Clean Water Facility
Design Workshop #2
5/6/2015Design Workshop #2
Project Status and Update
5/6/2015Design Workshop #2
 Project schedule
 Outfall construction begins Summer 2015
2010 2011 2012 2013 2014 2015 2016 2017
Open House
Potential Locations
Open House
Top 5 Sites
Open House
Top 3 Sites
City Council
Windjammer Vicinity
Architectural
Charrette
Ch 10 Program Charrette
Top 2 Sites
Charrette
Orientation on
Property
Architectural
Charrette
Aug 2010 Nov 2013Facilities Plan
Mar 2013 Dec 2015Design
Jun 2015 Dec 2017Construction
Public Feedback Opportunities
Design Workshop #2 5/6/2015
Outfall Construction - Summer 2015
5/6/2015Design Workshop #2
 Outfall construction schedule is separate from the facility
design/construction schedule
 Location was selected independent of facility location
 Essential piece of wastewater infrastructure needed to
support increased system use in Oak Harbor
RECAP OF WHERE WE
WERE AND WHERE
WE ARE NOW…
MAY 6, 2015
OLD SCHEME SITE PLAN– AUGUST 6TH 2014MAY 6, 2015
OLD SCHEME – AUGUST 6TH 2014MAY 6, 2015
OLD SCHEME – AUGUST 6TH 2014MAY 6, 2015
NOVEMBER 13TH 2014 DESIGN WORKSHOP #1
CONCEPT 1: CAMPUS CONCEPT 2: COURTYARD
MAY 6, 2015
NOVEMBER 13TH 2014 DESIGN WORKSHOP #1
CONCEPT 1: CAMPUS
CONCEPT 2: COURTYARD
MAY 6, 2015
KEY TAKEAWAYS FROM DESIGN
WORKSHOP #1
• Facility should set the stage for a community design aesthetic
• A combination of both a campus and a courtyard with higher priority on
campus
• Regional design as an architectural aesthetic, incorporate both contemporary
and traditional NW architecture
• Open and light, enhance sight lines to water, park, and windmill
• Allow for community interaction with facility, include educational features
• Varying heights of roof lines
• Provide “camouflaging” – it should not advertise that it’s a sewage treatment
plant
• Integrate with surroundings – WJ Park, harbor area, downtown
2014 Design Workshop Results:
MAY 6, 2015
DESIGN IMPETUS
A building that isn’t
what it seems on the
outside, integrates
(blends) with its
surroundings
MAY 6, 2015
V
DESIGN DIAGRAM - 1MAY 6, 2015
V
DESIGN DIAGRAM - 2MAY 6, 2015
V
DESIGN DIAGRAM - 3MAY 6, 2015
V
DESIGN DIAGRAM - 4
Screening element
added to the spaces
between building
masses
Screens are pushed
back from façade to
accentuate the
building campus
form
MAY 6, 2015
V
DESIGN DIAGRAM - 5
Taller building elements
pulled up from masses
below create roof lines
of varying height
These elements are
translucent to enhance
the open and light
concept
MAY 6, 2015
SITE PLAN PRIOR TO VALUE ENGINEERINGMAY 6, 2015
CURRENT SITE PLAN LAYOUT
RELOCATION OF
HEADWORKS
BUILDING
FOOTPRINT AND
CONFIGURATION BEING REVISED
MAY 6, 2015
MATERIAL PALLET
SIMPLE, CLEAN & DURABLE
MAY 6, 2015
MATERIAL EXAMPLES
SSG CURTAIN WALL SYSTEM
“Open and light, provide for transparency”
MAY 6, 2015
MATERIAL EXAMPLES
MASONRY
Textural qualities of a long lasting material “set
the stage for a community design aesthetic”
MAY 6, 2015
MASONRY TEXTURE STUDIES
MASONRY
MAY 6, 2015
MATERIAL EXAMPLES
WOOD SIDING & SCREENING
ELEMENTS
Regional design with wood shading
elements relates to an abundance
of driftwood on this site
MAY 6, 2015
GATE CONCEPT
BIFOLD GATES
MAY 6, 2015
AERIAL PERSPECTIVE LOOKING NORTH
Within a campus style, provide varied roof lines, solids and voids with building masses
MAY 6, 2015
ADMINISTRATION / MAINTENANCE PLAN – GROUND FLOOR
Allow for community interaction with facility,
include educational features
MAINTENANCEADMINISTRATION
MAY 6, 2015
TRAINING CENTER PLAN– SECOND FLOOR
2ND FLOOR TRAINING FACILITY
MAY 6, 2015
WEST ELEVATION | Administration Building
MAY 6, 2015
VIEW AT PROMENADE | Looking South
MAY 6, 2015
AERIAL VIEW | Looking North
MAY 6, 2015
PERSPECTIVE | Looking North
MAY 6, 2015
AERIAL VIEW | City Beach
MAY 6, 2015
PERSPECTIVE | City Beach & Bay Shore
MAY 6, 2015
CONCEPTUAL LANDSCAPE PLAN
WINDJAMMER PARK
MAY 6, 2015
WINDJAMMER PARK
MAY 6, 2015 CONCEPTUAL LANDSCAPE PLAN
CONCEPTUAL HARD/SOFTSCAPEMAY 6, 2015
CONCEPTUAL LANDSCAPE – STORMWATER & SEATINGMAY 6, 2015
CONCEPTUAL LANDSCAPE – STORMWATER & SEATINGMAY 6, 2015
KEY TAKEAWAYS FROM DESIGN WORKSHOP #1
• Facility should set the stage for a community design aesthetic
• A combination of both a campus and a courtyard with higher priority on
campus
• Regional design as an architectural aesthetic, incorporate both contemporary
and traditional NW architecture
• Open and light, enhance sight lines to water, park, and windmill
• Allow for community interaction with facility, include educational features
• Varying heights of roof lines
• Provide “camouflaging” – it should not advertise that it’s a sewage treatment
plant
• Integrate with surroundings – WJ Park, harbor area, downtown
2014 Design Workshop Results:
MAY 6, 2015
Group Discussion
5/6/2015Design Workshop #2
Design Concept
5/6/2015Design Workshop #2
 Where do you see your feedback incorporated?
Please write your thoughts on the large matrix on the wall
Design Concept
5/6/2015Design Workshop #2
 What is it about the design that best reflects feedback
from previous discussion?
 Where is more work needed?
 Have we missed anything?
Design Concept - Landscape
5/6/2015Design Workshop #2
 What portions of the updated design will be benefitted
most by landscape/hardscape?
 Have we missed anything?

Oh workshop02 full_final

  • 1.
    Clean Water Facility DesignWorkshop #2 5/6/2015Design Workshop #2
  • 2.
    Project Status andUpdate 5/6/2015Design Workshop #2  Project schedule  Outfall construction begins Summer 2015
  • 3.
    2010 2011 20122013 2014 2015 2016 2017 Open House Potential Locations Open House Top 5 Sites Open House Top 3 Sites City Council Windjammer Vicinity Architectural Charrette Ch 10 Program Charrette Top 2 Sites Charrette Orientation on Property Architectural Charrette Aug 2010 Nov 2013Facilities Plan Mar 2013 Dec 2015Design Jun 2015 Dec 2017Construction Public Feedback Opportunities Design Workshop #2 5/6/2015
  • 4.
    Outfall Construction -Summer 2015 5/6/2015Design Workshop #2  Outfall construction schedule is separate from the facility design/construction schedule  Location was selected independent of facility location  Essential piece of wastewater infrastructure needed to support increased system use in Oak Harbor
  • 5.
    RECAP OF WHEREWE WERE AND WHERE WE ARE NOW… MAY 6, 2015
  • 6.
    OLD SCHEME SITEPLAN– AUGUST 6TH 2014MAY 6, 2015
  • 7.
    OLD SCHEME –AUGUST 6TH 2014MAY 6, 2015
  • 8.
    OLD SCHEME –AUGUST 6TH 2014MAY 6, 2015
  • 9.
    NOVEMBER 13TH 2014DESIGN WORKSHOP #1 CONCEPT 1: CAMPUS CONCEPT 2: COURTYARD MAY 6, 2015
  • 10.
    NOVEMBER 13TH 2014DESIGN WORKSHOP #1 CONCEPT 1: CAMPUS CONCEPT 2: COURTYARD MAY 6, 2015
  • 11.
    KEY TAKEAWAYS FROMDESIGN WORKSHOP #1 • Facility should set the stage for a community design aesthetic • A combination of both a campus and a courtyard with higher priority on campus • Regional design as an architectural aesthetic, incorporate both contemporary and traditional NW architecture • Open and light, enhance sight lines to water, park, and windmill • Allow for community interaction with facility, include educational features • Varying heights of roof lines • Provide “camouflaging” – it should not advertise that it’s a sewage treatment plant • Integrate with surroundings – WJ Park, harbor area, downtown 2014 Design Workshop Results: MAY 6, 2015
  • 12.
    DESIGN IMPETUS A buildingthat isn’t what it seems on the outside, integrates (blends) with its surroundings MAY 6, 2015
  • 13.
    V DESIGN DIAGRAM -1MAY 6, 2015
  • 14.
    V DESIGN DIAGRAM -2MAY 6, 2015
  • 15.
    V DESIGN DIAGRAM -3MAY 6, 2015
  • 16.
    V DESIGN DIAGRAM -4 Screening element added to the spaces between building masses Screens are pushed back from façade to accentuate the building campus form MAY 6, 2015
  • 17.
    V DESIGN DIAGRAM -5 Taller building elements pulled up from masses below create roof lines of varying height These elements are translucent to enhance the open and light concept MAY 6, 2015
  • 18.
    SITE PLAN PRIORTO VALUE ENGINEERINGMAY 6, 2015
  • 19.
    CURRENT SITE PLANLAYOUT RELOCATION OF HEADWORKS BUILDING FOOTPRINT AND CONFIGURATION BEING REVISED MAY 6, 2015
  • 20.
    MATERIAL PALLET SIMPLE, CLEAN& DURABLE MAY 6, 2015
  • 21.
    MATERIAL EXAMPLES SSG CURTAINWALL SYSTEM “Open and light, provide for transparency” MAY 6, 2015
  • 22.
    MATERIAL EXAMPLES MASONRY Textural qualitiesof a long lasting material “set the stage for a community design aesthetic” MAY 6, 2015
  • 23.
  • 24.
    MATERIAL EXAMPLES WOOD SIDING& SCREENING ELEMENTS Regional design with wood shading elements relates to an abundance of driftwood on this site MAY 6, 2015
  • 25.
  • 26.
    AERIAL PERSPECTIVE LOOKINGNORTH Within a campus style, provide varied roof lines, solids and voids with building masses MAY 6, 2015
  • 27.
    ADMINISTRATION / MAINTENANCEPLAN – GROUND FLOOR Allow for community interaction with facility, include educational features MAINTENANCEADMINISTRATION MAY 6, 2015
  • 28.
    TRAINING CENTER PLAN–SECOND FLOOR 2ND FLOOR TRAINING FACILITY MAY 6, 2015
  • 29.
    WEST ELEVATION |Administration Building MAY 6, 2015
  • 30.
    VIEW AT PROMENADE| Looking South MAY 6, 2015
  • 31.
    AERIAL VIEW |Looking North MAY 6, 2015
  • 32.
    PERSPECTIVE | LookingNorth MAY 6, 2015
  • 33.
    AERIAL VIEW |City Beach MAY 6, 2015
  • 34.
    PERSPECTIVE | CityBeach & Bay Shore MAY 6, 2015
  • 35.
  • 36.
    WINDJAMMER PARK MAY 6,2015 CONCEPTUAL LANDSCAPE PLAN
  • 37.
  • 38.
    CONCEPTUAL LANDSCAPE –STORMWATER & SEATINGMAY 6, 2015
  • 39.
    CONCEPTUAL LANDSCAPE –STORMWATER & SEATINGMAY 6, 2015
  • 40.
    KEY TAKEAWAYS FROMDESIGN WORKSHOP #1 • Facility should set the stage for a community design aesthetic • A combination of both a campus and a courtyard with higher priority on campus • Regional design as an architectural aesthetic, incorporate both contemporary and traditional NW architecture • Open and light, enhance sight lines to water, park, and windmill • Allow for community interaction with facility, include educational features • Varying heights of roof lines • Provide “camouflaging” – it should not advertise that it’s a sewage treatment plant • Integrate with surroundings – WJ Park, harbor area, downtown 2014 Design Workshop Results: MAY 6, 2015
  • 41.
  • 42.
    Design Concept 5/6/2015Design Workshop#2  Where do you see your feedback incorporated? Please write your thoughts on the large matrix on the wall
  • 43.
    Design Concept 5/6/2015Design Workshop#2  What is it about the design that best reflects feedback from previous discussion?  Where is more work needed?  Have we missed anything?
  • 44.
    Design Concept -Landscape 5/6/2015Design Workshop #2  What portions of the updated design will be benefitted most by landscape/hardscape?  Have we missed anything?