SlideShare a Scribd company logo
Introduction to Power System Planning
EEE 6561 taziz.eee@aust.edu
POWER SYSTEM PLANNING
Contents
 Introduction to Power System Planning
 Power System Elements and Structures
 Power System Studies- A Time-horizon Perspective
 Planning Issues
2
3
Failing to plan is planning to fail.
Introduction
How to Get Control of Your Time and Your Life (1973)
Alan Lakein
Introduction
4
 The electric power industry has evolved over many decades, from a low power
generator, serving a limited area, to highly interconnected networks, serving a
large number of countries, or even continents. Nowadays, an electric power system
is the largest man-made system, comprising of huge number of components.
 Running this very large system is a real difficult task. It has caused numerous
problems to be solved by both the educational and the industrial bodies. Lessons
have to be learnt from the past. At the same time, the current situation should be
run in an efficient manner with proper insights to the future.
 The word operation is the normal electric power term used for running the
current situation. Referring to the future, the power system experts use the term
planning to denote the actions required for the future. The past experiences are
always used for efficient operation and planning of the system.
Power System Elements & Structure
5
 A typical power system is comprised of enormous number of elements. The
elements may vary from a small lamp switch to a giant generator. However, the
main elements of interest are
• Generation facilities
• Transmission facilities
– Substations
– Network (lines, cables)
• Loads
In power system planning, the details of each
element design are not of main interest. For
instance, for a generation facility, the type
(steam turbine, gas turbine, etc.), the capacity
and its location are only determined.
Power System Elements & Structure
6
Fig. : One line diagram of a typical power system
Power System Studies- A Time Horizon
7
First, suppose it is foreseen that the
predicted load in 10 years from now,
may be served provided that a new
power plant is built. The expert has to
decide on its required capacity, type
and where the plant has to be
connected to the network. Once
decided properly, its construction has
to be started ahead of time, so that
the plant is available in 10 years time.
This is a typical long-term study of
power systems.
Two typical studies that power system experts perform in real life -
Second, suppose we are going to build a
transmission line, passing through a mountainous
area. Once built, the line may be subject to
severe lightning. Lightning is such a very fast
phenomena that it affects the system within
nanoseconds. The designer should think of
appropriate provisions on the line, by proper
modeling the system in these very fast situations
and performing enough studies, to make sure
that the line does not fail, if such lightning
happens in practice. This is a typical very short-
term study of power systems.
Power System Studies- A Time Horizon
8
• Hours to 1 week -
example - unit commitment
• Several minutes to 1 h-
example - economic
dispatch, Optimal Power
Flow (OPF)
• Minutes –
Example - Automatic
Generation Control (AGC).
Fig: A time-horizon perspective of power system studies
Power System Studies- A Time Horizon
9
To discuss, briefly, the points mentioned
above, suppose from ten power plants of
a system, in the coming week, three are
not available due to scheduled
maintenances. The decision maker should
decide on using the available plants for
serving the predicted load for each hour
of the coming week.
Moreover, he or she should decide on the
generation level of each plant, as the
generation capacities of all plants may
be noticeably higher than the predicted
load. This type of study is commonly
referred to as unit commitment.
His or her decision may be based on
some technical and/or economical
considerations.
Power System Studies- A Time Horizon
10
• Commit unit 1 (generation level: 100 MW), unit 3 (generation level: 150 MW) and unit 6 (generation
level: 125 MW), to serve the predicted load of 375 MW at hour 27 of the week (1 week = 168 h).
• Commit unit 1 (generation level: 75 MW) and unit 3 (generation level: 120 MW), to serve the
predicted load of 195 MW at hour 35 of the week. A complete list for all hours of the week should be
generated. As mentioned earlier, this is known as unit commitment.
Once we come to the exact hour, the actual load may not be equal to the predicted load. Suppose, for
instance, that the actual load at hour 27 to be 390 MW, instead of 375 MW. A further study has to be
performed in that hour to allocate the actual load of 390 MW among the available plants at that hour
(units 1, 3 and 6). This type of study may be based on some technical and/or economical considerations
and is commonly referred to as economic dispatch or Optimal Power Flow (OPF).
Coming to the faster time periods, the next step is to automatically control the generation of the plants
(for instance units 1, 3 and 6) via telemetry signals to required levels, to satisfy the load of 390 MW at
hour 27. This task is normally referred to as Automatic Generation Control (AGC) and should be
performed, periodically (say in minutes); as otherwise, the system frequency may undesirably change.
Further going towards the faster time periods, we come to power system dynamics studies, in
milliseconds to seconds. In this time period, the effects of some components such as the power plants
excitation systems and governors may be significant. Two typical examples are stability studies and
Sub-Synchronous Resonance (SSR) phenomenon. The last stage of study is called power system
transients studies, involving studies on lightning, switching transients and similar. The time period of
interest is from milliseconds to nanoseconds or even picoseconds.
Power System Planning Issues
11
Power system planning is a process in which the aim is to decide on new as
well as upgrading existing system elements, to adequately satisfy the loads
for a foreseen future.
The elements may be
• Generation facilities
• Substations
• Transmission lines and/or cables
• Capacitors/Reactors
• Etc. The decisions should be
• Where to allocate the element (for instance,
the sending and receiving end of a line),
• When to install the element (for instance,
2019,2020),
• What to select, in terms of the element
specifications (for instance, number of bundles
and conductor type).
Power System Planning Issues
12
There is no golden rule in specifying short-term
or long-term planning issues.
Normally, ‘less than 1 year’ falls into the
operational planning, where the aim is to
manage and operate available resources in an
efficient manner.
More than that falls into the planning stages. If
installing new equipment and predicting system
behavior are possible in a shorter time (for
instance, for distribution systems, 1–3 years), the
term of short-term planning may be used.
More than that (3–10 years and even higher) is
called long-term planning (typically
transmission planning) in which predicting the
system behavior is possible for these longer
periods.
Short-term planning
for the peak loading condition of the coming year, a
power system utility expert notices that from the two
lines, feeding a substation, one would be overloaded
by 10% of its rating, while, the other would be
loaded by 60% of its rating. After careful studies, he
or she finds out that if a control device is installed on
one line, the load distribution may be balanced on
both lines. Once decided, the installation process of
this device can be performed in such a way that no
problem arises for the coming year.
Long-term Versus Short-term Planning
Long term planning
Suppose that the load forecasting for the coming
years shows that with all already available and
planned generations, there would be a shortfall of
generation in 9 years from now, onward. After a
careful study, the planner decides on adding a new
2 x 500 MW steam power plant at a specific bus in
that year. Its construction should start well in advance
so that it would be available at the required time.
Power System Planning Issues
13
Example of Short-term planning
The equation of power flow in transmission line
is shown as
Where, VS and VR are sending and receiving
end voltages, X is the impedance and δ is the
power angle.
Thyristor Controlled Series Capacitor
(TCSC) is a FACTS device connected in
series on the transmission lines to control
the dynamic power flow.
Power System Planning Issues
14
Example of Short-term planning
Power Grid Corporation of India Ltd (PGCIL) has purchased
two Thyristor Controlled Series Capacitors (TCSC) from ABB.
The banks were installed on the Rourkela-Raipur double
circuit 400 kV power transmission interconnector between the
Eastern and Western regions of the grid to enable export of
surplus energy from the Eastern to the Western regions of
India.
Power System Planning Issues
15
Load Forecasting
The first crucial step for any planning study is to predict the
consumption for the study period (say 2019–2024), as all
subsequent studies will be based on that. This is referred to as load
forecasting. The same term is used for operational purposes, too.
However, it is understood that a short-term load forecasting, used
for operational studies, is significantly different from the long-term
one used in planning studies.
In a short-term load forecasting, for predicting the load for
instance, of the next week, we come across predicting the load for
each hour of the coming week. It is obvious that the determining
factors may be weather conditions, special TV programs and
similar.
In a long-term load forecasting which is of the main interest of this
course, we normally wish to predict the peak loading conditions of
the coming years. Obviously, the determining factors are different
here. Population rate increase, GDP (Gross Domestic Product) and
similar terms have dominant effects.
Load Forecasting
GEP
SEP
NEP
RPP
Power System Planning Issues
16
Generation Expansion Planning (GEP)
After predicting the load, the next step is to determine the
generation requirements to satisfy the load. An obvious simple
solution is to assume a generation increase equal to load
increase. If, for instance, in year 2020, the peak load would be
40,000 MW and at that time, the available generation is 35,000
MW, an extra
generation of 5,000 MW would be required. Unfortunately, the
solution is not so simple at all. Some obvious reasons are
• What types of power plants do we have to install (thermal, gas
turbine, nuclear, etc.)?
• Where do we have to install the power plants (distributed
among 5 specific buses, 10 specific buses, etc.)?
• What capacities do we have to install (5 x 1000 MW, or 2 x 1000
MW and 6 x 500 MW, or …)?
• As there may be an outage of a power plant (either existing or
new), should we install extra generations to account for these
situations? If yes, what, where and how?
Load Forecasting
GEP
SEP
NEP
RPP
Power System Planning Issues
17
Substation Expansion Planning (SEP)
Once the load is predicted and the generation requirements are
known, the next step is to determine the substation requirements,
both, in terms of
• Expanding the existing ones,
• Installing some new ones.
This is referred to as Substation Expansion Planning (SEP). SEP is a
difficult task as many factors are involved such as
•constraints due to the upward grid, feeding the substations,
•constraints due to the downward grid, through which the substation
supplies the loads,
•constraints due to the factors to be observed for the substation
itself.
Load Forecasting
GEP
SEP
NEP
RPP
Power System Planning Issues
18
Network Expansion Planning (NEP)
Through NEP, specifications of transmission lines, cables, etc. are
determined. In fact, the network is a media for transmitting the
power, efficiently and in a reliable manner from generation
resources to the load centers. As inputs to the NEP problem, GEP
and SEP results are assumed to be known.
Reactive Power Planning (RPP)
In running NEP, the voltages are assumed to be flat (i.e. 1 p.u.) and
it is normally based on using Direct Current Load Flow (DCLF). Upon
running GEP, SEP and NEP, the network topology is determined.
However, it may perform unsatisfactorily. To solve such a difficulty,
static reactive power compensators, such as capacitors and reactors
may be used. Moreover, some more flexible reactive power
resources such as SVCs may also be required. The problems
include:
• Where to install these devices?
• What capacities do we have to employ?
• What types do we have to use?
Load Forecasting
GEP
SEP
NEP
RPP
Power System Planning Issues
19
Planning in Presence of Uncertainties
The electric power industry has drastically changed over the last
two decades. It has moved towards a market oriented environment
in which the electric power is transacted in the form of a
commodity. Now the generation, transmission and distribution are
unbundled and may belong to separate entities. The planner can
not, for instance, dictate where the generation resources have to be
allocated. In this way, NEP problem is confronted by an uncertain
GEP input. So, how NEP can be solved, once the input data is
uncertain?
Load Forecasting
GEP
SEP
NEP
RPP
Power System Planning Issues
20
Thank You.
Questions? Confusions!
21

More Related Content

What's hot

Grid integration issues and solutions
Grid integration issues and solutionsGrid integration issues and solutions
Grid integration issues and solutions
Swathi Venugopal
 
Loading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission LinesLoading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission Lines
Raja Adapa
 
Unit commitment in power system
Unit commitment in power systemUnit commitment in power system
Unit commitment in power system
Abrar Ahmed
 
Load Forecasting
Load ForecastingLoad Forecasting
Load Forecasting
linsstalex
 
Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)
Asha Anu Kurian
 
Interconnection issue in microgrid
Interconnection issue in microgridInterconnection issue in microgrid
Interconnection issue in microgrid
Amarjeet S Pandey
 
Computer Application in Power system: Chapter three - fault studies
Computer Application in Power system: Chapter three - fault studiesComputer Application in Power system: Chapter three - fault studies
Computer Application in Power system: Chapter three - fault studies
Adama Science and Technology University
 
Power system security
Power system security Power system security
Power system security
MANGESHKULKARNI72
 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal scheduling
ASHIRBAD BARIK
 
Design & Analysis of Grid Connected Photovoltaic System
Design & Analysis of Grid Connected Photovoltaic SystemDesign & Analysis of Grid Connected Photovoltaic System
Design & Analysis of Grid Connected Photovoltaic System
Sulaman Muhammad
 
Abt meter
Abt meterAbt meter
Abt meter
Jay Ranvir
 
Load forecasting
Load forecastingLoad forecasting
Load forecastingsushrut p
 
Statcom
StatcomStatcom
Statcom
jawaharramaya
 
Power system planing and operation (pce5312) chapter four
Power system planing and operation (pce5312) chapter fourPower system planing and operation (pce5312) chapter four
Power system planing and operation (pce5312) chapter four
Adama Science and Technology University
 
Demand side management: Demand response
Demand side management: Demand response Demand side management: Demand response
Demand side management: Demand response
Siksha 'O' Anusandhan (Deemed to be University )
 
Voltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridVoltage and Frequency Control of the Grid
Voltage and Frequency Control of the Grid
Leonardo ENERGY
 
Droop control approach for power sharing in AC microgrid
Droop control approach for power sharing in AC microgrid Droop control approach for power sharing in AC microgrid
Droop control approach for power sharing in AC microgrid
Siksha 'O' Anusandhan (Deemed to be University )
 
Computer Application in Power system chapter one - introduction
Computer Application in Power system chapter one - introductionComputer Application in Power system chapter one - introduction
Computer Application in Power system chapter one - introduction
Adama Science and Technology University
 
Forecasting & Planning
Forecasting & PlanningForecasting & Planning
Forecasting & Planning
linsstalex
 
Input output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental costInput output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental cost
Eklavya Sharma
 

What's hot (20)

Grid integration issues and solutions
Grid integration issues and solutionsGrid integration issues and solutions
Grid integration issues and solutions
 
Loading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission LinesLoading Capability Limits of Transmission Lines
Loading Capability Limits of Transmission Lines
 
Unit commitment in power system
Unit commitment in power systemUnit commitment in power system
Unit commitment in power system
 
Load Forecasting
Load ForecastingLoad Forecasting
Load Forecasting
 
Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)
 
Interconnection issue in microgrid
Interconnection issue in microgridInterconnection issue in microgrid
Interconnection issue in microgrid
 
Computer Application in Power system: Chapter three - fault studies
Computer Application in Power system: Chapter three - fault studiesComputer Application in Power system: Chapter three - fault studies
Computer Application in Power system: Chapter three - fault studies
 
Power system security
Power system security Power system security
Power system security
 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal scheduling
 
Design & Analysis of Grid Connected Photovoltaic System
Design & Analysis of Grid Connected Photovoltaic SystemDesign & Analysis of Grid Connected Photovoltaic System
Design & Analysis of Grid Connected Photovoltaic System
 
Abt meter
Abt meterAbt meter
Abt meter
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
 
Statcom
StatcomStatcom
Statcom
 
Power system planing and operation (pce5312) chapter four
Power system planing and operation (pce5312) chapter fourPower system planing and operation (pce5312) chapter four
Power system planing and operation (pce5312) chapter four
 
Demand side management: Demand response
Demand side management: Demand response Demand side management: Demand response
Demand side management: Demand response
 
Voltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridVoltage and Frequency Control of the Grid
Voltage and Frequency Control of the Grid
 
Droop control approach for power sharing in AC microgrid
Droop control approach for power sharing in AC microgrid Droop control approach for power sharing in AC microgrid
Droop control approach for power sharing in AC microgrid
 
Computer Application in Power system chapter one - introduction
Computer Application in Power system chapter one - introductionComputer Application in Power system chapter one - introduction
Computer Application in Power system chapter one - introduction
 
Forecasting & Planning
Forecasting & PlanningForecasting & Planning
Forecasting & Planning
 
Input output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental costInput output , heat rate characteristics and Incremental cost
Input output , heat rate characteristics and Incremental cost
 

Similar to Lecture 1_Introduction to power system planning.pdf

The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...
arvindsinghrathore6
 
Power System Planning
Power System PlanningPower System Planning
Power System Planning
linsstalex
 
Automatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systemsAutomatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systems
Alexander Decker
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]
Sifan Welisa
 
J010146169
J010146169J010146169
J010146169
IOSR Journals
 
Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load shedding
BIJAY NAYAK
 
Rap india working draft 1 1
Rap india   working draft 1 1Rap india   working draft 1 1
Rap india working draft 1 1
Kabeed Mansur
 
Transient Stability Assessment and Enhancement in Power System
Transient Stability Assessment and Enhancement in Power  SystemTransient Stability Assessment and Enhancement in Power  System
Transient Stability Assessment and Enhancement in Power System
IJMER
 
G011115473
G011115473G011115473
G011115473
IOSR Journals
 
Constant Frequency Operation of a Bulk Power System with Very High Levels of ...
Constant Frequency Operation of a Bulk Power System with Very High Levels of ...Constant Frequency Operation of a Bulk Power System with Very High Levels of ...
Constant Frequency Operation of a Bulk Power System with Very High Levels of ...
Power System Operation
 
Adıgüzel Hydroelectric Power Plant’s Modelling and LoadFrequency Control by F...
Adıgüzel Hydroelectric Power Plant’s Modelling and LoadFrequency Control by F...Adıgüzel Hydroelectric Power Plant’s Modelling and LoadFrequency Control by F...
Adıgüzel Hydroelectric Power Plant’s Modelling and LoadFrequency Control by F...
IJERA Editor
 
An approach for a multi-stage under-frequency based load shedding scheme for...
An approach for a multi-stage under-frequency based  load shedding scheme for...An approach for a multi-stage under-frequency based  load shedding scheme for...
An approach for a multi-stage under-frequency based load shedding scheme for...
IJECEIAES
 
Power system operation Question and answers
Power system operation Question and answersPower system operation Question and answers
Power system operation Question and answers
AdhithyaS5
 
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
IJERA Editor
 
IRJET- Optimal Shipboard Power Management by Classical and Differential Evolu...
IRJET- Optimal Shipboard Power Management by Classical and Differential Evolu...IRJET- Optimal Shipboard Power Management by Classical and Differential Evolu...
IRJET- Optimal Shipboard Power Management by Classical and Differential Evolu...
IRJET Journal
 
Elwerfelli2008
Elwerfelli2008Elwerfelli2008
Elwerfelli2008
Gene Rubira
 
EE6603 - Power System Operation & Control
EE6603 - Power System Operation & ControlEE6603 - Power System Operation & Control
EE6603 - Power System Operation & Control
Vel Tech High Tech Dr. Rangarajan Dr. Sakunthala Engg. College
 
Load Frequency Control in Three Area Power System using Fuzzy Logic Controller
Load Frequency Control in Three Area Power System using Fuzzy Logic ControllerLoad Frequency Control in Three Area Power System using Fuzzy Logic Controller
Load Frequency Control in Three Area Power System using Fuzzy Logic Controller
ijtsrd
 

Similar to Lecture 1_Introduction to power system planning.pdf (20)

The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...
 
Power System Planning
Power System PlanningPower System Planning
Power System Planning
 
Automatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systemsAutomatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systems
 
N020698101
N020698101N020698101
N020698101
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]
 
J010146169
J010146169J010146169
J010146169
 
Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load shedding
 
Rap india working draft 1 1
Rap india   working draft 1 1Rap india   working draft 1 1
Rap india working draft 1 1
 
Transient Stability Assessment and Enhancement in Power System
Transient Stability Assessment and Enhancement in Power  SystemTransient Stability Assessment and Enhancement in Power  System
Transient Stability Assessment and Enhancement in Power System
 
G011115473
G011115473G011115473
G011115473
 
Constant Frequency Operation of a Bulk Power System with Very High Levels of ...
Constant Frequency Operation of a Bulk Power System with Very High Levels of ...Constant Frequency Operation of a Bulk Power System with Very High Levels of ...
Constant Frequency Operation of a Bulk Power System with Very High Levels of ...
 
Adıgüzel Hydroelectric Power Plant’s Modelling and LoadFrequency Control by F...
Adıgüzel Hydroelectric Power Plant’s Modelling and LoadFrequency Control by F...Adıgüzel Hydroelectric Power Plant’s Modelling and LoadFrequency Control by F...
Adıgüzel Hydroelectric Power Plant’s Modelling and LoadFrequency Control by F...
 
An approach for a multi-stage under-frequency based load shedding scheme for...
An approach for a multi-stage under-frequency based  load shedding scheme for...An approach for a multi-stage under-frequency based  load shedding scheme for...
An approach for a multi-stage under-frequency based load shedding scheme for...
 
Power system operation Question and answers
Power system operation Question and answersPower system operation Question and answers
Power system operation Question and answers
 
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
 
Work Portfolio
Work PortfolioWork Portfolio
Work Portfolio
 
IRJET- Optimal Shipboard Power Management by Classical and Differential Evolu...
IRJET- Optimal Shipboard Power Management by Classical and Differential Evolu...IRJET- Optimal Shipboard Power Management by Classical and Differential Evolu...
IRJET- Optimal Shipboard Power Management by Classical and Differential Evolu...
 
Elwerfelli2008
Elwerfelli2008Elwerfelli2008
Elwerfelli2008
 
EE6603 - Power System Operation & Control
EE6603 - Power System Operation & ControlEE6603 - Power System Operation & Control
EE6603 - Power System Operation & Control
 
Load Frequency Control in Three Area Power System using Fuzzy Logic Controller
Load Frequency Control in Three Area Power System using Fuzzy Logic ControllerLoad Frequency Control in Three Area Power System using Fuzzy Logic Controller
Load Frequency Control in Three Area Power System using Fuzzy Logic Controller
 

Recently uploaded

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 

Lecture 1_Introduction to power system planning.pdf

  • 1. Introduction to Power System Planning EEE 6561 taziz.eee@aust.edu POWER SYSTEM PLANNING
  • 2. Contents  Introduction to Power System Planning  Power System Elements and Structures  Power System Studies- A Time-horizon Perspective  Planning Issues 2
  • 3. 3 Failing to plan is planning to fail. Introduction How to Get Control of Your Time and Your Life (1973) Alan Lakein
  • 4. Introduction 4  The electric power industry has evolved over many decades, from a low power generator, serving a limited area, to highly interconnected networks, serving a large number of countries, or even continents. Nowadays, an electric power system is the largest man-made system, comprising of huge number of components.  Running this very large system is a real difficult task. It has caused numerous problems to be solved by both the educational and the industrial bodies. Lessons have to be learnt from the past. At the same time, the current situation should be run in an efficient manner with proper insights to the future.  The word operation is the normal electric power term used for running the current situation. Referring to the future, the power system experts use the term planning to denote the actions required for the future. The past experiences are always used for efficient operation and planning of the system.
  • 5. Power System Elements & Structure 5  A typical power system is comprised of enormous number of elements. The elements may vary from a small lamp switch to a giant generator. However, the main elements of interest are • Generation facilities • Transmission facilities – Substations – Network (lines, cables) • Loads In power system planning, the details of each element design are not of main interest. For instance, for a generation facility, the type (steam turbine, gas turbine, etc.), the capacity and its location are only determined.
  • 6. Power System Elements & Structure 6 Fig. : One line diagram of a typical power system
  • 7. Power System Studies- A Time Horizon 7 First, suppose it is foreseen that the predicted load in 10 years from now, may be served provided that a new power plant is built. The expert has to decide on its required capacity, type and where the plant has to be connected to the network. Once decided properly, its construction has to be started ahead of time, so that the plant is available in 10 years time. This is a typical long-term study of power systems. Two typical studies that power system experts perform in real life - Second, suppose we are going to build a transmission line, passing through a mountainous area. Once built, the line may be subject to severe lightning. Lightning is such a very fast phenomena that it affects the system within nanoseconds. The designer should think of appropriate provisions on the line, by proper modeling the system in these very fast situations and performing enough studies, to make sure that the line does not fail, if such lightning happens in practice. This is a typical very short- term study of power systems.
  • 8. Power System Studies- A Time Horizon 8 • Hours to 1 week - example - unit commitment • Several minutes to 1 h- example - economic dispatch, Optimal Power Flow (OPF) • Minutes – Example - Automatic Generation Control (AGC). Fig: A time-horizon perspective of power system studies
  • 9. Power System Studies- A Time Horizon 9 To discuss, briefly, the points mentioned above, suppose from ten power plants of a system, in the coming week, three are not available due to scheduled maintenances. The decision maker should decide on using the available plants for serving the predicted load for each hour of the coming week. Moreover, he or she should decide on the generation level of each plant, as the generation capacities of all plants may be noticeably higher than the predicted load. This type of study is commonly referred to as unit commitment. His or her decision may be based on some technical and/or economical considerations.
  • 10. Power System Studies- A Time Horizon 10 • Commit unit 1 (generation level: 100 MW), unit 3 (generation level: 150 MW) and unit 6 (generation level: 125 MW), to serve the predicted load of 375 MW at hour 27 of the week (1 week = 168 h). • Commit unit 1 (generation level: 75 MW) and unit 3 (generation level: 120 MW), to serve the predicted load of 195 MW at hour 35 of the week. A complete list for all hours of the week should be generated. As mentioned earlier, this is known as unit commitment. Once we come to the exact hour, the actual load may not be equal to the predicted load. Suppose, for instance, that the actual load at hour 27 to be 390 MW, instead of 375 MW. A further study has to be performed in that hour to allocate the actual load of 390 MW among the available plants at that hour (units 1, 3 and 6). This type of study may be based on some technical and/or economical considerations and is commonly referred to as economic dispatch or Optimal Power Flow (OPF). Coming to the faster time periods, the next step is to automatically control the generation of the plants (for instance units 1, 3 and 6) via telemetry signals to required levels, to satisfy the load of 390 MW at hour 27. This task is normally referred to as Automatic Generation Control (AGC) and should be performed, periodically (say in minutes); as otherwise, the system frequency may undesirably change. Further going towards the faster time periods, we come to power system dynamics studies, in milliseconds to seconds. In this time period, the effects of some components such as the power plants excitation systems and governors may be significant. Two typical examples are stability studies and Sub-Synchronous Resonance (SSR) phenomenon. The last stage of study is called power system transients studies, involving studies on lightning, switching transients and similar. The time period of interest is from milliseconds to nanoseconds or even picoseconds.
  • 11. Power System Planning Issues 11 Power system planning is a process in which the aim is to decide on new as well as upgrading existing system elements, to adequately satisfy the loads for a foreseen future. The elements may be • Generation facilities • Substations • Transmission lines and/or cables • Capacitors/Reactors • Etc. The decisions should be • Where to allocate the element (for instance, the sending and receiving end of a line), • When to install the element (for instance, 2019,2020), • What to select, in terms of the element specifications (for instance, number of bundles and conductor type).
  • 12. Power System Planning Issues 12 There is no golden rule in specifying short-term or long-term planning issues. Normally, ‘less than 1 year’ falls into the operational planning, where the aim is to manage and operate available resources in an efficient manner. More than that falls into the planning stages. If installing new equipment and predicting system behavior are possible in a shorter time (for instance, for distribution systems, 1–3 years), the term of short-term planning may be used. More than that (3–10 years and even higher) is called long-term planning (typically transmission planning) in which predicting the system behavior is possible for these longer periods. Short-term planning for the peak loading condition of the coming year, a power system utility expert notices that from the two lines, feeding a substation, one would be overloaded by 10% of its rating, while, the other would be loaded by 60% of its rating. After careful studies, he or she finds out that if a control device is installed on one line, the load distribution may be balanced on both lines. Once decided, the installation process of this device can be performed in such a way that no problem arises for the coming year. Long-term Versus Short-term Planning Long term planning Suppose that the load forecasting for the coming years shows that with all already available and planned generations, there would be a shortfall of generation in 9 years from now, onward. After a careful study, the planner decides on adding a new 2 x 500 MW steam power plant at a specific bus in that year. Its construction should start well in advance so that it would be available at the required time.
  • 13. Power System Planning Issues 13 Example of Short-term planning The equation of power flow in transmission line is shown as Where, VS and VR are sending and receiving end voltages, X is the impedance and δ is the power angle. Thyristor Controlled Series Capacitor (TCSC) is a FACTS device connected in series on the transmission lines to control the dynamic power flow.
  • 14. Power System Planning Issues 14 Example of Short-term planning Power Grid Corporation of India Ltd (PGCIL) has purchased two Thyristor Controlled Series Capacitors (TCSC) from ABB. The banks were installed on the Rourkela-Raipur double circuit 400 kV power transmission interconnector between the Eastern and Western regions of the grid to enable export of surplus energy from the Eastern to the Western regions of India.
  • 15. Power System Planning Issues 15 Load Forecasting The first crucial step for any planning study is to predict the consumption for the study period (say 2019–2024), as all subsequent studies will be based on that. This is referred to as load forecasting. The same term is used for operational purposes, too. However, it is understood that a short-term load forecasting, used for operational studies, is significantly different from the long-term one used in planning studies. In a short-term load forecasting, for predicting the load for instance, of the next week, we come across predicting the load for each hour of the coming week. It is obvious that the determining factors may be weather conditions, special TV programs and similar. In a long-term load forecasting which is of the main interest of this course, we normally wish to predict the peak loading conditions of the coming years. Obviously, the determining factors are different here. Population rate increase, GDP (Gross Domestic Product) and similar terms have dominant effects. Load Forecasting GEP SEP NEP RPP
  • 16. Power System Planning Issues 16 Generation Expansion Planning (GEP) After predicting the load, the next step is to determine the generation requirements to satisfy the load. An obvious simple solution is to assume a generation increase equal to load increase. If, for instance, in year 2020, the peak load would be 40,000 MW and at that time, the available generation is 35,000 MW, an extra generation of 5,000 MW would be required. Unfortunately, the solution is not so simple at all. Some obvious reasons are • What types of power plants do we have to install (thermal, gas turbine, nuclear, etc.)? • Where do we have to install the power plants (distributed among 5 specific buses, 10 specific buses, etc.)? • What capacities do we have to install (5 x 1000 MW, or 2 x 1000 MW and 6 x 500 MW, or …)? • As there may be an outage of a power plant (either existing or new), should we install extra generations to account for these situations? If yes, what, where and how? Load Forecasting GEP SEP NEP RPP
  • 17. Power System Planning Issues 17 Substation Expansion Planning (SEP) Once the load is predicted and the generation requirements are known, the next step is to determine the substation requirements, both, in terms of • Expanding the existing ones, • Installing some new ones. This is referred to as Substation Expansion Planning (SEP). SEP is a difficult task as many factors are involved such as •constraints due to the upward grid, feeding the substations, •constraints due to the downward grid, through which the substation supplies the loads, •constraints due to the factors to be observed for the substation itself. Load Forecasting GEP SEP NEP RPP
  • 18. Power System Planning Issues 18 Network Expansion Planning (NEP) Through NEP, specifications of transmission lines, cables, etc. are determined. In fact, the network is a media for transmitting the power, efficiently and in a reliable manner from generation resources to the load centers. As inputs to the NEP problem, GEP and SEP results are assumed to be known. Reactive Power Planning (RPP) In running NEP, the voltages are assumed to be flat (i.e. 1 p.u.) and it is normally based on using Direct Current Load Flow (DCLF). Upon running GEP, SEP and NEP, the network topology is determined. However, it may perform unsatisfactorily. To solve such a difficulty, static reactive power compensators, such as capacitors and reactors may be used. Moreover, some more flexible reactive power resources such as SVCs may also be required. The problems include: • Where to install these devices? • What capacities do we have to employ? • What types do we have to use? Load Forecasting GEP SEP NEP RPP
  • 19. Power System Planning Issues 19 Planning in Presence of Uncertainties The electric power industry has drastically changed over the last two decades. It has moved towards a market oriented environment in which the electric power is transacted in the form of a commodity. Now the generation, transmission and distribution are unbundled and may belong to separate entities. The planner can not, for instance, dictate where the generation resources have to be allocated. In this way, NEP problem is confronted by an uncertain GEP input. So, how NEP can be solved, once the input data is uncertain? Load Forecasting GEP SEP NEP RPP