SlideShare a Scribd company logo
Open Circuit saturation test
Table of Content:
1 Objective...................................................................................................
2 Scope........................................................................................................
3 Referenced Documents ............................................................................
4 Definitions and Abbreviations....................................................................
5 Preparation................................................................................................
6 Conduction of test ....................................................................................
7 Proceeding in case of deviations...............................................................
8 Copyright...................................................................................................
1 Objective
This procedure describes the open-circuit (no-load) test, which is performed to establish
the relationship between the voltage at the terminals of the open-circuited armature
winding and the excitation current.
From the measurement data of the open-circuit test the following machine
characteristics and
quantities are determined:
- open circuit saturation characteristic (with separate and/or brushless excitation)
- direct-axis synchronous reactance Xd
- short-circuit ratio Kc
- Potier reactance Xp rated voltage regulation ∆UN
Note:
During the open-circuit test also the follow ing quantities are measured (see
corresponding procedures):
- Shaft voltage (with saturation characteristic)
- Balance of phases (at rated voltage)
- Voltage wave form, harmonic analysis and THF-factor (at rated voltage)
- Residual voltage
- Sequence of phases (preferably at residual voltage)
- Constant losses for turbogenerators w ith calibrated machine method (loss curve,
included in Short Commercial Test for GE orders)
- Vibration (at rated voltage)
- Noise (at rated voltage)
2 Scope
All types of synchronous machines during final tests in workshop or at site.
3 Referenced Documents
IEC 34-4, 25*), 27
(EN 60034-4, 25, 27)
IEEE Std. 115, 4.2.5
Page 1 of 3
4 Definitions and Abbreviations
None.
5 Preparation
- Set the generator in the three-phase armature winding open-circuit condition
- Install the precision instruments for the armature voltage and field current
measurement respectively.
- The voltage should be measured with potential transformers
- Check electrical clearances around generator terminals.
- For work shop tests either install temporary slip rings for separate excitation, or install a
rotating shunt with a signal transmission system for the shunt voltage drop (telemetric
system or measuring slip rings).
6 Conduction of test
- Operate the unit at rated speed with the manual control of the excitation system
Note: When a prime mover is not available, this test can be conducted acc. IEC 34-4 *),
running the machine as a motor (unity power factor test) or during OC-excited
retardation.
- Supply small field current and check that instruments, excitation system and generator
are in the proper condition
- After that, gradually change field current and measure armature voltages and field
currents.
If not otherwise specified in the contract, measurement voltage steps shall be app. 10 %
UN.
- Maximum armature voltage is limited to 130 % of the rated armature voltage, however
with turbogenerators do not exceed 120 % UN.
- Readings shall be taken at increasing excitation currents, from residual to maximum
voltage, continuing with decreasing excitation currents as well
- During the OC-tests, the field current should not exceed the rated value either.
- Check the armature voltage balance in the three phases at approximately rated
voltage.
The voltages on each phase should be the same ±1 %.
- When the saturation characteristic has been measured with separate excitation, repeat
with excitation from own exciter (brushless), after the original state of the excitation
system is reestablished.
- Measure the shaft voltage
- At residual voltage level check the sequence of the voltages on the generator terminals
with phase sequence meter. Time sequence of phases must be in correspondence to
the terminal numbering and the sense of rotation of the rotor as specified in the contract.
Page 2 of 3
Appendix for site testing:
- When a work shop test was performed but the OC-test is repeated on site (this holds
generally for commissioning of turbogenerators), it is sufficient to measure only one (or a
few points), including approximately rated voltage, in order to check correspondence
with the originally measured characteristic and verify balance of generated voltages. For
comparison data see the original test report of the tested machine, or the type test report
of another machine and exciter of the same design. Sometimes temporary slip rings are
not installed on site, so field current cannot be measured directly. Only a rough check of
the excitation current will be possible by measuring the field current of the exciter
machine.
- Excitation of the generator is from its own exciter (brushless) or from an external
(static) excitation system as appropriate.
- Secondary voltages are taken from the potential transformers installed in the plant.
7 Proceeding in case of deviations
Any nominal value, minimum value, maximum value, tolerance etc given in an instruction
is intended to serve for quality control purposes only. In the case of deviations, a
nonconformity report has to be written according to PNG Power Standard.
8 Copyright
This Document is properly of PNG Power internal use only and must neither be copied.
Neither is it to be handed over nor in other way communicated to a third party.
Infringement will lead to prosecution.
Page 3 of 3

More Related Content

What's hot

Saudi Aramco Engineering Procedures (SAEP) 5
Saudi Aramco Engineering Procedures (SAEP) 5Saudi Aramco Engineering Procedures (SAEP) 5
Saudi Aramco Engineering Procedures (SAEP) 5ROBERTO BATAHOY GAMALE JR
 
Araby (James Joyce)
Araby (James Joyce)Araby (James Joyce)
Araby (James Joyce)
Aswa Nina
 
When lilacs last in dooryard
When lilacs last in dooryardWhen lilacs last in dooryard
When lilacs last in dooryardChristine Capen
 
English for aviation mechanics
English for aviation mechanicsEnglish for aviation mechanics
English for aviation mechanics
tariqdyab
 
A
AA
Nathaniel hawthorne
Nathaniel hawthorneNathaniel hawthorne
Nathaniel hawthorne
Ariadne Rooney
 
Biographia Literaria coleridge.
Biographia Literaria coleridge.Biographia Literaria coleridge.
Biographia Literaria coleridge.
dayagohel
 
Api 1104 study guide
Api 1104 study guideApi 1104 study guide
Api 1104 study guideHani Mohamad
 
Welding book
Welding bookWelding book
Welding book
Michaelui Michaelui
 
Literary criticism
Literary criticismLiterary criticism
Literary criticism
ShyamSunder Naik
 
Maya Angelou
Maya AngelouMaya Angelou
Maya Angelou
Troy State University
 
Hamartia
HamartiaHamartia
Hamartia
AshaDhedhi
 
Aramco inspection handbook
Aramco inspection handbookAramco inspection handbook
Aramco inspection handbookram111eg
 
Aerospace fastener applications_part2_r2010
Aerospace fastener applications_part2_r2010Aerospace fastener applications_part2_r2010
Aerospace fastener applications_part2_r2010Merlin4SC
 
Ludwig van Beethoven
Ludwig van BeethovenLudwig van Beethoven
Ludwig van Beethoven
ChrisHermesch1
 
Banked turn and its effects on Stall speed of an Airplane
Banked turn and its effects on Stall speed of an AirplaneBanked turn and its effects on Stall speed of an Airplane
Banked turn and its effects on Stall speed of an Airplane
JagrataBanerjee
 
Sylvia plath: Her Life and Sufferings
Sylvia plath: Her Life and SufferingsSylvia plath: Her Life and Sufferings
Sylvia plath: Her Life and Sufferings
Bibi Halima
 
Decoding shakespeare
Decoding shakespeareDecoding shakespeare
Decoding shakespeareMsRae
 

What's hot (20)

Saudi Aramco Engineering Procedures (SAEP) 5
Saudi Aramco Engineering Procedures (SAEP) 5Saudi Aramco Engineering Procedures (SAEP) 5
Saudi Aramco Engineering Procedures (SAEP) 5
 
Araby (James Joyce)
Araby (James Joyce)Araby (James Joyce)
Araby (James Joyce)
 
Prioress
PrioressPrioress
Prioress
 
When lilacs last in dooryard
When lilacs last in dooryardWhen lilacs last in dooryard
When lilacs last in dooryard
 
English for aviation mechanics
English for aviation mechanicsEnglish for aviation mechanics
English for aviation mechanics
 
A
AA
A
 
Nathaniel hawthorne
Nathaniel hawthorneNathaniel hawthorne
Nathaniel hawthorne
 
Biographia Literaria coleridge.
Biographia Literaria coleridge.Biographia Literaria coleridge.
Biographia Literaria coleridge.
 
Api 1104 study guide
Api 1104 study guideApi 1104 study guide
Api 1104 study guide
 
Welding book
Welding bookWelding book
Welding book
 
Literary criticism
Literary criticismLiterary criticism
Literary criticism
 
Maya Angelou
Maya AngelouMaya Angelou
Maya Angelou
 
Hamartia
HamartiaHamartia
Hamartia
 
Aramco inspection handbook
Aramco inspection handbookAramco inspection handbook
Aramco inspection handbook
 
Aerospace fastener applications_part2_r2010
Aerospace fastener applications_part2_r2010Aerospace fastener applications_part2_r2010
Aerospace fastener applications_part2_r2010
 
Ludwig van Beethoven
Ludwig van BeethovenLudwig van Beethoven
Ludwig van Beethoven
 
Banked turn and its effects on Stall speed of an Airplane
Banked turn and its effects on Stall speed of an AirplaneBanked turn and its effects on Stall speed of an Airplane
Banked turn and its effects on Stall speed of an Airplane
 
Sylvia plath: Her Life and Sufferings
Sylvia plath: Her Life and SufferingsSylvia plath: Her Life and Sufferings
Sylvia plath: Her Life and Sufferings
 
Saudi Aramco Engineering Procedures (SAEP)1
Saudi Aramco Engineering Procedures (SAEP)1Saudi Aramco Engineering Procedures (SAEP)1
Saudi Aramco Engineering Procedures (SAEP)1
 
Decoding shakespeare
Decoding shakespeareDecoding shakespeare
Decoding shakespeare
 

Viewers also liked

Short circuit
Short circuit   Short circuit
Short circuit
Maria Romina Angustia
 
Sudden three phase short-circuit test
Sudden three phase short-circuit testSudden three phase short-circuit test
Sudden three phase short-circuit testDonald Stephen
 
Electrical power ecx3232 lab report
Electrical power ecx3232 lab reportElectrical power ecx3232 lab report
Electrical power ecx3232 lab reportSandun Perera
 
Series and parallel circuit
Series and parallel circuitSeries and parallel circuit
Series and parallel circuit
Noman Rajput
 
Sc and oc test on transformer
Sc and oc test on transformerSc and oc test on transformer
Sc and oc test on transformer
Pooja Dubey
 
Electrical machine lab
Electrical machine labElectrical machine lab
Electrical machine lab
DHEERAJ DHAKAR
 
7.3 series and parallel circuits
7.3 series and parallel circuits7.3 series and parallel circuits
7.3 series and parallel circuits
Adlishah Risal Bili
 
open circuit and short circuit test on transformer
open circuit and short circuit test on transformeropen circuit and short circuit test on transformer
open circuit and short circuit test on transformer
MILAN MANAVAR
 
Transformer testing
Transformer testingTransformer testing
Transformer testingajayknows
 

Viewers also liked (9)

Short circuit
Short circuit   Short circuit
Short circuit
 
Sudden three phase short-circuit test
Sudden three phase short-circuit testSudden three phase short-circuit test
Sudden three phase short-circuit test
 
Electrical power ecx3232 lab report
Electrical power ecx3232 lab reportElectrical power ecx3232 lab report
Electrical power ecx3232 lab report
 
Series and parallel circuit
Series and parallel circuitSeries and parallel circuit
Series and parallel circuit
 
Sc and oc test on transformer
Sc and oc test on transformerSc and oc test on transformer
Sc and oc test on transformer
 
Electrical machine lab
Electrical machine labElectrical machine lab
Electrical machine lab
 
7.3 series and parallel circuits
7.3 series and parallel circuits7.3 series and parallel circuits
7.3 series and parallel circuits
 
open circuit and short circuit test on transformer
open circuit and short circuit test on transformeropen circuit and short circuit test on transformer
open circuit and short circuit test on transformer
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
 

Similar to Open circuit saturation test

Sustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent testSustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent testDonald Stephen
 
Determination of the transient open circuit time constant
Determination of the transient open circuit time constantDetermination of the transient open circuit time constant
Determination of the transient open circuit time constant
Donald Stephen
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100
Ali Sepehri
 
Load test
Load testLoad test
Load test
Donald Stephen
 
Line to-line sustained short-circuit test
Line to-line sustained short-circuit testLine to-line sustained short-circuit test
Line to-line sustained short-circuit testDonald Stephen
 
Instrumentation & Control Lab Manual.pdf
Instrumentation & Control Lab Manual.pdfInstrumentation & Control Lab Manual.pdf
Instrumentation & Control Lab Manual.pdf
NTU Faisalabad
 
mechine vibration diagnotics for beginer
mechine vibration diagnotics for beginermechine vibration diagnotics for beginer
mechine vibration diagnotics for beginer
Angga896790
 
Hioki solution car_industry_ denkei
Hioki solution car_industry_ denkeiHioki solution car_industry_ denkei
Hioki solution car_industry_ denkei
NIHON DENKEI SINGAPORE
 
Temperature rise test
Temperature rise testTemperature rise test
Temperature rise test
Donald Stephen
 
Basic instrumentation-measuring-devices-and-basic-pid-control
Basic instrumentation-measuring-devices-and-basic-pid-controlBasic instrumentation-measuring-devices-and-basic-pid-control
Basic instrumentation-measuring-devices-and-basic-pid-control
Tutul .
 
Basic instrumentation
Basic instrumentationBasic instrumentation
Basic instrumentation
Kusuma Zulyanto
 
Cfakepathbasic instrumentation-measuring-devices-and-basic-pid-control-091029...
Cfakepathbasic instrumentation-measuring-devices-and-basic-pid-control-091029...Cfakepathbasic instrumentation-measuring-devices-and-basic-pid-control-091029...
Cfakepathbasic instrumentation-measuring-devices-and-basic-pid-control-091029...
Shamim Osman
 
Measurement of winding resistances
Measurement of winding resistancesMeasurement of winding resistances
Measurement of winding resistancesDonald Stephen
 
Basics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud DetectionBasics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud Detection
Abhisek Swain
 
Sun vat 40 ops-1979
Sun vat 40 ops-1979Sun vat 40 ops-1979
Sun vat 40 ops-1979
MartinJorgeDiazGarci1
 
Wash machine test equipment
Wash machine test equipmentWash machine test equipment
Wash machine test equipment
Sangone Kim
 
Basic instrumentation
Basic instrumentationBasic instrumentation
Basic instrumentationss61
 
Condition monitoring of induction motor with a case study
Condition monitoring of induction motor with a case studyCondition monitoring of induction motor with a case study
Condition monitoring of induction motor with a case study
IAEME Publication
 
Condition monitoring of induction motor with a case study
Condition monitoring of induction motor with a case studyCondition monitoring of induction motor with a case study
Condition monitoring of induction motor with a case study
IAEME Publication
 

Similar to Open circuit saturation test (20)

Sustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent testSustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent test
 
Determination of the transient open circuit time constant
Determination of the transient open circuit time constantDetermination of the transient open circuit time constant
Determination of the transient open circuit time constant
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100
 
Load test
Load testLoad test
Load test
 
Line to-line sustained short-circuit test
Line to-line sustained short-circuit testLine to-line sustained short-circuit test
Line to-line sustained short-circuit test
 
Instrumentation & Control Lab Manual.pdf
Instrumentation & Control Lab Manual.pdfInstrumentation & Control Lab Manual.pdf
Instrumentation & Control Lab Manual.pdf
 
mechine vibration diagnotics for beginer
mechine vibration diagnotics for beginermechine vibration diagnotics for beginer
mechine vibration diagnotics for beginer
 
Hioki solution car_industry_ denkei
Hioki solution car_industry_ denkeiHioki solution car_industry_ denkei
Hioki solution car_industry_ denkei
 
Temperature rise test
Temperature rise testTemperature rise test
Temperature rise test
 
Basic instrumentation-measuring-devices-and-basic-pid-control
Basic instrumentation-measuring-devices-and-basic-pid-controlBasic instrumentation-measuring-devices-and-basic-pid-control
Basic instrumentation-measuring-devices-and-basic-pid-control
 
Basic instrumentation
Basic instrumentationBasic instrumentation
Basic instrumentation
 
Cfakepathbasic instrumentation-measuring-devices-and-basic-pid-control-091029...
Cfakepathbasic instrumentation-measuring-devices-and-basic-pid-control-091029...Cfakepathbasic instrumentation-measuring-devices-and-basic-pid-control-091029...
Cfakepathbasic instrumentation-measuring-devices-and-basic-pid-control-091029...
 
Measurement of winding resistances
Measurement of winding resistancesMeasurement of winding resistances
Measurement of winding resistances
 
Basic Instrument PID
Basic Instrument PID Basic Instrument PID
Basic Instrument PID
 
Basics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud DetectionBasics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud Detection
 
Sun vat 40 ops-1979
Sun vat 40 ops-1979Sun vat 40 ops-1979
Sun vat 40 ops-1979
 
Wash machine test equipment
Wash machine test equipmentWash machine test equipment
Wash machine test equipment
 
Basic instrumentation
Basic instrumentationBasic instrumentation
Basic instrumentation
 
Condition monitoring of induction motor with a case study
Condition monitoring of induction motor with a case studyCondition monitoring of induction motor with a case study
Condition monitoring of induction motor with a case study
 
Condition monitoring of induction motor with a case study
Condition monitoring of induction motor with a case studyCondition monitoring of induction motor with a case study
Condition monitoring of induction motor with a case study
 

More from Donald Stephen

Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report formDonald Stephen
 
Stator insulation test setup
Stator insulation test setupStator insulation test setup
Stator insulation test setupDonald Stephen
 
Stator core induction test
Stator core induction testStator core induction test
Stator core induction testDonald Stephen
 
Stator core compr test
Stator core compr testStator core compr test
Stator core compr test
Donald Stephen
 
Rotor insul test setup
Rotor insul test setupRotor insul test setup
Rotor insul test setup
Donald Stephen
 
Measurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsMeasurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsDonald Stephen
 
Measurement of partial discharges
Measurement of partial dischargesMeasurement of partial discharges
Measurement of partial dischargesDonald Stephen
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta test
Donald Stephen
 
Insulation resistance testing
Insulation resistance testingInsulation resistance testing
Insulation resistance testing
Donald Stephen
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance test
Donald Stephen
 
Impedance measurement of field windings
Impedance measurement of field windingsImpedance measurement of field windings
Impedance measurement of field windings
Donald Stephen
 
High potential test
High potential testHigh potential test
High potential test
Donald Stephen
 
Efficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodEfficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric method
Donald Stephen
 
Determination of inertia by load rejection
Determination of inertia by load rejectionDetermination of inertia by load rejection
Determination of inertia by load rejection
Donald Stephen
 
Core deffect detector
Core deffect detectorCore deffect detector
Core deffect detector
Donald Stephen
 
Check pole connector
Check pole connectorCheck pole connector
Check pole connector
Donald Stephen
 
Future strategic-issues-and-warfare
Future strategic-issues-and-warfareFuture strategic-issues-and-warfare
Future strategic-issues-and-warfare
Donald Stephen
 
Participants 2009 bilderberg meetings
Participants 2009   bilderberg meetingsParticipants 2009   bilderberg meetings
Participants 2009 bilderberg meetings
Donald Stephen
 

More from Donald Stephen (20)

Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report form
 
Stator insulation test setup
Stator insulation test setupStator insulation test setup
Stator insulation test setup
 
Stator core induction test
Stator core induction testStator core induction test
Stator core induction test
 
Stator core compr test
Stator core compr testStator core compr test
Stator core compr test
 
Rotor insul test setup
Rotor insul test setupRotor insul test setup
Rotor insul test setup
 
Noise measurement
Noise measurementNoise measurement
Noise measurement
 
Measurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsMeasurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearings
 
Measurement of partial discharges
Measurement of partial dischargesMeasurement of partial discharges
Measurement of partial discharges
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta test
 
Insulation resistance testing
Insulation resistance testingInsulation resistance testing
Insulation resistance testing
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance test
 
Impedance measurement of field windings
Impedance measurement of field windingsImpedance measurement of field windings
Impedance measurement of field windings
 
High potential test
High potential testHigh potential test
High potential test
 
Efficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodEfficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric method
 
Determination of inertia by load rejection
Determination of inertia by load rejectionDetermination of inertia by load rejection
Determination of inertia by load rejection
 
Crack monitor
Crack monitorCrack monitor
Crack monitor
 
Core deffect detector
Core deffect detectorCore deffect detector
Core deffect detector
 
Check pole connector
Check pole connectorCheck pole connector
Check pole connector
 
Future strategic-issues-and-warfare
Future strategic-issues-and-warfareFuture strategic-issues-and-warfare
Future strategic-issues-and-warfare
 
Participants 2009 bilderberg meetings
Participants 2009   bilderberg meetingsParticipants 2009   bilderberg meetings
Participants 2009 bilderberg meetings
 

Recently uploaded

Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
top1002
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 

Recently uploaded (20)

Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 

Open circuit saturation test

  • 1. Open Circuit saturation test Table of Content: 1 Objective................................................................................................... 2 Scope........................................................................................................ 3 Referenced Documents ............................................................................ 4 Definitions and Abbreviations.................................................................... 5 Preparation................................................................................................ 6 Conduction of test .................................................................................... 7 Proceeding in case of deviations............................................................... 8 Copyright................................................................................................... 1 Objective This procedure describes the open-circuit (no-load) test, which is performed to establish the relationship between the voltage at the terminals of the open-circuited armature winding and the excitation current. From the measurement data of the open-circuit test the following machine characteristics and quantities are determined: - open circuit saturation characteristic (with separate and/or brushless excitation) - direct-axis synchronous reactance Xd - short-circuit ratio Kc - Potier reactance Xp rated voltage regulation ∆UN Note: During the open-circuit test also the follow ing quantities are measured (see corresponding procedures): - Shaft voltage (with saturation characteristic) - Balance of phases (at rated voltage) - Voltage wave form, harmonic analysis and THF-factor (at rated voltage) - Residual voltage - Sequence of phases (preferably at residual voltage) - Constant losses for turbogenerators w ith calibrated machine method (loss curve, included in Short Commercial Test for GE orders) - Vibration (at rated voltage) - Noise (at rated voltage) 2 Scope All types of synchronous machines during final tests in workshop or at site. 3 Referenced Documents IEC 34-4, 25*), 27 (EN 60034-4, 25, 27) IEEE Std. 115, 4.2.5 Page 1 of 3
  • 2. 4 Definitions and Abbreviations None. 5 Preparation - Set the generator in the three-phase armature winding open-circuit condition - Install the precision instruments for the armature voltage and field current measurement respectively. - The voltage should be measured with potential transformers - Check electrical clearances around generator terminals. - For work shop tests either install temporary slip rings for separate excitation, or install a rotating shunt with a signal transmission system for the shunt voltage drop (telemetric system or measuring slip rings). 6 Conduction of test - Operate the unit at rated speed with the manual control of the excitation system Note: When a prime mover is not available, this test can be conducted acc. IEC 34-4 *), running the machine as a motor (unity power factor test) or during OC-excited retardation. - Supply small field current and check that instruments, excitation system and generator are in the proper condition - After that, gradually change field current and measure armature voltages and field currents. If not otherwise specified in the contract, measurement voltage steps shall be app. 10 % UN. - Maximum armature voltage is limited to 130 % of the rated armature voltage, however with turbogenerators do not exceed 120 % UN. - Readings shall be taken at increasing excitation currents, from residual to maximum voltage, continuing with decreasing excitation currents as well - During the OC-tests, the field current should not exceed the rated value either. - Check the armature voltage balance in the three phases at approximately rated voltage. The voltages on each phase should be the same ±1 %. - When the saturation characteristic has been measured with separate excitation, repeat with excitation from own exciter (brushless), after the original state of the excitation system is reestablished. - Measure the shaft voltage - At residual voltage level check the sequence of the voltages on the generator terminals with phase sequence meter. Time sequence of phases must be in correspondence to the terminal numbering and the sense of rotation of the rotor as specified in the contract. Page 2 of 3
  • 3. Appendix for site testing: - When a work shop test was performed but the OC-test is repeated on site (this holds generally for commissioning of turbogenerators), it is sufficient to measure only one (or a few points), including approximately rated voltage, in order to check correspondence with the originally measured characteristic and verify balance of generated voltages. For comparison data see the original test report of the tested machine, or the type test report of another machine and exciter of the same design. Sometimes temporary slip rings are not installed on site, so field current cannot be measured directly. Only a rough check of the excitation current will be possible by measuring the field current of the exciter machine. - Excitation of the generator is from its own exciter (brushless) or from an external (static) excitation system as appropriate. - Secondary voltages are taken from the potential transformers installed in the plant. 7 Proceeding in case of deviations Any nominal value, minimum value, maximum value, tolerance etc given in an instruction is intended to serve for quality control purposes only. In the case of deviations, a nonconformity report has to be written according to PNG Power Standard. 8 Copyright This Document is properly of PNG Power internal use only and must neither be copied. Neither is it to be handed over nor in other way communicated to a third party. Infringement will lead to prosecution. Page 3 of 3