SlideShare a Scribd company logo
1 of 44
Download to read offline
Clean Water Facility
Design Workshop #2
5/6/2015Design Workshop #2
Project Status and Update
5/6/2015Design Workshop #2
 Project schedule
 Outfall construction begins Summer 2015
2010 2011 2012 2013 2014 2015 2016 2017
Open House
Potential Locations
Open House
Top 5 Sites
Open House
Top 3 Sites
City Council
Windjammer Vicinity
Architectural
Charrette
Ch 10 Program Charrette
Top 2 Sites
Charrette
Orientation on
Property
Architectural
Charrette
Aug 2010 Nov 2013Facilities Plan
Mar 2013 Dec 2015Design
Jun 2015 Dec 2017Construction
Public Feedback Opportunities
Design Workshop #2 5/6/2015
Outfall Construction - Summer 2015
5/6/2015Design Workshop #2
 Outfall construction schedule is separate from the facility
design/construction schedule
 Location was selected independent of facility location
 Essential piece of wastewater infrastructure needed to
support increased system use in Oak Harbor
RECAP OF WHERE WE
WERE AND WHERE
WE ARE NOW…
MAY 6, 2015
OLD SCHEME SITE PLAN– AUGUST 6TH 2014MAY 6, 2015
OLD SCHEME – AUGUST 6TH 2014MAY 6, 2015
OLD SCHEME – AUGUST 6TH 2014MAY 6, 2015
NOVEMBER 13TH 2014 DESIGN WORKSHOP #1
CONCEPT 1: CAMPUS CONCEPT 2: COURTYARD
MAY 6, 2015
NOVEMBER 13TH 2014 DESIGN WORKSHOP #1
CONCEPT 1: CAMPUS
CONCEPT 2: COURTYARD
MAY 6, 2015
KEY TAKEAWAYS FROM DESIGN
WORKSHOP #1
• Facility should set the stage for a community design aesthetic
• A combination of both a campus and a courtyard with higher priority on
campus
• Regional design as an architectural aesthetic, incorporate both contemporary
and traditional NW architecture
• Open and light, enhance sight lines to water, park, and windmill
• Allow for community interaction with facility, include educational features
• Varying heights of roof lines
• Provide “camouflaging” – it should not advertise that it’s a sewage treatment
plant
• Integrate with surroundings – WJ Park, harbor area, downtown
2014 Design Workshop Results:
MAY 6, 2015
DESIGN IMPETUS
A building that isn’t
what it seems on the
outside, integrates
(blends) with its
surroundings
MAY 6, 2015
V
DESIGN DIAGRAM - 1MAY 6, 2015
V
DESIGN DIAGRAM - 2MAY 6, 2015
V
DESIGN DIAGRAM - 3MAY 6, 2015
V
DESIGN DIAGRAM - 4
Screening element
added to the spaces
between building
masses
Screens are pushed
back from façade to
accentuate the
building campus
form
MAY 6, 2015
V
DESIGN DIAGRAM - 5
Taller building elements
pulled up from masses
below create roof lines
of varying height
These elements are
translucent to enhance
the open and light
concept
MAY 6, 2015
SITE PLAN PRIOR TO VALUE ENGINEERINGMAY 6, 2015
CURRENT SITE PLAN LAYOUT
RELOCATION OF
HEADWORKS
BUILDING
FOOTPRINT AND
CONFIGURATION BEING REVISED
MAY 6, 2015
MATERIAL PALLET
SIMPLE, CLEAN & DURABLE
MAY 6, 2015
MATERIAL EXAMPLES
SSG CURTAIN WALL SYSTEM
“Open and light, provide for transparency”
MAY 6, 2015
MATERIAL EXAMPLES
MASONRY
Textural qualities of a long lasting material “set
the stage for a community design aesthetic”
MAY 6, 2015
MASONRY TEXTURE STUDIES
MASONRY
MAY 6, 2015
MATERIAL EXAMPLES
WOOD SIDING & SCREENING
ELEMENTS
Regional design with wood shading
elements relates to an abundance
of driftwood on this site
MAY 6, 2015
GATE CONCEPT
BIFOLD GATES
MAY 6, 2015
AERIAL PERSPECTIVE LOOKING NORTH
Within a campus style, provide varied roof lines, solids and voids with building masses
MAY 6, 2015
ADMINISTRATION / MAINTENANCE PLAN – GROUND FLOOR
Allow for community interaction with facility,
include educational features
MAINTENANCEADMINISTRATION
MAY 6, 2015
TRAINING CENTER PLAN– SECOND FLOOR
2ND FLOOR TRAINING FACILITY
MAY 6, 2015
WEST ELEVATION | Administration Building
MAY 6, 2015
VIEW AT PROMENADE | Looking South
MAY 6, 2015
AERIAL VIEW | Looking North
MAY 6, 2015
PERSPECTIVE | Looking North
MAY 6, 2015
AERIAL VIEW | City Beach
MAY 6, 2015
PERSPECTIVE | City Beach & Bay Shore
MAY 6, 2015
CONCEPTUAL LANDSCAPE PLAN
WINDJAMMER PARK
MAY 6, 2015
WINDJAMMER PARK
MAY 6, 2015 CONCEPTUAL LANDSCAPE PLAN
CONCEPTUAL HARD/SOFTSCAPEMAY 6, 2015
CONCEPTUAL LANDSCAPE – STORMWATER & SEATINGMAY 6, 2015
CONCEPTUAL LANDSCAPE – STORMWATER & SEATINGMAY 6, 2015
KEY TAKEAWAYS FROM DESIGN WORKSHOP #1
• Facility should set the stage for a community design aesthetic
• A combination of both a campus and a courtyard with higher priority on
campus
• Regional design as an architectural aesthetic, incorporate both contemporary
and traditional NW architecture
• Open and light, enhance sight lines to water, park, and windmill
• Allow for community interaction with facility, include educational features
• Varying heights of roof lines
• Provide “camouflaging” – it should not advertise that it’s a sewage treatment
plant
• Integrate with surroundings – WJ Park, harbor area, downtown
2014 Design Workshop Results:
MAY 6, 2015
Group Discussion
5/6/2015Design Workshop #2
Design Concept
5/6/2015Design Workshop #2
 Where do you see your feedback incorporated?
Please write your thoughts on the large matrix on the wall
Design Concept
5/6/2015Design Workshop #2
 What is it about the design that best reflects feedback
from previous discussion?
 Where is more work needed?
 Have we missed anything?
Design Concept - Landscape
5/6/2015Design Workshop #2
 What portions of the updated design will be benefitted
most by landscape/hardscape?
 Have we missed anything?

More Related Content

What's hot

Presentation of Windjammer Park Integration Plan to City Council
Presentation of Windjammer Park Integration Plan to City CouncilPresentation of Windjammer Park Integration Plan to City Council
Presentation of Windjammer Park Integration Plan to City Councilpublicinvolvement
 
Presentation of Windjammer Park 60% Design to City Council
Presentation of Windjammer Park 60% Design to City CouncilPresentation of Windjammer Park 60% Design to City Council
Presentation of Windjammer Park 60% Design to City Councilpublicinvolvement
 
Preview of Windjammer Park 30% Design to City Council
Preview of Windjammer Park 30% Design to City CouncilPreview of Windjammer Park 30% Design to City Council
Preview of Windjammer Park 30% Design to City Councilpublicinvolvement
 
Windjammer Park Phase 1 Design Open House
Windjammer Park Phase 1 Design Open HouseWindjammer Park Phase 1 Design Open House
Windjammer Park Phase 1 Design Open Housepublicinvolvement
 
Design charrette council presentation
Design charrette council presentationDesign charrette council presentation
Design charrette council presentationpublicinvolvement
 
Windjammer Park Integration Plan - Council presentation
Windjammer Park Integration Plan - Council presentationWindjammer Park Integration Plan - Council presentation
Windjammer Park Integration Plan - Council presentationpublicinvolvement
 
Windjammer Park Integration Plan CAG meeting 1
Windjammer Park Integration Plan CAG meeting 1Windjammer Park Integration Plan CAG meeting 1
Windjammer Park Integration Plan CAG meeting 1publicinvolvement
 
Hearst community meeting 10.02.18 pn_3-30pm
Hearst community meeting   10.02.18 pn_3-30pmHearst community meeting   10.02.18 pn_3-30pm
Hearst community meeting 10.02.18 pn_3-30pmRamaChilamkurthy
 
Friendship Recreation Center - ANC Presentation (January 12, 2017)
Friendship Recreation Center - ANC Presentation (January 12, 2017)Friendship Recreation Center - ANC Presentation (January 12, 2017)
Friendship Recreation Center - ANC Presentation (January 12, 2017)DC Department of General Services
 
Rosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting PresentationRosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting Presentationknelischer
 
Eastern market metro park project community meeting 07-22-2020
Eastern market metro park project community meeting  07-22-2020Eastern market metro park project community meeting  07-22-2020
Eastern market metro park project community meeting 07-22-2020RamaChilamkurthy
 
Fort lincoln park community mtg presentation 2019 09 24 final
Fort lincoln park  community mtg presentation 2019 09 24 finalFort lincoln park  community mtg presentation 2019 09 24 final
Fort lincoln park community mtg presentation 2019 09 24 finalRamaChilamkurthy
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_knelischer
 
Benning Stoddert Recreation Center Community Meeting Presentation (April 8, 2...
Benning Stoddert Recreation Center Community Meeting Presentation (April 8, 2...Benning Stoddert Recreation Center Community Meeting Presentation (April 8, 2...
Benning Stoddert Recreation Center Community Meeting Presentation (April 8, 2...DC Department of General Services
 
Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15VDOT Northern Virginia
 
Medical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park PropertyMedical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park PropertyCity of College Station
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 finalToronto Public Consultation Unit
 

What's hot (20)

Presentation of Windjammer Park Integration Plan to City Council
Presentation of Windjammer Park Integration Plan to City CouncilPresentation of Windjammer Park Integration Plan to City Council
Presentation of Windjammer Park Integration Plan to City Council
 
Presentation of Windjammer Park 60% Design to City Council
Presentation of Windjammer Park 60% Design to City CouncilPresentation of Windjammer Park 60% Design to City Council
Presentation of Windjammer Park 60% Design to City Council
 
Preview of Windjammer Park 30% Design to City Council
Preview of Windjammer Park 30% Design to City CouncilPreview of Windjammer Park 30% Design to City Council
Preview of Windjammer Park 30% Design to City Council
 
Windjammer Park Phase 1 Design Open House
Windjammer Park Phase 1 Design Open HouseWindjammer Park Phase 1 Design Open House
Windjammer Park Phase 1 Design Open House
 
Design charrette council presentation
Design charrette council presentationDesign charrette council presentation
Design charrette council presentation
 
Windjammer Park Integration Plan - Council presentation
Windjammer Park Integration Plan - Council presentationWindjammer Park Integration Plan - Council presentation
Windjammer Park Integration Plan - Council presentation
 
Windjammer Park Integration Plan CAG meeting 1
Windjammer Park Integration Plan CAG meeting 1Windjammer Park Integration Plan CAG meeting 1
Windjammer Park Integration Plan CAG meeting 1
 
Hearst community meeting 10.02.18 pn_3-30pm
Hearst community meeting   10.02.18 pn_3-30pmHearst community meeting   10.02.18 pn_3-30pm
Hearst community meeting 10.02.18 pn_3-30pm
 
December 6 Public Forum
December 6 Public ForumDecember 6 Public Forum
December 6 Public Forum
 
Friendship Recreation Center - ANC Presentation (January 12, 2017)
Friendship Recreation Center - ANC Presentation (January 12, 2017)Friendship Recreation Center - ANC Presentation (January 12, 2017)
Friendship Recreation Center - ANC Presentation (January 12, 2017)
 
Rosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting PresentationRosehill Vision Committee May 31 2017 Meeting Presentation
Rosehill Vision Committee May 31 2017 Meeting Presentation
 
Eastern market metro park project community meeting 07-22-2020
Eastern market metro park project community meeting  07-22-2020Eastern market metro park project community meeting  07-22-2020
Eastern market metro park project community meeting 07-22-2020
 
Fort lincoln park community mtg presentation 2019 09 24 final
Fort lincoln park  community mtg presentation 2019 09 24 finalFort lincoln park  community mtg presentation 2019 09 24 final
Fort lincoln park community mtg presentation 2019 09 24 final
 
City Hall Site Selection
City Hall Site SelectionCity Hall Site Selection
City Hall Site Selection
 
Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_Oct 13 rosehill reservoir_preliminary_overview_
Oct 13 rosehill reservoir_preliminary_overview_
 
Benning Stoddert Recreation Center Community Meeting Presentation (April 8, 2...
Benning Stoddert Recreation Center Community Meeting Presentation (April 8, 2...Benning Stoddert Recreation Center Community Meeting Presentation (April 8, 2...
Benning Stoddert Recreation Center Community Meeting Presentation (April 8, 2...
 
Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15
 
Medical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park PropertyMedical District Trunk Line Easement on Park Property
Medical District Trunk Line Easement on Park Property
 
Display boards
Display boardsDisplay boards
Display boards
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 

Viewers also liked

130306 City Council Workshop
130306 City Council Workshop130306 City Council Workshop
130306 City Council Workshoppublicinvolvement
 
C8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_finalC8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_finalpublicinvolvement
 
C7 aug 14 city council meeting 120814_final
C7 aug 14 city council meeting 120814_finalC7 aug 14 city council meeting 120814_final
C7 aug 14 city council meeting 120814_finalpublicinvolvement
 
C6 further refine_alts_council_4-18_rev1
C6 further refine_alts_council_4-18_rev1C6 further refine_alts_council_4-18_rev1
C6 further refine_alts_council_4-18_rev1publicinvolvement
 
2015 04-07 city-council_workshop_presentation
2015 04-07 city-council_workshop_presentation2015 04-07 city-council_workshop_presentation
2015 04-07 city-council_workshop_presentationpublicinvolvement
 
Windjammer Park Integration Plan Community Advisory Group meeting 4
Windjammer Park Integration Plan Community Advisory Group meeting 4Windjammer Park Integration Plan Community Advisory Group meeting 4
Windjammer Park Integration Plan Community Advisory Group meeting 4publicinvolvement
 
Oak Harbor Wastewater Treatment Facility: Resolution 15-34, Community Room
Oak Harbor Wastewater Treatment Facility: Resolution 15-34, Community RoomOak Harbor Wastewater Treatment Facility: Resolution 15-34, Community Room
Oak Harbor Wastewater Treatment Facility: Resolution 15-34, Community Roompublicinvolvement
 
60% Design and Cost Estimate
60% Design and Cost Estimate60% Design and Cost Estimate
60% Design and Cost Estimatepublicinvolvement
 
March 9, 2011 City Council Workshop
March 9, 2011 City Council WorkshopMarch 9, 2011 City Council Workshop
March 9, 2011 City Council Workshoppublicinvolvement
 
January 13, 2011 City Council Workshop
January 13, 2011 City Council WorkshopJanuary 13, 2011 City Council Workshop
January 13, 2011 City Council Workshoppublicinvolvement
 
Special Workshop presentation on Finance
Special Workshop presentation on FinanceSpecial Workshop presentation on Finance
Special Workshop presentation on Financepublicinvolvement
 
July 31 public forum & workshop
July 31 public forum & workshopJuly 31 public forum & workshop
July 31 public forum & workshoppublicinvolvement
 
Oak Harbor Clean Water Facility GMP #7
Oak Harbor Clean Water Facility GMP #7Oak Harbor Clean Water Facility GMP #7
Oak Harbor Clean Water Facility GMP #7publicinvolvement
 
C5 Council Workshop Presentation 7-27-11
C5 Council Workshop Presentation 7-27-11C5 Council Workshop Presentation 7-27-11
C5 Council Workshop Presentation 7-27-11publicinvolvement
 
Clean Water Facility 60% Cost Estimate Preview
Clean Water Facility 60% Cost Estimate PreviewClean Water Facility 60% Cost Estimate Preview
Clean Water Facility 60% Cost Estimate Previewpublicinvolvement
 
August 24 Clean Water Facility Planning Public Forum
August 24 Clean Water Facility Planning Public ForumAugust 24 Clean Water Facility Planning Public Forum
August 24 Clean Water Facility Planning Public Forumpublicinvolvement
 
Oak Harbor City Council Meeting: GMP 9
Oak Harbor City Council Meeting: GMP 9Oak Harbor City Council Meeting: GMP 9
Oak Harbor City Council Meeting: GMP 9publicinvolvement
 

Viewers also liked (19)

130306 City Council Workshop
130306 City Council Workshop130306 City Council Workshop
130306 City Council Workshop
 
C8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_finalC8 nov20 city council meeting 121120_final
C8 nov20 city council meeting 121120_final
 
C7 aug 14 city council meeting 120814_final
C7 aug 14 city council meeting 120814_finalC7 aug 14 city council meeting 120814_final
C7 aug 14 city council meeting 120814_final
 
C6 further refine_alts_council_4-18_rev1
C6 further refine_alts_council_4-18_rev1C6 further refine_alts_council_4-18_rev1
C6 further refine_alts_council_4-18_rev1
 
2015 04-07 city-council_workshop_presentation
2015 04-07 city-council_workshop_presentation2015 04-07 city-council_workshop_presentation
2015 04-07 city-council_workshop_presentation
 
Windjammer Park Integration Plan Community Advisory Group meeting 4
Windjammer Park Integration Plan Community Advisory Group meeting 4Windjammer Park Integration Plan Community Advisory Group meeting 4
Windjammer Park Integration Plan Community Advisory Group meeting 4
 
T5 further refine alts min
T5 further refine alts minT5 further refine alts min
T5 further refine alts min
 
Oak Harbor Wastewater Treatment Facility: Resolution 15-34, Community Room
Oak Harbor Wastewater Treatment Facility: Resolution 15-34, Community RoomOak Harbor Wastewater Treatment Facility: Resolution 15-34, Community Room
Oak Harbor Wastewater Treatment Facility: Resolution 15-34, Community Room
 
60% Design and Cost Estimate
60% Design and Cost Estimate60% Design and Cost Estimate
60% Design and Cost Estimate
 
March 9, 2011 City Council Workshop
March 9, 2011 City Council WorkshopMarch 9, 2011 City Council Workshop
March 9, 2011 City Council Workshop
 
January 13, 2011 City Council Workshop
January 13, 2011 City Council WorkshopJanuary 13, 2011 City Council Workshop
January 13, 2011 City Council Workshop
 
Special Workshop presentation on Finance
Special Workshop presentation on FinanceSpecial Workshop presentation on Finance
Special Workshop presentation on Finance
 
July 31 public forum & workshop
July 31 public forum & workshopJuly 31 public forum & workshop
July 31 public forum & workshop
 
Oak Harbor Clean Water Facility GMP #7
Oak Harbor Clean Water Facility GMP #7Oak Harbor Clean Water Facility GMP #7
Oak Harbor Clean Water Facility GMP #7
 
C5 Council Workshop Presentation 7-27-11
C5 Council Workshop Presentation 7-27-11C5 Council Workshop Presentation 7-27-11
C5 Council Workshop Presentation 7-27-11
 
Oak Harbor Rate Study
Oak Harbor Rate StudyOak Harbor Rate Study
Oak Harbor Rate Study
 
Clean Water Facility 60% Cost Estimate Preview
Clean Water Facility 60% Cost Estimate PreviewClean Water Facility 60% Cost Estimate Preview
Clean Water Facility 60% Cost Estimate Preview
 
August 24 Clean Water Facility Planning Public Forum
August 24 Clean Water Facility Planning Public ForumAugust 24 Clean Water Facility Planning Public Forum
August 24 Clean Water Facility Planning Public Forum
 
Oak Harbor City Council Meeting: GMP 9
Oak Harbor City Council Meeting: GMP 9Oak Harbor City Council Meeting: GMP 9
Oak Harbor City Council Meeting: GMP 9
 

Similar to Oh workshop02 full_final

Portfolio_MikeGrogan
Portfolio_MikeGroganPortfolio_MikeGrogan
Portfolio_MikeGroganMike Grogan
 
Kellen Kyger Portfolio with Revit 013117
Kellen Kyger Portfolio with Revit 013117Kellen Kyger Portfolio with Revit 013117
Kellen Kyger Portfolio with Revit 013117Kellen Kyger
 
WatsonMArch Portfolio
WatsonMArch PortfolioWatsonMArch Portfolio
WatsonMArch PortfolioReva Watson
 
Garrison Elementary School SIT Presentation (December 9, 2015)
Garrison Elementary School SIT Presentation (December 9, 2015)Garrison Elementary School SIT Presentation (December 9, 2015)
Garrison Elementary School SIT Presentation (December 9, 2015)DC Department of General Services
 
Resumé of Suvir Hira
Resumé of Suvir HiraResumé of Suvir Hira
Resumé of Suvir HiraSuvir Hira
 
Parklet handbook din_2017 - Seattle
Parklet handbook din_2017 - SeattleParklet handbook din_2017 - Seattle
Parklet handbook din_2017 - SeattleJosé Furtado
 
Detweiler Engineering Resume (1)
Detweiler Engineering Resume (1)Detweiler Engineering Resume (1)
Detweiler Engineering Resume (1)David Detweiler
 
Tough projects keeping them on course -1- mike mellin 02-18-16
Tough projects   keeping them on course -1- mike mellin 02-18-16Tough projects   keeping them on course -1- mike mellin 02-18-16
Tough projects keeping them on course -1- mike mellin 02-18-16Mike Mellin, BSEE/MS
 
Mammoth downtown revitalization action summit presentation by Darin Dinsmore
Mammoth downtown revitalization action summit presentation by Darin DinsmoreMammoth downtown revitalization action summit presentation by Darin Dinsmore
Mammoth downtown revitalization action summit presentation by Darin DinsmoreDarin Dinsmore
 
Lean-agile management at Finnish Broadcasting Company Yle
Lean-agile management at Finnish Broadcasting Company YleLean-agile management at Finnish Broadcasting Company Yle
Lean-agile management at Finnish Broadcasting Company YleMirette Kangas
 
Adopted Glenferrie Road and High Street Structure Plan
Adopted Glenferrie Road and High Street Structure PlanAdopted Glenferrie Road and High Street Structure Plan
Adopted Glenferrie Road and High Street Structure PlanStonnington
 
January 28, 2022 Greening Lower Grand Avenue Update
January 28, 2022 Greening Lower Grand Avenue UpdateJanuary 28, 2022 Greening Lower Grand Avenue Update
January 28, 2022 Greening Lower Grand Avenue UpdatePlanetCommunities
 

Similar to Oh workshop02 full_final (20)

Portfolio_MikeGrogan
Portfolio_MikeGroganPortfolio_MikeGrogan
Portfolio_MikeGrogan
 
Kellen Kyger Portfolio with Revit 013117
Kellen Kyger Portfolio with Revit 013117Kellen Kyger Portfolio with Revit 013117
Kellen Kyger Portfolio with Revit 013117
 
Portfolio 2016 - Nakorn
Portfolio 2016 - NakornPortfolio 2016 - Nakorn
Portfolio 2016 - Nakorn
 
Professional Portfolio
Professional PortfolioProfessional Portfolio
Professional Portfolio
 
WatsonMArch Portfolio
WatsonMArch PortfolioWatsonMArch Portfolio
WatsonMArch Portfolio
 
Newport Beach Civic Center and Park - Lessons Learned in Sustainability
Newport Beach Civic Center and Park - Lessons Learned in SustainabilityNewport Beach Civic Center and Park - Lessons Learned in Sustainability
Newport Beach Civic Center and Park - Lessons Learned in Sustainability
 
Benning Park Meeting Presentation (July 28, 2016)
Benning Park Meeting Presentation (July 28, 2016)Benning Park Meeting Presentation (July 28, 2016)
Benning Park Meeting Presentation (July 28, 2016)
 
Garrison Elementary School SIT Presentation (December 9, 2015)
Garrison Elementary School SIT Presentation (December 9, 2015)Garrison Elementary School SIT Presentation (December 9, 2015)
Garrison Elementary School SIT Presentation (December 9, 2015)
 
Resumé of Suvir Hira
Resumé of Suvir HiraResumé of Suvir Hira
Resumé of Suvir Hira
 
Parklet handbook din_2017 - Seattle
Parklet handbook din_2017 - SeattleParklet handbook din_2017 - Seattle
Parklet handbook din_2017 - Seattle
 
Portfolio
PortfolioPortfolio
Portfolio
 
Detweiler Engineering Resume (1)
Detweiler Engineering Resume (1)Detweiler Engineering Resume (1)
Detweiler Engineering Resume (1)
 
ABC's of Cap Parks
ABC's of Cap ParksABC's of Cap Parks
ABC's of Cap Parks
 
Tough projects keeping them on course -1- mike mellin 02-18-16
Tough projects   keeping them on course -1- mike mellin 02-18-16Tough projects   keeping them on course -1- mike mellin 02-18-16
Tough projects keeping them on course -1- mike mellin 02-18-16
 
Mammoth downtown revitalization action summit presentation by Darin Dinsmore
Mammoth downtown revitalization action summit presentation by Darin DinsmoreMammoth downtown revitalization action summit presentation by Darin Dinsmore
Mammoth downtown revitalization action summit presentation by Darin Dinsmore
 
East Side Coastal Resiliency Project
East Side Coastal Resiliency ProjectEast Side Coastal Resiliency Project
East Side Coastal Resiliency Project
 
Lean-agile management at Finnish Broadcasting Company Yle
Lean-agile management at Finnish Broadcasting Company YleLean-agile management at Finnish Broadcasting Company Yle
Lean-agile management at Finnish Broadcasting Company Yle
 
Adopted Glenferrie Road and High Street Structure Plan
Adopted Glenferrie Road and High Street Structure PlanAdopted Glenferrie Road and High Street Structure Plan
Adopted Glenferrie Road and High Street Structure Plan
 
Pm project 1
Pm project 1Pm project 1
Pm project 1
 
January 28, 2022 Greening Lower Grand Avenue Update
January 28, 2022 Greening Lower Grand Avenue UpdateJanuary 28, 2022 Greening Lower Grand Avenue Update
January 28, 2022 Greening Lower Grand Avenue Update
 

More from publicinvolvement

Guaranteed Maximum Price Amendment #13
Guaranteed Maximum Price Amendment #13Guaranteed Maximum Price Amendment #13
Guaranteed Maximum Price Amendment #13publicinvolvement
 
Community Advisory Group meeting 5
Community Advisory Group meeting 5Community Advisory Group meeting 5
Community Advisory Group meeting 5publicinvolvement
 
Oak Harbor Windjammer Park Integration Plan
Oak Harbor Windjammer Park Integration Plan Oak Harbor Windjammer Park Integration Plan
Oak Harbor Windjammer Park Integration Plan publicinvolvement
 
Oak Harbor Community Advisory Group meeing 2 and public open house
Oak Harbor Community Advisory Group meeing 2 and public open houseOak Harbor Community Advisory Group meeing 2 and public open house
Oak Harbor Community Advisory Group meeing 2 and public open housepublicinvolvement
 
150604 Oak Harbor Wastewater Treatment Plant Update
150604 Oak Harbor Wastewater Treatment Plant Update150604 Oak Harbor Wastewater Treatment Plant Update
150604 Oak Harbor Wastewater Treatment Plant Updatepublicinvolvement
 
130306 city council workshop revised
130306 city council workshop revised130306 city council workshop revised
130306 city council workshop revisedpublicinvolvement
 

More from publicinvolvement (7)

Guaranteed Maximum Price Amendment #13
Guaranteed Maximum Price Amendment #13Guaranteed Maximum Price Amendment #13
Guaranteed Maximum Price Amendment #13
 
Community Advisory Group meeting 5
Community Advisory Group meeting 5Community Advisory Group meeting 5
Community Advisory Group meeting 5
 
Oak Harbor Windjammer Park Integration Plan
Oak Harbor Windjammer Park Integration Plan Oak Harbor Windjammer Park Integration Plan
Oak Harbor Windjammer Park Integration Plan
 
Oak Harbor Community Advisory Group meeing 2 and public open house
Oak Harbor Community Advisory Group meeing 2 and public open houseOak Harbor Community Advisory Group meeing 2 and public open house
Oak Harbor Community Advisory Group meeing 2 and public open house
 
150604 Oak Harbor Wastewater Treatment Plant Update
150604 Oak Harbor Wastewater Treatment Plant Update150604 Oak Harbor Wastewater Treatment Plant Update
150604 Oak Harbor Wastewater Treatment Plant Update
 
130306 city council workshop revised
130306 city council workshop revised130306 city council workshop revised
130306 city council workshop revised
 
Volume i executive summary
Volume i executive summaryVolume i executive summary
Volume i executive summary
 

Oh workshop02 full_final

  • 1. Clean Water Facility Design Workshop #2 5/6/2015Design Workshop #2
  • 2. Project Status and Update 5/6/2015Design Workshop #2  Project schedule  Outfall construction begins Summer 2015
  • 3. 2010 2011 2012 2013 2014 2015 2016 2017 Open House Potential Locations Open House Top 5 Sites Open House Top 3 Sites City Council Windjammer Vicinity Architectural Charrette Ch 10 Program Charrette Top 2 Sites Charrette Orientation on Property Architectural Charrette Aug 2010 Nov 2013Facilities Plan Mar 2013 Dec 2015Design Jun 2015 Dec 2017Construction Public Feedback Opportunities Design Workshop #2 5/6/2015
  • 4. Outfall Construction - Summer 2015 5/6/2015Design Workshop #2  Outfall construction schedule is separate from the facility design/construction schedule  Location was selected independent of facility location  Essential piece of wastewater infrastructure needed to support increased system use in Oak Harbor
  • 5. RECAP OF WHERE WE WERE AND WHERE WE ARE NOW… MAY 6, 2015
  • 6. OLD SCHEME SITE PLAN– AUGUST 6TH 2014MAY 6, 2015
  • 7. OLD SCHEME – AUGUST 6TH 2014MAY 6, 2015
  • 8. OLD SCHEME – AUGUST 6TH 2014MAY 6, 2015
  • 9. NOVEMBER 13TH 2014 DESIGN WORKSHOP #1 CONCEPT 1: CAMPUS CONCEPT 2: COURTYARD MAY 6, 2015
  • 10. NOVEMBER 13TH 2014 DESIGN WORKSHOP #1 CONCEPT 1: CAMPUS CONCEPT 2: COURTYARD MAY 6, 2015
  • 11. KEY TAKEAWAYS FROM DESIGN WORKSHOP #1 • Facility should set the stage for a community design aesthetic • A combination of both a campus and a courtyard with higher priority on campus • Regional design as an architectural aesthetic, incorporate both contemporary and traditional NW architecture • Open and light, enhance sight lines to water, park, and windmill • Allow for community interaction with facility, include educational features • Varying heights of roof lines • Provide “camouflaging” – it should not advertise that it’s a sewage treatment plant • Integrate with surroundings – WJ Park, harbor area, downtown 2014 Design Workshop Results: MAY 6, 2015
  • 12. DESIGN IMPETUS A building that isn’t what it seems on the outside, integrates (blends) with its surroundings MAY 6, 2015
  • 13. V DESIGN DIAGRAM - 1MAY 6, 2015
  • 14. V DESIGN DIAGRAM - 2MAY 6, 2015
  • 15. V DESIGN DIAGRAM - 3MAY 6, 2015
  • 16. V DESIGN DIAGRAM - 4 Screening element added to the spaces between building masses Screens are pushed back from façade to accentuate the building campus form MAY 6, 2015
  • 17. V DESIGN DIAGRAM - 5 Taller building elements pulled up from masses below create roof lines of varying height These elements are translucent to enhance the open and light concept MAY 6, 2015
  • 18. SITE PLAN PRIOR TO VALUE ENGINEERINGMAY 6, 2015
  • 19. CURRENT SITE PLAN LAYOUT RELOCATION OF HEADWORKS BUILDING FOOTPRINT AND CONFIGURATION BEING REVISED MAY 6, 2015
  • 20. MATERIAL PALLET SIMPLE, CLEAN & DURABLE MAY 6, 2015
  • 21. MATERIAL EXAMPLES SSG CURTAIN WALL SYSTEM “Open and light, provide for transparency” MAY 6, 2015
  • 22. MATERIAL EXAMPLES MASONRY Textural qualities of a long lasting material “set the stage for a community design aesthetic” MAY 6, 2015
  • 24. MATERIAL EXAMPLES WOOD SIDING & SCREENING ELEMENTS Regional design with wood shading elements relates to an abundance of driftwood on this site MAY 6, 2015
  • 26. AERIAL PERSPECTIVE LOOKING NORTH Within a campus style, provide varied roof lines, solids and voids with building masses MAY 6, 2015
  • 27. ADMINISTRATION / MAINTENANCE PLAN – GROUND FLOOR Allow for community interaction with facility, include educational features MAINTENANCEADMINISTRATION MAY 6, 2015
  • 28. TRAINING CENTER PLAN– SECOND FLOOR 2ND FLOOR TRAINING FACILITY MAY 6, 2015
  • 29. WEST ELEVATION | Administration Building MAY 6, 2015
  • 30. VIEW AT PROMENADE | Looking South MAY 6, 2015
  • 31. AERIAL VIEW | Looking North MAY 6, 2015
  • 32. PERSPECTIVE | Looking North MAY 6, 2015
  • 33. AERIAL VIEW | City Beach MAY 6, 2015
  • 34. PERSPECTIVE | City Beach & Bay Shore MAY 6, 2015
  • 36. WINDJAMMER PARK MAY 6, 2015 CONCEPTUAL LANDSCAPE PLAN
  • 38. CONCEPTUAL LANDSCAPE – STORMWATER & SEATINGMAY 6, 2015
  • 39. CONCEPTUAL LANDSCAPE – STORMWATER & SEATINGMAY 6, 2015
  • 40. KEY TAKEAWAYS FROM DESIGN WORKSHOP #1 • Facility should set the stage for a community design aesthetic • A combination of both a campus and a courtyard with higher priority on campus • Regional design as an architectural aesthetic, incorporate both contemporary and traditional NW architecture • Open and light, enhance sight lines to water, park, and windmill • Allow for community interaction with facility, include educational features • Varying heights of roof lines • Provide “camouflaging” – it should not advertise that it’s a sewage treatment plant • Integrate with surroundings – WJ Park, harbor area, downtown 2014 Design Workshop Results: MAY 6, 2015
  • 42. Design Concept 5/6/2015Design Workshop #2  Where do you see your feedback incorporated? Please write your thoughts on the large matrix on the wall
  • 43. Design Concept 5/6/2015Design Workshop #2  What is it about the design that best reflects feedback from previous discussion?  Where is more work needed?  Have we missed anything?
  • 44. Design Concept - Landscape 5/6/2015Design Workshop #2  What portions of the updated design will be benefitted most by landscape/hardscape?  Have we missed anything?