SlideShare a Scribd company logo
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
1-Jun-21 1
1
SEMINAR PRESENTATION
DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING
CHAITHANYA BHARATHI INSTITUTE OF TECHNOLOGY
GANDIPET, HYDERABAD
2014
Submitted by
K .V. V. Satyanarayana
Roll No: 1601-14-766-006
M. E (Power Systems & Power Electronics)
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
CONTENTS
1. Introduction
2. Bushings
3.System Description
4. Bushing monitoring
4.1.Capacitively controlled insulator bushings
4.2.Bushing capacitance C and dielectric dissipation factor tanδ.
4.3.Voltage sensor
4.4.Operating voltages and overvoltages
4.5Bush Capacitance
4.6.Dielectric dissipation factor tan δ and sum phasor
4.7.Bushing oil pressure
5.Insulation System And Tap Changer
6 Reference
1-Jun-21 2
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
I. INTRODUCTION
• A bushing must be designed to withstand the electrical field
strength produced in the insulation, when any earthed material is
present
• In a Oil-filled power transformers, their bushings, tap changer,
insulation system and auxiliary equipment are critical to the
operation of every electrical power system to such an extend that
their reliable and uninterrupted functioning is a key factor in
profitable generation, transmission and distribution.
• Recent years on-line monitoring systems have been installed in a
large scale at power transformers.
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
Causes Of Bushing Failures
1-Jun-21 4
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
Offline Buhing Test
Hence tests to be conducted & monitoring is done
1-Jun-21 5
Online Bushing Test
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
Bushing capacitance test
1-Jun-21 6
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
• The utilities network (Ethernet) can
transport the information from the
substation to every PC (web based
visualization)
• Starting from the strict point of view
of monitoring it is then proceed
forward with the presentation of
diagnostics, prognosis is done.
• The task of on-line monitoring is
then to provide focused, purposeful
diagnosis information, so that
remedial measures can be initiated if
needed should faults occur during
operation.
On-line visualization of transformer condition and its
information about trending, diagnostics and prognostics
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
II. SYSTEM DESCRIPTION
On-line monitoring system is employed
1. Ageing rate,
2. Overloading condition,
3. Change in the bushing capacitance
• Data acquisition is time-controlled and event controlled.
Thus,when a transformer is switched on, the voltages are recorded
for a duration of 10 seconds with a resolution of 20 ms.
• In comparison, the changes in the bushing capacitance are
sampled every 20 ms and saved every 15 minutes consequently the
size of the database is optimized.
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
A. Capacitively controlled insulator bushings
• In the voltage range from 110 kV upwards, modern bushings
are generally designed with closely stepped capacitive control
layers.
• Basic insulating systems of capacitive controlled high voltage
bushings can be classified as:
1. Resin-bonded paper bushings (RBP)
2. Resin-impregnated paper bushings (RIP)
3. Oil-impregnated paper bushings (OIP)
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
Bushing capacitance C and dielectric dissipation
factor (tan δ)
• Measurement of the bushing capacitance C and the dielectric
dissipation factor tan δ are important parameters for
evaluating the operational state of a high voltage bushing.
• dissipation factor
tan δ = 1/R C.
• Range of tan δ for normal operation
new resin-bonded paper bushing, it is in the range 0.5 ... 0.7 %.
resin-impregnated bushings, it is in the range 0.25 ... 0.45 %
oil-impregnated bushings, values between 0.25 ... 0.5%
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
Equivalent circuit diagram and vector diagram of
the dielectric loss factor tan δ
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
• Dielectric losses in the insulation result in a capacitive loss
current in the dielectric material.
• Depending on the ageing, the bushing capacitance and the tan
δ can change.
• Table below shows guide values for tan δ and capacitance
values as examples for resin bonded paper bushings.
• When these limiting values are reached, continued operation
is not recommended.
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
• Reasons for a change in the values of tan δ and ∆ C
External influences : moisture and dirt on the porcelain.
∆ C can also be caused by an oil-impregnation in the
case of resin-bonded paper bushings.
• Increase in the ∆ C for all bushing types indicates partial
breakdowns between control layers
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
C. Voltage sensor
• The monitoring of the electrical measurement quantities is achieved
with a voltage sensor . The sensor is connected directly to the
measurement tap of the bushing . This design allows a reliable
measurement with a bandwidth of up to 2 MHz
Bushing
Bushing voltage sensors installed on the
measurement tap of the bushings
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
• The sensor essentially consists of
capacitor Cm, which normally has values of 1 .. 2 µF.
1. Cm >> C2 (i.e C2 ≈ 300 pF), I2 is practically 0.
2. R terminates the coaxial cable with a surge impedance of 50 Ω.
3. potential divider ratio between C1 and CM is so dimensioned that a
measurement voltage Um of 57 V AC is set.
4. overvoltage suppressor (Ü) installed, which protects the sensor and
the cable from overvoltages, and as there are no electronic
components used in the sensor at the bushing, this measurement
procedure is not sensitive to electromagnetic emission.
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
Case study-1:
Three-phase operating voltages on the 275 kV bushings of a 185
MVA generator transformer together with detected overvoltages
recorded over a period of 18 months.
present-day technology easily allows the continuous acquisition
and archiving of all the data even for longer than 18 months,
across many years (life).
Continuously monitored
3-phase operating
voltages (phases L1, L2,
L3) with overvoltages,
voltage fluctuations and
network asymmetries
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
Bushing capacitance
• Monitoring of the change in the bushing capacitances (∆ C)
is achieved by means of a three-phase voltage
measurement.the output signal of a voltage sensor is
compared with the two remaining phases.
• In consequence, the relative change in capacitance is used
for determining the ∆ C.
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
• Case study 2:
• The effect of a partial flashover of 2 layers of a 420 kV
bushing is depicted in 3-phase operating voltages (phase
L1, L2, L3) together with overvoltage's of the 350 MVA
regulating transformer.
• After only 1 ½ years of bushing operation a warning was
generated automatically by the on-line monitoring system.
1-Jun-21 18
Detection of partial
flashover of 420 kV bushing
and avoidance of collateral
damage of 350 MVA
regulating transformer, 3-
phase operating voltages
(phase L1, L2, L3) with
overvoltages identified by
change of capacitance ∆ C
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
Dielectric dissipation factor tan δ and sum phasor
• The measurement of the phase angle between the three phases
makes it possible to detect changes in the dielectric dissipation
(loss) factor tan δ.
• The difficulty in the measurement technique is in being able
to detect even very slight changes.
• A change in the loss factor tan δ by 0.1 % means that the phase
changes by an angle of 0.057 °.
• The measurement data has to be recorded with a very high
resolution in terms of time in order to achieve this accuracy.
• In this case, the sampling rate is 10 µs, to detect the zero
crossing of the 50/60 Hz AC voltage.
• In addition, the evaluation algorithm carries out an
interpolation to achieve further improvement in the accuracy.
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
• For the acquisition of the ∆ tan δ, an accuracy of at least ± 0.15
% must be reached.
• The reason for this is that the dissipation factor for the various
types of construction of bushings moves in the range of about 0.5
% and a maximum warning threshold has to be assumed at about
0.7 %.
• In on-line measurement, as in the process described here, the
voltage of another phase is used as a reference.
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
• Different types of interpretation methods (change of
dissipation factor vs. sum current phasor) with their
advantages and disadvantages are discussed
• Therefore, a depiction of the sum vector in a polar diagram as
suggested in does not appear very meaningful.
• A better interpretation of the data is achieved by depicting the
change in the dissipation factor
Polar diagram of the sum
vector of a 3-phase bushing
monitoring on a 400 kV
generator transformer
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
G. Bushing oil pressure
• For oil-filled bushings, it is possible to measure the
bushing oil pressure, thus detecting possible oil leaks.
• Reason for changes in the bushing oil pressure is
thermal overload,
partial discharges.
3-phase monitoring of
the change in the
bushing oil pressure on
a 400 kV agenerator
transformer with
detection of an oil leak
on phase L1
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
INSULATION SYSTEM AND TAP CHANGER
• To monitor the condition of the active part of a power transformer
various measurement and analysing quantities can be realised. As
main parameters are to
1. Mention temperatures,
2. Loading conditions,
3. Gas-in oil content,
4. Moisture of oil and paper insulation system.
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
case study 3:
• A 75 MVA furnace transformer was put in service in a
steelworks factory. the 75 MVA furnace together with two
more transformers of this site were equipped with an MS 2000
on-line monitoring system the recommendations of MS 2000 a
DGA was performed and indicated the presence of a hot-spot.
• when the gas-in-oil content crossed the 1000 ppm limit the
transformer tripped through the Buchholz relay with a
collateral damage.
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
CONCLUSION :
• By on-line condition monitoring and diagnosis we can realize and demonstrate
how capacitively controlled bushings can be monitored on-line in a simple
manner.
• The change in the bushing capacitance as the most important characteristic
quantity for determining the operational state can be analyzed reliably on this
basis.
• A critical damage of a 350 MVA grid coupling transformer could be avoided.
Another collateral damage could be prevented by detection of an oil leak on a 185
MVA generator transformer by means of monitoring the bushing oil pressure.
• Furthermore a 75 MVA furnace transformer has demonstrated the detection of its
condition from beginning of a fault until collateral damage. It has been
demonstrated that the operating condition of the transformer can be made
transparent with the use of an on-line monitorings
• Overally the malfunctions that are building up in power transformers can be
detected earlier with the deployment of an efficient on-line monitoring system and
as a result, there is a lower potential for transformer endangerment. g therefrom,
overvoltage's and transient voltages can be detected.
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
REFERENCES
• http://www.google.com/online condition monitoring and diagnosis of
power transformers their bushings .tap changers and insulation system
”, IEEE Power Engineering Society Winter Meeting, Columbus, Ohio,
2001
• http://www.inmr.com/2014/02/brazilian-research-centre-develops-
software-tools-diagnostic-tests-network-components/4/
• http://www.google.co.in/search?q=transformer+bushing+damage&safe
=active&biw=400&bih=609&source=lnms
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
• http://www.google.co.in/search?tbm=isch&biw=1366&bih=578&q=tr
ansformer+bushing+damage&safe=active&surl=1&norc=1&zx=14241
48024109
• http://www.google.co.in/search?tbm=isch&biw=1366&bih=578&q=tr
ansformer+bushing+damage&safe=active&surl=1&norc=1&zx=14241
48024109#imgrc=47tHkhVor6Qf5M%253A
• http://www.google.co.in/search?tbm=isch&biw=1366&bih=578&q=tr
ansformer+bushing+damage&safe=active&surl=1&norc=1&zx=14241
48024109
1-Jun-21 27
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
Thank you
EEE Dept. CBIT, Hyderabad
EEE Dept. CBIT, Hyderabad
Queries

More Related Content

What's hot

Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit Breakers
Ameen San
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
Rohit Dave
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
siddharam kantoli
 
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
AHMED MOHAMED HEGAB
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation Equipments
Sumeet Ratnawat
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
Ahmed Saada, (PRMG)
 
Presentation_Power_Transformers-1
Presentation_Power_Transformers-1Presentation_Power_Transformers-1
Presentation_Power_Transformers-1
Nageswar Rao
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
pk130992
 
HT and LT SWITCHGEAR
HT and LT SWITCHGEARHT and LT SWITCHGEAR
HT and LT SWITCHGEAR
Ravindra Kumar
 
Instrument transformer CT & PT
Instrument transformer CT & PTInstrument transformer CT & PT
Instrument transformer CT & PT
Chandan Singh
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
Ang Sovann
 
Breaker Operation & Maintenance
Breaker Operation & MaintenanceBreaker Operation & Maintenance
Breaker Operation & Maintenance
Sheikh Nazmul Islam
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
SMRITI KESHARWANI
 
Circuit breaker
Circuit breakerCircuit breaker
Circuit breaker
Biswajit Pratihari
 
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Sheikh Nazmul Islam
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
H. Kheir
 
Transformer Oil Testing
Transformer Oil TestingTransformer Oil Testing
Transformer Oil Testing
engrsurif
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformer
ROOPAL PANCHOLI
 
switchgear and protection by vala kamlesh
switchgear and protection by vala kamleshswitchgear and protection by vala kamlesh
switchgear and protection by vala kamlesh
Kamlesh Vala
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
Living Online
 

What's hot (20)

Circuit Breakers
Circuit BreakersCircuit Breakers
Circuit Breakers
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation Equipments
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Presentation_Power_Transformers-1
Presentation_Power_Transformers-1Presentation_Power_Transformers-1
Presentation_Power_Transformers-1
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
HT and LT SWITCHGEAR
HT and LT SWITCHGEARHT and LT SWITCHGEAR
HT and LT SWITCHGEAR
 
Instrument transformer CT & PT
Instrument transformer CT & PTInstrument transformer CT & PT
Instrument transformer CT & PT
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
Breaker Operation & Maintenance
Breaker Operation & MaintenanceBreaker Operation & Maintenance
Breaker Operation & Maintenance
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Circuit breaker
Circuit breakerCircuit breaker
Circuit breaker
 
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV Switchgear
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
 
Transformer Oil Testing
Transformer Oil TestingTransformer Oil Testing
Transformer Oil Testing
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformer
 
switchgear and protection by vala kamlesh
switchgear and protection by vala kamleshswitchgear and protection by vala kamlesh
switchgear and protection by vala kamlesh
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 

Similar to Online Condition Monitoring And Diagnosis Of Power Transformers Their Bushings ,Tap Changer And Insulation System

Liquid Insulation Dissipation factor and Dielectric Factor Measurement Unit
Liquid Insulation Dissipation factor and Dielectric Factor Measurement UnitLiquid Insulation Dissipation factor and Dielectric Factor Measurement Unit
Liquid Insulation Dissipation factor and Dielectric Factor Measurement Unit
NadiiaHubar
 
Executive summary
Executive summaryExecutive summary
Executive summary
ANAND SHEKHAR
 
IRJET-Power Quality Improvement by using CHB Inverter based DVR
IRJET-Power Quality Improvement by using CHB Inverter based DVRIRJET-Power Quality Improvement by using CHB Inverter based DVR
IRJET-Power Quality Improvement by using CHB Inverter based DVR
IRJET Journal
 
K.kufa meter test - c
K.kufa meter test - cK.kufa meter test - c
K.kufa meter test - c
Kumbirai Kufa
 
IRJET - Design of High Gain DC-DC Step Up Converter
IRJET -  	  Design of High Gain DC-DC Step Up ConverterIRJET -  	  Design of High Gain DC-DC Step Up Converter
IRJET - Design of High Gain DC-DC Step Up Converter
IRJET Journal
 
A Three Phase AC-AC ZCS Resonant Converter for Induction Heating
A Three Phase AC-AC ZCS Resonant Converter for Induction HeatingA Three Phase AC-AC ZCS Resonant Converter for Induction Heating
A Three Phase AC-AC ZCS Resonant Converter for Induction Heating
IJMTST Journal
 
Very high voltage boost converter based on boot strap capcitors and ...
Very  high  voltage  boost  converter  based  on  boot strap  capcitors  and ...Very  high  voltage  boost  converter  based  on  boot strap  capcitors  and ...
Very high voltage boost converter based on boot strap capcitors and ...
IAEME Publication
 
Thermistor temperature sensing alarm report
Thermistor temperature sensing alarm reportThermistor temperature sensing alarm report
Thermistor temperature sensing alarm report
BhargavChowdary39
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
TESCO - The Eastern Specialty Company
 
IRJET- Generation and Control of Transient Overvoltages in Power System Networks
IRJET- Generation and Control of Transient Overvoltages in Power System NetworksIRJET- Generation and Control of Transient Overvoltages in Power System Networks
IRJET- Generation and Control of Transient Overvoltages in Power System Networks
IRJET Journal
 
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part IITESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO - The Eastern Specialty Company
 
IRJET- Comparison of H5 and HERIC Trasformerless Inverter Topology Conserning...
IRJET- Comparison of H5 and HERIC Trasformerless Inverter Topology Conserning...IRJET- Comparison of H5 and HERIC Trasformerless Inverter Topology Conserning...
IRJET- Comparison of H5 and HERIC Trasformerless Inverter Topology Conserning...
IRJET Journal
 
IRJET-Three Phase Interleaved Boost Converter
IRJET-Three Phase Interleaved Boost ConverterIRJET-Three Phase Interleaved Boost Converter
IRJET-Three Phase Interleaved Boost Converter
IRJET Journal
 
Review of DC Offset Compensation Techniques for Grid Connected Inverters
Review of DC Offset Compensation Techniques for Grid Connected InvertersReview of DC Offset Compensation Techniques for Grid Connected Inverters
Review of DC Offset Compensation Techniques for Grid Connected Inverters
International Journal of Power Electronics and Drive Systems
 
Closed Loop Simulation and Implementation of Digital Integral Control of Sy...
Closed Loop Simulation and Implementation of  Digital Integral  Control of Sy...Closed Loop Simulation and Implementation of  Digital Integral  Control of Sy...
Closed Loop Simulation and Implementation of Digital Integral Control of Sy...
IRJET Journal
 
IRJET- Interleaved DC-DC Boost Converter with High Voltage Gain and Effic...
IRJET-  	  Interleaved DC-DC Boost Converter with High Voltage Gain and Effic...IRJET-  	  Interleaved DC-DC Boost Converter with High Voltage Gain and Effic...
IRJET- Interleaved DC-DC Boost Converter with High Voltage Gain and Effic...
IRJET Journal
 
RGPV EX7102 UNITIV
RGPV EX7102 UNITIVRGPV EX7102 UNITIV
RGPV EX7102 UNITIV
Mani Deep Dutt
 
Ppt iitr
Ppt iitrPpt iitr
Ppt iitr
NIT MEGHALAYA
 
Closed Loop Analysis of Multilevel Inverter Fed Drives 
Closed Loop Analysis of Multilevel Inverter Fed Drives Closed Loop Analysis of Multilevel Inverter Fed Drives 
Closed Loop Analysis of Multilevel Inverter Fed Drives 
IJPEDS-IAES
 
IRJET- Modified Cascaded H - Bridge Multilevel Inverter for Household Appliances
IRJET- Modified Cascaded H - Bridge Multilevel Inverter for Household AppliancesIRJET- Modified Cascaded H - Bridge Multilevel Inverter for Household Appliances
IRJET- Modified Cascaded H - Bridge Multilevel Inverter for Household Appliances
IRJET Journal
 

Similar to Online Condition Monitoring And Diagnosis Of Power Transformers Their Bushings ,Tap Changer And Insulation System (20)

Liquid Insulation Dissipation factor and Dielectric Factor Measurement Unit
Liquid Insulation Dissipation factor and Dielectric Factor Measurement UnitLiquid Insulation Dissipation factor and Dielectric Factor Measurement Unit
Liquid Insulation Dissipation factor and Dielectric Factor Measurement Unit
 
Executive summary
Executive summaryExecutive summary
Executive summary
 
IRJET-Power Quality Improvement by using CHB Inverter based DVR
IRJET-Power Quality Improvement by using CHB Inverter based DVRIRJET-Power Quality Improvement by using CHB Inverter based DVR
IRJET-Power Quality Improvement by using CHB Inverter based DVR
 
K.kufa meter test - c
K.kufa meter test - cK.kufa meter test - c
K.kufa meter test - c
 
IRJET - Design of High Gain DC-DC Step Up Converter
IRJET -  	  Design of High Gain DC-DC Step Up ConverterIRJET -  	  Design of High Gain DC-DC Step Up Converter
IRJET - Design of High Gain DC-DC Step Up Converter
 
A Three Phase AC-AC ZCS Resonant Converter for Induction Heating
A Three Phase AC-AC ZCS Resonant Converter for Induction HeatingA Three Phase AC-AC ZCS Resonant Converter for Induction Heating
A Three Phase AC-AC ZCS Resonant Converter for Induction Heating
 
Very high voltage boost converter based on boot strap capcitors and ...
Very  high  voltage  boost  converter  based  on  boot strap  capcitors  and ...Very  high  voltage  boost  converter  based  on  boot strap  capcitors  and ...
Very high voltage boost converter based on boot strap capcitors and ...
 
Thermistor temperature sensing alarm report
Thermistor temperature sensing alarm reportThermistor temperature sensing alarm report
Thermistor temperature sensing alarm report
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
 
IRJET- Generation and Control of Transient Overvoltages in Power System Networks
IRJET- Generation and Control of Transient Overvoltages in Power System NetworksIRJET- Generation and Control of Transient Overvoltages in Power System Networks
IRJET- Generation and Control of Transient Overvoltages in Power System Networks
 
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part IITESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
 
IRJET- Comparison of H5 and HERIC Trasformerless Inverter Topology Conserning...
IRJET- Comparison of H5 and HERIC Trasformerless Inverter Topology Conserning...IRJET- Comparison of H5 and HERIC Trasformerless Inverter Topology Conserning...
IRJET- Comparison of H5 and HERIC Trasformerless Inverter Topology Conserning...
 
IRJET-Three Phase Interleaved Boost Converter
IRJET-Three Phase Interleaved Boost ConverterIRJET-Three Phase Interleaved Boost Converter
IRJET-Three Phase Interleaved Boost Converter
 
Review of DC Offset Compensation Techniques for Grid Connected Inverters
Review of DC Offset Compensation Techniques for Grid Connected InvertersReview of DC Offset Compensation Techniques for Grid Connected Inverters
Review of DC Offset Compensation Techniques for Grid Connected Inverters
 
Closed Loop Simulation and Implementation of Digital Integral Control of Sy...
Closed Loop Simulation and Implementation of  Digital Integral  Control of Sy...Closed Loop Simulation and Implementation of  Digital Integral  Control of Sy...
Closed Loop Simulation and Implementation of Digital Integral Control of Sy...
 
IRJET- Interleaved DC-DC Boost Converter with High Voltage Gain and Effic...
IRJET-  	  Interleaved DC-DC Boost Converter with High Voltage Gain and Effic...IRJET-  	  Interleaved DC-DC Boost Converter with High Voltage Gain and Effic...
IRJET- Interleaved DC-DC Boost Converter with High Voltage Gain and Effic...
 
RGPV EX7102 UNITIV
RGPV EX7102 UNITIVRGPV EX7102 UNITIV
RGPV EX7102 UNITIV
 
Ppt iitr
Ppt iitrPpt iitr
Ppt iitr
 
Closed Loop Analysis of Multilevel Inverter Fed Drives 
Closed Loop Analysis of Multilevel Inverter Fed Drives Closed Loop Analysis of Multilevel Inverter Fed Drives 
Closed Loop Analysis of Multilevel Inverter Fed Drives 
 
IRJET- Modified Cascaded H - Bridge Multilevel Inverter for Household Appliances
IRJET- Modified Cascaded H - Bridge Multilevel Inverter for Household AppliancesIRJET- Modified Cascaded H - Bridge Multilevel Inverter for Household Appliances
IRJET- Modified Cascaded H - Bridge Multilevel Inverter for Household Appliances
 

Recently uploaded

Bituminous road construction project based learning report
Bituminous road construction project based learning reportBituminous road construction project based learning report
Bituminous road construction project based learning report
CE19KaushlendraKumar
 
OOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming languageOOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming language
PreethaV16
 
Levelised Cost of Hydrogen (LCOH) Calculator Manual
Levelised Cost of Hydrogen  (LCOH) Calculator ManualLevelised Cost of Hydrogen  (LCOH) Calculator Manual
Levelised Cost of Hydrogen (LCOH) Calculator Manual
Massimo Talia
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
felixwold
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
DharmaBanothu
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
nedcocy
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
Kamal Acharya
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
Paris Salesforce Developer Group
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
Indrajeet sahu
 
Power Electronics- AC -AC Converters.pptx
Power Electronics- AC -AC Converters.pptxPower Electronics- AC -AC Converters.pptx
Power Electronics- AC -AC Converters.pptx
Poornima D
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Zener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and ApplicationsZener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and Applications
Shiny Christobel
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
AnasAhmadNoor
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
sydezfe
 
Unit -II Spectroscopy - EC I B.Tech.pdf
Unit -II Spectroscopy - EC  I B.Tech.pdfUnit -II Spectroscopy - EC  I B.Tech.pdf
Unit -II Spectroscopy - EC I B.Tech.pdf
TeluguBadi
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
Kamal Acharya
 

Recently uploaded (20)

Bituminous road construction project based learning report
Bituminous road construction project based learning reportBituminous road construction project based learning report
Bituminous road construction project based learning report
 
OOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming languageOOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming language
 
Levelised Cost of Hydrogen (LCOH) Calculator Manual
Levelised Cost of Hydrogen  (LCOH) Calculator ManualLevelised Cost of Hydrogen  (LCOH) Calculator Manual
Levelised Cost of Hydrogen (LCOH) Calculator Manual
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
 
Power Electronics- AC -AC Converters.pptx
Power Electronics- AC -AC Converters.pptxPower Electronics- AC -AC Converters.pptx
Power Electronics- AC -AC Converters.pptx
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Zener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and ApplicationsZener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and Applications
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
 
Unit -II Spectroscopy - EC I B.Tech.pdf
Unit -II Spectroscopy - EC  I B.Tech.pdfUnit -II Spectroscopy - EC  I B.Tech.pdf
Unit -II Spectroscopy - EC I B.Tech.pdf
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
 

Online Condition Monitoring And Diagnosis Of Power Transformers Their Bushings ,Tap Changer And Insulation System

  • 1. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad 1-Jun-21 1 1 SEMINAR PRESENTATION DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING CHAITHANYA BHARATHI INSTITUTE OF TECHNOLOGY GANDIPET, HYDERABAD 2014 Submitted by K .V. V. Satyanarayana Roll No: 1601-14-766-006 M. E (Power Systems & Power Electronics)
  • 2. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad CONTENTS 1. Introduction 2. Bushings 3.System Description 4. Bushing monitoring 4.1.Capacitively controlled insulator bushings 4.2.Bushing capacitance C and dielectric dissipation factor tanδ. 4.3.Voltage sensor 4.4.Operating voltages and overvoltages 4.5Bush Capacitance 4.6.Dielectric dissipation factor tan δ and sum phasor 4.7.Bushing oil pressure 5.Insulation System And Tap Changer 6 Reference 1-Jun-21 2
  • 3. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad I. INTRODUCTION • A bushing must be designed to withstand the electrical field strength produced in the insulation, when any earthed material is present • In a Oil-filled power transformers, their bushings, tap changer, insulation system and auxiliary equipment are critical to the operation of every electrical power system to such an extend that their reliable and uninterrupted functioning is a key factor in profitable generation, transmission and distribution. • Recent years on-line monitoring systems have been installed in a large scale at power transformers.
  • 4. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad Causes Of Bushing Failures 1-Jun-21 4
  • 5. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad Offline Buhing Test Hence tests to be conducted & monitoring is done 1-Jun-21 5 Online Bushing Test
  • 6. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad Bushing capacitance test 1-Jun-21 6
  • 7. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad • The utilities network (Ethernet) can transport the information from the substation to every PC (web based visualization) • Starting from the strict point of view of monitoring it is then proceed forward with the presentation of diagnostics, prognosis is done. • The task of on-line monitoring is then to provide focused, purposeful diagnosis information, so that remedial measures can be initiated if needed should faults occur during operation. On-line visualization of transformer condition and its information about trending, diagnostics and prognostics
  • 8. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad II. SYSTEM DESCRIPTION On-line monitoring system is employed 1. Ageing rate, 2. Overloading condition, 3. Change in the bushing capacitance • Data acquisition is time-controlled and event controlled. Thus,when a transformer is switched on, the voltages are recorded for a duration of 10 seconds with a resolution of 20 ms. • In comparison, the changes in the bushing capacitance are sampled every 20 ms and saved every 15 minutes consequently the size of the database is optimized.
  • 9. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad A. Capacitively controlled insulator bushings • In the voltage range from 110 kV upwards, modern bushings are generally designed with closely stepped capacitive control layers. • Basic insulating systems of capacitive controlled high voltage bushings can be classified as: 1. Resin-bonded paper bushings (RBP) 2. Resin-impregnated paper bushings (RIP) 3. Oil-impregnated paper bushings (OIP)
  • 10. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad Bushing capacitance C and dielectric dissipation factor (tan δ) • Measurement of the bushing capacitance C and the dielectric dissipation factor tan δ are important parameters for evaluating the operational state of a high voltage bushing. • dissipation factor tan δ = 1/R C. • Range of tan δ for normal operation new resin-bonded paper bushing, it is in the range 0.5 ... 0.7 %. resin-impregnated bushings, it is in the range 0.25 ... 0.45 % oil-impregnated bushings, values between 0.25 ... 0.5%
  • 11. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad Equivalent circuit diagram and vector diagram of the dielectric loss factor tan δ
  • 12. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad • Dielectric losses in the insulation result in a capacitive loss current in the dielectric material. • Depending on the ageing, the bushing capacitance and the tan δ can change. • Table below shows guide values for tan δ and capacitance values as examples for resin bonded paper bushings. • When these limiting values are reached, continued operation is not recommended.
  • 13. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad • Reasons for a change in the values of tan δ and ∆ C External influences : moisture and dirt on the porcelain. ∆ C can also be caused by an oil-impregnation in the case of resin-bonded paper bushings. • Increase in the ∆ C for all bushing types indicates partial breakdowns between control layers
  • 14. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad C. Voltage sensor • The monitoring of the electrical measurement quantities is achieved with a voltage sensor . The sensor is connected directly to the measurement tap of the bushing . This design allows a reliable measurement with a bandwidth of up to 2 MHz Bushing Bushing voltage sensors installed on the measurement tap of the bushings
  • 15. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad • The sensor essentially consists of capacitor Cm, which normally has values of 1 .. 2 µF. 1. Cm >> C2 (i.e C2 ≈ 300 pF), I2 is practically 0. 2. R terminates the coaxial cable with a surge impedance of 50 Ω. 3. potential divider ratio between C1 and CM is so dimensioned that a measurement voltage Um of 57 V AC is set. 4. overvoltage suppressor (Ü) installed, which protects the sensor and the cable from overvoltages, and as there are no electronic components used in the sensor at the bushing, this measurement procedure is not sensitive to electromagnetic emission.
  • 16. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad Case study-1: Three-phase operating voltages on the 275 kV bushings of a 185 MVA generator transformer together with detected overvoltages recorded over a period of 18 months. present-day technology easily allows the continuous acquisition and archiving of all the data even for longer than 18 months, across many years (life). Continuously monitored 3-phase operating voltages (phases L1, L2, L3) with overvoltages, voltage fluctuations and network asymmetries
  • 17. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad Bushing capacitance • Monitoring of the change in the bushing capacitances (∆ C) is achieved by means of a three-phase voltage measurement.the output signal of a voltage sensor is compared with the two remaining phases. • In consequence, the relative change in capacitance is used for determining the ∆ C.
  • 18. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad • Case study 2: • The effect of a partial flashover of 2 layers of a 420 kV bushing is depicted in 3-phase operating voltages (phase L1, L2, L3) together with overvoltage's of the 350 MVA regulating transformer. • After only 1 ½ years of bushing operation a warning was generated automatically by the on-line monitoring system. 1-Jun-21 18 Detection of partial flashover of 420 kV bushing and avoidance of collateral damage of 350 MVA regulating transformer, 3- phase operating voltages (phase L1, L2, L3) with overvoltages identified by change of capacitance ∆ C
  • 19. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad Dielectric dissipation factor tan δ and sum phasor • The measurement of the phase angle between the three phases makes it possible to detect changes in the dielectric dissipation (loss) factor tan δ. • The difficulty in the measurement technique is in being able to detect even very slight changes. • A change in the loss factor tan δ by 0.1 % means that the phase changes by an angle of 0.057 °. • The measurement data has to be recorded with a very high resolution in terms of time in order to achieve this accuracy. • In this case, the sampling rate is 10 µs, to detect the zero crossing of the 50/60 Hz AC voltage. • In addition, the evaluation algorithm carries out an interpolation to achieve further improvement in the accuracy.
  • 20. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad • For the acquisition of the ∆ tan δ, an accuracy of at least ± 0.15 % must be reached. • The reason for this is that the dissipation factor for the various types of construction of bushings moves in the range of about 0.5 % and a maximum warning threshold has to be assumed at about 0.7 %. • In on-line measurement, as in the process described here, the voltage of another phase is used as a reference.
  • 21. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad • Different types of interpretation methods (change of dissipation factor vs. sum current phasor) with their advantages and disadvantages are discussed • Therefore, a depiction of the sum vector in a polar diagram as suggested in does not appear very meaningful. • A better interpretation of the data is achieved by depicting the change in the dissipation factor Polar diagram of the sum vector of a 3-phase bushing monitoring on a 400 kV generator transformer
  • 22. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad G. Bushing oil pressure • For oil-filled bushings, it is possible to measure the bushing oil pressure, thus detecting possible oil leaks. • Reason for changes in the bushing oil pressure is thermal overload, partial discharges. 3-phase monitoring of the change in the bushing oil pressure on a 400 kV agenerator transformer with detection of an oil leak on phase L1
  • 23. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad INSULATION SYSTEM AND TAP CHANGER • To monitor the condition of the active part of a power transformer various measurement and analysing quantities can be realised. As main parameters are to 1. Mention temperatures, 2. Loading conditions, 3. Gas-in oil content, 4. Moisture of oil and paper insulation system.
  • 24. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad case study 3: • A 75 MVA furnace transformer was put in service in a steelworks factory. the 75 MVA furnace together with two more transformers of this site were equipped with an MS 2000 on-line monitoring system the recommendations of MS 2000 a DGA was performed and indicated the presence of a hot-spot. • when the gas-in-oil content crossed the 1000 ppm limit the transformer tripped through the Buchholz relay with a collateral damage.
  • 25. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad CONCLUSION : • By on-line condition monitoring and diagnosis we can realize and demonstrate how capacitively controlled bushings can be monitored on-line in a simple manner. • The change in the bushing capacitance as the most important characteristic quantity for determining the operational state can be analyzed reliably on this basis. • A critical damage of a 350 MVA grid coupling transformer could be avoided. Another collateral damage could be prevented by detection of an oil leak on a 185 MVA generator transformer by means of monitoring the bushing oil pressure. • Furthermore a 75 MVA furnace transformer has demonstrated the detection of its condition from beginning of a fault until collateral damage. It has been demonstrated that the operating condition of the transformer can be made transparent with the use of an on-line monitorings • Overally the malfunctions that are building up in power transformers can be detected earlier with the deployment of an efficient on-line monitoring system and as a result, there is a lower potential for transformer endangerment. g therefrom, overvoltage's and transient voltages can be detected.
  • 26. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad REFERENCES • http://www.google.com/online condition monitoring and diagnosis of power transformers their bushings .tap changers and insulation system ”, IEEE Power Engineering Society Winter Meeting, Columbus, Ohio, 2001 • http://www.inmr.com/2014/02/brazilian-research-centre-develops- software-tools-diagnostic-tests-network-components/4/ • http://www.google.co.in/search?q=transformer+bushing+damage&safe =active&biw=400&bih=609&source=lnms
  • 27. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad • http://www.google.co.in/search?tbm=isch&biw=1366&bih=578&q=tr ansformer+bushing+damage&safe=active&surl=1&norc=1&zx=14241 48024109 • http://www.google.co.in/search?tbm=isch&biw=1366&bih=578&q=tr ansformer+bushing+damage&safe=active&surl=1&norc=1&zx=14241 48024109#imgrc=47tHkhVor6Qf5M%253A • http://www.google.co.in/search?tbm=isch&biw=1366&bih=578&q=tr ansformer+bushing+damage&safe=active&surl=1&norc=1&zx=14241 48024109 1-Jun-21 27
  • 28. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad Thank you
  • 29. EEE Dept. CBIT, Hyderabad EEE Dept. CBIT, Hyderabad Queries