SlideShare a Scribd company logo
Project Management Professional
Time Management
Vincent McKeown
PMP, MBA
Project Management Process Table
2
 5 Process Groups
 Initiation, Planning, Executing, Monitoring & Controlling,
and Closing
 10 Knowledge Areas
 Integration, Scope, Time, Cost, Quality, Human
Resources, Communication, Risk, Procurement, and
Stakeholder.
 47 Total Processes
 Processes are categorized by Process Group and
Knowledge Area.
Project Management Process Table
Integration 1 1 1 2 1
Scope 4 2
Time 6 1
Cost 3 1
Quality 1 1 1
Human
Resources
1 3 1
Communication
s
1 1
Risk 5 1
Procurement 1 1 1 1
Stakeholder 1 1 1 1
3
Time Management
Plan
Schedule
Management
Control
Schedule
Define
Activities
Sequence
Activities
Estimate
Activity
Resources
Estimate
Activity
Durations
Develop
Schedule
4
Time Management
Plan Schedule Management Process
 All knowledge areas consist of a plan on how that
knowledge area is to be developed.
 This process creates the Schedule Management Plan.
 Key inputs to this process are the Project Management
Plan, Project Charter, Enterprise Environmental Factors,
and Organizational Process Assets.
 Same inputs as in the Scope Management Plan.
 A Project Manager will use Expert Judgment, Analytical
Techniques, and Meetings to develop the Schedule
Management Plan.
Planning – Plan Schedule
Management
5
Time Management
Schedule Management Plan
 Establishes policies, procedures, and documentation for
planning, developing, managing, executing, and
controlling the project schedule.
 Provides guidance and direction on how the project schedule
will be managed throughout the project.
Planning – Plan Schedule
Management
6
Planning – Plan Schedule
Management
Time Management
Project Management Plan
Project Charter
Organizational Process
Assets
Schedule Management Plan
Expert Judgment
Meetings
Inputs Outputs
Tools
Plan Scope
Management
Process
Enterprise Environmental Factors
7
Analytical Techniques
Time Management
Plan
Schedule
Management
Control
Schedule
Define
Activities
Sequence
Activities
Estimate
Activity
Resources
Estimate
Activity
Durations
Develop
Schedule
8
Time Management
Define Activities Process
 Focus on the activities that are required to create the
deliverables for the project.
 This process creates the Milestone List and the Activity
List.
 Key inputs to this process are the Schedule Management
Plan, Scope Baseline, Enterprise Environmental Factors,
and Organizational Process Assets.
 A Project Manager will use Decomposition, Expert
Judgment, and Rolling Wave Planning to develop the
Milestone List and Activity List.
9
Planning – Define Activities
Time Management
Activity List
 Describes what needs to be done in the project.
 Activities are commonly referred to as tasks.
 Activities should be broken down to durations between 4
and 80 hours.
10
Planning – Define Activities
Time Management
Milestone List
 States the milestones of the project.
 Milestones are reference points of the project.
 Milestones are entered as 0 hours.
Planning – Define Activities
11
Planning – Define Activities
Time Management
Schedule Management
Plan
Scope Baseline
Organizational Process
Assets
Activity List
Milestone List
Expert Judgment
Decomposition
Inputs Outputs
Tools
Define
Activities
Process
Enterprise Environmental Factors
12
Rolling Wave
Time Management
Plan
Schedule
Management
Control
Schedule
Define
Activities
Sequence
Activities
Estimate
Activity
Resources
Estimate
Activity
Durations
Develop
Schedule
13
Time Management
Sequence Activities Process
 Focus on placing the activities in order.
 This process creates the Project Schedule Network
Diagrams.
 Key inputs to this process are the Schedule Management
Plan, Activity List, Milestone List, Activity Attributes,
Enterprise Environmental Factors, and Organizational
Process Assets.
 A Project Manager will use Precedence Diagramming
Method, Dependency Determination, and Leads and Lags
to develop the Project Schedule Network Diagrams.
14
Planning – Sequence Activities
Planning – Define Activities
Time Management
Schedule Management
Plan
Activity List
Organizational Process
Assets
Project Schedule Network
Diagrams
Precedence Diagramming Method
Dependency Determination
Inputs Outputs
Tools
Define
Activities
Process
Enterprise Environmental Factors
15
Leads and Lags
Milestone List
Time Management
Precedence Diagramming Method
16
Planning – Sequence Activities
A
FC
E
D
B
G
4
1
2
1
4
1
2
Design Dog
House
Purchase
Material
Dig
Foundation
Pour
Concrete
Build Dog
House
Install
Fencing
Train Dog
Time Management
Dependencies
 When sequencing, dependencies will determine the order
of activities.
 Mandatory
 Discretionary
 Internal
 External
17
Planning – Sequence Activities
Time Management
Predecessors:
 Predecessors are used to help with sequencing activities.
Determines when the following activity will occur.
 Finish to Start
 Finish to Finish
 Start to Start
 Start to Finish
18
Planning – Sequence Activities
Time Management
Predecessors
19
Planning – Sequence Activities
A
B
4
1
Design Dog
House
Purchase
Material
Start
Start Finis
h
Finis
h
Time Management
Predecessor:
Finish to Start
20
Planning – Sequence Activities
A
B
4
1
Design Dog
House
Purchase
Material
Start
Start Finis
h
Finis
h
Time Management
Predecessor:
Finish to Finish
21
Planning – Sequence Activities
A
B
4
1
Design Dog
House
Purchase
Material
Start
Start Finis
h
Finis
h
Time Management
Predecessor:
Start to Start
22
Planning – Sequence Activities
A
B
4
1
Design Dog
House
Purchase
Material
Start
Start Finis
h
Finis
h
Time Management
Predecessor:
Start to Finish
23
Planning – Sequence Activities
A
B
4
1
Design Dog
House
Purchase
Material
Start
Start Finis
h
Finis
h
Time Management
24
Planning – Sequence Activities
Leads and Lags:
 Leads can start before an activity is complete.
 Lags require a delay before an activity can start.
A
B
4
1
Mon Tue Wed Thu Fri Sat
A A A A
B
Mon Tue Wed Thu Fri Sat
A A A A
B
A
B
1
4
Time Management
Plan
Schedule
Management
Control
Schedule
Define
Activities
Sequence
Activities
Estimate
Activity
Resources
Estimate
Activity
Durations
Develop
Schedule
25
Time Management
Sequence Activities Process
 Focus on resources for the project.
 Material
 Personnel
 Equipment
 This process creates the Activity Resources Requirements and
the Resource Breakdown Structure.
 Key inputs to this process are the Schedule Management Plan,
Activity List, Resource Calendars, Risk Register, Activity Cost
Estimates, Activity Attributes, Enterprise Environmental
Factors, and Organizational Process Assets.
 A Project Manager will use Expert Judgment, Alternative
Analysis, Published Estimating Data, Bottom-Up estimating,
and Project Management Software to develop the Activity
Resource Requirements and Resource Breakdown Structure.
26
Planning – Estimating Activity
Resources
Time Management
Resource Breakdown Structure
 A display that is a breakdown by resource type across an
organization.
27
1
Project
Resources
1.1
People
1.1.1
Project
Managers
1.1.2
Engineers
1.1.3
Systems
Analyst
1.1.3.1
Audio Visual
1.1.3.2
Radio
1.1.3.3
IT
1.1.4
Production
1,2
Material
1.3
Equipment
Planning – Estimating Activity
Resources
Time Management
Activity Resource Requirements
 Identifies the resources required for the project based on
the activities.
 Resources include;
 Personnel
 Equipment
 Infrastructure
28
Planning – Estimating Activity
Resources
Time Management
Schedule Management
Plan
Activity List
Organizational Process
Assets
Activity Resource Requirements
Resource Breakdown Structure
Expert Judgment
Alternative Analysis
Inputs Outputs
Tools
Estimate
Activity
Resources
Enterprise Environmental Factors
29
Published Estimating Data
Planning – Estimating Activity
Resources
Resource Calendars
Risk Register
Activity Cost Estimates
Activity Attributes
Bottom-Up Estimating
Project Management Software
Time Management
Estimating Methods
 Analogous (Top-down)
 Bottom-up
 Parametric
 Computerized (Monte Carlo)
 PERT
30
Planning – Estimating Activity
Resources
Time Management
Estimating Methods
 Analogous
 Usually an estimate based on something similar.
 Also known as Top-Down
 Advantages
 Can be created quickly
 Disadvantages
 Lacks details
31
Planning – Estimating Activity
Resources
Time Management
Estimating Methods
 Bottom Up
 Created from activities.
 Advantages
 A lot of detail and accuracy
 Disadvantages
 Very time consuming
 Team can pad time (Parkinson’s Law)
 Parkinson’s Law – Work expands to consume the time schedule for it’s
completion.
32
Planning – Estimating Activity
Resources
Time Management
Estimating Methods
 Parametric
 Based on an existing parameter.
 Can use Industry Standards
 Advantages
 Can be done both quickly and accurate
33
Planning – Estimating Activity
Resources
Time Management
Estimating Methods
 Computerized (Monte Carlo)
 Computerized tool that simulates project outcomes.
 Can results in Time, Cost, or number of resources needed.
 Also known as Top-Down
 Advantages
 Very accurate
 Disadvantages
 Very time consuming to setup
34
Planning – Estimating Activity
Resources
Time Management
Estimating Methods
 Program Evaluation Review Technique (PERT)
 Uses pessimistic, optimistic, and most likely estimates
(O + P + (4 * M))
6
35
Planning – Estimating Activity
Resources
Time Management
Plan
Schedule
Management
Control
Schedule
Define
Activities
Sequence
Activities
Estimate
Activity
Resources
Estimate
Activity
Durations
Develop
Schedule
36
Time Management
Estimate Activities Durations Process
 Focus on estimating the hours for each activity then
summing them for a high level estimate.
 This process creates the Activity Duration Estimates.
 Key inputs to this process are the Schedule Management
Plan, Activity List, Activity Resource Requirements,
Resource Calendars, Risk Register, Resource Breakdown
Structure, Project Scope Statement, Activity Attributes,
Enterprise Environmental Factors, and Organizational
Process Assets.
 A Project Manager will use Expert Judgment, Analogous
Estimating, Parametric Estimating, Three-Point
Estimating, Group Decision Making Techniques, and
Reserve Analysis to develop the Activity Duration
Estimates.
37
Planning – Estimating Activity
Durations
Time Management
Activity Duration Estimates
 Identifies the duration of the activities with plus and minus
ranges.
 Activity “A” – 4 days +/- 2 days. Range is 2 to 6 days.
38
Planning – Estimating Activity
Durations
A
4
Design Dog
House
Time Management
Schedule Management
Plan
Activity List
Organizational Process
Assets
Activity Duration Estimate
Expert Judgment
Alternative Analysis
Inputs Outputs
Tools
Estimate
Activity
Duration
Enterprise Environmental Factors
39
Published Estimating Data
Planning – Estimating Activity
Durations
Resource Calendars
Risk Register
Project Scope Statement
Activity Attributes
Bottom-Up Estimating
Project Management Software
Activity Resource Requirements
Time Management
Plan
Schedule
Management
Control
Schedule
Define
Activities
Sequence
Activities
Estimate
Activity
Resources
Estimate
Activity
Durations
Develop
Schedule
40
Time Management
Develop Schedule
 This process reviews the resource needs, sequence activities,
and estimating activity durations to develop the schedule. This
process brings together the activity list, the work breakdown
structure, the start and finish dates, and sequence activities.
 This process creates the Schedule baseline, Project Schedule,
and Project Calendars.
 Key inputs to this process are the Schedule Management Plan,
Activity List, Network Diagrams, Activity Resource
Requirements, Resource Calendars, Risk Register, Resource
Breakdown Structure, Project Scope Statement, Activity
Attributes, Project Staff Assignments, Enterprise Environmental
Factors, and Organizational Process Assets.
 A Project Manager will use Schedule Network Analysis, Critical
Path Method, Critical Chain Method, Resource Optimization
Techniques, Modeling Techniques, Leads and Lags, Schedule
Compression, and Scheduling Tool.
41
Planning – Develop Schedule
Time Management
Schedule Baseline
 The planned timeline for the project execution.
 Baseline dates
42
Planning – Develop Schedule
Time Management
Project Schedule
 Integrated lists the activities, start and finish dates,
resources, and sequencing.
 Format can include;
 Milestone charts
 Bar charts
 Project Schedule Network Diagrams
43
Planning – Develop Schedule
Time Management
Project Calendars
 Shows scheduled resource usage and availability.
44
Planning – Develop Schedule
Time Management
Calculating the Critical Path
45
A
FC
E
D
B
G
4
1
2
1
4
1
2
Design Dog
House
Purchase
Material
Dig
Foundation
Pour
Concrete
Build Dog
House
Install
Fencing
Train Dog
1
Start
on
Day 1
Forward Pass
Planning – Develop Schedule
Time Management
Calculating the Critical Path
46
A
FC
E
D
B
G
4
1
2
1
4
1
2
Design Dog
House
Purchase
Material
Dig
Foundation
Pour
Concrete
Build Dog
House
Install
Fencing
Train Dog
1
Forward Pass
4
1+4-
1
5
5
+1
+1
Planning – Develop Schedule
Time Management
Calculating the Critical Path
47
A
FC
E
D
B
G
4
1
2
1
4
1
2
Design Dog
House
Purchase
Material
Dig
Foundation
Pour
Concrete
Build Dog
House
Install
Fencing
Train Dog
1
Forward Pass
4
5
5
5
6
5+1-1
5+2-1
+1
+1
7
Go with the
High
Number
Planning – Develop Schedule
Time Management
Calculating the Critical Path
48
Planning – Sequence Activities
A
FC
E
D
B
G
4
1
2
1
4
1
2
Design Dog
House
Purchase
Material
Dig
Foundation
Pour
Concrete
Build Dog
House
Install
Fencing
Train Dog
1
Forward Pass
4
5
5
5
6
7 7
8
8 8
11
7+1-1
8+4-1
8+1-1
12+2-1
12 13
Time Management
Calculating the Critical Path
49
A
FC
E
D
B
G
4
1
2
1
4
1
2
Design Dog
House
Purchase
Material
Dig
Foundation
Pour
Concrete
Build Dog
House
Install
Fencing
Train Dog
1
Forward Pass
4
5
5
5
6
7 7
8
8 8
11
7+1-1
8+4-1
8+1-1
12+2-1
12 13
Planning – Develop Schedule
Time Management
Calculating the Critical Path
50
A
FC
E
D
B
G
4
1
2
1
4
1
2
Design Dog
House
Purchase
Material
Dig
Foundation
Pour
Concrete
Build Dog
House
Install
Fencing
Train Dog
1
Backward Pass
4
5
5
5
6
7 7
8
8 8
11
12 13
1312
-1
-1
11
11
Planning – Develop Schedule
Time Management
Calculating the Critical Path
51
A
FC
E
D
B
G
4
1
2
1
4
1
2
Design Dog
House
Purchase
Material
Dig
Foundation
Pour
Concrete
Build Dog
House
Install
Fencing
Train Dog
1
Backward Pass
4
5
5
5
6
7 7
8
8 8
11
12 13
1312
-1
-1
11
11
11
8
7 7
6
65
6
41
Lower
Number
wins!
Lower
Number
wins!
4-4+1
6-2+1
7-1+1
11-1+1
11-4+16-1+1
Planning – Develop Schedule
Time Management
Calculating the Critical Path
52
A
FC
E
D
B
G
4
1
2
1
4
1
2
Design Dog
House
Purchase
Material
Dig
Foundation
Pour
Concrete
Build Dog
House
Install
Fencing
Train Dog
1
Calculating Slack
4
5
5
5
6
7 7
8
8 8
11
12 13
1312
11
11
11
8
7 7
6
65
6
41
6-5=1
11-8=3
Planning – Develop Schedule
Time Management
Calculating the Critical Path
53
Planning – Develop Schedule
A
FC
E
D
B
G
4
1
2
1
4
1
2
Design Dog
House
Purchase
Material
Dig
Foundation
Pour
Concrete
Build Dog
House
Install
Fencing
Train Dog
1
Critical Path
4
5
5
5
6
7 7
8
8 8
11
12 13
1312
11
11
11
8
7 7
6
65
6
41
Time Management
Plan
Schedule
Management
Control
Schedule
Define
Activities
Sequence
Activities
Estimate
Activity
Resources
Estimate
Activity
Durations
Develop
Schedule
54
Time Management
Control Schedule
 This process is for the control and management of
changes to the schedule.
 This process creates Work Performance Information,
Schedule Forecasts, and Change Requests.
 Key inputs to this process are the Project Management
Plan, Project Schedule, Work Performance Data, Project
Calendars, schedule Data, and Organizational Process
Assets.
 A Project Manager will use Performance Reviews, Project
Management Software, Resource Optimization
Techniques, Modeling Techniques, Leads and Lags,
Schedule Compression, and Scheduling Tools to perform
this process.
55
Monitoring & Controlling – Control
Schedule
Time Management
Work Performance Information
 Information that helps to determine current schedule
metrics compared to planned schedule metrics.
 This is the information that helps with determining Earned
Value
56
Monitoring & Controlling – Control
Schedule
Time Management
Schedule Forecast
 Anticipated situations and incidents that will likely occur in
the future based off of current information.
57
Monitoring & Controlling – Control
Schedule
Time Management
Change Requests
 A variance in schedule after an analysis will result in a
change request.
 Changes that have been requested, but not yet formally
approved.
58
Monitoring & Controlling – Control
Schedule

More Related Content

What's hot

PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
tkrikau
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
Ahmed Elshaboury,PMP,LEED GA
 
project time management
 project time management project time management
project time management
Hira Atiq
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
dyaksa hanindito
 
Chap06 project time management
Chap06 project time managementChap06 project time management
Chap06 project time management
DM's College, Assagao Goa
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
Hisham Ali,PMP
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
Agus Suhanto
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
rielaantonio
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material
Abdel Rahman okasha
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
Serdar Temiz
 
Project management
Project managementProject management
Project management
Ahmed Said
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
Jeanette C. Patindol
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | Edureka
Edureka!
 
105 project time management
105 project time management105 project time management
105 project time management
Dr Fereidoun Dejahang
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
Craig Brown
 
Project Time Management
Project Time Management Project Time Management
Project Time Management
Waqar Ali
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
Mohamed Loey
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Schedule
shofiulalom
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
Ahmed Elshaboury,PMP,LEED GA
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
Reetesh Gupta
 

What's hot (20)

PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
project time management
 project time management project time management
project time management
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Chap06 project time management
Chap06 project time managementChap06 project time management
Chap06 project time management
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project management
Project managementProject management
Project management
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | Edureka
 
105 project time management
105 project time management105 project time management
105 project time management
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
Project Time Management
Project Time Management Project Time Management
Project Time Management
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Schedule
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 

Similar to PMP: Module 3 - Time

Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
MohanadRabea1
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
HuyNguyen657394
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
محمد عصمت عبد الرازق
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
Ahmed Alageed
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
DavidMcLachlan1
 
PMP Training Project Time Management Part 1
PMP Training Project Time Management Part 1PMP Training Project Time Management Part 1
PMP Training Project Time Management Part 1
Skillogic Solutions
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
MuhammadAmanAzam
 
Planning process group
Planning process groupPlanning process group
Planning process group
Mudassir Iqbal
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
hatemk
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Management
chaitanyakrsk
 
1 project management framework
1  project management framework1  project management framework
1 project management framework
Bahaa Mostafa Mostafa
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
sneha saranya
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
Rasan Samarasinghe
 
A project portfolio management capability framework
A project portfolio management capability frameworkA project portfolio management capability framework
A project portfolio management capability framework
Robert Greca, PMP, SA
 
2) PMT & PIM.pptx
2) PMT & PIM.pptx2) PMT & PIM.pptx
2) PMT & PIM.pptx
MuhammadAmanAzam
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
Yousef Abugosh, PMP, MA
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
Dhamo daran
 
Managingtripleconstraint aam
Managingtripleconstraint aamManagingtripleconstraint aam
Managingtripleconstraint aam
Aldo Arecco
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
Muzette Charles, PMP
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
ahmad bassiouny
 

Similar to PMP: Module 3 - Time (20)

Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
PMP Training Project Time Management Part 1
PMP Training Project Time Management Part 1PMP Training Project Time Management Part 1
PMP Training Project Time Management Part 1
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Management
 
1 project management framework
1  project management framework1  project management framework
1 project management framework
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
A project portfolio management capability framework
A project portfolio management capability frameworkA project portfolio management capability framework
A project portfolio management capability framework
 
2) PMT & PIM.pptx
2) PMT & PIM.pptx2) PMT & PIM.pptx
2) PMT & PIM.pptx
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
Managingtripleconstraint aam
Managingtripleconstraint aamManagingtripleconstraint aam
Managingtripleconstraint aam
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 

Recently uploaded

Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
Top Forex Brokers Review
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
Norma Mushkat Gaffin
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
ssuser567e2d
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
SEOSMMEARTH
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
my Pandit
 
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
SOFTTECHHUB
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
CA Dr. Prithvi Ranjan Parhi
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
Corey Perlman, Social Media Speaker and Consultant
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
my Pandit
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
AnnySerafinaLove
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
ecamare2
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
jeffkluth1
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
Corey Perlman, Social Media Speaker and Consultant
 
Understanding User Needs and Satisfying Them
Understanding User Needs and Satisfying ThemUnderstanding User Needs and Satisfying Them
Understanding User Needs and Satisfying Them
Aggregage
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
Alexandra Fulford
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
NZSG
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Avirahi City Dholera
 

Recently uploaded (20)

Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
 
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
 
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
 
Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431Observation Lab PowerPoint Assignment for TEM 431
Observation Lab PowerPoint Assignment for TEM 431
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
 
Understanding User Needs and Satisfying Them
Understanding User Needs and Satisfying ThemUnderstanding User Needs and Satisfying Them
Understanding User Needs and Satisfying Them
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
 

PMP: Module 3 - Time

  • 1. Project Management Professional Time Management Vincent McKeown PMP, MBA
  • 2. Project Management Process Table 2  5 Process Groups  Initiation, Planning, Executing, Monitoring & Controlling, and Closing  10 Knowledge Areas  Integration, Scope, Time, Cost, Quality, Human Resources, Communication, Risk, Procurement, and Stakeholder.  47 Total Processes  Processes are categorized by Process Group and Knowledge Area.
  • 3. Project Management Process Table Integration 1 1 1 2 1 Scope 4 2 Time 6 1 Cost 3 1 Quality 1 1 1 Human Resources 1 3 1 Communication s 1 1 Risk 5 1 Procurement 1 1 1 1 Stakeholder 1 1 1 1 3
  • 5. Time Management Plan Schedule Management Process  All knowledge areas consist of a plan on how that knowledge area is to be developed.  This process creates the Schedule Management Plan.  Key inputs to this process are the Project Management Plan, Project Charter, Enterprise Environmental Factors, and Organizational Process Assets.  Same inputs as in the Scope Management Plan.  A Project Manager will use Expert Judgment, Analytical Techniques, and Meetings to develop the Schedule Management Plan. Planning – Plan Schedule Management 5
  • 6. Time Management Schedule Management Plan  Establishes policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.  Provides guidance and direction on how the project schedule will be managed throughout the project. Planning – Plan Schedule Management 6
  • 7. Planning – Plan Schedule Management Time Management Project Management Plan Project Charter Organizational Process Assets Schedule Management Plan Expert Judgment Meetings Inputs Outputs Tools Plan Scope Management Process Enterprise Environmental Factors 7 Analytical Techniques
  • 9. Time Management Define Activities Process  Focus on the activities that are required to create the deliverables for the project.  This process creates the Milestone List and the Activity List.  Key inputs to this process are the Schedule Management Plan, Scope Baseline, Enterprise Environmental Factors, and Organizational Process Assets.  A Project Manager will use Decomposition, Expert Judgment, and Rolling Wave Planning to develop the Milestone List and Activity List. 9 Planning – Define Activities
  • 10. Time Management Activity List  Describes what needs to be done in the project.  Activities are commonly referred to as tasks.  Activities should be broken down to durations between 4 and 80 hours. 10 Planning – Define Activities
  • 11. Time Management Milestone List  States the milestones of the project.  Milestones are reference points of the project.  Milestones are entered as 0 hours. Planning – Define Activities 11
  • 12. Planning – Define Activities Time Management Schedule Management Plan Scope Baseline Organizational Process Assets Activity List Milestone List Expert Judgment Decomposition Inputs Outputs Tools Define Activities Process Enterprise Environmental Factors 12 Rolling Wave
  • 14. Time Management Sequence Activities Process  Focus on placing the activities in order.  This process creates the Project Schedule Network Diagrams.  Key inputs to this process are the Schedule Management Plan, Activity List, Milestone List, Activity Attributes, Enterprise Environmental Factors, and Organizational Process Assets.  A Project Manager will use Precedence Diagramming Method, Dependency Determination, and Leads and Lags to develop the Project Schedule Network Diagrams. 14 Planning – Sequence Activities
  • 15. Planning – Define Activities Time Management Schedule Management Plan Activity List Organizational Process Assets Project Schedule Network Diagrams Precedence Diagramming Method Dependency Determination Inputs Outputs Tools Define Activities Process Enterprise Environmental Factors 15 Leads and Lags Milestone List
  • 16. Time Management Precedence Diagramming Method 16 Planning – Sequence Activities A FC E D B G 4 1 2 1 4 1 2 Design Dog House Purchase Material Dig Foundation Pour Concrete Build Dog House Install Fencing Train Dog
  • 17. Time Management Dependencies  When sequencing, dependencies will determine the order of activities.  Mandatory  Discretionary  Internal  External 17 Planning – Sequence Activities
  • 18. Time Management Predecessors:  Predecessors are used to help with sequencing activities. Determines when the following activity will occur.  Finish to Start  Finish to Finish  Start to Start  Start to Finish 18 Planning – Sequence Activities
  • 19. Time Management Predecessors 19 Planning – Sequence Activities A B 4 1 Design Dog House Purchase Material Start Start Finis h Finis h
  • 20. Time Management Predecessor: Finish to Start 20 Planning – Sequence Activities A B 4 1 Design Dog House Purchase Material Start Start Finis h Finis h
  • 21. Time Management Predecessor: Finish to Finish 21 Planning – Sequence Activities A B 4 1 Design Dog House Purchase Material Start Start Finis h Finis h
  • 22. Time Management Predecessor: Start to Start 22 Planning – Sequence Activities A B 4 1 Design Dog House Purchase Material Start Start Finis h Finis h
  • 23. Time Management Predecessor: Start to Finish 23 Planning – Sequence Activities A B 4 1 Design Dog House Purchase Material Start Start Finis h Finis h
  • 24. Time Management 24 Planning – Sequence Activities Leads and Lags:  Leads can start before an activity is complete.  Lags require a delay before an activity can start. A B 4 1 Mon Tue Wed Thu Fri Sat A A A A B Mon Tue Wed Thu Fri Sat A A A A B A B 1 4
  • 26. Time Management Sequence Activities Process  Focus on resources for the project.  Material  Personnel  Equipment  This process creates the Activity Resources Requirements and the Resource Breakdown Structure.  Key inputs to this process are the Schedule Management Plan, Activity List, Resource Calendars, Risk Register, Activity Cost Estimates, Activity Attributes, Enterprise Environmental Factors, and Organizational Process Assets.  A Project Manager will use Expert Judgment, Alternative Analysis, Published Estimating Data, Bottom-Up estimating, and Project Management Software to develop the Activity Resource Requirements and Resource Breakdown Structure. 26 Planning – Estimating Activity Resources
  • 27. Time Management Resource Breakdown Structure  A display that is a breakdown by resource type across an organization. 27 1 Project Resources 1.1 People 1.1.1 Project Managers 1.1.2 Engineers 1.1.3 Systems Analyst 1.1.3.1 Audio Visual 1.1.3.2 Radio 1.1.3.3 IT 1.1.4 Production 1,2 Material 1.3 Equipment Planning – Estimating Activity Resources
  • 28. Time Management Activity Resource Requirements  Identifies the resources required for the project based on the activities.  Resources include;  Personnel  Equipment  Infrastructure 28 Planning – Estimating Activity Resources
  • 29. Time Management Schedule Management Plan Activity List Organizational Process Assets Activity Resource Requirements Resource Breakdown Structure Expert Judgment Alternative Analysis Inputs Outputs Tools Estimate Activity Resources Enterprise Environmental Factors 29 Published Estimating Data Planning – Estimating Activity Resources Resource Calendars Risk Register Activity Cost Estimates Activity Attributes Bottom-Up Estimating Project Management Software
  • 30. Time Management Estimating Methods  Analogous (Top-down)  Bottom-up  Parametric  Computerized (Monte Carlo)  PERT 30 Planning – Estimating Activity Resources
  • 31. Time Management Estimating Methods  Analogous  Usually an estimate based on something similar.  Also known as Top-Down  Advantages  Can be created quickly  Disadvantages  Lacks details 31 Planning – Estimating Activity Resources
  • 32. Time Management Estimating Methods  Bottom Up  Created from activities.  Advantages  A lot of detail and accuracy  Disadvantages  Very time consuming  Team can pad time (Parkinson’s Law)  Parkinson’s Law – Work expands to consume the time schedule for it’s completion. 32 Planning – Estimating Activity Resources
  • 33. Time Management Estimating Methods  Parametric  Based on an existing parameter.  Can use Industry Standards  Advantages  Can be done both quickly and accurate 33 Planning – Estimating Activity Resources
  • 34. Time Management Estimating Methods  Computerized (Monte Carlo)  Computerized tool that simulates project outcomes.  Can results in Time, Cost, or number of resources needed.  Also known as Top-Down  Advantages  Very accurate  Disadvantages  Very time consuming to setup 34 Planning – Estimating Activity Resources
  • 35. Time Management Estimating Methods  Program Evaluation Review Technique (PERT)  Uses pessimistic, optimistic, and most likely estimates (O + P + (4 * M)) 6 35 Planning – Estimating Activity Resources
  • 37. Time Management Estimate Activities Durations Process  Focus on estimating the hours for each activity then summing them for a high level estimate.  This process creates the Activity Duration Estimates.  Key inputs to this process are the Schedule Management Plan, Activity List, Activity Resource Requirements, Resource Calendars, Risk Register, Resource Breakdown Structure, Project Scope Statement, Activity Attributes, Enterprise Environmental Factors, and Organizational Process Assets.  A Project Manager will use Expert Judgment, Analogous Estimating, Parametric Estimating, Three-Point Estimating, Group Decision Making Techniques, and Reserve Analysis to develop the Activity Duration Estimates. 37 Planning – Estimating Activity Durations
  • 38. Time Management Activity Duration Estimates  Identifies the duration of the activities with plus and minus ranges.  Activity “A” – 4 days +/- 2 days. Range is 2 to 6 days. 38 Planning – Estimating Activity Durations A 4 Design Dog House
  • 39. Time Management Schedule Management Plan Activity List Organizational Process Assets Activity Duration Estimate Expert Judgment Alternative Analysis Inputs Outputs Tools Estimate Activity Duration Enterprise Environmental Factors 39 Published Estimating Data Planning – Estimating Activity Durations Resource Calendars Risk Register Project Scope Statement Activity Attributes Bottom-Up Estimating Project Management Software Activity Resource Requirements
  • 41. Time Management Develop Schedule  This process reviews the resource needs, sequence activities, and estimating activity durations to develop the schedule. This process brings together the activity list, the work breakdown structure, the start and finish dates, and sequence activities.  This process creates the Schedule baseline, Project Schedule, and Project Calendars.  Key inputs to this process are the Schedule Management Plan, Activity List, Network Diagrams, Activity Resource Requirements, Resource Calendars, Risk Register, Resource Breakdown Structure, Project Scope Statement, Activity Attributes, Project Staff Assignments, Enterprise Environmental Factors, and Organizational Process Assets.  A Project Manager will use Schedule Network Analysis, Critical Path Method, Critical Chain Method, Resource Optimization Techniques, Modeling Techniques, Leads and Lags, Schedule Compression, and Scheduling Tool. 41 Planning – Develop Schedule
  • 42. Time Management Schedule Baseline  The planned timeline for the project execution.  Baseline dates 42 Planning – Develop Schedule
  • 43. Time Management Project Schedule  Integrated lists the activities, start and finish dates, resources, and sequencing.  Format can include;  Milestone charts  Bar charts  Project Schedule Network Diagrams 43 Planning – Develop Schedule
  • 44. Time Management Project Calendars  Shows scheduled resource usage and availability. 44 Planning – Develop Schedule
  • 45. Time Management Calculating the Critical Path 45 A FC E D B G 4 1 2 1 4 1 2 Design Dog House Purchase Material Dig Foundation Pour Concrete Build Dog House Install Fencing Train Dog 1 Start on Day 1 Forward Pass Planning – Develop Schedule
  • 46. Time Management Calculating the Critical Path 46 A FC E D B G 4 1 2 1 4 1 2 Design Dog House Purchase Material Dig Foundation Pour Concrete Build Dog House Install Fencing Train Dog 1 Forward Pass 4 1+4- 1 5 5 +1 +1 Planning – Develop Schedule
  • 47. Time Management Calculating the Critical Path 47 A FC E D B G 4 1 2 1 4 1 2 Design Dog House Purchase Material Dig Foundation Pour Concrete Build Dog House Install Fencing Train Dog 1 Forward Pass 4 5 5 5 6 5+1-1 5+2-1 +1 +1 7 Go with the High Number Planning – Develop Schedule
  • 48. Time Management Calculating the Critical Path 48 Planning – Sequence Activities A FC E D B G 4 1 2 1 4 1 2 Design Dog House Purchase Material Dig Foundation Pour Concrete Build Dog House Install Fencing Train Dog 1 Forward Pass 4 5 5 5 6 7 7 8 8 8 11 7+1-1 8+4-1 8+1-1 12+2-1 12 13
  • 49. Time Management Calculating the Critical Path 49 A FC E D B G 4 1 2 1 4 1 2 Design Dog House Purchase Material Dig Foundation Pour Concrete Build Dog House Install Fencing Train Dog 1 Forward Pass 4 5 5 5 6 7 7 8 8 8 11 7+1-1 8+4-1 8+1-1 12+2-1 12 13 Planning – Develop Schedule
  • 50. Time Management Calculating the Critical Path 50 A FC E D B G 4 1 2 1 4 1 2 Design Dog House Purchase Material Dig Foundation Pour Concrete Build Dog House Install Fencing Train Dog 1 Backward Pass 4 5 5 5 6 7 7 8 8 8 11 12 13 1312 -1 -1 11 11 Planning – Develop Schedule
  • 51. Time Management Calculating the Critical Path 51 A FC E D B G 4 1 2 1 4 1 2 Design Dog House Purchase Material Dig Foundation Pour Concrete Build Dog House Install Fencing Train Dog 1 Backward Pass 4 5 5 5 6 7 7 8 8 8 11 12 13 1312 -1 -1 11 11 11 8 7 7 6 65 6 41 Lower Number wins! Lower Number wins! 4-4+1 6-2+1 7-1+1 11-1+1 11-4+16-1+1 Planning – Develop Schedule
  • 52. Time Management Calculating the Critical Path 52 A FC E D B G 4 1 2 1 4 1 2 Design Dog House Purchase Material Dig Foundation Pour Concrete Build Dog House Install Fencing Train Dog 1 Calculating Slack 4 5 5 5 6 7 7 8 8 8 11 12 13 1312 11 11 11 8 7 7 6 65 6 41 6-5=1 11-8=3 Planning – Develop Schedule
  • 53. Time Management Calculating the Critical Path 53 Planning – Develop Schedule A FC E D B G 4 1 2 1 4 1 2 Design Dog House Purchase Material Dig Foundation Pour Concrete Build Dog House Install Fencing Train Dog 1 Critical Path 4 5 5 5 6 7 7 8 8 8 11 12 13 1312 11 11 11 8 7 7 6 65 6 41
  • 55. Time Management Control Schedule  This process is for the control and management of changes to the schedule.  This process creates Work Performance Information, Schedule Forecasts, and Change Requests.  Key inputs to this process are the Project Management Plan, Project Schedule, Work Performance Data, Project Calendars, schedule Data, and Organizational Process Assets.  A Project Manager will use Performance Reviews, Project Management Software, Resource Optimization Techniques, Modeling Techniques, Leads and Lags, Schedule Compression, and Scheduling Tools to perform this process. 55 Monitoring & Controlling – Control Schedule
  • 56. Time Management Work Performance Information  Information that helps to determine current schedule metrics compared to planned schedule metrics.  This is the information that helps with determining Earned Value 56 Monitoring & Controlling – Control Schedule
  • 57. Time Management Schedule Forecast  Anticipated situations and incidents that will likely occur in the future based off of current information. 57 Monitoring & Controlling – Control Schedule
  • 58. Time Management Change Requests  A variance in schedule after an analysis will result in a change request.  Changes that have been requested, but not yet formally approved. 58 Monitoring & Controlling – Control Schedule