SlideShare a Scribd company logo
1 of 28
CONFIGURATION 
AND WORKING 
POINT AND STATE 
ESTIMATION 
BY 
OBALEYE DANIEL OLUWATIMILEHIN 
13400007007 
28-10-2014
PRESENTATION OUTLINE 
• Introduction. 
• Generic system 
• Network Presentation 
• Choice of the working point-constraints 
• Capability limits of a generating unit 
• Schematic diagram for the choice of the working point. 
• Characteristic generic hydroelectric unit for operation 
• Choice of the working point, through active and reactive dispatching 
• Previsional scheduling 
• Real-time scheduling 
• State estimation 
• Conclusion 
• References
INTRODUCTION 
The definition of the generic steady-state working point primarily requires: 
• the system configuration and parameters are constant; 
• load demands are constant; 
• the three-phase electrical part is physically symmetrical with linear behavior. 
If one would account for what actually happens in distribution and 
utilization systems, 
• an enormous amount of data, difficult (or practically impossible) to be 
collected and subjected to significant uncertainties, would have to be 
known; 
• the overall system model would be excessively overburdened possibly in an 
unjustifiable way, because many details may actually have effects that are 
predominantly local; 
• the previously mentioned hypotheses could appear unrealistic.
INTRODUCTION CONTD. 
However, such inconveniences are of minor importance in 
the overall behavior of the system; so it appears 
reasonable (and convenient) that distribution and 
utilization systems be considered only for behavior as 
“seen” from the transmission network, by treating them 
as equivalent circuits (more or less approximately) 
consisting of: 
• “equivalent loads,” directly fed by the transmission network 
through nodes (called “load nodes”) to which distribution 
networks are connected; 
• connections among these nodes, to account for interactions 
(e.g., at the subtransmission level) between distribution 
networks.
GENERIC SYSTEM
GENERIC SYSTEM contd. 
Figure 2.1 represents a generic system; which 
indicates the block named “network” defined 
within types of “terminal” nodes, which can be 
classified as follows: 
• generation nodes, which correspond to the synchronous generator 
terminals (i.e., at the primary side terminals of step-up 
transformers). 
• reactive compensation nodes, which correspond in an analogous 
way to synchronous and static compensator terminals. 
• load nodes, i.e., nodes supplying the equivalent loads. 
• possible boundary nodes, for connection with external systems.
NETWORK REPRESENTATION 
In the generic steady-state, phase voltages and currents are, at 
any given network point, sinusoidal, of positive sequence, and at a 
“network” frequency equal to the electrical speed of the 
synchronous machines. Also, at any given point, active and 
reactive powers are constant. Specifically, by applying the Park’s 
transformation with a “synchronous” reference (i.e., rotating at 
the same electrical speed as the synchronous machines), the 
following holds: 
• each set of phase voltages or currents transforms into a constant 
vector; 
• the characteristics of the (passive) elements of the network and the 
relationships between the mentioned vectors are defined by the 
corresponding positive sequence equivalent circuits, both passive 
and linear, with impedances (or admittances) evaluated at the 
network frequency, and “phase-shifters” in the case of transformers 
with complex ratio.
NETWORK REPRESENTATION 
Therefore, the whole network is represented by a passive and 
linear circuit, with “nodes” connected through “branches”. More 
precisely, apart from the “reference” node for voltage vectors, the 
following node types can be identified; 
• terminal nodes (see Section 2.1.1), through which an outside 
“injection” of current or power is generally performed. 
• internal nodes, which refer only to network elements and do not 
allow any outside injection. 
A generic branch may be: 
• a series branch, if it connects a pair of the above-mentioned nodes 
(terminal and/or internal); 
• a shunt branch, if it connects one of the above-mentioned nodes with 
the voltage reference node.
CHOICE OF THE WORKING POINT-Constraints 
At the scheduling stage, every future working point should be 
chosen by considering not only the network equations, but also: 
• conditions at the terminal nodes, which are defined by operating 
characteristics and admissibility limits of the external equipment 
connected to the network itself (e.g., generators, equivalent loads, 
etc.). 
• operating requirements (quality, economy, security). 
• admissibility limits for each network equipment. 
To meet quality requirements in this connection, the network 
frequency should be kept at the nominal, e.g., ω = ωnom, whereas 
node voltages (particularly terminal node voltages) must have 
magnitudes not far from the nominal values, according to 
“inequality” constraints; v ∈ [vmin, vmax] 
Example; vmin = 0.90–0.95 vnom and vmax = 1.05–1.10 vnom.
• Moreover, at the terminal nodes, further constraints on injected 
powers must be evaluated, concerning the characteristics of the 
equipment external to the network. 
• With load nodes, the active power Pc and the reactive power Qc 
absorbed by a generic “equivalent load” may be assumed as input 
data to the problem, so that “equality” constraints: 
P = −Pc, Q = −Qc 
The negative sign is the result of assuming P and Q as the generic 
injected powers entering into the network. 
• With generation nodes, the capability limits of each generating unit 
should be evaluated, with inequality constraints (see Fig. 2.9): 
P ∈ [Pmin, Pmax] 
Q ∈ [Qmin,Qmax]
CAPABILITY LIMITS OF A GENERATING 
UNIT.
SCHEMATIC DIAGRAM FOR THE 
CHOICE OF THE WORKING POINT.
CHARACTERISTIC GENERIC HYDROELECTRIC UNIT FOR 
OPERATION 
• For a generic 
hydroelectric unit, the 
used water flow q 
(disregarding losses) 
depends on the active 
power P supplied to the 
grid, according to a 
characteristic shown in 
Figure 2.14a. Such a 
characteristic may vary 
with the operating 
conditions of the plant 
(e.g., water level in the 
reservoir) and its 
efficiency status.
CHOICE OF THE WORKING POINT, THROUGH 
ACTIVE AND REACTIVE DISPATCHING.
ACTIVE AND REACTIVE 
DISPATCHING 
• Active Dispatching is the determination of the 
active power share at different generation nodes and, 
possibly, boundary nodes, which minimizes the overall 
generation cost, accounting for constraints on generated 
active powers and currents (with adequate margins, for 
security requirements). Active dispatching also can take 
advantage of adjustable parameters, if the system is 
equipped with “quadrature”-regulating transformers to 
modify the different branch currents in the network. To 
obtain a satisfactory solution, the system configuration, and 
more specifically the set of operating generators, may 
require correction to meet the requirements of spinning 
reserve.
ACTIVE AND REACTIVE 
DISPATCHING CONTD. 
• Reactive Dispatching implies the choice of 
voltages (except at load nodes) by considering constraints on all 
voltages (at terminal and internal nodes) and generated reactive 
powers (at generation and reactive compensation nodes), and 
providing sufficient reactive power margins. In reactive dispatching, 
the role of adjustable parameters—corresponding to tap-changing 
transformers, adjustable condensers and reactors, and “in-phase” 
regulating transformers—is particularly important. To obtain a 
satisfactory solution, the system configuration and, more 
specifically, the whole set of operating compensators (and/or 
generators themselves) may need to be corrected so that at the 
corresponding nodes the required reactive power margins can be 
achieved.
CHOICE OF THE HYDROELECTRIC 
GENERATION SCHEDULE. 
• The hydroelectric generation schedule has been 
assumed to be preassigned up to now. Actually it 
must be properly coordinated with the thermal 
generation schedule, so that the most 
economical overall solution may be obtained. 
Such coordination must be performed “over 
time,” based on: 
• forecasting hydraulic inflows, and spillages for uses different 
from generation; 
• scheduling water storages in reservoirs and basins.
PREVISIONAL SCHEDULING 
Data for the previsional scheduling basically concern: 
• system components; 
• load demands; 
• different inflows available for generation. 
Data about system components concern not only already 
existing equipment, but also those on the way into 
service. Thus problems relevant for the operational 
scheduling also can overlap—particularly in the long 
term, e.g., from 6 months to several years—with those 
concerning the system development planning.
PREVISIONAL SCHEDULING contd. 
Load demands are defined, in detail, by the variations with time (“load 
diagram”), as active and reactive powers absorbed at each load 
node. However, because of uncertainties in forecasting, it may be 
preferable to accept simpler more easily predictable specifications, 
by grouping loads at a single or a few “equivalent” nodes and/or 
assuming step-varying load diagrams defined by mean values within 
each time interval, etc., according to the following (risks resulting 
from forecasting errors should be accounted for).
PREVISIONAL SCHEDULING contd. 
• The different inflows available for generation 
are typically constituted by water inflows (having subtracted 
possible spillages) in the hydroplants. Similarly, we may consider 
natural inflows of fuel or of motive fluid to possible geothermal 
power plants, and so on. Hydraulic inflows are basically the natural 
ones, caused by rain and snow and ice melting, and then depending 
on meteorological conditions and water travel times. Moreover, in 
the case of snow and ice melting, the inflows depend on the state 
of snow fields and glaciers, and thus on the meteorological 
conditions of the preceding winter. Further inflows may be added to 
natural ones, such as those due to hydraulic coupling, i.e., caused by 
the outflow from hydroplants located upstream and belonging to 
the same valley, and those due to pumping.
TYPES OF PREVISIONAL 
SCHEDULING 
• long-term scheduling: T = 1 year; 
• medium-term scheduling: T = 1 week; 
• short-term scheduling: T = 1 day, 
(a) Long-Term Scheduling 
• With the long-term, the choice T = 1 year 
appears particularly reasonable, because it 
corresponds to the longest time interval by 
which load demands and hydraulic inflows 
vary more or less cyclically.
TYPES OF PREVISIONAL 
SCHEDULING CONTD. 
(b) Medium-Term Scheduling 
The fundamental problems to be solved in medium-term scheduling concern 
configuration and water storages; precisely, the typical goals are: 
• determination of water storages at the end of subsequent days (for any value of 
the storage at the beginning of the week), for each hydroelectric plant; 
• determination of the operating schedule of units (unit commitment), specifically 
thermal units. 
The choice of a total interval duration T = 1 week, as assumed in the following, may 
be efficient and meaningful, as: 
• it allows a good link with the long-term scheduling; 
• the operating schedule of thermal units (with possible startups and shutdowns) 
must be chosen along a time interval including at least 1 week because of the 
alternating working days and holidays, with significantly different load demands; 
• considering a period of 1 week, it is possible to use data reliable enough, with 
respect to the described goals.
TYPES OF PREVISIONAL 
SCHEDULING CONTD. 
• (c) Short-Term Scheduling 
• The fundamental aim of short-term scheduling is to 
accurately define the hydroelectrical and thermal 
generation schedules and, more generally, the working 
points of the system with reference, for instance, to the 
next day. 
The choice T = 1 day allows a precise connection with 
medium-term scheduling, at least for water storages in 
hydroelectric plants; whereas errors in forecasting load 
behavior, etc. may be considered acceptable, without 
adopting a shorter duration, because their effects can 
be compensated by real-time scheduling.
REAL-TIME SCHEDULING 
The goals to be achieved by means of Real-time Scheduling are: 
• to check the actual working point with relation to quality, security, 
and economy requirements, based on measurements performed on 
the system during real operation; 
• to determine necessary corrective actions (on control system set-points, 
parameters, and system configuration itself), to obtain the 
most satisfying working point. 
• Real-time scheduling assumes that the operating state is a steady-state 
that is kept unchanged for a sufficiently long time interval, 
considering the unavoidable delay between the measurement 
achievement and the corrective actions. This delay may be some 
minutes, because of state estimation and dispatching (with security 
checks, etc.), teletransmission of corrective signals, and their 
subsequent actuation.
STATE ESTIMATION 
• The “state estimation” may be performed 
according to Figure 2.44. Analogtype 
measurements to be converted into digital may 
concern active and reactive generated powers, 
active exchanged powers, voltage magnitudes, 
active and reactive power flows and, rarely, active 
and reactive powers absorbed by loads. Digital 
measurements typically concern the status (open 
or closed) of circuit breakers and disconnectors, 
and the values of adjustable parameters 
(discontinuous ones, such as transformer tap-changer 
position).
STATE ESTIMATION PROCEDURE
CONCLUSION 
• In order to get the needed and adequate 
power output from hydropower generation 
the Configuration and Working point and State 
Estimation must be considered.
REFERENCE 
• ELECTRIC POWER SYSTEMS BY Fabio 
Saccomanno

More Related Content

What's hot

A novel control strategy for synchronous rectifier buck converter for improve...
A novel control strategy for synchronous rectifier buck converter for improve...A novel control strategy for synchronous rectifier buck converter for improve...
A novel control strategy for synchronous rectifier buck converter for improve...IAEME Publication
 
Optimal supplementary-damping-controller-design-for-tcsc-employing-rcga
Optimal supplementary-damping-controller-design-for-tcsc-employing-rcgaOptimal supplementary-damping-controller-design-for-tcsc-employing-rcga
Optimal supplementary-damping-controller-design-for-tcsc-employing-rcgaCemal Ardil
 
F0315040047
F0315040047F0315040047
F0315040047theijes
 
P-Q Theory Based UPQC for Reactive Power Compensation with UCAP
P-Q Theory Based UPQC for Reactive Power Compensation with UCAPP-Q Theory Based UPQC for Reactive Power Compensation with UCAP
P-Q Theory Based UPQC for Reactive Power Compensation with UCAPIRJET Journal
 
IRJET-Robust Intelligent Controller for Voltage Stabilization of dc-dc Boost ...
IRJET-Robust Intelligent Controller for Voltage Stabilization of dc-dc Boost ...IRJET-Robust Intelligent Controller for Voltage Stabilization of dc-dc Boost ...
IRJET-Robust Intelligent Controller for Voltage Stabilization of dc-dc Boost ...IRJET Journal
 
Voltage profile Improvement Using Static Synchronous Compensator STATCOM
Voltage profile Improvement Using Static Synchronous Compensator STATCOMVoltage profile Improvement Using Static Synchronous Compensator STATCOM
Voltage profile Improvement Using Static Synchronous Compensator STATCOMINFOGAIN PUBLICATION
 
Optimal Placement of TCSC and SVC Using PSO
Optimal Placement of TCSC and SVC Using PSOOptimal Placement of TCSC and SVC Using PSO
Optimal Placement of TCSC and SVC Using PSOIOSR Journals
 
A voltage sensitivity index application for power system load shedding consid...
A voltage sensitivity index application for power system load shedding consid...A voltage sensitivity index application for power system load shedding consid...
A voltage sensitivity index application for power system load shedding consid...IJAEMSJORNAL
 
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...IRJET Journal
 
Analysis of Six Active Power Control Strategies of Interconnected Grids with ...
Analysis of Six Active Power Control Strategies of Interconnected Grids with ...Analysis of Six Active Power Control Strategies of Interconnected Grids with ...
Analysis of Six Active Power Control Strategies of Interconnected Grids with ...Power System Operation
 
Reparation of Inductive Power in Power System by the use of FACTS devices
Reparation of Inductive Power in Power System by the use of FACTS devicesReparation of Inductive Power in Power System by the use of FACTS devices
Reparation of Inductive Power in Power System by the use of FACTS devicesIJMTST Journal
 
Power Quality Improvement in Microgrids using STATCOM under Unbalanced Voltag...
Power Quality Improvement in Microgrids using STATCOM under Unbalanced Voltag...Power Quality Improvement in Microgrids using STATCOM under Unbalanced Voltag...
Power Quality Improvement in Microgrids using STATCOM under Unbalanced Voltag...mohammad hossein mousavi
 
Modeling of Hysteresis Current Control Technique for Three Phase PV Based VSI...
Modeling of Hysteresis Current Control Technique for Three Phase PV Based VSI...Modeling of Hysteresis Current Control Technique for Three Phase PV Based VSI...
Modeling of Hysteresis Current Control Technique for Three Phase PV Based VSI...IRJET Journal
 

What's hot (19)

0178__Waseda__HCMUT
0178__Waseda__HCMUT0178__Waseda__HCMUT
0178__Waseda__HCMUT
 
A novel control strategy for synchronous rectifier buck converter for improve...
A novel control strategy for synchronous rectifier buck converter for improve...A novel control strategy for synchronous rectifier buck converter for improve...
A novel control strategy for synchronous rectifier buck converter for improve...
 
Optimal supplementary-damping-controller-design-for-tcsc-employing-rcga
Optimal supplementary-damping-controller-design-for-tcsc-employing-rcgaOptimal supplementary-damping-controller-design-for-tcsc-employing-rcga
Optimal supplementary-damping-controller-design-for-tcsc-employing-rcga
 
Performance Comparison of Star Connected Cascaded STATCOM Using Different PWM...
Performance Comparison of Star Connected Cascaded STATCOM Using Different PWM...Performance Comparison of Star Connected Cascaded STATCOM Using Different PWM...
Performance Comparison of Star Connected Cascaded STATCOM Using Different PWM...
 
F0315040047
F0315040047F0315040047
F0315040047
 
A new switching look-up table for direct power control of grid connected 3L-N...
A new switching look-up table for direct power control of grid connected 3L-N...A new switching look-up table for direct power control of grid connected 3L-N...
A new switching look-up table for direct power control of grid connected 3L-N...
 
P-Q Theory Based UPQC for Reactive Power Compensation with UCAP
P-Q Theory Based UPQC for Reactive Power Compensation with UCAPP-Q Theory Based UPQC for Reactive Power Compensation with UCAP
P-Q Theory Based UPQC for Reactive Power Compensation with UCAP
 
Kf2417451751
Kf2417451751Kf2417451751
Kf2417451751
 
IRJET-Robust Intelligent Controller for Voltage Stabilization of dc-dc Boost ...
IRJET-Robust Intelligent Controller for Voltage Stabilization of dc-dc Boost ...IRJET-Robust Intelligent Controller for Voltage Stabilization of dc-dc Boost ...
IRJET-Robust Intelligent Controller for Voltage Stabilization of dc-dc Boost ...
 
Voltage profile Improvement Using Static Synchronous Compensator STATCOM
Voltage profile Improvement Using Static Synchronous Compensator STATCOMVoltage profile Improvement Using Static Synchronous Compensator STATCOM
Voltage profile Improvement Using Static Synchronous Compensator STATCOM
 
Optimal Placement of TCSC and SVC Using PSO
Optimal Placement of TCSC and SVC Using PSOOptimal Placement of TCSC and SVC Using PSO
Optimal Placement of TCSC and SVC Using PSO
 
A voltage (1)
A voltage (1)A voltage (1)
A voltage (1)
 
A voltage sensitivity index application for power system load shedding consid...
A voltage sensitivity index application for power system load shedding consid...A voltage sensitivity index application for power system load shedding consid...
A voltage sensitivity index application for power system load shedding consid...
 
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
 
Analysis of Six Active Power Control Strategies of Interconnected Grids with ...
Analysis of Six Active Power Control Strategies of Interconnected Grids with ...Analysis of Six Active Power Control Strategies of Interconnected Grids with ...
Analysis of Six Active Power Control Strategies of Interconnected Grids with ...
 
Reparation of Inductive Power in Power System by the use of FACTS devices
Reparation of Inductive Power in Power System by the use of FACTS devicesReparation of Inductive Power in Power System by the use of FACTS devices
Reparation of Inductive Power in Power System by the use of FACTS devices
 
White paper
White paperWhite paper
White paper
 
Power Quality Improvement in Microgrids using STATCOM under Unbalanced Voltag...
Power Quality Improvement in Microgrids using STATCOM under Unbalanced Voltag...Power Quality Improvement in Microgrids using STATCOM under Unbalanced Voltag...
Power Quality Improvement in Microgrids using STATCOM under Unbalanced Voltag...
 
Modeling of Hysteresis Current Control Technique for Three Phase PV Based VSI...
Modeling of Hysteresis Current Control Technique for Three Phase PV Based VSI...Modeling of Hysteresis Current Control Technique for Three Phase PV Based VSI...
Modeling of Hysteresis Current Control Technique for Three Phase PV Based VSI...
 

Viewers also liked

Parallel kalman filter based time domain harmonic state estimation 160406
Parallel kalman filter based time domain harmonic state estimation 160406Parallel kalman filter based time domain harmonic state estimation 160406
Parallel kalman filter based time domain harmonic state estimation 160406Benito Ortiz Bejar
 
Lecture14
Lecture14Lecture14
Lecture14zukun
 
Estimation & project planning
Estimation & project planningEstimation & project planning
Estimation & project planningalle_tode
 
Questionnaire for media mag. jenny.
Questionnaire for media mag. jenny.Questionnaire for media mag. jenny.
Questionnaire for media mag. jenny.Jennykam
 
State Estimation of Power System with Interline Power Flow Controller
State Estimation of Power System with Interline Power Flow ControllerState Estimation of Power System with Interline Power Flow Controller
State Estimation of Power System with Interline Power Flow ControllerIDES Editor
 
State estimation and Mean-Field Control with application to demand dispatch
State estimation and Mean-Field Control with application to demand dispatchState estimation and Mean-Field Control with application to demand dispatch
State estimation and Mean-Field Control with application to demand dispatchSean Meyn
 
Time domain harmonic state estimation using filtered measurements based on fo...
Time domain harmonic state estimation using filtered measurements based on fo...Time domain harmonic state estimation using filtered measurements based on fo...
Time domain harmonic state estimation using filtered measurements based on fo...Benito Ortiz Bejar
 
Power System State Estimation - A Review
Power System State Estimation - A ReviewPower System State Estimation - A Review
Power System State Estimation - A ReviewIDES Editor
 
VSC based HVDC system
VSC based HVDC systemVSC based HVDC system
VSC based HVDC systemmdhsudhan
 

Viewers also liked (12)

Parallel kalman filter based time domain harmonic state estimation 160406
Parallel kalman filter based time domain harmonic state estimation 160406Parallel kalman filter based time domain harmonic state estimation 160406
Parallel kalman filter based time domain harmonic state estimation 160406
 
Lecture14
Lecture14Lecture14
Lecture14
 
06 2015 pesgm_wllv_vsc
06 2015 pesgm_wllv_vsc06 2015 pesgm_wllv_vsc
06 2015 pesgm_wllv_vsc
 
Estimation & project planning
Estimation & project planningEstimation & project planning
Estimation & project planning
 
Questionnaire for media mag. jenny.
Questionnaire for media mag. jenny.Questionnaire for media mag. jenny.
Questionnaire for media mag. jenny.
 
State Estimation of Power System with Interline Power Flow Controller
State Estimation of Power System with Interline Power Flow ControllerState Estimation of Power System with Interline Power Flow Controller
State Estimation of Power System with Interline Power Flow Controller
 
State estimation and Mean-Field Control with application to demand dispatch
State estimation and Mean-Field Control with application to demand dispatchState estimation and Mean-Field Control with application to demand dispatch
State estimation and Mean-Field Control with application to demand dispatch
 
Time domain harmonic state estimation using filtered measurements based on fo...
Time domain harmonic state estimation using filtered measurements based on fo...Time domain harmonic state estimation using filtered measurements based on fo...
Time domain harmonic state estimation using filtered measurements based on fo...
 
State estimation
State estimationState estimation
State estimation
 
Power System State Estimation - A Review
Power System State Estimation - A ReviewPower System State Estimation - A Review
Power System State Estimation - A Review
 
VSC based HVDC system
VSC based HVDC systemVSC based HVDC system
VSC based HVDC system
 
P1111130668
P1111130668P1111130668
P1111130668
 

Similar to Configuration and working point and state estimation

Power Flow & Voltage Stability Analysis using MATLAB
Power Flow & Voltage Stability Analysis using MATLAB Power Flow & Voltage Stability Analysis using MATLAB
Power Flow & Voltage Stability Analysis using MATLAB IRJET Journal
 
Power Flow Control using Quadrature Boosters
Power Flow Control using Quadrature BoostersPower Flow Control using Quadrature Boosters
Power Flow Control using Quadrature Boostersbalasubu2k
 
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...IRJET Journal
 
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...IJERA Editor
 
Admittance model and Power flow study.pptx
Admittance model and Power flow study.pptxAdmittance model and Power flow study.pptx
Admittance model and Power flow study.pptxJoseeMusabyimana
 
HVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission LinesHVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission LinesRajaram Meena
 
Modeling of BESS for Blackstart System Restoration Studies
Modeling of BESS for Blackstart System Restoration StudiesModeling of BESS for Blackstart System Restoration Studies
Modeling of BESS for Blackstart System Restoration StudiesPower System Operation
 
Enhancement of Reactive Power Compensation in PV Grid System To Increase The ...
Enhancement of Reactive Power Compensation in PV Grid System To Increase The ...Enhancement of Reactive Power Compensation in PV Grid System To Increase The ...
Enhancement of Reactive Power Compensation in PV Grid System To Increase The ...IJSRD
 
212741860 assignment
212741860 assignment212741860 assignment
212741860 assignmenthomeworkping8
 
DigSILENT PF - 03 loadflow theory
DigSILENT PF - 03 loadflow theoryDigSILENT PF - 03 loadflow theory
DigSILENT PF - 03 loadflow theoryHimmelstern
 
DigSILENT PF - 04 (es) loadflow theory
DigSILENT PF - 04 (es) loadflow theoryDigSILENT PF - 04 (es) loadflow theory
DigSILENT PF - 04 (es) loadflow theoryHimmelstern
 
Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptxPoojaAnupGarg
 
Shunt Compensation for Power Quality Improvement using a STATCOM Controller
Shunt Compensation for Power Quality Improvement using a STATCOM ControllerShunt Compensation for Power Quality Improvement using a STATCOM Controller
Shunt Compensation for Power Quality Improvement using a STATCOM ControllerIDES Editor
 
presentation-140515043704-phpapp02.pptx
presentation-140515043704-phpapp02.pptxpresentation-140515043704-phpapp02.pptx
presentation-140515043704-phpapp02.pptxAbinayaT21
 
WAMS Applications , Wide Area Monitoring Systems WAMS
WAMS Applications , Wide Area Monitoring Systems WAMSWAMS Applications , Wide Area Monitoring Systems WAMS
WAMS Applications , Wide Area Monitoring Systems WAMSPower System Operation
 
Improving the Stability of Cascaded DC Power Supply System by Adaptive Active...
Improving the Stability of Cascaded DC Power Supply System by Adaptive Active...Improving the Stability of Cascaded DC Power Supply System by Adaptive Active...
Improving the Stability of Cascaded DC Power Supply System by Adaptive Active...IJMER
 
IRJET- Mitigation of Current and Voltage Harmonics using MAF based UPQC
IRJET- Mitigation of Current and Voltage Harmonics using MAF based UPQCIRJET- Mitigation of Current and Voltage Harmonics using MAF based UPQC
IRJET- Mitigation of Current and Voltage Harmonics using MAF based UPQCIRJET Journal
 
Real and Reactive Power Compensation by using Diode Clamped Multilevel Invert...
Real and Reactive Power Compensation by using Diode Clamped Multilevel Invert...Real and Reactive Power Compensation by using Diode Clamped Multilevel Invert...
Real and Reactive Power Compensation by using Diode Clamped Multilevel Invert...IRJET Journal
 

Similar to Configuration and working point and state estimation (20)

Power Flow & Voltage Stability Analysis using MATLAB
Power Flow & Voltage Stability Analysis using MATLAB Power Flow & Voltage Stability Analysis using MATLAB
Power Flow & Voltage Stability Analysis using MATLAB
 
Power Flow Control using Quadrature Boosters
Power Flow Control using Quadrature BoostersPower Flow Control using Quadrature Boosters
Power Flow Control using Quadrature Boosters
 
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...
IMPROVEMENT OF POWER QUALITY BY USING MULTICONVERTER UNIFIED POWER QUALITY CO...
 
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
Design and Simulation of a Three Phase Power Converter Connected To a Distrib...
 
Admittance model and Power flow study.pptx
Admittance model and Power flow study.pptxAdmittance model and Power flow study.pptx
Admittance model and Power flow study.pptx
 
RAJARAM PPT
RAJARAM PPTRAJARAM PPT
RAJARAM PPT
 
HVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission LinesHVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
HVDC and FACTS for Improved Power Delivery Through Long Transmission Lines
 
Modeling of BESS for Blackstart System Restoration Studies
Modeling of BESS for Blackstart System Restoration StudiesModeling of BESS for Blackstart System Restoration Studies
Modeling of BESS for Blackstart System Restoration Studies
 
Enhancement of Reactive Power Compensation in PV Grid System To Increase The ...
Enhancement of Reactive Power Compensation in PV Grid System To Increase The ...Enhancement of Reactive Power Compensation in PV Grid System To Increase The ...
Enhancement of Reactive Power Compensation in PV Grid System To Increase The ...
 
212741860 assignment
212741860 assignment212741860 assignment
212741860 assignment
 
DigSILENT PF - 03 loadflow theory
DigSILENT PF - 03 loadflow theoryDigSILENT PF - 03 loadflow theory
DigSILENT PF - 03 loadflow theory
 
DigSILENT PF - 04 (es) loadflow theory
DigSILENT PF - 04 (es) loadflow theoryDigSILENT PF - 04 (es) loadflow theory
DigSILENT PF - 04 (es) loadflow theory
 
Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptx
 
Shunt Compensation for Power Quality Improvement using a STATCOM Controller
Shunt Compensation for Power Quality Improvement using a STATCOM ControllerShunt Compensation for Power Quality Improvement using a STATCOM Controller
Shunt Compensation for Power Quality Improvement using a STATCOM Controller
 
D011122934
D011122934D011122934
D011122934
 
presentation-140515043704-phpapp02.pptx
presentation-140515043704-phpapp02.pptxpresentation-140515043704-phpapp02.pptx
presentation-140515043704-phpapp02.pptx
 
WAMS Applications , Wide Area Monitoring Systems WAMS
WAMS Applications , Wide Area Monitoring Systems WAMSWAMS Applications , Wide Area Monitoring Systems WAMS
WAMS Applications , Wide Area Monitoring Systems WAMS
 
Improving the Stability of Cascaded DC Power Supply System by Adaptive Active...
Improving the Stability of Cascaded DC Power Supply System by Adaptive Active...Improving the Stability of Cascaded DC Power Supply System by Adaptive Active...
Improving the Stability of Cascaded DC Power Supply System by Adaptive Active...
 
IRJET- Mitigation of Current and Voltage Harmonics using MAF based UPQC
IRJET- Mitigation of Current and Voltage Harmonics using MAF based UPQCIRJET- Mitigation of Current and Voltage Harmonics using MAF based UPQC
IRJET- Mitigation of Current and Voltage Harmonics using MAF based UPQC
 
Real and Reactive Power Compensation by using Diode Clamped Multilevel Invert...
Real and Reactive Power Compensation by using Diode Clamped Multilevel Invert...Real and Reactive Power Compensation by using Diode Clamped Multilevel Invert...
Real and Reactive Power Compensation by using Diode Clamped Multilevel Invert...
 

Recently uploaded

Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxNadaHaitham1
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 

Recently uploaded (20)

Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 

Configuration and working point and state estimation

  • 1. CONFIGURATION AND WORKING POINT AND STATE ESTIMATION BY OBALEYE DANIEL OLUWATIMILEHIN 13400007007 28-10-2014
  • 2. PRESENTATION OUTLINE • Introduction. • Generic system • Network Presentation • Choice of the working point-constraints • Capability limits of a generating unit • Schematic diagram for the choice of the working point. • Characteristic generic hydroelectric unit for operation • Choice of the working point, through active and reactive dispatching • Previsional scheduling • Real-time scheduling • State estimation • Conclusion • References
  • 3. INTRODUCTION The definition of the generic steady-state working point primarily requires: • the system configuration and parameters are constant; • load demands are constant; • the three-phase electrical part is physically symmetrical with linear behavior. If one would account for what actually happens in distribution and utilization systems, • an enormous amount of data, difficult (or practically impossible) to be collected and subjected to significant uncertainties, would have to be known; • the overall system model would be excessively overburdened possibly in an unjustifiable way, because many details may actually have effects that are predominantly local; • the previously mentioned hypotheses could appear unrealistic.
  • 4. INTRODUCTION CONTD. However, such inconveniences are of minor importance in the overall behavior of the system; so it appears reasonable (and convenient) that distribution and utilization systems be considered only for behavior as “seen” from the transmission network, by treating them as equivalent circuits (more or less approximately) consisting of: • “equivalent loads,” directly fed by the transmission network through nodes (called “load nodes”) to which distribution networks are connected; • connections among these nodes, to account for interactions (e.g., at the subtransmission level) between distribution networks.
  • 6. GENERIC SYSTEM contd. Figure 2.1 represents a generic system; which indicates the block named “network” defined within types of “terminal” nodes, which can be classified as follows: • generation nodes, which correspond to the synchronous generator terminals (i.e., at the primary side terminals of step-up transformers). • reactive compensation nodes, which correspond in an analogous way to synchronous and static compensator terminals. • load nodes, i.e., nodes supplying the equivalent loads. • possible boundary nodes, for connection with external systems.
  • 7. NETWORK REPRESENTATION In the generic steady-state, phase voltages and currents are, at any given network point, sinusoidal, of positive sequence, and at a “network” frequency equal to the electrical speed of the synchronous machines. Also, at any given point, active and reactive powers are constant. Specifically, by applying the Park’s transformation with a “synchronous” reference (i.e., rotating at the same electrical speed as the synchronous machines), the following holds: • each set of phase voltages or currents transforms into a constant vector; • the characteristics of the (passive) elements of the network and the relationships between the mentioned vectors are defined by the corresponding positive sequence equivalent circuits, both passive and linear, with impedances (or admittances) evaluated at the network frequency, and “phase-shifters” in the case of transformers with complex ratio.
  • 8. NETWORK REPRESENTATION Therefore, the whole network is represented by a passive and linear circuit, with “nodes” connected through “branches”. More precisely, apart from the “reference” node for voltage vectors, the following node types can be identified; • terminal nodes (see Section 2.1.1), through which an outside “injection” of current or power is generally performed. • internal nodes, which refer only to network elements and do not allow any outside injection. A generic branch may be: • a series branch, if it connects a pair of the above-mentioned nodes (terminal and/or internal); • a shunt branch, if it connects one of the above-mentioned nodes with the voltage reference node.
  • 9. CHOICE OF THE WORKING POINT-Constraints At the scheduling stage, every future working point should be chosen by considering not only the network equations, but also: • conditions at the terminal nodes, which are defined by operating characteristics and admissibility limits of the external equipment connected to the network itself (e.g., generators, equivalent loads, etc.). • operating requirements (quality, economy, security). • admissibility limits for each network equipment. To meet quality requirements in this connection, the network frequency should be kept at the nominal, e.g., ω = ωnom, whereas node voltages (particularly terminal node voltages) must have magnitudes not far from the nominal values, according to “inequality” constraints; v ∈ [vmin, vmax] Example; vmin = 0.90–0.95 vnom and vmax = 1.05–1.10 vnom.
  • 10. • Moreover, at the terminal nodes, further constraints on injected powers must be evaluated, concerning the characteristics of the equipment external to the network. • With load nodes, the active power Pc and the reactive power Qc absorbed by a generic “equivalent load” may be assumed as input data to the problem, so that “equality” constraints: P = −Pc, Q = −Qc The negative sign is the result of assuming P and Q as the generic injected powers entering into the network. • With generation nodes, the capability limits of each generating unit should be evaluated, with inequality constraints (see Fig. 2.9): P ∈ [Pmin, Pmax] Q ∈ [Qmin,Qmax]
  • 11. CAPABILITY LIMITS OF A GENERATING UNIT.
  • 12. SCHEMATIC DIAGRAM FOR THE CHOICE OF THE WORKING POINT.
  • 13. CHARACTERISTIC GENERIC HYDROELECTRIC UNIT FOR OPERATION • For a generic hydroelectric unit, the used water flow q (disregarding losses) depends on the active power P supplied to the grid, according to a characteristic shown in Figure 2.14a. Such a characteristic may vary with the operating conditions of the plant (e.g., water level in the reservoir) and its efficiency status.
  • 14. CHOICE OF THE WORKING POINT, THROUGH ACTIVE AND REACTIVE DISPATCHING.
  • 15. ACTIVE AND REACTIVE DISPATCHING • Active Dispatching is the determination of the active power share at different generation nodes and, possibly, boundary nodes, which minimizes the overall generation cost, accounting for constraints on generated active powers and currents (with adequate margins, for security requirements). Active dispatching also can take advantage of adjustable parameters, if the system is equipped with “quadrature”-regulating transformers to modify the different branch currents in the network. To obtain a satisfactory solution, the system configuration, and more specifically the set of operating generators, may require correction to meet the requirements of spinning reserve.
  • 16. ACTIVE AND REACTIVE DISPATCHING CONTD. • Reactive Dispatching implies the choice of voltages (except at load nodes) by considering constraints on all voltages (at terminal and internal nodes) and generated reactive powers (at generation and reactive compensation nodes), and providing sufficient reactive power margins. In reactive dispatching, the role of adjustable parameters—corresponding to tap-changing transformers, adjustable condensers and reactors, and “in-phase” regulating transformers—is particularly important. To obtain a satisfactory solution, the system configuration and, more specifically, the whole set of operating compensators (and/or generators themselves) may need to be corrected so that at the corresponding nodes the required reactive power margins can be achieved.
  • 17. CHOICE OF THE HYDROELECTRIC GENERATION SCHEDULE. • The hydroelectric generation schedule has been assumed to be preassigned up to now. Actually it must be properly coordinated with the thermal generation schedule, so that the most economical overall solution may be obtained. Such coordination must be performed “over time,” based on: • forecasting hydraulic inflows, and spillages for uses different from generation; • scheduling water storages in reservoirs and basins.
  • 18. PREVISIONAL SCHEDULING Data for the previsional scheduling basically concern: • system components; • load demands; • different inflows available for generation. Data about system components concern not only already existing equipment, but also those on the way into service. Thus problems relevant for the operational scheduling also can overlap—particularly in the long term, e.g., from 6 months to several years—with those concerning the system development planning.
  • 19. PREVISIONAL SCHEDULING contd. Load demands are defined, in detail, by the variations with time (“load diagram”), as active and reactive powers absorbed at each load node. However, because of uncertainties in forecasting, it may be preferable to accept simpler more easily predictable specifications, by grouping loads at a single or a few “equivalent” nodes and/or assuming step-varying load diagrams defined by mean values within each time interval, etc., according to the following (risks resulting from forecasting errors should be accounted for).
  • 20. PREVISIONAL SCHEDULING contd. • The different inflows available for generation are typically constituted by water inflows (having subtracted possible spillages) in the hydroplants. Similarly, we may consider natural inflows of fuel or of motive fluid to possible geothermal power plants, and so on. Hydraulic inflows are basically the natural ones, caused by rain and snow and ice melting, and then depending on meteorological conditions and water travel times. Moreover, in the case of snow and ice melting, the inflows depend on the state of snow fields and glaciers, and thus on the meteorological conditions of the preceding winter. Further inflows may be added to natural ones, such as those due to hydraulic coupling, i.e., caused by the outflow from hydroplants located upstream and belonging to the same valley, and those due to pumping.
  • 21. TYPES OF PREVISIONAL SCHEDULING • long-term scheduling: T = 1 year; • medium-term scheduling: T = 1 week; • short-term scheduling: T = 1 day, (a) Long-Term Scheduling • With the long-term, the choice T = 1 year appears particularly reasonable, because it corresponds to the longest time interval by which load demands and hydraulic inflows vary more or less cyclically.
  • 22. TYPES OF PREVISIONAL SCHEDULING CONTD. (b) Medium-Term Scheduling The fundamental problems to be solved in medium-term scheduling concern configuration and water storages; precisely, the typical goals are: • determination of water storages at the end of subsequent days (for any value of the storage at the beginning of the week), for each hydroelectric plant; • determination of the operating schedule of units (unit commitment), specifically thermal units. The choice of a total interval duration T = 1 week, as assumed in the following, may be efficient and meaningful, as: • it allows a good link with the long-term scheduling; • the operating schedule of thermal units (with possible startups and shutdowns) must be chosen along a time interval including at least 1 week because of the alternating working days and holidays, with significantly different load demands; • considering a period of 1 week, it is possible to use data reliable enough, with respect to the described goals.
  • 23. TYPES OF PREVISIONAL SCHEDULING CONTD. • (c) Short-Term Scheduling • The fundamental aim of short-term scheduling is to accurately define the hydroelectrical and thermal generation schedules and, more generally, the working points of the system with reference, for instance, to the next day. The choice T = 1 day allows a precise connection with medium-term scheduling, at least for water storages in hydroelectric plants; whereas errors in forecasting load behavior, etc. may be considered acceptable, without adopting a shorter duration, because their effects can be compensated by real-time scheduling.
  • 24. REAL-TIME SCHEDULING The goals to be achieved by means of Real-time Scheduling are: • to check the actual working point with relation to quality, security, and economy requirements, based on measurements performed on the system during real operation; • to determine necessary corrective actions (on control system set-points, parameters, and system configuration itself), to obtain the most satisfying working point. • Real-time scheduling assumes that the operating state is a steady-state that is kept unchanged for a sufficiently long time interval, considering the unavoidable delay between the measurement achievement and the corrective actions. This delay may be some minutes, because of state estimation and dispatching (with security checks, etc.), teletransmission of corrective signals, and their subsequent actuation.
  • 25. STATE ESTIMATION • The “state estimation” may be performed according to Figure 2.44. Analogtype measurements to be converted into digital may concern active and reactive generated powers, active exchanged powers, voltage magnitudes, active and reactive power flows and, rarely, active and reactive powers absorbed by loads. Digital measurements typically concern the status (open or closed) of circuit breakers and disconnectors, and the values of adjustable parameters (discontinuous ones, such as transformer tap-changer position).
  • 27. CONCLUSION • In order to get the needed and adequate power output from hydropower generation the Configuration and Working point and State Estimation must be considered.
  • 28. REFERENCE • ELECTRIC POWER SYSTEMS BY Fabio Saccomanno