Process Assets
 Stakeholder Analysis- Power/Interest grid, Power/Influence grid, Power/Impact
grid, Salience model
 Control Stakeholders- Negotiations, Communications etc
qualitative and quantitative analysis is required to
systematically determine the interest of stakeholders
throughout the project
Management Profiles(Non-Technical)
 Business Development
 Land DD, Legal and Contracts
 Financial Analysis
 Banks and FI Handling
 Corporate Structuring
 Tender Process
 Documentation (DPR, FS etc)
 Payments and Accounts
 EPC and Consultant Engagement
Skills Required for Construction project
Manager
 Communication Skills: Listen, Persuade
 Must be able to respond quickly and effectively to unusual or emergency
situations
 Organizational Skills- Plan, set goals, analyzes
 Team Building Skills: Shows Empathy
 Leadership Skills: Set Examples, Provides Vision(Big Picture), delegates,
Positive Energy
 Coping Skills: Flexible, Creative, patient, persistant
 Technology Skills: Primavera, MSP, BIM etc
Different Career Areas
1.Real Estate-
2.Residential Buildings
3.Commercial Buildings
4.Hospital buildings
5.Institutional/Educational
Buildings
6.Land Development
1.Infrastructure
2.Roads and Highways
3.Bridges and mega structures
4.Airports/Ports
5.Railways/Metros
1.Industrial Construction
2.Chemical Industries
3.Hydro Electric Projects
New trends in Construction
 Building Information Management
 Drone Drivers
 Artificial Intelligence
 Modular Construction
 3 D Printing
 Green Buildings
Certifications For Improving Profile
 Indian Green Building Council –Associate Professional (IGBC-AP)
 Six Sigma Certifications (YELLOW, GREEN, BLACK AND MASTER
BLACK BELT)
 Project Management Institute-Project Management Professional and Certified
Associate in Project Management (PMP/CAPM)
 Green Rating for Integrated Habitat Assessment Certification (GRIHA)
 Leadership in Energy and Environmental Design (LEED)
 Learn BIM and about other technologies
THANKYOU!

More Related Content

What's hot

Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
温 庄壁
 
1. introduction to construction technology by 15CRP46
1. introduction to construction technology by 15CRP461. introduction to construction technology by 15CRP46
1. introduction to construction technology by 15CRP46
Noshad Ahmed Wahocho
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Alberto Sanchez
 
Construction Productivity
Construction ProductivityConstruction Productivity
Construction Productivity
Sunil Manjeri
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
Mohamed Abdalla
 
Process of Building Construction
Process of Building ConstructionProcess of Building Construction
Process of Building Construction
AyushHajare
 
Construction project management
Construction project managementConstruction project management
Construction project management
Senthil Kannan
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
Kabilan Kabi
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction
Thanigaivel Asokan
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
srinivas2036
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
McLachlan Lister Pty Limited
 
Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTION
SANJEEV Wazir
 
Quantity Surveyors (Practice)
Quantity Surveyors (Practice)Quantity Surveyors (Practice)
Quantity Surveyors (Practice)
Unais Mohamed Aliyar
 
Quality management
Quality managementQuality management
Quality management
charliesleopanadan
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
haroldtaylor1113
 
Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In Construction
Isidro Sid Calayag
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
Vimal Daluwatta
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
Manit Agarwal
 
1. introduction cm 2014
1. introduction cm 20141. introduction cm 2014
1. introduction cm 2014
dattseg
 

What's hot (20)

Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
1. introduction to construction technology by 15CRP46
1. introduction to construction technology by 15CRP461. introduction to construction technology by 15CRP46
1. introduction to construction technology by 15CRP46
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Construction Productivity
Construction ProductivityConstruction Productivity
Construction Productivity
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
 
Process of Building Construction
Process of Building ConstructionProcess of Building Construction
Process of Building Construction
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTION
 
Quantity Surveyors (Practice)
Quantity Surveyors (Practice)Quantity Surveyors (Practice)
Quantity Surveyors (Practice)
 
Quality management
Quality managementQuality management
Quality management
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In Construction
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
1. introduction cm 2014
1. introduction cm 20141. introduction cm 2014
1. introduction cm 2014
 

Similar to Presentation construction management profiles

Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
Saumya Ganguly
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
samansari22
 
L1-Project Integration Management.pdf
L1-Project Integration Management.pdfL1-Project Integration Management.pdf
L1-Project Integration Management.pdf
MUST
 
Project management
Project managementProject management
Project management
Satish Yadavalli
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
petch phanpha
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
samansari22
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
Brown Smith Wallace
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptx
Chandrasen Sharma
 
6396901
63969016396901
6396901
addisu kahsay
 
Intro to Project Management
Intro to Project ManagementIntro to Project Management
Intro to Project Management
Noman Aftab
 
Editable Elements
Editable ElementsEditable Elements
Editable Elements
Self Employed
 
Session 1 PMP 4th edition
Session 1 PMP 4th editionSession 1 PMP 4th edition
Session 1 PMP 4th edition
محمد عصمت عبد الرازق
 
Raghu CV 30_12_15
Raghu CV 30_12_15Raghu CV 30_12_15
Raghu CV 30_12_15
Raghunatha MN
 
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptx
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptxprojectplanningandprojectworkplan-130828212658-phpapp02-converted.pptx
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptx
Chandrasen Sharma
 
Project Integration Management - PMP Preparation
Project Integration Management - PMP PreparationProject Integration Management - PMP Preparation
Project Integration Management - PMP Preparation
Vladimir Vujovic
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
Zaur Ahmadov, PMP
 
My resume
My resumeMy resume
My resume
Anu Ravi
 
Project management
Project managementProject management
Project management
Anshu Suri
 
bingsusu.pptx
bingsusu.pptxbingsusu.pptx
bingsusu.pptx
giahuy646563
 
The path to planning
The path to planningThe path to planning
The path to planning
Stephen Pincher
 

Similar to Presentation construction management profiles (20)

Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
L1-Project Integration Management.pdf
L1-Project Integration Management.pdfL1-Project Integration Management.pdf
L1-Project Integration Management.pdf
 
Project management
Project managementProject management
Project management
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptx
 
6396901
63969016396901
6396901
 
Intro to Project Management
Intro to Project ManagementIntro to Project Management
Intro to Project Management
 
Editable Elements
Editable ElementsEditable Elements
Editable Elements
 
Session 1 PMP 4th edition
Session 1 PMP 4th editionSession 1 PMP 4th edition
Session 1 PMP 4th edition
 
Raghu CV 30_12_15
Raghu CV 30_12_15Raghu CV 30_12_15
Raghu CV 30_12_15
 
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptx
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptxprojectplanningandprojectworkplan-130828212658-phpapp02-converted.pptx
projectplanningandprojectworkplan-130828212658-phpapp02-converted.pptx
 
Project Integration Management - PMP Preparation
Project Integration Management - PMP PreparationProject Integration Management - PMP Preparation
Project Integration Management - PMP Preparation
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
My resume
My resumeMy resume
My resume
 
Project management
Project managementProject management
Project management
 
bingsusu.pptx
bingsusu.pptxbingsusu.pptx
bingsusu.pptx
 
The path to planning
The path to planningThe path to planning
The path to planning
 

Recently uploaded

A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 

Recently uploaded (20)

A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 

Presentation construction management profiles

  • 1. CONSTRUCTION PROJECT MANAGEMENT By- Er. Priyanka Kale Planning Engineer (Roads and Highway)
  • 2. DIFFERENT STAGES & PROFILES IN CONSTRUCTION PROJECT 1. Initiation • Project Manager • Construction Manager • Planning Manager • Project Document Controller • Contract manager 2. Planning and Design • Planning engineer • Design Manager • Project Co- ordinator • Design Engineer • Quantity Surveyor • Estimator • Chartered Accountant 3. Procurement and Execution • Procurement Manager • Suppliers • Warehouse Manager 4. Monitoring and Controlling • Field Engineer • Project Engineer • Quality assurance and control manager • Safety Engineer 5. Closing Chartered Accountant
  • 4. Planning and Design  Schematic Design  Design Development  Construction Document and Permitting  Construction Plans and Specifications  Communication Plan  Stakeholder Integration Plan  Risk Management  Planning engineer  Quantity surveyor  Project manager
  • 5. Procurement and Execution  Processing steps and time is defined  Budget Approval  Quotation Requests  Negotiation and Contracts  Receive Good/Services  Three way matching  Invoice Approval Payment  Record Keeping
  • 6. Monitoring and Controlling  Keep track of scope  Project Engineer  Quality assurance and control manager  Monitoring change in scope  Control cost, schedule and quality  Facilitate stakeholder communication  Corrective actions  Risk Mitigation  Monitoring Resources
  • 7. Closing Phase  Handing over the project deliverables to the client  Confirm the project completion  Review all contracts and documentations  Release resources  Conduct most-mortem  Archive documentation
  • 8. 10 Management knowledge areas Integration Management Scope Management Time management Cost Management Quality Management Resource Management Communication Management Risk Management Procurement Management Stakeholder Management
  • 9. Project Integration Management 1. Develop Project Charter 2. Develop Project Management Plan 3. Direct and Manage Project Work 4. Manage Project Knowledge 5. Monitor and Control Project Work 6. Perform Integrated Change Control 7. Close Project or Phase
  • 10. Project Scope Management • Details all the boundaries of the project while also establishing the responsibilities of the team, • Defines all the procedures that need to be followed for verifying and approving the finished work, and, • Gives team members a definitive guideline for making project-related decisions. • Ensure to create a Work Breakdown Structure (WBS) as it will provide a breakdown of the scope statement into smaller, more manageable parcels. • To avoid unnecessary work and stress, avoid ambiguity in your scope. Define it as clearly as possible. • Make the process of defining scope a collaborative process to prevent misinterpretations of requirements.
  • 11. Project Time Management  Defining Activities  Sequencing Activities  Resource Estimating for Activities  Duration and Effort Estimation  Development of the Schedule  Schedule Control
  • 12. Project Cost Management  Cost Management  Resource planning  Cost estimation-Cost aggregation, Reserve analysis, Historical data, Funding limit reconciliation  Cost budget- Earned value management  Cost control- Earned value management, Forecasting, To-complete performance index (TCPI), Variance analysis, Performance reviews
  • 13. Project Quality Management Quality planning Quality assurance Quality control Affinity diagrams Process decision program charts Interrelationship diagrams Prioritization matrices Network diagrams Matrix diagrams
  • 14. Project Resource Management Resource Allocation • Labor Consumables & materials Equipment & Tools Facilities Finance Resource Levelling • A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply Resource Forecasting • Project scope and client requirements can change anytime during the project lifecycle. Therefore, continuously monitoring and controlling procedures ensure that you have a skilled workforce ready
  • 15. Communication Management 1. Collection and analysis of data 2. Creation of messages for communication 3. Transmission or distribution of communications 4. Storage of any communication reports, files, or documents 5. Retrieval of any stored communications 6. Disposal of any old communications upon project closure or a set date
  • 16. Risk Management • Risk Identification • Risk Analysis • Risk Assessment • Risk Monitoring
  • 17. Procurement Management • RFP forms • Vendor selection criteria • Statements of work • Documented make-or-buy decisions • Change request forms or process documentation • Any noted risks added to the risk register and risk management plan
  • 18. Project Stakeholder Management  Identify Stakeholders- Project Charter, Procurement Documents, Enterprise Environmental Factors, Organizational Process Assets  Stakeholder Analysis- Power/Interest grid, Power/Influence grid, Power/Impact grid, Salience model  Control Stakeholders- Negotiations, Communications etc qualitative and quantitative analysis is required to systematically determine the interest of stakeholders throughout the project
  • 19. Management Profiles(Non-Technical)  Business Development  Land DD, Legal and Contracts  Financial Analysis  Banks and FI Handling  Corporate Structuring  Tender Process  Documentation (DPR, FS etc)  Payments and Accounts  EPC and Consultant Engagement
  • 20. Skills Required for Construction project Manager  Communication Skills: Listen, Persuade  Must be able to respond quickly and effectively to unusual or emergency situations  Organizational Skills- Plan, set goals, analyzes  Team Building Skills: Shows Empathy  Leadership Skills: Set Examples, Provides Vision(Big Picture), delegates, Positive Energy  Coping Skills: Flexible, Creative, patient, persistant  Technology Skills: Primavera, MSP, BIM etc
  • 21. Different Career Areas 1.Real Estate- 2.Residential Buildings 3.Commercial Buildings 4.Hospital buildings 5.Institutional/Educational Buildings 6.Land Development 1.Infrastructure 2.Roads and Highways 3.Bridges and mega structures 4.Airports/Ports 5.Railways/Metros 1.Industrial Construction 2.Chemical Industries 3.Hydro Electric Projects
  • 22. New trends in Construction  Building Information Management  Drone Drivers  Artificial Intelligence  Modular Construction  3 D Printing  Green Buildings
  • 23. Certifications For Improving Profile  Indian Green Building Council –Associate Professional (IGBC-AP)  Six Sigma Certifications (YELLOW, GREEN, BLACK AND MASTER BLACK BELT)  Project Management Institute-Project Management Professional and Certified Associate in Project Management (PMP/CAPM)  Green Rating for Integrated Habitat Assessment Certification (GRIHA)  Leadership in Energy and Environmental Design (LEED)  Learn BIM and about other technologies THANKYOU!