SlideShare a Scribd company logo
www.GLOBALSKILLUP.com
PMP® Certification Training!
www.GLOBALSKILLUP.com
2
CONNECT WITH US
www.GLOBALSKILLUP.com
Human Resource
Management
Chapter 9
www.GLOBALSKILLUP.com
Chapter 9
Objectives
Understand the different Human Resource
Management Processes
Their Inputs, Tools and Techniques,
Outputs
This chapter entails one to
understand the various
Human Resource
Management aspects
required to ensure the
desired Project work is
accomplished.
Driving the project towards
the desired outcome while
getting the project activities
are completed to make the
project successful!
www.GLOBALSKILLUP.com
HR Management includes the processes to
ensure the required resources are planned,
acquired, evolved and managed to deliver the
project deliverables inline with the objectives.
Ensuring the resources(project staff) are
included in the early engagement of the project
would increase their project commitment.
Project Management team is responsible for all
leadership activities such as Initiating, Planning,
Executing, Monitoring, Controlling and Closing.
Knowledge Area: Human Resource Management
www.GLOBALSKILLUP.com
There are 4 HR Management processes,
namely:
1. Plan HR Management
Identification of the HR Personnel required
to be on the project, Engaging them on the
project and finally release them once their
role has ended in project
2. Acquire Project Team
Confirmation of required resource
availability for the project to be executed
3. Develop Project Team
Ensuring the project staff are capable to
deliver the project by up-skilling the staff,
training, coaching and ensuring the
effective communication and motivation
across the project staff to achieve the
project objectives.
4. Manage Project Team
Continuous engagement of the staff to
ensure the team understands their
importance to the project, how their work
has impact on the project by providing
them continuous feedback, resolve any
conflicts and recognize/reward accordingly
to keep the upbeat in the team.
Knowledge Area: Human Resource Management
www.GLOBALSKILLUP.com
9.1 Plan Human Resource Management
Inputs
• Project Management
Plan
• Activity Resource
Requirements
• Enterprise
Environmental Factors
• Organizational Process
Assets
Tools &
Techniques
• Organization Charts
and Positions
Descriptions
• Networking
• Organization Theory
• Expert Judgment
• Meetings
Outputs
• HR
Management
Plan
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
Process of identifying and documenting the project roles, responsibilities,
required skills, reporting relationships, and creating a staffing
management plan.
Benefits include the establishment of Project roles and responsibilities,
organization charts, staffing management plan(includes the acquisition,
management, transition and release of resources), identification of
training needs, team building strategies, plan for recognition and
rewards.
Effective HR planning ensures the project critical resources are planned
well and utilized in manner which is collaborative to other projects in the
organization and minimized competing for the same resources.
www.GLOBALSKILLUP.com
Most of the organization charts are intended to provide
the complete ambiguity less understanding of the project
roles and responsibilities at various levels such as at high
level(graphical tree structure) and low level which
includes the text description along with a mix and match
of organization.
Hierarchical Type Charts
These charts typically represent information in a graphical
manner with a top down approach with positions and
departments.
OBS (Organization Breakdown Structure) defines the
Organizational units, project teams structured at very high
level.
RBS (Resource Breakdown Structure) defines the
resources in the category and resource type. Usually
RBS can be considered as a sub-component of OBS,
however, it can exist as standalone to the project as well.
RBS benefits the project management team with the aid
of connecting these resources cost to the tracking of
project costs.
Matrix Based Charts
A RAM (Responsibility Assignment Matrix) depicts
how the resources or groups are assigned to the work
packages.
A common example of RAM is RACI Chart. RACI
(Responsible, Accountable, Consult, Inform)
RACI chart is used to define clear demarcations of the
behaviors expected from resources for each individual
activity. This is especially helpful when the teams are
internally and externally split working organizations.
Text Oriented Formats. Project Management Team has to ensure the
clear and detailed descriptions of the individual roles and
responsibilities to be performed and publish them for ready
references.
Organization Charts & Position Descriptions
www.GLOBALSKILLUP.com
Networking is the way people connect with each
other and evolve relationships which play a
crucial importance in project management team
dynamics to understand the underlying political
and interpersonal factors.
Few of the most popular networking activities
include lunch meetings, coffee breaks, events,
formal and informal gatherings, meetings, social
networking connections, friend of friend, email
correspondence and so on.
In the essence of project management,
networking helps build that interpersonal
connections to influence the outcomes of the
work being accomplished as part of the project.
Henry Ford (who is he?) once implemented an
innovative design by modifying factory production and
creating an assembly line. This setup is still being
used by Ford to make it easier for company to
Produce effectively and efficiently across the Ford
Motor.
Behavioral information about the organizational
units, teams and people in the organization can
help improve the effectiveness of the HR
Management Plan.
Identification of the recurring patterns and
themes in the organization supplement readily
project management plan to develop efficiencies
by adopting patterns of response by individual
groups, teams and units.
Networking Organization Theory
www.GLOBALSKILLUP.com
Maslow’s
Hierarchy of Needs
Theory
Starts from Lower level of needs to progress gradually upwards to
Highest level of needs. Employees are at the peak of motivation at the
tip of the pyramid.
Physiological → Safety → Social → Self-Esteem → Self-Actualization
Herzberg’s
Motivation &
Hygiene
Theory
Motivation comes from: Intrinsic Conditions of the Job such as Professional & Personal Growth,
Achievement, Recognition.
Hygiene factors which are externally motivating beyond the job itself such as Compensation,
Company Policies, Supervisor Behavior & Closeness to Employee, Peer Behavior & Team
Bonding
Victor Vroom’s
Expectancy
Theory
Employees are motivated when they understand that their superior job performance will
yield to their superior organizational rewards.
McGregor’s
X & Y
Theory
X Theory suggests people are lazy, don’t want to work and needs to be micro managed
Y Theory suggests people are self motivated and need not be managed
Z Theory (derivative of Y) suggests people are at peak motivation with a lifetime career
and a happy work-life balance with overall well being of the employee
McClelland’s
Need for
Achievement
Theory
Low Need for Achievement
People pick the easy tasks to minimize the risk of failure OR
People pick the extremely difficult tasks to fail themselves but avoid embarrassment
High Need for Achievement
People pick the moderately challenging tasks to ensure they are challenged but they could
accomplish and well within their reach
Self-Actualization
Self-Esteem
Social
Safety
Physiological
OrganizationalTheoriestoMotivation
www.GLOBALSKILLUP.com
9.2 Acquire Project Team
Inputs
• Human Resources
Management Plan
• Enterprise Environmental
Factors
• Organizational Process
Assets
Tools & Techniques
• Pre-assignment
• Negotiation
• Acquisition
• Virtual Teams
• Multi Criteria Decision
Analysis
Outputs
• Project Staff Assignments
• Resource Calendars
• Project Management Plan
Updates
•Integration
•Direct and Manage Project Work
•Scope
•Time
•Cost
•Quality
•Perform Quality Assurance
•Human Resource
•Acquire Project Team
•Develop Project Team
•Manage Project Team
•Communications
•Manage Communications
•Risk
•Procurement
•Conduct Procurements
•Stakeholder
•Manage Stakeholder Engagement
Executing Process Ensuring the Project Team Members
are allocated to work on the project for
the project duration is the main
objective of the Acquire Project Team.
Key Benefits include we have a ready
team which is selected(based on skill,
cost, availability…) for the project team
to accomplish the work.
Team members Selection is at times an
organizational decision to hire from a
subcontractor pool or from a different
business unit. Hence it may not be
always in the hands of project team to
select team members.
In all cases the project management
team is responsible for acquiring the
resources and engaging them on the
project work.
Non availability of the intended
resources for the project work may
need to undergo various options, like
replacement, alternate solutions,
scheduling change and in extreme
situations project being halted or
cancelled permanently.
Project Management team is
responsible to bring out such risks and
communicate to the stakeholders
appropriately.
www.GLOBALSKILLUP.com
Pre-Assignment
In some cases, the project staff are pre-selected
for a particular purpose of the project inception.
These staff are Pre-Assigned due to their special
skills or knowledge about the project upfront.
Allocating key resources at the Project beginning
stage ensures Project moves at a good rate.
Multitasking by key resources is quite common.
Staff allocation on project is one of the critical
activity a project management team performs.
Allocation of right set of resources for the job
ensures the work is efficiently and effectively
done in quality manner.
In order to ensure the right set of resources,
project management team often negotiates with
functional managers, procurement team,
vendors, contractors, suppliers.
Allocation of scarce resources who are highly
skilled is always a negotiation between the
project manager and functional manager.
Negotiation
www.GLOBALSKILLUP.com
Acquisition
Wherever the work cannot be accomplished with
internal resources, external parties are engaged
to provide these resources for completion of
work.
Bringing variety of roles of professionals working
on the project ensures it is taken care for delivery
of final product.
We need everyone. Not just SME’s alone.
Teams often comprise of people who are not
directly working on the job location and they may
be working from elsewhere to accomplish the
project work.
Indeed the advancement in technology has
ensured the major portions of work is being
delivered through virtual remote teams or
locations.
Though Virtual Team concept provides multiple
benefits in terms of cost, acquisition of
specialized resources and access to quantity of
resources.
Downsides being cultural differences, isolated
team not understanding requirements, missing
natural cohesiveness in the team. And intensive
communications overhead.
Virtual Teams
www.GLOBALSKILLUP.com
9.3 Develop Project Team
Inputs
•HR Management Plan
•Project Staff Assignments
•Resource Calendars
Tools & Techniques
•Interpersonal Skills
•Training
•Team Building Activities
•Ground Rules
•Colocation
•Recognition And Rewards
•Personnel Assessment Tools
Outputs
•Team Performance
Assessments
•Enterprise Environmental
Factors Updates
•Integration
•Direct and Manage Project Work
•Scope
•Time
•Cost
•Quality
•Perform Quality Assurance
•Human Resource
•Acquire Project Team
•Develop Project Team
•Manage Project Team
•Communications
•Manage Communications
•Risk
•Procurement
•Conduct Procurements
•Stakeholder
•Manage Stakeholder Engagement
Executing Process Develop Project Team ensures that the performing project team is improved
in terms of their capabilities, skills, knowledge and are motivated to perform
at their peak levels.
Key Benefit of this process is it provides a motivated team staff to deliver
project objectives inline with the expectations. This process also reduces the
staff turnover rate.
Fostering team work, Rewards and Recognition, Providing challenges and
Opportunities are few of the key HR activities a project manager may need
to perform to ensure the team is performing well.
Open communication, Building trust and transparency, managing conflicts in
a constructive manner are few actions project manager can perform to
ensure the high performance of the team.
www.GLOBALSKILLUP.com
Resource Calendars indicates the availability of the resources(HR,
Material, Equipment) from when to when and whether they are
available for the project duration or activity duration, including the
availability in various geographical location of the resource.
Resource Calendars aid to achieve further reliability in the estimation
since it is based on the understanding of the resource availability,
schedule constraints, time zone, work hours, vacation, local holidays,
other commitments and so on.
Additionally, in case of contracted resources, these resource
calendars may include the special pricing for any off peak periods,
which project manager may want to exploit.
Similarly, if there are resource groups, whether the quantity and
availability of resources expected is active on those particular dates
for execution. Resource preparedness levels and so on can be
further defined in resource calendars.
Resource Calendars
www.GLOBALSKILLUP.com
Project Manager’s Interpersonal skills are very helpful to be applied across the course of the project to gain the
desired outcomes from conversations and engagements with team.
Leadership
Project Manager may adopt different leadership hats depending on the situation/need.
Authoritarian (Close Supervision)
Paternalistic (Caretaker)
Democratic (Shared Decision Making)
Laissez-Faire (Delegate & Wash Hands) – Let them do
Transactional (Rewards & Punishments)
Transformational (Transform Followers Thinking)
The most important aspect which Project Manager should ensure is to showcase the vision of the project and
inspire team to deliver / work towards it.
Influencing
Project manager is supposed to exert influence over the topic of interests and resources to achieve project
objectives. How, when, Who, Why to influence depends.
Decision Making
Project Manager has to make critical decisions at various intersections of the project and how effectively
these decisions are made and based on what assumptions or data decides on the decisions evolved.
Interpersonal Skills
www.GLOBALSKILLUP.com
Interpersonal Skills
These are the behavioral aspects of how a team member interacts with another or
in a group dynamic. Interaction is at various levels including communication,
influencing, motivating, articulation and conflict resolution.
Having team members with superior interpersonal skills often results in improved
team bonding, cohesiveness and discovery of undiscovered work tasks and
objectives of the project.
www.GLOBALSKILLUP.com
Team members supposed to perform the project activities should be capable and
skilled to ensure the proper and quality aspect of the delivery.
In most cases, any gaps in capabilities or skills, these are planned by organized
scheduled trainings. Though in some cases these gaps are identified in later stages
and may result in ad-hoc unplanned trainings.
Trainings may be formal or informal & individual or group & internal or external
event based on project need.
Training
www.GLOBALSKILLUP.com
Teams working from remote locations
often do not get a chance to interact
in person and may lead to
communication-misunderstanding-
conflict gaps.
In order to ensure the teams work as
cohesive group and effectively with
none of the mentioned symptoms,
many a team building activities could
be facilitated.
Activities may include team
discussions, meetings, informal
lunches, get-togethers, organized
events and or professionally run
offsite events.
Team Development may go through
Tuckman Ladder’s five stages in either
direction:
Team Building Activities
• Team formation by understanding individual
roles and responsibilities
1. Forming
• Team starts working on deliverables with each
other, any gaps between members arise
conflicts
2. Storming
• Members start to trust each other and adjust
behaviors to deliver the project objectives
3. Norming
• Teams start to work collaboratively and with
interdependence for smooth and effective
delivery
4. Performing
• Team starts completion of work effectively &
moves on to next projects, end of project
5. Adjourning
www.GLOBALSKILLUP.com
Ground Rules
In order to ensure all team members share
the same underlying behavior or aspects
towards project delivery, there are certain
ground rules which need to be established,
communicated and published across the
teams.
These are the anticipated behaviors and
values of team members expected during
the course of the project delivery.
Examples include the Confidentiality of the
Information Sharing, Meeting Rules, Dress
Codes, Ethical Practices…
Moving all the project responsible teams to
sit in an closer locations such that the face
to face and interactions are more frequent
than wait and watch interactions bring
additional efficiency to deliver the
objectives known as Collocation. Also
known as Tight Matrix.
Often the global distribution of teams and
spread across geographies, it may be
impractical to ensure collocation. In such a
situation based on the critical timeframe of
the project it may be easier to have them
collocated for shorter durations.
Also, this model may be best suited when
there is a specific need to be met and
requires specialists to sit together in a War
room to achieve a critical end objective.
Collocation
Hey! Stop
www.GLOBALSKILLUP.com
A war room is a meeting room for the purpose of
strategizing and deployment of action
plans/measures on the specific intervals of project
to accomplish a quick achievement/milestone.
Entire set of individuals responsible to deliver in
this achievement / milestone are available to each
other to answer questions, discuss outstanding
issues and respond with swift actions.
In addition, they may discuss the resources
needed such as man power, the budget, the
timeline and possible challenges to be faced and
what can be done about the pitfalls which may
occur.
To aid the entire process, valuable visual
information such as budget, time table and project
information may also be made available as charts
in the war room.
War Room
www.GLOBALSKILLUP.com
Recognition and Rewards
People working on the project need to be
continuously recognized and rewarded for
their best work towards accomplishment of
the Project work.
Recognition and rewards should be
planned at continuous intervals and
implemented to boost the team morale.
Recognition for their good work and
providing them new growth opportunities,
challenges are the intangible benefits
which project manager may plan well in
advance.
Rewards may be monetary and non-
monetary and this can again be planned
upfront during the planning.
These tools assist project manager to
understand the aspirations of the project
team members, their preferences and
similar aspects.
Using this information project management
team can gain most by aligning them in
line with the project objectives.
PersonnelAssessment Tools
Assess
AnalyzeAct
www.GLOBALSKILLUP.com
Implementation of various team development activities
ensure the team makes effective and efficient
progress.
At the same time it is natural to see which tools have
caused the major team performance improvements
and are assessed over a period of time.
Ensuring the team performance is at the peak levels
increase the confidence levels of delivery of the project
objectives.
High performance teams are characterized by meeting
the project objectives (scope, time, cost, quality).
Where ever the shortfalls are identified for achieving
the peak team performance levels, relevant actions
have to be defined by the project management team
and circulated to the actionable owners.
Team Performance Assessments
 Outstanding
 Exceeds
 Meets
 Improve
 Poor
www.GLOBALSKILLUP.com
9.4 Manage Project Team
Inputs
•HR Management Plan
•Project Staff Assignments
•Team Performance
Assessments
•Issue Log
•Work Performance Reports
•Organizational Process Assets
Tools & Techniques
•Observation And
Conversation
•Project Performance
Appraisals
•Conflict Management
•Interpersonal Skills
Outputs
•Change Requests
•Project Management Plan
Updates
•Project Document Updates
•Enterprise Environmental
Factors Updates
•Organizational Process Assets
Updates
•Integration
•Direct and Manage Project Work
•Scope
•Time
•Cost
•Quality
•Perform Quality Assurance
•Human Resource
•Acquire Project Team
•Develop Project Team
•Manage Project Team
•Communications
•Manage Communications
•Risk
•Procurement
•Conduct Procurements
•Stakeholder
•Manage Stakeholder Engagement
Executing Process It is the process of managing the
project team performance, providing
them required support & feedback, and
adopt suitable team changes as
required.
Key benefit of this process is that it
changes the team behavior, manages
conflict, resolve issues, and provide
performance appraisals.
As part of the process it is evident to
provide continuous feedback for better
performance of team members,
recognize team for their extraordinary
work and keep the momentum upbeat.
Formal Appraisals and Recognitions for
Challenging work performed with the
respective functional managers is also
critical to the future success and
performance of the team members.
Project managers should ensure the
performance is documented and
recorded after formal discussions with
the team members individually.
Team management involves special
skills such as Team Leadership, Team
Building, Team Motivation, Team
Communication, Team Conflict
Management and Negotiation.
www.GLOBALSKILLUP.com
Comparison of current work performance to the planned work performance gives vital
feedback to the forecasted work performance.
Based on the forecasted work performance, corrective and preventive actions for the future
course of action on the human resources could be planned for control.
Areas of work which may be compared include Schedule, Cost, Scope and Quality aspects.
Work Performance Reports
www.GLOBALSKILLUP.com
Observation and Conversation
Project Management Team has to have
continuous observation of the work in progress
and delivered by the team members.
In addition, to that having regular conversations
to discover the topics which may be harnessed
for the benefit of the project delivery.
Project Team performance appraisals boost the
team morale and increase the engagement of the
team on the project.
Performance may be appraised on various
factors and having positive and constructive
feedback increases the team members
performance significantly.
Having team members formally appraised and
providing them improvement plans ensure they
adopt those and follow the course of the project
in the desired manner and behavior.
Project PerformanceAppraisals
www.GLOBALSKILLUP.com
Conflicts arise due to many reasons.
Many or majority of the conflicts in the
Projects are due to some of the key
aspects of missing elements. Such as:
New / Missing
/ Conflicting
Scope
On the team,
major conflicts
are due to the
scope aspects
being not
represented or
guided correctly
in the first place.
Unrealistic
Schedule/
Sequencing
Many a times, the
estimates
become the
actual plan
without being
checked for the
actual reality.
Also not so
correct
sequencing of the
activities lead to
conflicts in
activities.
Project
Priorities
When projects
are not defined
as per priorities, it
become evident
that
stakeholders/proj
ect
manager/shared
resources
encounter many
ambiguities.
Unattainable
Cost / Mislead
Procurements
Cost of activities
especially
outsourced which
have not been set
right expectations
of performance
lead to unwanted
discussions and
debates for
conflicts.
Personalities
/Human
Resources
Project is a mix of
team members
effort and
collaboration with
each other with
their own
personalities
based work
accomplished.
Why does Conflicts arise?
www.GLOBALSKILLUP.com
It is natural to have conflicts
when people work with each
other, have different view
points for the benefit of
project.
How best, conflicts could be
managed and reduced
involve setting up ground
rules, effective
communication, clarity on the
project vision and best
practices adopted across
project.
Ensuring conflicts are
resolved builds trust and
engagement levels among
parties for further
collaboration + commitment.
Conflicts may be resolved
with following techniques:
Withdraw /
Avoid
• Avoiding the point of conflict ensures the conflict
resolution takes least priority and it may/not
actually resolve the conflict naturally over the
course of period. Lose-Lose Situation.
Smooth /
Accommodate
• In some cases, it may be beneficial to openly talk
about the points agreed and some points which are
not agreed. This builds transparency & gains others
trust. At the same time, the issue itself is not
addressed directly. Lose-Lose Situation.
Compromise /
Reconcile
• Adjustments to the view points ensure both the
parties needs are partially met and brings new
comfort level for the work to proceed for desired
results. However each party looses something.
Lose-Lose Situation.
Conflict Management
www.GLOBALSKILLUP.com
Force /
Direct
• Some view points are
forced upon the other party
to agree upon. “Just listen
to what I say”. This is a
win-lose situation.
Collaborate
/ Problem
Solve
• Win-Win situation. Ensure
each point of conflict is
picked up and discussed in
detail and why reasons so
that both parties
understand openly the
view points and agree to
the forward approach with
consensus.
Conflict Management
www.GLOBALSKILLUP.com
Chapter 9 - Debrief
www.GLOBALSKILLUP.com
THIS BRINGS TO “HUMAN RESOURCE MANAGEMENT”
COMPLETION.
From what we have understood so far is:
 4 Human Resource Management Knowledge Area Processes
 Identified their Inputs, Tools & Techniques, Outputs
Chapter 9
www.GLOBALSKILLUP.com
PMP Group Trainings across India
Bangalore | Hyderabad | Pune | Delhi | Chennai | Mumbai | Noida | Gurgaon
Online Trainings Too
www.GLOBALSKILLUP.com
Acknowledgements & Disclaimer
PMI, PMBOK, PMP, CAPM, PgMP, PMI-
ACP, PMI-RMP, PMI-SP are registered
marks of Project Management Institute,
Inc.
All registered trademarks, symbols, names
are marks of their respective owners and
acknowledged.

More Related Content

What's hot

project human resources management
project human resources managementproject human resources management
project human resources management
Mohamed , PMP
 
Project human resource management
Project human resource managementProject human resource management
Project human resource managementJahangeer Shams
 
Project human Resource Management by Muzaffar Ansari
Project human Resource Management by Muzaffar AnsariProject human Resource Management by Muzaffar Ansari
Project human Resource Management by Muzaffar Ansari
M Ansari
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
Muzette Charles, PMP
 
6. project human resource management
6. project human resource management6. project human resource management
6. project human resource management
Mohamed Salah Eldien Mohamed Ali
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
Muzette Charles, PMP
 
096 Project Human Resource Management
096 Project Human Resource Management096 Project Human Resource Management
096 Project Human Resource Management
Dr Fereidoun Dejahang
 
People issues in project management
People issues in project managementPeople issues in project management
People issues in project management
Aswin prakash i , Xantus Technologies
 
Leadership In Project Management
Leadership In Project ManagementLeadership In Project Management
Leadership In Project Management
guest484a666
 
Project Manager Competency Overview
Project Manager Competency OverviewProject Manager Competency Overview
Project Manager Competency Overview
Joni Brown-Irons
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
Marten Schoonman
 
How to Start a Project
How to Start a ProjectHow to Start a Project
How to Start a Project
Craig Brown
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - Fundamentals
Julen Mohanty
 
Strategies for successful engineering management
Strategies for successful engineering managementStrategies for successful engineering management
Strategies for successful engineering management
Carla Fair-Wright
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
Crysanthus Raharjo, PMP
 
project management essentials
project management essentialsproject management essentials
project management essentials
Info-Tech Research Group
 
Project team management
Project team managementProject team management
Project team management
sirjana Tiwari
 
Challenges of Project Management “Communication & Collaboration-VSR
Challenges of Project Management “Communication & Collaboration-VSRChallenges of Project Management “Communication & Collaboration-VSR
Challenges of Project Management “Communication & Collaboration-VSR
VSR *
 

What's hot (20)

project human resources management
project human resources managementproject human resources management
project human resources management
 
Project management
Project managementProject management
Project management
 
Project human resource management
Project human resource managementProject human resource management
Project human resource management
 
Project human Resource Management by Muzaffar Ansari
Project human Resource Management by Muzaffar AnsariProject human Resource Management by Muzaffar Ansari
Project human Resource Management by Muzaffar Ansari
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
 
6. project human resource management
6. project human resource management6. project human resource management
6. project human resource management
 
Chap09 project human resource management
Chap09 project human resource managementChap09 project human resource management
Chap09 project human resource management
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
096 Project Human Resource Management
096 Project Human Resource Management096 Project Human Resource Management
096 Project Human Resource Management
 
People issues in project management
People issues in project managementPeople issues in project management
People issues in project management
 
Leadership In Project Management
Leadership In Project ManagementLeadership In Project Management
Leadership In Project Management
 
Project Manager Competency Overview
Project Manager Competency OverviewProject Manager Competency Overview
Project Manager Competency Overview
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
How to Start a Project
How to Start a ProjectHow to Start a Project
How to Start a Project
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - Fundamentals
 
Strategies for successful engineering management
Strategies for successful engineering managementStrategies for successful engineering management
Strategies for successful engineering management
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
project management essentials
project management essentialsproject management essentials
project management essentials
 
Project team management
Project team managementProject team management
Project team management
 
Challenges of Project Management “Communication & Collaboration-VSR
Challenges of Project Management “Communication & Collaboration-VSRChallenges of Project Management “Communication & Collaboration-VSR
Challenges of Project Management “Communication & Collaboration-VSR
 

Viewers also liked

Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
GlobalSkillup
 
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge AreaOnline PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
GlobalSkillup
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
GlobalSkillup
 
Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...
GlobalSkillup
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
GlobalSkillup
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
GlobalSkillup
 
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamEasy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
GlobalSkillup
 
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge AreaOnline PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
GlobalSkillup
 
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
GlobalSkillup
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
GlobalSkillup
 
Online PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsOnline PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groups
GlobalSkillup
 
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
GlobalSkillup
 
PMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementPMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource management
Anand Bobade
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
tltiede
 
Project human resources manangement
Project human resources manangementProject human resources manangement
Project human resources manangementRahmat Taufiq Sigit
 
project human resource managment
project human resource managmentproject human resource managment
project human resource managmentAroosa Chodhary
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
Hisham Ali,PMP
 
1
11
Pmp6
Pmp6Pmp6
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
Jamil Faraj , PMP
 

Viewers also liked (20)

Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge AreaOnline PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
 
Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...
 
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge AreaOnline PMP Training Material for PMP Exam - Risk Management Knowledge Area
Online PMP Training Material for PMP Exam - Risk Management Knowledge Area
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
 
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamEasy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
 
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge AreaOnline PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
 
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
 
Online PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsOnline PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groups
 
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
 
PMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementPMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource management
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Project human resources manangement
Project human resources manangementProject human resources manangement
Project human resources manangement
 
project human resource managment
project human resource managmentproject human resource managment
project human resource managment
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
1
11
1
 
Pmp6
Pmp6Pmp6
Pmp6
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 

Similar to Online PMP Training Material for PMP Exam - Human Resources Management Knowledge Area

Hr interventions
Hr interventionsHr interventions
Hr interventions
Betsy Booboo
 
Project Human Resource Management
Project Human Resource ManagementProject Human Resource Management
Project Human Resource Management
Andersson Lujan Ojeda
 
Hr in projects
Hr in projectsHr in projects
Hr in projects
Betsy Booboo
 
Project Human Resource Management.pptx
Project Human Resource Management.pptxProject Human Resource Management.pptx
Project Human Resource Management.pptx
Ikram192675
 
HRM in PM (1).pptx
HRM in PM (1).pptxHRM in PM (1).pptx
HRM in PM (1).pptx
umairshams6
 
Project Human Resource Management
Project Human Resource ManagementProject Human Resource Management
Project Human Resource Management
Azeem Anwar
 
2.09 hr management 1
2.09 hr management 12.09 hr management 1
2.09 hr management 1reddvise
 
OD Framework
OD FrameworkOD Framework
OD Framework
ProofofLeadership
 
Recruitment and Selection ProjectArie McQuarley.docx
Recruitment and Selection ProjectArie McQuarley.docxRecruitment and Selection ProjectArie McQuarley.docx
Recruitment and Selection ProjectArie McQuarley.docx
audeleypearl
 
Executing and Managing a Project
Executing and Managing a ProjectExecuting and Managing a Project
Executing and Managing a Project
Nishant Munjal
 
The 5 Critical Elements to Creating a Project Management Center of Excellence
The 5 Critical Elements to Creating a Project Management Center of ExcellenceThe 5 Critical Elements to Creating a Project Management Center of Excellence
The 5 Critical Elements to Creating a Project Management Center of Excellence
Flevy.com Best Practices
 
Innovation white paper final
Innovation white paper finalInnovation white paper final
Innovation white paper finalastdny
 
Project planning , Productivity metrics,Cost estimation - COCOMO & COCOMO II,...
Project planning , Productivity metrics,Cost estimation - COCOMO & COCOMO II,...Project planning , Productivity metrics,Cost estimation - COCOMO & COCOMO II,...
Project planning , Productivity metrics,Cost estimation - COCOMO & COCOMO II,...
nimmik4u
 
Human Resource Management
Human Resource ManagementHuman Resource Management
Human Resource Management
Sanjay Rajpoot
 
InstructionsPart 6 Team Development PlanFor the project sel
InstructionsPart 6 Team Development PlanFor the project selInstructionsPart 6 Team Development PlanFor the project sel
InstructionsPart 6 Team Development PlanFor the project sel
TatianaMajor22
 
PMSE_seminar3.pptx
PMSE_seminar3.pptxPMSE_seminar3.pptx
PMSE_seminar3.pptx
MuhammedSahil26
 
INTRO.pptx
INTRO.pptxINTRO.pptx
INTRO.pptx
Sankalp Sharma
 

Similar to Online PMP Training Material for PMP Exam - Human Resources Management Knowledge Area (20)

Hr interventions
Hr interventionsHr interventions
Hr interventions
 
Project Human Resource Management
Project Human Resource ManagementProject Human Resource Management
Project Human Resource Management
 
W frec04
W frec04W frec04
W frec04
 
HR PM T@T
HR PM T@THR PM T@T
HR PM T@T
 
Hr in projects
Hr in projectsHr in projects
Hr in projects
 
Project Human Resource Management.pptx
Project Human Resource Management.pptxProject Human Resource Management.pptx
Project Human Resource Management.pptx
 
HRM in PM (1).pptx
HRM in PM (1).pptxHRM in PM (1).pptx
HRM in PM (1).pptx
 
Project Human Resource Management
Project Human Resource ManagementProject Human Resource Management
Project Human Resource Management
 
2.09 hr management 1
2.09 hr management 12.09 hr management 1
2.09 hr management 1
 
OD Framework
OD FrameworkOD Framework
OD Framework
 
Recruitment and Selection ProjectArie McQuarley.docx
Recruitment and Selection ProjectArie McQuarley.docxRecruitment and Selection ProjectArie McQuarley.docx
Recruitment and Selection ProjectArie McQuarley.docx
 
Executing and Managing a Project
Executing and Managing a ProjectExecuting and Managing a Project
Executing and Managing a Project
 
The 5 Critical Elements to Creating a Project Management Center of Excellence
The 5 Critical Elements to Creating a Project Management Center of ExcellenceThe 5 Critical Elements to Creating a Project Management Center of Excellence
The 5 Critical Elements to Creating a Project Management Center of Excellence
 
Session 14 4th edition PMP
Session  14 4th edition PMPSession  14 4th edition PMP
Session 14 4th edition PMP
 
Innovation white paper final
Innovation white paper finalInnovation white paper final
Innovation white paper final
 
Project planning , Productivity metrics,Cost estimation - COCOMO & COCOMO II,...
Project planning , Productivity metrics,Cost estimation - COCOMO & COCOMO II,...Project planning , Productivity metrics,Cost estimation - COCOMO & COCOMO II,...
Project planning , Productivity metrics,Cost estimation - COCOMO & COCOMO II,...
 
Human Resource Management
Human Resource ManagementHuman Resource Management
Human Resource Management
 
InstructionsPart 6 Team Development PlanFor the project sel
InstructionsPart 6 Team Development PlanFor the project selInstructionsPart 6 Team Development PlanFor the project sel
InstructionsPart 6 Team Development PlanFor the project sel
 
PMSE_seminar3.pptx
PMSE_seminar3.pptxPMSE_seminar3.pptx
PMSE_seminar3.pptx
 
INTRO.pptx
INTRO.pptxINTRO.pptx
INTRO.pptx
 

Recently uploaded

一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
juniourjohnstone
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
Amir H. Fassihi
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
William (Bill) H. Bender, FCSI
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
ssuserf63bd7
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
akaash13
 
TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
Tata Consultancy Services
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
CIOWomenMagazine
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 

Recently uploaded (9)

一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
 
TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 

Online PMP Training Material for PMP Exam - Human Resources Management Knowledge Area

  • 4. www.GLOBALSKILLUP.com Chapter 9 Objectives Understand the different Human Resource Management Processes Their Inputs, Tools and Techniques, Outputs This chapter entails one to understand the various Human Resource Management aspects required to ensure the desired Project work is accomplished. Driving the project towards the desired outcome while getting the project activities are completed to make the project successful!
  • 5. www.GLOBALSKILLUP.com HR Management includes the processes to ensure the required resources are planned, acquired, evolved and managed to deliver the project deliverables inline with the objectives. Ensuring the resources(project staff) are included in the early engagement of the project would increase their project commitment. Project Management team is responsible for all leadership activities such as Initiating, Planning, Executing, Monitoring, Controlling and Closing. Knowledge Area: Human Resource Management
  • 6. www.GLOBALSKILLUP.com There are 4 HR Management processes, namely: 1. Plan HR Management Identification of the HR Personnel required to be on the project, Engaging them on the project and finally release them once their role has ended in project 2. Acquire Project Team Confirmation of required resource availability for the project to be executed 3. Develop Project Team Ensuring the project staff are capable to deliver the project by up-skilling the staff, training, coaching and ensuring the effective communication and motivation across the project staff to achieve the project objectives. 4. Manage Project Team Continuous engagement of the staff to ensure the team understands their importance to the project, how their work has impact on the project by providing them continuous feedback, resolve any conflicts and recognize/reward accordingly to keep the upbeat in the team. Knowledge Area: Human Resource Management
  • 7. www.GLOBALSKILLUP.com 9.1 Plan Human Resource Management Inputs • Project Management Plan • Activity Resource Requirements • Enterprise Environmental Factors • Organizational Process Assets Tools & Techniques • Organization Charts and Positions Descriptions • Networking • Organization Theory • Expert Judgment • Meetings Outputs • HR Management Plan •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process Process of identifying and documenting the project roles, responsibilities, required skills, reporting relationships, and creating a staffing management plan. Benefits include the establishment of Project roles and responsibilities, organization charts, staffing management plan(includes the acquisition, management, transition and release of resources), identification of training needs, team building strategies, plan for recognition and rewards. Effective HR planning ensures the project critical resources are planned well and utilized in manner which is collaborative to other projects in the organization and minimized competing for the same resources.
  • 8. www.GLOBALSKILLUP.com Most of the organization charts are intended to provide the complete ambiguity less understanding of the project roles and responsibilities at various levels such as at high level(graphical tree structure) and low level which includes the text description along with a mix and match of organization. Hierarchical Type Charts These charts typically represent information in a graphical manner with a top down approach with positions and departments. OBS (Organization Breakdown Structure) defines the Organizational units, project teams structured at very high level. RBS (Resource Breakdown Structure) defines the resources in the category and resource type. Usually RBS can be considered as a sub-component of OBS, however, it can exist as standalone to the project as well. RBS benefits the project management team with the aid of connecting these resources cost to the tracking of project costs. Matrix Based Charts A RAM (Responsibility Assignment Matrix) depicts how the resources or groups are assigned to the work packages. A common example of RAM is RACI Chart. RACI (Responsible, Accountable, Consult, Inform) RACI chart is used to define clear demarcations of the behaviors expected from resources for each individual activity. This is especially helpful when the teams are internally and externally split working organizations. Text Oriented Formats. Project Management Team has to ensure the clear and detailed descriptions of the individual roles and responsibilities to be performed and publish them for ready references. Organization Charts & Position Descriptions
  • 9. www.GLOBALSKILLUP.com Networking is the way people connect with each other and evolve relationships which play a crucial importance in project management team dynamics to understand the underlying political and interpersonal factors. Few of the most popular networking activities include lunch meetings, coffee breaks, events, formal and informal gatherings, meetings, social networking connections, friend of friend, email correspondence and so on. In the essence of project management, networking helps build that interpersonal connections to influence the outcomes of the work being accomplished as part of the project. Henry Ford (who is he?) once implemented an innovative design by modifying factory production and creating an assembly line. This setup is still being used by Ford to make it easier for company to Produce effectively and efficiently across the Ford Motor. Behavioral information about the organizational units, teams and people in the organization can help improve the effectiveness of the HR Management Plan. Identification of the recurring patterns and themes in the organization supplement readily project management plan to develop efficiencies by adopting patterns of response by individual groups, teams and units. Networking Organization Theory
  • 10. www.GLOBALSKILLUP.com Maslow’s Hierarchy of Needs Theory Starts from Lower level of needs to progress gradually upwards to Highest level of needs. Employees are at the peak of motivation at the tip of the pyramid. Physiological → Safety → Social → Self-Esteem → Self-Actualization Herzberg’s Motivation & Hygiene Theory Motivation comes from: Intrinsic Conditions of the Job such as Professional & Personal Growth, Achievement, Recognition. Hygiene factors which are externally motivating beyond the job itself such as Compensation, Company Policies, Supervisor Behavior & Closeness to Employee, Peer Behavior & Team Bonding Victor Vroom’s Expectancy Theory Employees are motivated when they understand that their superior job performance will yield to their superior organizational rewards. McGregor’s X & Y Theory X Theory suggests people are lazy, don’t want to work and needs to be micro managed Y Theory suggests people are self motivated and need not be managed Z Theory (derivative of Y) suggests people are at peak motivation with a lifetime career and a happy work-life balance with overall well being of the employee McClelland’s Need for Achievement Theory Low Need for Achievement People pick the easy tasks to minimize the risk of failure OR People pick the extremely difficult tasks to fail themselves but avoid embarrassment High Need for Achievement People pick the moderately challenging tasks to ensure they are challenged but they could accomplish and well within their reach Self-Actualization Self-Esteem Social Safety Physiological OrganizationalTheoriestoMotivation
  • 11. www.GLOBALSKILLUP.com 9.2 Acquire Project Team Inputs • Human Resources Management Plan • Enterprise Environmental Factors • Organizational Process Assets Tools & Techniques • Pre-assignment • Negotiation • Acquisition • Virtual Teams • Multi Criteria Decision Analysis Outputs • Project Staff Assignments • Resource Calendars • Project Management Plan Updates •Integration •Direct and Manage Project Work •Scope •Time •Cost •Quality •Perform Quality Assurance •Human Resource •Acquire Project Team •Develop Project Team •Manage Project Team •Communications •Manage Communications •Risk •Procurement •Conduct Procurements •Stakeholder •Manage Stakeholder Engagement Executing Process Ensuring the Project Team Members are allocated to work on the project for the project duration is the main objective of the Acquire Project Team. Key Benefits include we have a ready team which is selected(based on skill, cost, availability…) for the project team to accomplish the work. Team members Selection is at times an organizational decision to hire from a subcontractor pool or from a different business unit. Hence it may not be always in the hands of project team to select team members. In all cases the project management team is responsible for acquiring the resources and engaging them on the project work. Non availability of the intended resources for the project work may need to undergo various options, like replacement, alternate solutions, scheduling change and in extreme situations project being halted or cancelled permanently. Project Management team is responsible to bring out such risks and communicate to the stakeholders appropriately.
  • 12. www.GLOBALSKILLUP.com Pre-Assignment In some cases, the project staff are pre-selected for a particular purpose of the project inception. These staff are Pre-Assigned due to their special skills or knowledge about the project upfront. Allocating key resources at the Project beginning stage ensures Project moves at a good rate. Multitasking by key resources is quite common. Staff allocation on project is one of the critical activity a project management team performs. Allocation of right set of resources for the job ensures the work is efficiently and effectively done in quality manner. In order to ensure the right set of resources, project management team often negotiates with functional managers, procurement team, vendors, contractors, suppliers. Allocation of scarce resources who are highly skilled is always a negotiation between the project manager and functional manager. Negotiation
  • 13. www.GLOBALSKILLUP.com Acquisition Wherever the work cannot be accomplished with internal resources, external parties are engaged to provide these resources for completion of work. Bringing variety of roles of professionals working on the project ensures it is taken care for delivery of final product. We need everyone. Not just SME’s alone. Teams often comprise of people who are not directly working on the job location and they may be working from elsewhere to accomplish the project work. Indeed the advancement in technology has ensured the major portions of work is being delivered through virtual remote teams or locations. Though Virtual Team concept provides multiple benefits in terms of cost, acquisition of specialized resources and access to quantity of resources. Downsides being cultural differences, isolated team not understanding requirements, missing natural cohesiveness in the team. And intensive communications overhead. Virtual Teams
  • 14. www.GLOBALSKILLUP.com 9.3 Develop Project Team Inputs •HR Management Plan •Project Staff Assignments •Resource Calendars Tools & Techniques •Interpersonal Skills •Training •Team Building Activities •Ground Rules •Colocation •Recognition And Rewards •Personnel Assessment Tools Outputs •Team Performance Assessments •Enterprise Environmental Factors Updates •Integration •Direct and Manage Project Work •Scope •Time •Cost •Quality •Perform Quality Assurance •Human Resource •Acquire Project Team •Develop Project Team •Manage Project Team •Communications •Manage Communications •Risk •Procurement •Conduct Procurements •Stakeholder •Manage Stakeholder Engagement Executing Process Develop Project Team ensures that the performing project team is improved in terms of their capabilities, skills, knowledge and are motivated to perform at their peak levels. Key Benefit of this process is it provides a motivated team staff to deliver project objectives inline with the expectations. This process also reduces the staff turnover rate. Fostering team work, Rewards and Recognition, Providing challenges and Opportunities are few of the key HR activities a project manager may need to perform to ensure the team is performing well. Open communication, Building trust and transparency, managing conflicts in a constructive manner are few actions project manager can perform to ensure the high performance of the team.
  • 15. www.GLOBALSKILLUP.com Resource Calendars indicates the availability of the resources(HR, Material, Equipment) from when to when and whether they are available for the project duration or activity duration, including the availability in various geographical location of the resource. Resource Calendars aid to achieve further reliability in the estimation since it is based on the understanding of the resource availability, schedule constraints, time zone, work hours, vacation, local holidays, other commitments and so on. Additionally, in case of contracted resources, these resource calendars may include the special pricing for any off peak periods, which project manager may want to exploit. Similarly, if there are resource groups, whether the quantity and availability of resources expected is active on those particular dates for execution. Resource preparedness levels and so on can be further defined in resource calendars. Resource Calendars
  • 16. www.GLOBALSKILLUP.com Project Manager’s Interpersonal skills are very helpful to be applied across the course of the project to gain the desired outcomes from conversations and engagements with team. Leadership Project Manager may adopt different leadership hats depending on the situation/need. Authoritarian (Close Supervision) Paternalistic (Caretaker) Democratic (Shared Decision Making) Laissez-Faire (Delegate & Wash Hands) – Let them do Transactional (Rewards & Punishments) Transformational (Transform Followers Thinking) The most important aspect which Project Manager should ensure is to showcase the vision of the project and inspire team to deliver / work towards it. Influencing Project manager is supposed to exert influence over the topic of interests and resources to achieve project objectives. How, when, Who, Why to influence depends. Decision Making Project Manager has to make critical decisions at various intersections of the project and how effectively these decisions are made and based on what assumptions or data decides on the decisions evolved. Interpersonal Skills
  • 17. www.GLOBALSKILLUP.com Interpersonal Skills These are the behavioral aspects of how a team member interacts with another or in a group dynamic. Interaction is at various levels including communication, influencing, motivating, articulation and conflict resolution. Having team members with superior interpersonal skills often results in improved team bonding, cohesiveness and discovery of undiscovered work tasks and objectives of the project.
  • 18. www.GLOBALSKILLUP.com Team members supposed to perform the project activities should be capable and skilled to ensure the proper and quality aspect of the delivery. In most cases, any gaps in capabilities or skills, these are planned by organized scheduled trainings. Though in some cases these gaps are identified in later stages and may result in ad-hoc unplanned trainings. Trainings may be formal or informal & individual or group & internal or external event based on project need. Training
  • 19. www.GLOBALSKILLUP.com Teams working from remote locations often do not get a chance to interact in person and may lead to communication-misunderstanding- conflict gaps. In order to ensure the teams work as cohesive group and effectively with none of the mentioned symptoms, many a team building activities could be facilitated. Activities may include team discussions, meetings, informal lunches, get-togethers, organized events and or professionally run offsite events. Team Development may go through Tuckman Ladder’s five stages in either direction: Team Building Activities • Team formation by understanding individual roles and responsibilities 1. Forming • Team starts working on deliverables with each other, any gaps between members arise conflicts 2. Storming • Members start to trust each other and adjust behaviors to deliver the project objectives 3. Norming • Teams start to work collaboratively and with interdependence for smooth and effective delivery 4. Performing • Team starts completion of work effectively & moves on to next projects, end of project 5. Adjourning
  • 20. www.GLOBALSKILLUP.com Ground Rules In order to ensure all team members share the same underlying behavior or aspects towards project delivery, there are certain ground rules which need to be established, communicated and published across the teams. These are the anticipated behaviors and values of team members expected during the course of the project delivery. Examples include the Confidentiality of the Information Sharing, Meeting Rules, Dress Codes, Ethical Practices… Moving all the project responsible teams to sit in an closer locations such that the face to face and interactions are more frequent than wait and watch interactions bring additional efficiency to deliver the objectives known as Collocation. Also known as Tight Matrix. Often the global distribution of teams and spread across geographies, it may be impractical to ensure collocation. In such a situation based on the critical timeframe of the project it may be easier to have them collocated for shorter durations. Also, this model may be best suited when there is a specific need to be met and requires specialists to sit together in a War room to achieve a critical end objective. Collocation Hey! Stop
  • 21. www.GLOBALSKILLUP.com A war room is a meeting room for the purpose of strategizing and deployment of action plans/measures on the specific intervals of project to accomplish a quick achievement/milestone. Entire set of individuals responsible to deliver in this achievement / milestone are available to each other to answer questions, discuss outstanding issues and respond with swift actions. In addition, they may discuss the resources needed such as man power, the budget, the timeline and possible challenges to be faced and what can be done about the pitfalls which may occur. To aid the entire process, valuable visual information such as budget, time table and project information may also be made available as charts in the war room. War Room
  • 22. www.GLOBALSKILLUP.com Recognition and Rewards People working on the project need to be continuously recognized and rewarded for their best work towards accomplishment of the Project work. Recognition and rewards should be planned at continuous intervals and implemented to boost the team morale. Recognition for their good work and providing them new growth opportunities, challenges are the intangible benefits which project manager may plan well in advance. Rewards may be monetary and non- monetary and this can again be planned upfront during the planning. These tools assist project manager to understand the aspirations of the project team members, their preferences and similar aspects. Using this information project management team can gain most by aligning them in line with the project objectives. PersonnelAssessment Tools Assess AnalyzeAct
  • 23. www.GLOBALSKILLUP.com Implementation of various team development activities ensure the team makes effective and efficient progress. At the same time it is natural to see which tools have caused the major team performance improvements and are assessed over a period of time. Ensuring the team performance is at the peak levels increase the confidence levels of delivery of the project objectives. High performance teams are characterized by meeting the project objectives (scope, time, cost, quality). Where ever the shortfalls are identified for achieving the peak team performance levels, relevant actions have to be defined by the project management team and circulated to the actionable owners. Team Performance Assessments  Outstanding  Exceeds  Meets  Improve  Poor
  • 24. www.GLOBALSKILLUP.com 9.4 Manage Project Team Inputs •HR Management Plan •Project Staff Assignments •Team Performance Assessments •Issue Log •Work Performance Reports •Organizational Process Assets Tools & Techniques •Observation And Conversation •Project Performance Appraisals •Conflict Management •Interpersonal Skills Outputs •Change Requests •Project Management Plan Updates •Project Document Updates •Enterprise Environmental Factors Updates •Organizational Process Assets Updates •Integration •Direct and Manage Project Work •Scope •Time •Cost •Quality •Perform Quality Assurance •Human Resource •Acquire Project Team •Develop Project Team •Manage Project Team •Communications •Manage Communications •Risk •Procurement •Conduct Procurements •Stakeholder •Manage Stakeholder Engagement Executing Process It is the process of managing the project team performance, providing them required support & feedback, and adopt suitable team changes as required. Key benefit of this process is that it changes the team behavior, manages conflict, resolve issues, and provide performance appraisals. As part of the process it is evident to provide continuous feedback for better performance of team members, recognize team for their extraordinary work and keep the momentum upbeat. Formal Appraisals and Recognitions for Challenging work performed with the respective functional managers is also critical to the future success and performance of the team members. Project managers should ensure the performance is documented and recorded after formal discussions with the team members individually. Team management involves special skills such as Team Leadership, Team Building, Team Motivation, Team Communication, Team Conflict Management and Negotiation.
  • 25. www.GLOBALSKILLUP.com Comparison of current work performance to the planned work performance gives vital feedback to the forecasted work performance. Based on the forecasted work performance, corrective and preventive actions for the future course of action on the human resources could be planned for control. Areas of work which may be compared include Schedule, Cost, Scope and Quality aspects. Work Performance Reports
  • 26. www.GLOBALSKILLUP.com Observation and Conversation Project Management Team has to have continuous observation of the work in progress and delivered by the team members. In addition, to that having regular conversations to discover the topics which may be harnessed for the benefit of the project delivery. Project Team performance appraisals boost the team morale and increase the engagement of the team on the project. Performance may be appraised on various factors and having positive and constructive feedback increases the team members performance significantly. Having team members formally appraised and providing them improvement plans ensure they adopt those and follow the course of the project in the desired manner and behavior. Project PerformanceAppraisals
  • 27. www.GLOBALSKILLUP.com Conflicts arise due to many reasons. Many or majority of the conflicts in the Projects are due to some of the key aspects of missing elements. Such as: New / Missing / Conflicting Scope On the team, major conflicts are due to the scope aspects being not represented or guided correctly in the first place. Unrealistic Schedule/ Sequencing Many a times, the estimates become the actual plan without being checked for the actual reality. Also not so correct sequencing of the activities lead to conflicts in activities. Project Priorities When projects are not defined as per priorities, it become evident that stakeholders/proj ect manager/shared resources encounter many ambiguities. Unattainable Cost / Mislead Procurements Cost of activities especially outsourced which have not been set right expectations of performance lead to unwanted discussions and debates for conflicts. Personalities /Human Resources Project is a mix of team members effort and collaboration with each other with their own personalities based work accomplished. Why does Conflicts arise?
  • 28. www.GLOBALSKILLUP.com It is natural to have conflicts when people work with each other, have different view points for the benefit of project. How best, conflicts could be managed and reduced involve setting up ground rules, effective communication, clarity on the project vision and best practices adopted across project. Ensuring conflicts are resolved builds trust and engagement levels among parties for further collaboration + commitment. Conflicts may be resolved with following techniques: Withdraw / Avoid • Avoiding the point of conflict ensures the conflict resolution takes least priority and it may/not actually resolve the conflict naturally over the course of period. Lose-Lose Situation. Smooth / Accommodate • In some cases, it may be beneficial to openly talk about the points agreed and some points which are not agreed. This builds transparency & gains others trust. At the same time, the issue itself is not addressed directly. Lose-Lose Situation. Compromise / Reconcile • Adjustments to the view points ensure both the parties needs are partially met and brings new comfort level for the work to proceed for desired results. However each party looses something. Lose-Lose Situation. Conflict Management
  • 29. www.GLOBALSKILLUP.com Force / Direct • Some view points are forced upon the other party to agree upon. “Just listen to what I say”. This is a win-lose situation. Collaborate / Problem Solve • Win-Win situation. Ensure each point of conflict is picked up and discussed in detail and why reasons so that both parties understand openly the view points and agree to the forward approach with consensus. Conflict Management
  • 31. www.GLOBALSKILLUP.com THIS BRINGS TO “HUMAN RESOURCE MANAGEMENT” COMPLETION. From what we have understood so far is:  4 Human Resource Management Knowledge Area Processes  Identified their Inputs, Tools & Techniques, Outputs Chapter 9
  • 32. www.GLOBALSKILLUP.com PMP Group Trainings across India Bangalore | Hyderabad | Pune | Delhi | Chennai | Mumbai | Noida | Gurgaon Online Trainings Too
  • 33. www.GLOBALSKILLUP.com Acknowledgements & Disclaimer PMI, PMBOK, PMP, CAPM, PgMP, PMI- ACP, PMI-RMP, PMI-SP are registered marks of Project Management Institute, Inc. All registered trademarks, symbols, names are marks of their respective owners and acknowledged.

Editor's Notes

  1. The phrase laissez-faire is French and literally means "let [them] do", but it broadly implies "let it be," "let them do as they will," or "leave it alone".
  2. The phrase laissez-faire is French and literally means "let [them] do", but it broadly implies "let it be," "let them do as they will," or "leave it alone".
  3. The phrase laissez-faire is French and literally means "let [them] do", but it broadly implies "let it be," "let them do as they will," or "leave it alone".
  4. The phrase laissez-faire is French and literally means "let [them] do", but it broadly implies "let it be," "let them do as they will," or "leave it alone".