SlideShare a Scribd company logo
1 of 4
Determination of the transient open-circuit time constant τdo´
Table of Content:
1 Objective.............................................................................................................
2 Scope..................................................................................................................
3 Referenced Documents.......................................................................................
4 Definitions and Abbreviations..............................................................................
5 Voltage Recovery Test .......................................................................................
5.1 Preparation......................................................................................................
5.2 Conduction of voltage recovery test ................................................................
6 Field Current Decay Test....................................................................................
6.1 Preparation.......................................................................................................
6.2 Conduction of test.........................................................................................
7 Evaluation of test ................................................................................................
8 Proceeding in case of deviations ........................................................................
1 Objective
This procedure defines the tests to be performed for the determination of the following
machine quantities:
- direct-axis transient open-circuit time constant τBdoB´
- direct-axis open-circuit subtransient time constant τBdoB´´
2 Scope
This procedure applies to all types of synchronous machines during final testing in the
work shop or at site. This test is performed as a type test, i.e. only on one machine out of
two or more units with same or almost similar design.
Two measuring methods may be used as convenient:
− Voltage recovery test
This method is preferably used on site with HYDRO-generators. It must be used with
generators having brushless excitation and when no temporary slip rings are mounted.
− Field current decay test with armature winding open-circuited
This test requires either static excitation or mounting of temporary slip rings for separate
excitation, since external circuit elements (like the short-circuit breaker and an eventual
current limiting resistor) cannot be inserted into the rotor circuit.
3 Referenced Documents
IEC 34-4, 42, 43 or 58, 59
EN 60034-4, 42, 43 or 58, 59
IEEE 115, 11.10.5 (Method 4) or 11.10.1.1 (Method 1)
HTUP GEN QC3 6119DEUTH Sudden three-phase short-circuit test
4 Definitions and Abbreviations
None
Page 1 of 4
5 Voltage Recovery Test
5.1 Preparation
The voltage recovery test is initiated after disconnection of a sustained three-phase
short-circuit.
It is usually performed immediately after the three-phase sudden short-circuit test, using
the plant circuit breaker to open the short-circuit.
In our work shop this test has to be carried out as an individual test, since the short-
circuit maker available in the Weiz test field cannot be reopened under load.
Preparatory work is similar to the procedure for the sudden short-circuit test (see also
P GEN QC3 6119DE).
Activities for work shop test only:
- disconnect the power cables between the line terminals and the short-circuit maker
- connect power cables between the line terminals and the circuit breaker used for this
test (Note: this c.b. must be capable of being reopened under load).
For site test only:
- connect power cables between the line terminals and the circuit breaker (this is not
necessary when the plant c.b. can be used)
For both work shop and site tests:
- install measuring devices. Recording instruments will be the same as used for the
sudden short-circuit test.
- connect output signals of armature p.t´s and one armature c.t. to the recorder
- calibrate and set trigger of the recording instruments to expected levels
5.2 Conduction of voltage recovery test
- operate the unit at rated speed in a sustained three-phase short-circuit condition, with
the excitation set according to approx. 0,5 Un no-load voltage
- reopen the circuit breaker to inititate the voltage recovery
- record one voltage and armature current until steady state has been reached (usually
after about 30 s).
- review the osilloscope data to make sure that data was captured correctly.
6 Field Current Decay Test
6.1 Preparation
The measuring circuit is set up according to fig. 1. Essential circuit elements are:
- Closing/opening contacts (S1/S2) of the switch activated by the same shaft.
- Slip rings (main or temporary)
- Measuring shunt for field current
- Static excitation equipment: The de-excitation resistor must be short-circuited for the
duration of this test. The test may be performed in current regulation mode.
6.2 Conduction of test
The machine is driven at rated speed with armature winding open-circuited and excited
to rated voltage. In normal operation, S1 is in closed position and S2 open. The
Page 2 of 4
excitation winding is then suddenly short circuited by closing first contact S2 and
immediately afterwards opening S1.
Decaying armature voltage, excitation current and slip ring voltage are recorded till
steady state.
Note: Activating EMERGENCY OFF of the static excitation equipment will trip the de-
excitation contactor and normally would insert the de-excitation resistor into the circuit.
However, this is shorted for this test and thus will also completely short-circuit the field
winding.
Since the excitation circuit must never come open, the de-excitation contactor will at the
same time bridge the excitation equipment for the short time element of the switch, so
that it will not take harm. The excitation will be automatically down regulated to zero.
7 Evaluation of test
− Mathematical or graphical evaluation follows the procedure given in the pertinent
standard.
− Evaluation procedure both for transient and subtransient time constants is analogous
to the evaluation of the sudden short-circuit test.
− Evaluation procedure is analogous for both measuring methods.
Note: After elapsing of 3 τBdoB´, the transient voltage component will have decreased to
approx. 0,05 of its initial value. When plotting the envelope of the decaying characteristic
against time on a semi-log scale, it may be more comfortable and accurate to use this
ordinate rather than the one after 1 τBdoB´ which must be interpolated to 0.368.
8 Proceeding in case of deviations
Page 3 of 4
Any nominal value, minimum value, maximum value, tolerance etc given in an instruction
is intended to serve for quality control purposes only. In the case of deviations, a
nonconformity report has to be written according to PNG Power Standard
Page 4 of 4

More Related Content

What's hot

Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, IndiaRajuMondal18
 
Pre commissioning checks & periodic inspection on power transformers
Pre commissioning checks & periodic inspection  on power transformersPre commissioning checks & periodic inspection  on power transformers
Pre commissioning checks & periodic inspection on power transformersayyadurai SHANMUGAM
 
Types of load cell and principle
Types of load cell and principle Types of load cell and principle
Types of load cell and principle Mostafa Ragab
 
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION RajuGupta88
 
Transformer testing on sight and off sight
Transformer testing on sight and off sightTransformer testing on sight and off sight
Transformer testing on sight and off sightDHAVALKUMAR JULASANA
 
Transformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisTransformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisHamedPasha1
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100Ali Sepehri
 
Ls catalog thiet bi tu dong dpr 1000-e_dienhathe.vn
Ls catalog thiet bi tu dong dpr 1000-e_dienhathe.vnLs catalog thiet bi tu dong dpr 1000-e_dienhathe.vn
Ls catalog thiet bi tu dong dpr 1000-e_dienhathe.vnDien Ha The
 
Troubleshooting and fault analysis
Troubleshooting and fault analysisTroubleshooting and fault analysis
Troubleshooting and fault analysisanithaa34
 
Transformer Oil Testing services
Transformer Oil Testing servicesTransformer Oil Testing services
Transformer Oil Testing servicesPower Electronical
 
TRANSFORMER TEST acceptance criteria
TRANSFORMER TEST acceptance criteriaTRANSFORMER TEST acceptance criteria
TRANSFORMER TEST acceptance criteriaRajuGupta88
 
High voltage testing of electrical transformer
High voltage testing of electrical transformerHigh voltage testing of electrical transformer
High voltage testing of electrical transformerPraveenKumar5880
 
Final instrumentation lab manual
Final instrumentation lab manualFinal instrumentation lab manual
Final instrumentation lab manualkishorereddy_btech
 
Operation and maintenance of transformer
Operation and maintenance of transformerOperation and maintenance of transformer
Operation and maintenance of transformerKapil Singh
 
Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)Rohini Haridas
 

What's hot (19)

Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
 
Pre commissioning checks & periodic inspection on power transformers
Pre commissioning checks & periodic inspection  on power transformersPre commissioning checks & periodic inspection  on power transformers
Pre commissioning checks & periodic inspection on power transformers
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
POINT ON WAVE SWITCHING
POINT ON WAVE SWITCHINGPOINT ON WAVE SWITCHING
POINT ON WAVE SWITCHING
 
Types of load cell and principle
Types of load cell and principle Types of load cell and principle
Types of load cell and principle
 
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION
TRANSFORMER SAMPLE REPORT DGA PHYSICAL CONDITION
 
Transformer testing on sight and off sight
Transformer testing on sight and off sightTransformer testing on sight and off sight
Transformer testing on sight and off sight
 
Transformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisTransformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response Analysis
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100
 
Ls catalog thiet bi tu dong dpr 1000-e_dienhathe.vn
Ls catalog thiet bi tu dong dpr 1000-e_dienhathe.vnLs catalog thiet bi tu dong dpr 1000-e_dienhathe.vn
Ls catalog thiet bi tu dong dpr 1000-e_dienhathe.vn
 
Ne555
Ne555Ne555
Ne555
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
Troubleshooting and fault analysis
Troubleshooting and fault analysisTroubleshooting and fault analysis
Troubleshooting and fault analysis
 
Transformer Oil Testing services
Transformer Oil Testing servicesTransformer Oil Testing services
Transformer Oil Testing services
 
TRANSFORMER TEST acceptance criteria
TRANSFORMER TEST acceptance criteriaTRANSFORMER TEST acceptance criteria
TRANSFORMER TEST acceptance criteria
 
High voltage testing of electrical transformer
High voltage testing of electrical transformerHigh voltage testing of electrical transformer
High voltage testing of electrical transformer
 
Final instrumentation lab manual
Final instrumentation lab manualFinal instrumentation lab manual
Final instrumentation lab manual
 
Operation and maintenance of transformer
Operation and maintenance of transformerOperation and maintenance of transformer
Operation and maintenance of transformer
 
Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)
 

Viewers also liked

Insulation resistance testing
Insulation resistance testingInsulation resistance testing
Insulation resistance testingDonald Stephen
 
Techniques for Improving Element Bandwidth
Techniques for Improving Element BandwidthTechniques for Improving Element Bandwidth
Techniques for Improving Element Bandwidthashish patil
 
Electromagnetic induction (2)
Electromagnetic induction (2)Electromagnetic induction (2)
Electromagnetic induction (2)mrmeredith
 
Out-of-Core Construction of Sparse Voxel Octrees
Out-of-Core Construction of Sparse Voxel OctreesOut-of-Core Construction of Sparse Voxel Octrees
Out-of-Core Construction of Sparse Voxel OctreesJeroen Baert
 
3.8 the 1931 cie s ystem
3.8 the 1931 cie s ystem3.8 the 1931 cie s ystem
3.8 the 1931 cie s ystemQC Labs
 
Faraday's law 333
Faraday's law 333Faraday's law 333
Faraday's law 333zonesid
 
Significant Figures
Significant FiguresSignificant Figures
Significant Figurescrespiryan
 
Medical physics slide show
Medical physics slide showMedical physics slide show
Medical physics slide showNengah Surata
 
Medical applications of nuclear physics
Medical applications of nuclear physicsMedical applications of nuclear physics
Medical applications of nuclear physicsRad Tech
 
AC & DC Generators
AC & DC GeneratorsAC & DC Generators
AC & DC GeneratorsAfrah Aamer
 
Mechanical sensor
Mechanical sensorMechanical sensor
Mechanical sensorB.k. Das
 
Megger (mega-ohm-meter)
Megger (mega-ohm-meter)Megger (mega-ohm-meter)
Megger (mega-ohm-meter)Kausik das
 
Magnetic field sensing
Magnetic field sensingMagnetic field sensing
Magnetic field sensingZaahir Salam
 
Insulation Resistance Testing / Megger
Insulation Resistance Testing / Megger Insulation Resistance Testing / Megger
Insulation Resistance Testing / Megger Roland Manansala
 
Electromagnetic Induction Class 12
Electromagnetic Induction Class 12 Electromagnetic Induction Class 12
Electromagnetic Induction Class 12 Self-employed
 
Capacitance and capacitor
Capacitance and capacitorCapacitance and capacitor
Capacitance and capacitorTouqeer Jumani
 

Viewers also liked (20)

Insulation resistance testing
Insulation resistance testingInsulation resistance testing
Insulation resistance testing
 
Shahid
ShahidShahid
Shahid
 
Techniques for Improving Element Bandwidth
Techniques for Improving Element BandwidthTechniques for Improving Element Bandwidth
Techniques for Improving Element Bandwidth
 
Electromagnetic induction (2)
Electromagnetic induction (2)Electromagnetic induction (2)
Electromagnetic induction (2)
 
Out-of-Core Construction of Sparse Voxel Octrees
Out-of-Core Construction of Sparse Voxel OctreesOut-of-Core Construction of Sparse Voxel Octrees
Out-of-Core Construction of Sparse Voxel Octrees
 
3.8 the 1931 cie s ystem
3.8 the 1931 cie s ystem3.8 the 1931 cie s ystem
3.8 the 1931 cie s ystem
 
Ch10 ln
Ch10 lnCh10 ln
Ch10 ln
 
Faraday's law 333
Faraday's law 333Faraday's law 333
Faraday's law 333
 
Significant Figures
Significant FiguresSignificant Figures
Significant Figures
 
CAT
CATCAT
CAT
 
Medical physics slide show
Medical physics slide showMedical physics slide show
Medical physics slide show
 
Medical applications of nuclear physics
Medical applications of nuclear physicsMedical applications of nuclear physics
Medical applications of nuclear physics
 
AC & DC Generators
AC & DC GeneratorsAC & DC Generators
AC & DC Generators
 
Mechanical sensor
Mechanical sensorMechanical sensor
Mechanical sensor
 
Megger (mega-ohm-meter)
Megger (mega-ohm-meter)Megger (mega-ohm-meter)
Megger (mega-ohm-meter)
 
Physics (significant figures)
Physics (significant figures)Physics (significant figures)
Physics (significant figures)
 
Magnetic field sensing
Magnetic field sensingMagnetic field sensing
Magnetic field sensing
 
Insulation Resistance Testing / Megger
Insulation Resistance Testing / Megger Insulation Resistance Testing / Megger
Insulation Resistance Testing / Megger
 
Electromagnetic Induction Class 12
Electromagnetic Induction Class 12 Electromagnetic Induction Class 12
Electromagnetic Induction Class 12
 
Capacitance and capacitor
Capacitance and capacitorCapacitance and capacitor
Capacitance and capacitor
 

Similar to Determination of the transient open circuit time constant

Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalNihal Shiroya
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakersKabilesh K
 
Electrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptxElectrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptxPritishPachhapure1
 
Line to-line sustained short-circuit test
Line to-line sustained short-circuit testLine to-line sustained short-circuit test
Line to-line sustained short-circuit testDonald Stephen
 
Chapter 57
Chapter 57Chapter 57
Chapter 57mcfalltj
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - labPremanandDesai
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushingNovia Putri
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSatish Pydimarla
 
Design and development of grid tie inverter with closed loop spwm single stag...
Design and development of grid tie inverter with closed loop spwm single stag...Design and development of grid tie inverter with closed loop spwm single stag...
Design and development of grid tie inverter with closed loop spwm single stag...eSAT Journals
 
Basics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud DetectionBasics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud DetectionAbhisek Swain
 
Zero setting PSB protection_CBIP
Zero setting PSB protection_CBIPZero setting PSB protection_CBIP
Zero setting PSB protection_CBIPBadal Patnaik
 

Similar to Determination of the transient open circuit time constant (20)

Testing of cb
Testing of cbTesting of cb
Testing of cb
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
 
Abb lv breakers working with trip curves
Abb lv breakers working with trip curvesAbb lv breakers working with trip curves
Abb lv breakers working with trip curves
 
Electrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptxElectrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptx
 
POINT ON WAVE SWITCHING
POINT ON WAVE SWITCHINGPOINT ON WAVE SWITCHING
POINT ON WAVE SWITCHING
 
Line to-line sustained short-circuit test
Line to-line sustained short-circuit testLine to-line sustained short-circuit test
Line to-line sustained short-circuit test
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Time current curves
Time current curvesTime current curves
Time current curves
 
High voltage
High voltageHigh voltage
High voltage
 
Chapter 57
Chapter 57Chapter 57
Chapter 57
 
Electrical testing
Electrical testingElectrical testing
Electrical testing
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - lab
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptx
 
Design and development of grid tie inverter with closed loop spwm single stag...
Design and development of grid tie inverter with closed loop spwm single stag...Design and development of grid tie inverter with closed loop spwm single stag...
Design and development of grid tie inverter with closed loop spwm single stag...
 
Basics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud DetectionBasics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud Detection
 
Fundamentals of Field Testing Meters
Fundamentals of Field Testing MetersFundamentals of Field Testing Meters
Fundamentals of Field Testing Meters
 
Zero setting PSB protection_CBIP
Zero setting PSB protection_CBIPZero setting PSB protection_CBIP
Zero setting PSB protection_CBIP
 
Sharp 32 pulg 32c24
Sharp 32 pulg 32c24Sharp 32 pulg 32c24
Sharp 32 pulg 32c24
 

More from Donald Stephen

Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report formDonald Stephen
 
Stator insulation test setup
Stator insulation test setupStator insulation test setup
Stator insulation test setupDonald Stephen
 
Stator core induction test
Stator core induction testStator core induction test
Stator core induction testDonald Stephen
 
Stator core compr test
Stator core compr testStator core compr test
Stator core compr testDonald Stephen
 
Rotor insul test setup
Rotor insul test setupRotor insul test setup
Rotor insul test setupDonald Stephen
 
Measurement of winding resistances
Measurement of winding resistancesMeasurement of winding resistances
Measurement of winding resistancesDonald Stephen
 
Measurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsMeasurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsDonald Stephen
 
Measurement of partial discharges
Measurement of partial dischargesMeasurement of partial discharges
Measurement of partial dischargesDonald Stephen
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta testDonald Stephen
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance testDonald Stephen
 
Impedance measurement of field windings
Impedance measurement of field windingsImpedance measurement of field windings
Impedance measurement of field windingsDonald Stephen
 
Efficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodEfficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodDonald Stephen
 
Determination of inertia by load rejection
Determination of inertia by load rejectionDetermination of inertia by load rejection
Determination of inertia by load rejectionDonald Stephen
 
Future strategic-issues-and-warfare
Future strategic-issues-and-warfareFuture strategic-issues-and-warfare
Future strategic-issues-and-warfareDonald Stephen
 

More from Donald Stephen (20)

Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report form
 
Stator insulation test setup
Stator insulation test setupStator insulation test setup
Stator insulation test setup
 
Stator core induction test
Stator core induction testStator core induction test
Stator core induction test
 
Stator core compr test
Stator core compr testStator core compr test
Stator core compr test
 
Rotor insul test setup
Rotor insul test setupRotor insul test setup
Rotor insul test setup
 
Noise measurement
Noise measurementNoise measurement
Noise measurement
 
Measurement of winding resistances
Measurement of winding resistancesMeasurement of winding resistances
Measurement of winding resistances
 
Measurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsMeasurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearings
 
Measurement of partial discharges
Measurement of partial dischargesMeasurement of partial discharges
Measurement of partial discharges
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta test
 
Load test
Load testLoad test
Load test
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance test
 
Impedance measurement of field windings
Impedance measurement of field windingsImpedance measurement of field windings
Impedance measurement of field windings
 
Efficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodEfficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric method
 
Determination of inertia by load rejection
Determination of inertia by load rejectionDetermination of inertia by load rejection
Determination of inertia by load rejection
 
Crack monitor
Crack monitorCrack monitor
Crack monitor
 
Core deffect detector
Core deffect detectorCore deffect detector
Core deffect detector
 
Check pole connector
Check pole connectorCheck pole connector
Check pole connector
 
Temperature rise test
Temperature rise testTemperature rise test
Temperature rise test
 
Future strategic-issues-and-warfare
Future strategic-issues-and-warfareFuture strategic-issues-and-warfare
Future strategic-issues-and-warfare
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

Determination of the transient open circuit time constant

  • 1. Determination of the transient open-circuit time constant τdo´ Table of Content: 1 Objective............................................................................................................. 2 Scope.................................................................................................................. 3 Referenced Documents....................................................................................... 4 Definitions and Abbreviations.............................................................................. 5 Voltage Recovery Test ....................................................................................... 5.1 Preparation...................................................................................................... 5.2 Conduction of voltage recovery test ................................................................ 6 Field Current Decay Test.................................................................................... 6.1 Preparation....................................................................................................... 6.2 Conduction of test......................................................................................... 7 Evaluation of test ................................................................................................ 8 Proceeding in case of deviations ........................................................................ 1 Objective This procedure defines the tests to be performed for the determination of the following machine quantities: - direct-axis transient open-circuit time constant τBdoB´ - direct-axis open-circuit subtransient time constant τBdoB´´ 2 Scope This procedure applies to all types of synchronous machines during final testing in the work shop or at site. This test is performed as a type test, i.e. only on one machine out of two or more units with same or almost similar design. Two measuring methods may be used as convenient: − Voltage recovery test This method is preferably used on site with HYDRO-generators. It must be used with generators having brushless excitation and when no temporary slip rings are mounted. − Field current decay test with armature winding open-circuited This test requires either static excitation or mounting of temporary slip rings for separate excitation, since external circuit elements (like the short-circuit breaker and an eventual current limiting resistor) cannot be inserted into the rotor circuit. 3 Referenced Documents IEC 34-4, 42, 43 or 58, 59 EN 60034-4, 42, 43 or 58, 59 IEEE 115, 11.10.5 (Method 4) or 11.10.1.1 (Method 1) HTUP GEN QC3 6119DEUTH Sudden three-phase short-circuit test 4 Definitions and Abbreviations None Page 1 of 4
  • 2. 5 Voltage Recovery Test 5.1 Preparation The voltage recovery test is initiated after disconnection of a sustained three-phase short-circuit. It is usually performed immediately after the three-phase sudden short-circuit test, using the plant circuit breaker to open the short-circuit. In our work shop this test has to be carried out as an individual test, since the short- circuit maker available in the Weiz test field cannot be reopened under load. Preparatory work is similar to the procedure for the sudden short-circuit test (see also P GEN QC3 6119DE). Activities for work shop test only: - disconnect the power cables between the line terminals and the short-circuit maker - connect power cables between the line terminals and the circuit breaker used for this test (Note: this c.b. must be capable of being reopened under load). For site test only: - connect power cables between the line terminals and the circuit breaker (this is not necessary when the plant c.b. can be used) For both work shop and site tests: - install measuring devices. Recording instruments will be the same as used for the sudden short-circuit test. - connect output signals of armature p.t´s and one armature c.t. to the recorder - calibrate and set trigger of the recording instruments to expected levels 5.2 Conduction of voltage recovery test - operate the unit at rated speed in a sustained three-phase short-circuit condition, with the excitation set according to approx. 0,5 Un no-load voltage - reopen the circuit breaker to inititate the voltage recovery - record one voltage and armature current until steady state has been reached (usually after about 30 s). - review the osilloscope data to make sure that data was captured correctly. 6 Field Current Decay Test 6.1 Preparation The measuring circuit is set up according to fig. 1. Essential circuit elements are: - Closing/opening contacts (S1/S2) of the switch activated by the same shaft. - Slip rings (main or temporary) - Measuring shunt for field current - Static excitation equipment: The de-excitation resistor must be short-circuited for the duration of this test. The test may be performed in current regulation mode. 6.2 Conduction of test The machine is driven at rated speed with armature winding open-circuited and excited to rated voltage. In normal operation, S1 is in closed position and S2 open. The Page 2 of 4
  • 3. excitation winding is then suddenly short circuited by closing first contact S2 and immediately afterwards opening S1. Decaying armature voltage, excitation current and slip ring voltage are recorded till steady state. Note: Activating EMERGENCY OFF of the static excitation equipment will trip the de- excitation contactor and normally would insert the de-excitation resistor into the circuit. However, this is shorted for this test and thus will also completely short-circuit the field winding. Since the excitation circuit must never come open, the de-excitation contactor will at the same time bridge the excitation equipment for the short time element of the switch, so that it will not take harm. The excitation will be automatically down regulated to zero. 7 Evaluation of test − Mathematical or graphical evaluation follows the procedure given in the pertinent standard. − Evaluation procedure both for transient and subtransient time constants is analogous to the evaluation of the sudden short-circuit test. − Evaluation procedure is analogous for both measuring methods. Note: After elapsing of 3 τBdoB´, the transient voltage component will have decreased to approx. 0,05 of its initial value. When plotting the envelope of the decaying characteristic against time on a semi-log scale, it may be more comfortable and accurate to use this ordinate rather than the one after 1 τBdoB´ which must be interpolated to 0.368. 8 Proceeding in case of deviations Page 3 of 4
  • 4. Any nominal value, minimum value, maximum value, tolerance etc given in an instruction is intended to serve for quality control purposes only. In the case of deviations, a nonconformity report has to be written according to PNG Power Standard Page 4 of 4