Opening of the Diverging Diamond Interchange
Interstate 66/Route 15 in Prince William County
Public Information Meeting
Christiana Briganti-Dunn, PE, CCM
Design-Build Program Manager
Virginia Department of Transportation
Jan A. Sherman
Design-Build Project Manager
The Lane Construction Corporation
December 7 and 13, 2016
Tonight’s Meeting
• Project Status
• Opening the Diverging Diamond Interchange
• Detour for One Night
• How to Navigate through the New DDI
• Project Schedule and Cost Updates
• Stations Around the Room:
• Simulation Videos
• FHWA Alternative Intersections Video
• Interactive Exhibit
2
3
Project Status
(Items in Orange are Complete, Blue are Ongoing)
• Reconstruct I-66/Route 15 interchange as a Diverging
Diamond Interchange (DDI)
• Replace Route 15 bridges over I-66
• Retaining walls, shared-use path, partial interchange
lighting, fencing, and architectural treatments
• Geometric and access management improvements to
ramps, intersections, Route 55, and frontage road
• Provide drainage and stormwater management facilities
• Replace/modify traffic signals, signs and sign structures,
and guardrail/barrier
• Construct a sound barrier Wall
• Landscaping (will be completed under separate contract)
Opening the DDI Configuration
• Close interchange and detour traffic starting 8 p.m.
Friday, Jan. 6 (or Jan. 13, weather depending), to place
final pavement markings
• Route 15 closed from south of Heathcote Blvd to north
of Route 55/Washington St
• Ramps to and from I-66 will also be closed
• Local traffic will be detoured to Old Carolina Rd/
Jefferson St
• Interstate traffic use Route 29 in Gainesville
• Open DDI to traffic by 9 a.m. Saturday, Jan. 7 (or Jan. 14)
• All ramps to and from the Interstate 66
• Two lanes in each direction on Route 15
4
Detour – Night of Jan. 6 (or Jan. 13)
5
6
Diverging Diamond Interchange
Traffic Flow
7
Diverging Diamond Interchange
Traffic Flow
8
Project Schedule
Contract awarded May 2014
Public information meeting October 2014
Began right-of-way acquisition Winter 2014
Began construction Spring Fall 2015*
Open DDI configuration January 2017
Project completion Fall Summer 2017
* Project construction is approximately 70% complete.
9
Project Costs
Preliminary engineering: $3 Million
Right-of-way acquisition and
relocation assistance: $8 Million
Design/Build contract (final design,
utility relocation, and construction),
Contingency and VDOT oversight: $48 Million
Total cost: $59 Million
The above estimate has remain unchanged since October 2014.
The project is fully funded by state and federal funds.
Stations Around the Room
• VISSIM simulation videos
• Based on actual design for DDI in Haymarket
• Shows future 2036 traffic volumes, AM and PM peaks
• FHWA Alternative Intersections Video – “As
easy as 1-2-3”:
• To Turn Left – Stay to the Left
• To Turn Right – Stay to the Right
• No Turns at Crossover Intersections – Go “Straight”
• Interactive exhibit
• Attendees are invited to “walk” through the DDI exhibit
the way they would drive through one
10
11
12
For More Information…
http://www.virginiadot.org/projects/northernvirginia/i-
66_and_route_15_interchange.asp
OR:
• Visit www.virginiadot.org
• Click on “Projects and Studies” in the orange bar
• Click on the “Northern Virginia” portion of the map
• Scroll to “Under Construction” and look for “I-66 and
Route 15 Interchange Reconstruction” link
Project Manager: Christiana Briganti-Dunn, P.E., CCM
Phone: 703-259-2960
E-mail: Christiana.Briganti@vdot.virginia.gov
Traffic Comparison to VDOT’s 1st DDI
180 270
120
0
120
450 310
300 90
700 180
60
0
160
Zion Crossroads DDI
1500
670
1110
720
I-64 WB
Off-Ramp
I-64 WB
On-Ramp
I-64 EB
On-Ramp
I-64 EB
Off-Ramp
US Route 15
I-64
2010 AM Peak
40 1160
320
0
200
40 600
580 780
510 810
130
0
100
Haymarket DDI
570
1520
1010
2880
I-66 WB
Off-Ramp
I-66 WB
On-Ramp
I-66 EB
On-Ramp
I-66 EB
Off-Ramp
US Route 15
I-66
2011 AM Peak
80 530
140
0
140
150 480
550 120
440 150
190
0
350
Zion Crossroads DDI
1070
1720
1120
1450
I-64 WB
Off-Ramp
I-64 WB
On-Ramp
I-64 EB
On-Ramp
I-64 EB
Off-Ramp
US Route 15
I-64
2010 PM Peak
110 1010
740
0
880
140 580
1510 380
680 310
40
0
50
Haymarket DDI
1130
740
2500
1340
I-66 WB
Off-Ramp
I-66 WB
On-Ramp
I-66 EB
On-Ramp
I-66 EB
Off-Ramp
US Route 15
I-66
2011 PM Peak
Traffic Comparison to VDOT’s 1st DDI
How Haymarket DDI differs from
Zion Crossroads DDI
15
Triple Left
Dual Left
3 Lanes NB/SB
Single
Right
Spur Ramp to H

Diverging Diamond Interchange: I-66 and Route 15

  • 1.
    Opening of theDiverging Diamond Interchange Interstate 66/Route 15 in Prince William County Public Information Meeting Christiana Briganti-Dunn, PE, CCM Design-Build Program Manager Virginia Department of Transportation Jan A. Sherman Design-Build Project Manager The Lane Construction Corporation December 7 and 13, 2016
  • 2.
    Tonight’s Meeting • ProjectStatus • Opening the Diverging Diamond Interchange • Detour for One Night • How to Navigate through the New DDI • Project Schedule and Cost Updates • Stations Around the Room: • Simulation Videos • FHWA Alternative Intersections Video • Interactive Exhibit 2
  • 3.
    3 Project Status (Items inOrange are Complete, Blue are Ongoing) • Reconstruct I-66/Route 15 interchange as a Diverging Diamond Interchange (DDI) • Replace Route 15 bridges over I-66 • Retaining walls, shared-use path, partial interchange lighting, fencing, and architectural treatments • Geometric and access management improvements to ramps, intersections, Route 55, and frontage road • Provide drainage and stormwater management facilities • Replace/modify traffic signals, signs and sign structures, and guardrail/barrier • Construct a sound barrier Wall • Landscaping (will be completed under separate contract)
  • 4.
    Opening the DDIConfiguration • Close interchange and detour traffic starting 8 p.m. Friday, Jan. 6 (or Jan. 13, weather depending), to place final pavement markings • Route 15 closed from south of Heathcote Blvd to north of Route 55/Washington St • Ramps to and from I-66 will also be closed • Local traffic will be detoured to Old Carolina Rd/ Jefferson St • Interstate traffic use Route 29 in Gainesville • Open DDI to traffic by 9 a.m. Saturday, Jan. 7 (or Jan. 14) • All ramps to and from the Interstate 66 • Two lanes in each direction on Route 15 4
  • 5.
    Detour – Nightof Jan. 6 (or Jan. 13) 5
  • 6.
  • 7.
  • 8.
    8 Project Schedule Contract awardedMay 2014 Public information meeting October 2014 Began right-of-way acquisition Winter 2014 Began construction Spring Fall 2015* Open DDI configuration January 2017 Project completion Fall Summer 2017 * Project construction is approximately 70% complete.
  • 9.
    9 Project Costs Preliminary engineering:$3 Million Right-of-way acquisition and relocation assistance: $8 Million Design/Build contract (final design, utility relocation, and construction), Contingency and VDOT oversight: $48 Million Total cost: $59 Million The above estimate has remain unchanged since October 2014. The project is fully funded by state and federal funds.
  • 10.
    Stations Around theRoom • VISSIM simulation videos • Based on actual design for DDI in Haymarket • Shows future 2036 traffic volumes, AM and PM peaks • FHWA Alternative Intersections Video – “As easy as 1-2-3”: • To Turn Left – Stay to the Left • To Turn Right – Stay to the Right • No Turns at Crossover Intersections – Go “Straight” • Interactive exhibit • Attendees are invited to “walk” through the DDI exhibit the way they would drive through one 10
  • 11.
  • 12.
    12 For More Information… http://www.virginiadot.org/projects/northernvirginia/i- 66_and_route_15_interchange.asp OR: •Visit www.virginiadot.org • Click on “Projects and Studies” in the orange bar • Click on the “Northern Virginia” portion of the map • Scroll to “Under Construction” and look for “I-66 and Route 15 Interchange Reconstruction” link Project Manager: Christiana Briganti-Dunn, P.E., CCM Phone: 703-259-2960 E-mail: Christiana.Briganti@vdot.virginia.gov
  • 13.
    Traffic Comparison toVDOT’s 1st DDI 180 270 120 0 120 450 310 300 90 700 180 60 0 160 Zion Crossroads DDI 1500 670 1110 720 I-64 WB Off-Ramp I-64 WB On-Ramp I-64 EB On-Ramp I-64 EB Off-Ramp US Route 15 I-64 2010 AM Peak 40 1160 320 0 200 40 600 580 780 510 810 130 0 100 Haymarket DDI 570 1520 1010 2880 I-66 WB Off-Ramp I-66 WB On-Ramp I-66 EB On-Ramp I-66 EB Off-Ramp US Route 15 I-66 2011 AM Peak
  • 14.
    80 530 140 0 140 150 480 550120 440 150 190 0 350 Zion Crossroads DDI 1070 1720 1120 1450 I-64 WB Off-Ramp I-64 WB On-Ramp I-64 EB On-Ramp I-64 EB Off-Ramp US Route 15 I-64 2010 PM Peak 110 1010 740 0 880 140 580 1510 380 680 310 40 0 50 Haymarket DDI 1130 740 2500 1340 I-66 WB Off-Ramp I-66 WB On-Ramp I-66 EB On-Ramp I-66 EB Off-Ramp US Route 15 I-66 2011 PM Peak Traffic Comparison to VDOT’s 1st DDI
  • 15.
    How Haymarket DDIdiffers from Zion Crossroads DDI 15 Triple Left Dual Left 3 Lanes NB/SB Single Right Spur Ramp to H