SlideShare a Scribd company logo
1 of 7
Download to read offline
PM World Journal PMO & the Tollgate Process
Vol. II, Issue V – May 2013 by Bob Prieto
www.pmworldjournal.net Featured Paper
© 2013 Bob Prieto www.pmworldlibrary.net Page 1 of 7
PMO & the Tollgate Process
Bob Prieto
Fluor
In enterprise-wide roles the PMO (Project Management Office or Program Management
Office) will have responsibility for management and implementation of a tollgate or
stage gate process for program and project approval. The purpose of this process is to
ensure that investment decisions are made on a sound basis, that project portfolios
have been rationalized and optimized, and that solid baseline foundations exist.
This paper we will take a closer look at the tollgate process and its oversight by the
PMO.
Tollgates and Stage Gates
Tollgates or stage gates represent approval points before proceeding to the next stage
of program or project development. The PMO will have defined standards and
requirements to have been met before approval can be gained to proceed to the next
stage and review of the readiness of each project at the “gate” ensures that the basis for
additional capital commitments exists.
The various “gate” reviews are formal processes with responsibilities, accountabilities
and authorities well defined. The impact of proceeding through the “gate” must be
understood across the organization. In simplest terms the PMO is the gatekeeper.
Organizational terminology and “gate” requirements will vary but in general terms
include:
 Project or concept identification
 Project selection or pre-feasibility
 Project definition or feasibility
 Implementation
A well implemented tollgate process has the opportunity to significantly influence
program and project success. The best opportunities to influence project outcomes are
the earliest possible stages. Getting the first steps right is key to controlling the
impactful cost of change at later stages. Decision processes at each gate must be
robust.
It is at each stage gate that the program’s risk register is built and further refined. The
stage gate process drives risk management front and center in the overall program
definition process.
PM World Journal PMO & the Tollgate Process
Vol. II, Issue V – May 2013 by Bob Prieto
www.pmworldjournal.net Featured Paper
© 2013 Bob Prieto www.pmworldlibrary.net Page 2 of 7
PMO Role in Capital Management
As gatekeeper, the PMO’s effectiveness has a huge influence on enterprise wide capital
management. The tollgate process has the ability to:
 Manage demand for capital
 Drive capital efficiency in projects as they advance through the tollgate
process
 Enhance project execution by providing a disciplined project development
framework and enforcing standards on management evaluation of
alternatives
 Influence acceptable risk frameworks commensurate with the investments
being undertaken and the risks the programs will face.
At each stage the PMO can lever the tollgate process to create value.
Project or Concept Identification
During the project identification or concept stage, program and project teams will:
 Defines outcomes to be achieved (Strategic Business Objectives or
SBOs)
 Identify minimum scope required to achieve the SBOs
 Define candidate projects or project portfolios
 Initially engage stakeholders
 Screen candidate projects and options
 Test recommendations against policies, financial hurdle rates and other
constraints that may act upon their success
 Ensure that an initial risk register has been assembled and that large
areas of uncertainty have been identified together with the strategies to
reduce these uncertainties in the next stage
 Define resource allocations in terms of time, money and management
 Confirm that adequate managerial and other resources exist to undertake
the program
Inputs considered during this stage may include:
 Market or Demand Forecasts
 Sales/Capacity Reconciliation (matching supply to contractual
commitments)
 Competitor Intelligence or Other Competitive Studies
 Legal Constraints and Challenges
 Environmental Constraints and Regulations
PM World Journal PMO & the Tollgate Process
Vol. II, Issue V – May 2013 by Bob Prieto
www.pmworldjournal.net Featured Paper
© 2013 Bob Prieto www.pmworldlibrary.net Page 3 of 7
 Value Added Assessments
 Technology Assessments including Required R&D
 Estimates by Others
 Stakeholder Surveys and Other Assessments
 Program or Product Development
 Business Objectives
Project Selection or Pre-Feasibility
Projects that have cleared the initial gate represented by the project or concept
identification stage discussed above will then undertake a series of activities to improve
project definition and confidence in order to meet the requirements of the project
selection or pre-feasibility gate. Selection frameworks and ultimate selection
justifications will be developed.
Activities during this stage will include:
 Comprehensive portfolio and option evaluations at both the program and
project levels. At the program level identification of the efficient frontier will
be a major objective. At the project level, cost-benefit analyses are
undertaken on a risk weighted basis.
 Projects comprising the selected portfolio better defined
 Project level risks, resource requirements, constraints and interactions
with other projects comprising the program defined
 Structured opportunity analysis and implementation of a range of value
improving programs
 Refinement of cost analysis
 More rigorous risk identification and assessment
 Benchmarking analysis against other projects or programs
 Development of a preliminary program execution strategy and plan
Specific items developed at this stage include:
 Identification of Non Process Infrastructure (NPI); Offsites & Utilities (O&U); or
other auxiliary program or project needs
 Hazards Reviews (HAZOP)
 Conceptual Engineering or FEL 2
 Economic Evaluation of Alternatives Including Scenario Analysis
 Site Selection Based on Established Selection Criteria and Methodology
 Process Flow Sheets or the Equivalent for Other Industries (Highway Right of
Way (ROW); Rail Alignment; Single Line Network Diagrams)
 Budget Estimates including Risk Based Provisions for Uncertainties and
Unknowns
PM World Journal PMO & the Tollgate Process
Vol. II, Issue V – May 2013 by Bob Prieto
www.pmworldjournal.net Featured Paper
© 2013 Bob Prieto www.pmworldlibrary.net Page 4 of 7
 Project Objectives, Linked to Programmatic Strategic Business Objectives
Project Definition or Feasibility
Having cleared the pre-feasibility stage, programs move to the feasibility stage.
Principle objectives at this stage include rigorously assessing the financial justification
for a particular project using pre-established and consistently applied methodology and
criteria.
Projects will undergo structured processes that allow all projects to be evaluated on a
consistent basis. In effect projects are competing for the same scarce resources.
Projects which clear this gate are “sanctioned” and full capital resources for
implementation are released to the project.
Specific items developed to support this stage, and which will be reviewed by the PMO,
include:
 Piping & Instrumentation Drawings (P&IDs)
 Equipment Specifications and as Appropriate Materials Specifications
 Procurement Plan including Use of Strategic Sourcing
 Execution Plan, Consistent with the Standards Established by the PMO
 General or Preliminary Arrangements
 Scope(s)of Work
 Baseline Schedule and Associated Analysis
 Baseline Estimate for “Sanction”
 Sign-offs from all Required Parties
In addition to leading evaluation of the various programs and projects, the PMO will be
looking at the enterprise’s overall portfolio, identifying portfolio risks and opportunities.
Project portfolio management is a key PMO responsibility.
Project portfolio management seeks to ensure that:
 The right projects are selected to achieve the strategic outcomes represented by
the organization’s Strategic Business Objectives
 Resources, financial and management, are optimally deployed
 Projects are monitored against key performance indicators which are developed
through the tollgate process and linked to key outcomes, critical success factors
or key results areas as appropriate
 Projects are executed in a well defined and comprehensive manner benefiting
from lessons learned on earlier efforts.
As part of its project portfolio management efforts the PMO will:
PM World Journal PMO & the Tollgate Process
Vol. II, Issue V – May 2013 by Bob Prieto
www.pmworldjournal.net Featured Paper
© 2013 Bob Prieto www.pmworldlibrary.net Page 5 of 7
 Establish project portfolio evaluation criteria and methodologies
 Establish project evaluation methodologies to ensure consistent evaluation of
projects
 Monitor alignment of Strategic Business Objectives, strategy and program and
project definition
 Ensure that top level KPIs have been appropriately cascaded down
 Confirm that selected portfolios and projects are consistent with the
organization’s risk appetite
 Confirm that changes in the external or internal environments have not altered
the viability of selected programs or projects
 Asses program, project and enterprise portfolio risks paying particular attention to
cross enterprise systemic risks; constraint coupling and assumption migration
 Define key strategic risks that must be considered in program and project
evaluations at each gate.
 Assess program resiliency and identify inherent complexity and flexibility
 Review dynamic factors impacting project delivery
 Assess adequacy of enterprise risk management and mitigation efforts including
required insurance programs
 Model cash flows under a range of scenarios and develop contingency strategies
 Model project and program hurdle rates recognizing that low performing projects
may be enablers for higher program performance.
 Assess adequacy of management and other human resources including overall
availability, competition for resources and possession of requisite skill levels
 Identify financial risk mitigation strategies and implement as tasked
 Ongoing project validation
 Top level stakeholder communication
 Implement project and program governance policies and practices
Implementation
The PMO will establish program and project execution standards and prepare go-by
documents for these execution plans. Execution requirements will be further supported
by policies, procedures and standards as required meeting the organization’s needs for
consistent program and project execution and performance.
Change control is a major focus area of the PMO recognizing the costly and disruptive
impacts of change. Reviews will include all affected stakeholders and occur in a timely
manner before each major construction activity.
Cross project and cross program impacts will be closely monitored by the PMO.
Opportunities for cost reduction, synergy capture, opportunity exploitation, and schedule
compression will also represent a major focus for the PMO.
PM World Journal PMO & the Tollgate Process
Vol. II, Issue V – May 2013 by Bob Prieto
www.pmworldjournal.net Featured Paper
© 2013 Bob Prieto www.pmworldlibrary.net Page 6 of 7
Post Implementation
Capturing project and program lessons learned and best practices is a key first step in a
broader knowledge management and continuous improvement effort led by the PMO.
The PMO will document key findings at the end of each tollgate stage and as part of
ongoing project reviews and conduct deep-dives when significant problems emerge.
Enterprise knowledge management programs are becoming increasingly important in
large programs as well as experienced based training to inculcate best practices into
program delivery efforts.
References:
1. The GIGA Factor; Program Management in the Engineering & Construction
Industry; CMAA; ISBN 978-1-938014-99-4; 2011
2. The Focus, Roles & Responsibilities of a Program Management Office; PM
World Today – April 2010 (Vol XII, Issue IV)
PM World Journal PMO & the Tollgate Process
Vol. II, Issue V – May 2013 by Bob Prieto
www.pmworldjournal.net Featured Paper
© 2013 Bob Prieto www.pmworldlibrary.net Page 7 of 7
About the Author
Bob Prieto
Senior Vice President
Fluor
Bob Prieto is a senior vice president of Fluor, one of the largest,
publicly traded engineering and construction companies in the world. He is responsible
for strategy for the firm’s Industrial & Infrastructure group which focuses on the
development and delivery of large, complex projects worldwide. The group
encompasses three major business lines including Infrastructure, with an emphasis on
Public Private Partnerships; Mining; and Industrial Services. Bob consults with owner’s
of large engineering & construction capital construction programs across all market
sectors in the development of programmatic delivery strategies encompassing planning,
engineering, procurement, construction and financing. He is author of “Strategic
Program Management” and “The Giga Factor: Program Management in the Engineering
and Construction Industry” published by the Construction Management Association of
America (CMAA) and “Topics in Strategic Program Management” as well as over 400
other papers and presentations.
Bob is a member of the ASCE Industry Leaders Council, National Academy of
Construction and a Fellow of the Construction Management Association of America.
Bob served until 2006 as one of three U.S. presidential appointees to the Asia Pacific
Economic Cooperation (APEC) Business Advisory Council (ABAC), working with U.S.
and Asia-Pacific business leaders to shape the framework for trade and economic
growth and had previously served as both as Chairman of the Engineering and
Construction Governors of the World Economic Forum and co-chair of the infrastructure
task force formed after September 11th by the New York City Chamber of Commerce.
Previously, he served as Chairman at Parsons Brinckerhoff (PB), one of the world’s
leading engineering companies. Bob Prieto can be contacted at Bob.Prieto@fluor.com.

More Related Content

What's hot

Prince2 explained in 30mins
Prince2 explained in 30minsPrince2 explained in 30mins
Prince2 explained in 30minsILX Group
 
IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)jimmcdonaldpmp
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter SummeryDerek Cooksey
 
Project Management To Project Governance , Knowledge Management
Project Management To Project Governance , Knowledge ManagementProject Management To Project Governance , Knowledge Management
Project Management To Project Governance , Knowledge Managementsubramanian K
 
PRINCE2 - Presentation
PRINCE2 - PresentationPRINCE2 - Presentation
PRINCE2 - PresentationMatt Trigg
 
PMO Setup with Microsoft Project Online
PMO Setup with Microsoft Project OnlinePMO Setup with Microsoft Project Online
PMO Setup with Microsoft Project OnlineGonzague PATINIER
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full courseMarten Schoonman
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
Project management-plan
Project management-planProject management-plan
Project management-planTran Tien
 
Project Execution & Control Checklist
Project Execution & Control ChecklistProject Execution & Control Checklist
Project Execution & Control ChecklistAnand Subramaniam
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Hussain Bandukwala
 
Projectcontrol
ProjectcontrolProjectcontrol
ProjectcontrolRaj Sampat
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesAnand Bobade
 
Establishing an Effective PMO
Establishing an Effective PMOEstablishing an Effective PMO
Establishing an Effective PMOBusiness Beam
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)PM Majik
 

What's hot (20)

Prince2 explained in 30mins
Prince2 explained in 30minsPrince2 explained in 30mins
Prince2 explained in 30mins
 
Building An Enterprise PMO
Building An Enterprise PMOBuilding An Enterprise PMO
Building An Enterprise PMO
 
IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter Summery
 
Establishing an effective epmo
Establishing an effective epmoEstablishing an effective epmo
Establishing an effective epmo
 
Project Management To Project Governance , Knowledge Management
Project Management To Project Governance , Knowledge ManagementProject Management To Project Governance , Knowledge Management
Project Management To Project Governance , Knowledge Management
 
PMO Challenges and Opportunities; DIPMF Presentation
PMO Challenges and Opportunities; DIPMF PresentationPMO Challenges and Opportunities; DIPMF Presentation
PMO Challenges and Opportunities; DIPMF Presentation
 
PRINCE2 - Presentation
PRINCE2 - PresentationPRINCE2 - Presentation
PRINCE2 - Presentation
 
PMO Setup with Microsoft Project Online
PMO Setup with Microsoft Project OnlinePMO Setup with Microsoft Project Online
PMO Setup with Microsoft Project Online
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
PMP
PMPPMP
PMP
 
Project management-plan
Project management-planProject management-plan
Project management-plan
 
Portfolio management
Portfolio managementPortfolio management
Portfolio management
 
Project Execution & Control Checklist
Project Execution & Control ChecklistProject Execution & Control Checklist
Project Execution & Control Checklist
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)
 
Projectcontrol
ProjectcontrolProjectcontrol
Projectcontrol
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
Establishing an Effective PMO
Establishing an Effective PMOEstablishing an Effective PMO
Establishing an Effective PMO
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)
 

Viewers also liked

Lean six sigma tollgate checklists
Lean six sigma tollgate checklistsLean six sigma tollgate checklists
Lean six sigma tollgate checklistsSteven Bonacorsi
 
Define Tollgate
Define TollgateDefine Tollgate
Define Tollgatedonhhenry
 
Making Sure New Products Don't Fail
Making Sure New Products Don't FailMaking Sure New Products Don't Fail
Making Sure New Products Don't FailRick Steinbrenner
 
Define phase lean six sigma tollgate template
Define phase   lean six sigma tollgate templateDefine phase   lean six sigma tollgate template
Define phase lean six sigma tollgate templateSteven Bonacorsi
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
Transition and Planning
Transition and Planning Transition and Planning
Transition and Planning AIESEC
 
PMO OBjectives - a quick guide
PMO OBjectives - a quick guidePMO OBjectives - a quick guide
PMO OBjectives - a quick guidePM Majik
 
Project Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and AgileProject Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and AgileKnowit_TM
 
NG BB 14 DEFINE Tollgate
NG BB 14 DEFINE TollgateNG BB 14 DEFINE Tollgate
NG BB 14 DEFINE TollgateLeanleaders.org
 
Stage gate innovation process powerpoint presentation templates
Stage gate innovation process powerpoint presentation templatesStage gate innovation process powerpoint presentation templates
Stage gate innovation process powerpoint presentation templatesSlideTeam.net
 
Toll app - Android project
Toll app - Android projectToll app - Android project
Toll app - Android projectArun prasath
 
Automatic Toll Tax Collection System by Using RFID
Automatic Toll Tax Collection System by Using RFIDAutomatic Toll Tax Collection System by Using RFID
Automatic Toll Tax Collection System by Using RFIDSahal Patel
 
Lean six sigma - Waste elimination (Yellow Belt)
Lean six sigma - Waste elimination (Yellow Belt)Lean six sigma - Waste elimination (Yellow Belt)
Lean six sigma - Waste elimination (Yellow Belt)Abhay Yadav
 
Control phase lean six sigma tollgate template
Control phase   lean six sigma tollgate templateControl phase   lean six sigma tollgate template
Control phase lean six sigma tollgate templateSteven Bonacorsi
 

Viewers also liked (20)

Lean six sigma tollgate checklists
Lean six sigma tollgate checklistsLean six sigma tollgate checklists
Lean six sigma tollgate checklists
 
Define Tollgate
Define TollgateDefine Tollgate
Define Tollgate
 
Tollgate Presentation
Tollgate PresentationTollgate Presentation
Tollgate Presentation
 
Making Sure New Products Don't Fail
Making Sure New Products Don't FailMaking Sure New Products Don't Fail
Making Sure New Products Don't Fail
 
Define phase lean six sigma tollgate template
Define phase   lean six sigma tollgate templateDefine phase   lean six sigma tollgate template
Define phase lean six sigma tollgate template
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
Toll plaza ppt
Toll plaza pptToll plaza ppt
Toll plaza ppt
 
Six sigma
Six  sigmaSix  sigma
Six sigma
 
PKS Delivery Excellence Framework
PKS Delivery Excellence FrameworkPKS Delivery Excellence Framework
PKS Delivery Excellence Framework
 
Transition and Planning
Transition and Planning Transition and Planning
Transition and Planning
 
PMO OBjectives - a quick guide
PMO OBjectives - a quick guidePMO OBjectives - a quick guide
PMO OBjectives - a quick guide
 
Project Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and AgileProject Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and Agile
 
It transition management an operational perspective
It transition management   an operational perspectiveIt transition management   an operational perspective
It transition management an operational perspective
 
NG BB 14 DEFINE Tollgate
NG BB 14 DEFINE TollgateNG BB 14 DEFINE Tollgate
NG BB 14 DEFINE Tollgate
 
Stage gate innovation process powerpoint presentation templates
Stage gate innovation process powerpoint presentation templatesStage gate innovation process powerpoint presentation templates
Stage gate innovation process powerpoint presentation templates
 
Stage gate process
Stage gate processStage gate process
Stage gate process
 
Toll app - Android project
Toll app - Android projectToll app - Android project
Toll app - Android project
 
Automatic Toll Tax Collection System by Using RFID
Automatic Toll Tax Collection System by Using RFIDAutomatic Toll Tax Collection System by Using RFID
Automatic Toll Tax Collection System by Using RFID
 
Lean six sigma - Waste elimination (Yellow Belt)
Lean six sigma - Waste elimination (Yellow Belt)Lean six sigma - Waste elimination (Yellow Belt)
Lean six sigma - Waste elimination (Yellow Belt)
 
Control phase lean six sigma tollgate template
Control phase   lean six sigma tollgate templateControl phase   lean six sigma tollgate template
Control phase lean six sigma tollgate template
 

Similar to PMO and Tollgate Process

Fundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revisedFundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revisedgorby626
 
E3 CER A Powerful tool for Governance
E3 CER A Powerful tool for GovernanceE3 CER A Powerful tool for Governance
E3 CER A Powerful tool for GovernanceMagued Moftah
 
E3 cer a powerful tool for governance
E3 cer a powerful tool for governanceE3 cer a powerful tool for governance
E3 cer a powerful tool for governanceMagued Moftah
 
Corporate project management model
Corporate project management modelCorporate project management model
Corporate project management modelLatte Media
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptxAtulBhagwat6
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAddisu15
 
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15Project Control | PROJ CTRL
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsIbrahim Al-Hudhaif
 
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docx
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docxC19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docx
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docxchestnutkaitlyn
 
Project Manangement Introduction
Project Manangement IntroductionProject Manangement Introduction
Project Manangement Introductionasim78
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...GlobalSkillup
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisalAmandaBvera
 
PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -Hossam Maghrabi
 
Project management processes Groups
Project management processes GroupsProject management processes Groups
Project management processes GroupsSourabh Kumar
 
2 a. project auditing
2 a. project auditing2 a. project auditing
2 a. project auditingDr.R. SELVAM
 
Opportunity analysis under strategic program management second edition
Opportunity analysis under strategic program management second editionOpportunity analysis under strategic program management second edition
Opportunity analysis under strategic program management second editionBob Prieto
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager PrimerTom Cremins
 

Similar to PMO and Tollgate Process (20)

Fundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revisedFundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revised
 
E3 CER A Powerful tool for Governance
E3 CER A Powerful tool for GovernanceE3 CER A Powerful tool for Governance
E3 CER A Powerful tool for Governance
 
E3 cer a powerful tool for governance
E3 cer a powerful tool for governanceE3 cer a powerful tool for governance
E3 cer a powerful tool for governance
 
Program management-steps
Program management-stepsProgram management-steps
Program management-steps
 
Corporate project management model
Corporate project management modelCorporate project management model
Corporate project management model
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptx
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdf
 
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
 
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docx
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docxC19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docx
C19 07142011 111853 Page 18719CHAPTER NINETEENProjec.docx
 
Project Manangement Introduction
Project Manangement IntroductionProject Manangement Introduction
Project Manangement Introduction
 
2.pptx
2.pptx2.pptx
2.pptx
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisal
 
PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -
 
Project management processes Groups
Project management processes GroupsProject management processes Groups
Project management processes Groups
 
2 a. project auditing
2 a. project auditing2 a. project auditing
2 a. project auditing
 
PMP integration review
PMP integration reviewPMP integration review
PMP integration review
 
Opportunity analysis under strategic program management second edition
Opportunity analysis under strategic program management second editionOpportunity analysis under strategic program management second edition
Opportunity analysis under strategic program management second edition
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager Primer
 

More from Bob Prieto

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Bob Prieto
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startupBob Prieto
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projectsBob Prieto
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projectsBob Prieto
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programsBob Prieto
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryBob Prieto
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface ManagementBob Prieto
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsBob Prieto
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global WarmingBob Prieto
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project successBob Prieto
 
Large complex project success
Large complex project successLarge complex project success
Large complex project successBob Prieto
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Bob Prieto
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under UncertaintyBob Prieto
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasBob Prieto
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentBob Prieto
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Bob Prieto
 

More from Bob Prieto (20)

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projects
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projects
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programs
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface Management
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global Warming
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project success
 
Large complex project success
Large complex project successLarge complex project success
Large complex project success
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under Uncertainty
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the Bahamas
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environment
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7
 

Recently uploaded

GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxAbhayThakur200703
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 

Recently uploaded (20)

GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptx
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 

PMO and Tollgate Process

  • 1. PM World Journal PMO & the Tollgate Process Vol. II, Issue V – May 2013 by Bob Prieto www.pmworldjournal.net Featured Paper © 2013 Bob Prieto www.pmworldlibrary.net Page 1 of 7 PMO & the Tollgate Process Bob Prieto Fluor In enterprise-wide roles the PMO (Project Management Office or Program Management Office) will have responsibility for management and implementation of a tollgate or stage gate process for program and project approval. The purpose of this process is to ensure that investment decisions are made on a sound basis, that project portfolios have been rationalized and optimized, and that solid baseline foundations exist. This paper we will take a closer look at the tollgate process and its oversight by the PMO. Tollgates and Stage Gates Tollgates or stage gates represent approval points before proceeding to the next stage of program or project development. The PMO will have defined standards and requirements to have been met before approval can be gained to proceed to the next stage and review of the readiness of each project at the “gate” ensures that the basis for additional capital commitments exists. The various “gate” reviews are formal processes with responsibilities, accountabilities and authorities well defined. The impact of proceeding through the “gate” must be understood across the organization. In simplest terms the PMO is the gatekeeper. Organizational terminology and “gate” requirements will vary but in general terms include:  Project or concept identification  Project selection or pre-feasibility  Project definition or feasibility  Implementation A well implemented tollgate process has the opportunity to significantly influence program and project success. The best opportunities to influence project outcomes are the earliest possible stages. Getting the first steps right is key to controlling the impactful cost of change at later stages. Decision processes at each gate must be robust. It is at each stage gate that the program’s risk register is built and further refined. The stage gate process drives risk management front and center in the overall program definition process.
  • 2. PM World Journal PMO & the Tollgate Process Vol. II, Issue V – May 2013 by Bob Prieto www.pmworldjournal.net Featured Paper © 2013 Bob Prieto www.pmworldlibrary.net Page 2 of 7 PMO Role in Capital Management As gatekeeper, the PMO’s effectiveness has a huge influence on enterprise wide capital management. The tollgate process has the ability to:  Manage demand for capital  Drive capital efficiency in projects as they advance through the tollgate process  Enhance project execution by providing a disciplined project development framework and enforcing standards on management evaluation of alternatives  Influence acceptable risk frameworks commensurate with the investments being undertaken and the risks the programs will face. At each stage the PMO can lever the tollgate process to create value. Project or Concept Identification During the project identification or concept stage, program and project teams will:  Defines outcomes to be achieved (Strategic Business Objectives or SBOs)  Identify minimum scope required to achieve the SBOs  Define candidate projects or project portfolios  Initially engage stakeholders  Screen candidate projects and options  Test recommendations against policies, financial hurdle rates and other constraints that may act upon their success  Ensure that an initial risk register has been assembled and that large areas of uncertainty have been identified together with the strategies to reduce these uncertainties in the next stage  Define resource allocations in terms of time, money and management  Confirm that adequate managerial and other resources exist to undertake the program Inputs considered during this stage may include:  Market or Demand Forecasts  Sales/Capacity Reconciliation (matching supply to contractual commitments)  Competitor Intelligence or Other Competitive Studies  Legal Constraints and Challenges  Environmental Constraints and Regulations
  • 3. PM World Journal PMO & the Tollgate Process Vol. II, Issue V – May 2013 by Bob Prieto www.pmworldjournal.net Featured Paper © 2013 Bob Prieto www.pmworldlibrary.net Page 3 of 7  Value Added Assessments  Technology Assessments including Required R&D  Estimates by Others  Stakeholder Surveys and Other Assessments  Program or Product Development  Business Objectives Project Selection or Pre-Feasibility Projects that have cleared the initial gate represented by the project or concept identification stage discussed above will then undertake a series of activities to improve project definition and confidence in order to meet the requirements of the project selection or pre-feasibility gate. Selection frameworks and ultimate selection justifications will be developed. Activities during this stage will include:  Comprehensive portfolio and option evaluations at both the program and project levels. At the program level identification of the efficient frontier will be a major objective. At the project level, cost-benefit analyses are undertaken on a risk weighted basis.  Projects comprising the selected portfolio better defined  Project level risks, resource requirements, constraints and interactions with other projects comprising the program defined  Structured opportunity analysis and implementation of a range of value improving programs  Refinement of cost analysis  More rigorous risk identification and assessment  Benchmarking analysis against other projects or programs  Development of a preliminary program execution strategy and plan Specific items developed at this stage include:  Identification of Non Process Infrastructure (NPI); Offsites & Utilities (O&U); or other auxiliary program or project needs  Hazards Reviews (HAZOP)  Conceptual Engineering or FEL 2  Economic Evaluation of Alternatives Including Scenario Analysis  Site Selection Based on Established Selection Criteria and Methodology  Process Flow Sheets or the Equivalent for Other Industries (Highway Right of Way (ROW); Rail Alignment; Single Line Network Diagrams)  Budget Estimates including Risk Based Provisions for Uncertainties and Unknowns
  • 4. PM World Journal PMO & the Tollgate Process Vol. II, Issue V – May 2013 by Bob Prieto www.pmworldjournal.net Featured Paper © 2013 Bob Prieto www.pmworldlibrary.net Page 4 of 7  Project Objectives, Linked to Programmatic Strategic Business Objectives Project Definition or Feasibility Having cleared the pre-feasibility stage, programs move to the feasibility stage. Principle objectives at this stage include rigorously assessing the financial justification for a particular project using pre-established and consistently applied methodology and criteria. Projects will undergo structured processes that allow all projects to be evaluated on a consistent basis. In effect projects are competing for the same scarce resources. Projects which clear this gate are “sanctioned” and full capital resources for implementation are released to the project. Specific items developed to support this stage, and which will be reviewed by the PMO, include:  Piping & Instrumentation Drawings (P&IDs)  Equipment Specifications and as Appropriate Materials Specifications  Procurement Plan including Use of Strategic Sourcing  Execution Plan, Consistent with the Standards Established by the PMO  General or Preliminary Arrangements  Scope(s)of Work  Baseline Schedule and Associated Analysis  Baseline Estimate for “Sanction”  Sign-offs from all Required Parties In addition to leading evaluation of the various programs and projects, the PMO will be looking at the enterprise’s overall portfolio, identifying portfolio risks and opportunities. Project portfolio management is a key PMO responsibility. Project portfolio management seeks to ensure that:  The right projects are selected to achieve the strategic outcomes represented by the organization’s Strategic Business Objectives  Resources, financial and management, are optimally deployed  Projects are monitored against key performance indicators which are developed through the tollgate process and linked to key outcomes, critical success factors or key results areas as appropriate  Projects are executed in a well defined and comprehensive manner benefiting from lessons learned on earlier efforts. As part of its project portfolio management efforts the PMO will:
  • 5. PM World Journal PMO & the Tollgate Process Vol. II, Issue V – May 2013 by Bob Prieto www.pmworldjournal.net Featured Paper © 2013 Bob Prieto www.pmworldlibrary.net Page 5 of 7  Establish project portfolio evaluation criteria and methodologies  Establish project evaluation methodologies to ensure consistent evaluation of projects  Monitor alignment of Strategic Business Objectives, strategy and program and project definition  Ensure that top level KPIs have been appropriately cascaded down  Confirm that selected portfolios and projects are consistent with the organization’s risk appetite  Confirm that changes in the external or internal environments have not altered the viability of selected programs or projects  Asses program, project and enterprise portfolio risks paying particular attention to cross enterprise systemic risks; constraint coupling and assumption migration  Define key strategic risks that must be considered in program and project evaluations at each gate.  Assess program resiliency and identify inherent complexity and flexibility  Review dynamic factors impacting project delivery  Assess adequacy of enterprise risk management and mitigation efforts including required insurance programs  Model cash flows under a range of scenarios and develop contingency strategies  Model project and program hurdle rates recognizing that low performing projects may be enablers for higher program performance.  Assess adequacy of management and other human resources including overall availability, competition for resources and possession of requisite skill levels  Identify financial risk mitigation strategies and implement as tasked  Ongoing project validation  Top level stakeholder communication  Implement project and program governance policies and practices Implementation The PMO will establish program and project execution standards and prepare go-by documents for these execution plans. Execution requirements will be further supported by policies, procedures and standards as required meeting the organization’s needs for consistent program and project execution and performance. Change control is a major focus area of the PMO recognizing the costly and disruptive impacts of change. Reviews will include all affected stakeholders and occur in a timely manner before each major construction activity. Cross project and cross program impacts will be closely monitored by the PMO. Opportunities for cost reduction, synergy capture, opportunity exploitation, and schedule compression will also represent a major focus for the PMO.
  • 6. PM World Journal PMO & the Tollgate Process Vol. II, Issue V – May 2013 by Bob Prieto www.pmworldjournal.net Featured Paper © 2013 Bob Prieto www.pmworldlibrary.net Page 6 of 7 Post Implementation Capturing project and program lessons learned and best practices is a key first step in a broader knowledge management and continuous improvement effort led by the PMO. The PMO will document key findings at the end of each tollgate stage and as part of ongoing project reviews and conduct deep-dives when significant problems emerge. Enterprise knowledge management programs are becoming increasingly important in large programs as well as experienced based training to inculcate best practices into program delivery efforts. References: 1. The GIGA Factor; Program Management in the Engineering & Construction Industry; CMAA; ISBN 978-1-938014-99-4; 2011 2. The Focus, Roles & Responsibilities of a Program Management Office; PM World Today – April 2010 (Vol XII, Issue IV)
  • 7. PM World Journal PMO & the Tollgate Process Vol. II, Issue V – May 2013 by Bob Prieto www.pmworldjournal.net Featured Paper © 2013 Bob Prieto www.pmworldlibrary.net Page 7 of 7 About the Author Bob Prieto Senior Vice President Fluor Bob Prieto is a senior vice president of Fluor, one of the largest, publicly traded engineering and construction companies in the world. He is responsible for strategy for the firm’s Industrial & Infrastructure group which focuses on the development and delivery of large, complex projects worldwide. The group encompasses three major business lines including Infrastructure, with an emphasis on Public Private Partnerships; Mining; and Industrial Services. Bob consults with owner’s of large engineering & construction capital construction programs across all market sectors in the development of programmatic delivery strategies encompassing planning, engineering, procurement, construction and financing. He is author of “Strategic Program Management” and “The Giga Factor: Program Management in the Engineering and Construction Industry” published by the Construction Management Association of America (CMAA) and “Topics in Strategic Program Management” as well as over 400 other papers and presentations. Bob is a member of the ASCE Industry Leaders Council, National Academy of Construction and a Fellow of the Construction Management Association of America. Bob served until 2006 as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC), working with U.S. and Asia-Pacific business leaders to shape the framework for trade and economic growth and had previously served as both as Chairman of the Engineering and Construction Governors of the World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. Previously, he served as Chairman at Parsons Brinckerhoff (PB), one of the world’s leading engineering companies. Bob Prieto can be contacted at Bob.Prieto@fluor.com.