Tutorial 2: 
 Creating a Project Schedule
 Creating a Project Sched le

Microsoft Project 2010
               ®




       http://www.learningquotient.in
In Tutorial Section 2.1                                           XP
      you will:
      you will:
      •     Start a new project
      •     Examine scheduling defaults
                       h d l d f l
      •     Change a project and task calendar
      •     Enter and edit tasks and durations
      •     Enter and edit recurring tasks and milestones
            Enter and edit recurring tasks and milestones
      •     Enter lag and lead times




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   2
In Tutorial Section 2.2                                           XP
      you will:
      you will:
      •     Enter and edit task dependencies
      •     View project statistics
      •     Show the project summary
      •     Review project statistics
      •     Create and manipulate summary tasks
            Create and manipulate summary tasks
      •     Develop a work breakdown structure




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   3
XP

      • By default, the new project file is scheduled from a 
        project Start date
        project Start date
      • All tasks are scheduled to begin as soon as possible
      • Project 2010 calculates the project’s Finish date
        Project 2010 calculates the project s Finish date 
        based on the: 
             – Tasks
             – Durations
             – Dependencies




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   4
Project Information Dialog Box                                    XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   5
Scheduling a Project from a Finish                                XP
      Date
      • When a project is scheduled from a Finish date, such 
        as a conference, all tasks are scheduled to begin as 
        as a conference all tasks are scheduled to begin as
        late as possible.
      • Project 2010 calculates the project’s Start date based
        Project 2010 calculates the project s Start date based 
        on the tasks, durations and dependencies.
      • The default is for all tasks and the project to start as 
                                             p j
        late as possible.
                                           y    pp y
      • To schedule from a Finish Date, you apply this setting  g
        as soon as the project is created.



                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   6
Project Scheduled From Finish Date                                XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   7
The Task Information Dialog Box                                   XP

      • The Task Information dialog box is a comprehensive 
        collection of all of the information about each task 
        collection of all of the information about each task
        organized into six categories:
             –    General
             –    Predecessors
             –    Resources
             –    Advanced
             –    Notes
             –    Custom Fields
                            ld
      • The Task Information dialog box is another view by 
        which you can examine and enter data about a task.
        which you can examine and enter data about a task

                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   8
The Task Information Dialog Box                                   XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   9
Constraints using Task Information
                                       XP

      • How the project is originally scheduled (from a Start 
        date or from a Finish date) determines the initial 
                                   )
        Constraint types (as soon as possible or as late as 
        possible).
      • The initial Constraint type has a tremendous impact 
         h        l                  h           d
        on the calculated start and finish dates for each task 
        entered into the project.
        entered into the project.
      • Always take the time to examine the Project 
        Information dialog box before starting a new project.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                              10
Examining Project Calendars                                       XP

      • By default, the entire project, each task, and each 
        resource is scheduled according to the Standard 
        calendar.
      • The Standard calendar specifies that Monday through 
        Friday are working days with 8 hours of work completed 
        Friday are working days with 8 hours of work completed
        each day.
      • Saturday and Sunday are designated as nonworking days.
      • The Calendar can be modified to identify holidays or 
        other nonworking days or times in which work should not 
        be scheduled.  
        be scheduled
      • You can also create unique calendars for tasks and 
        resources that do not follow the working and nonworking 
        times specified by the Standard calendar.
                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   11
Change Time for a Work Week                                       XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   12
Creating a Task Calendar                                          XP




      • An individual task calendar can be created for any
        An individual task calendar can be created for any 
        task that does not follow the working and 
        nonworking times specified by the project calendar. 
      • An individual resource calendar can be created for a 
        resource that does not follow the working and 
        nonworking times specified by the project calendar. 
        nonworking times specified by the project calendar
      • By default, all tasks and resource assignments inherit 
            p j                      y    p y            g
        the project calendar unless you specify something 
        else. 
                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   13
Changing the Calendar for a Task                                  XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   14
Applying a Task Calendar to a Task
                                       XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                              15
Entering Tasks and Durations                                      XP
      in the Entry Table
      in the Entry Table
      • Entering tasks and durations is probably the single 
        most important effort in developing a useful project 
                  p                     p g          p j
        file.
      • If tasks are omitted or durations underestimated, the 
        value of the project’s scheduling and cost 
           l    f h         ’ h d l         d
        information is compromised and the success of the 
        project might be jeopardized.
        project might be jeopardized.
      • Often you will need to change an existing task or 
        insert, delete, or move a task.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   16
Editing Tasks and Durations                                       XP
      in the Entry Table
      in the Entry Table
      • Project 2010 makes it very easy to edit an existing 
        p j
        project.
      • Many of the editing skills that you gained when 
        editing a spreadsheet will apply to a project table.
      • To change an existing entry, you first navigate to the 
        cell.  Once there, you have several options:
             –R t
               Retype the entry
                       th     t
             – Edit the entry directly in the cell
             – Edit an entry in the Entry bar
                           y             y




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   17
Entering and Editing Tasks                                        XP
      in the Entry Table
      in the Entry Table




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   18
To Delete a Task                                                  XP

      • If you want to delete an entire task row in Project 
        2010, you must select the entire row, then press the 
        2010 you must select the entire row then press the
        Delete key.
      • Project 2010 includes a Smart Tag to allow you to
        Project 2010 includes a Smart Tag to allow you to 
        specify what you want to delete.
      • A list arrow appears when you place the pointer over 
                      pp           y p            p
        the Smart Tag.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   19
Smart Tag Selection for Task                                      XP
      Deletion




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   20
Copy, Paste and Move                                              XP

      • Copying, pasting, and moving tasks are important 
        task editing skills.  
        task editing skills
      • Project 2010 offers a variety of tools that you can use 
        to accomplish these common tasks, including:
        to accomplish these common tasks, including:
             –    Menu bar options
             –    Toolbar buttons
             –    Quick keystrokes
             –    Right‐click shortcut menus




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   21
Fill Handle                                                       XP

      • If several task durations are the same, you can use 
        either the copy and paste features to quickly enter 
        either the copy and paste features to quickly enter
        the durations or the fill handle to populate cells.
      • If you have used the fill handle in Excel or another
        If you have used the fill handle in Excel or another 
        spreadsheet program, you will find it a very similar 
        process in Project 2010.
      • The fill handle is a small square that appears in the 
        lower corner of the selected cell.
      • When you drag a fill handle, the contents of the 
        active cell are copied.
      • You can also use the fill handle to fill task names.
                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   22
Fill Handle                                                       XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   23
Working with Duration Units of                                    XP
      Measure
      • Entering and editing durations involves 
        understanding the units of measure available for 
        understanding the units of measure available for
        them.
      • The default unit of measure is day, and therefore
        The default unit of measure is day, and therefore 
        “day” does not need to be entered.
      • To use any other unit, you must type the 
                  y          ,y          yp
        abbreviation.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   24
Units of Measure Abbreviations                                    XP

      • Elapsed refers to clock time rather than working 
        time.
      • An example is the task “Allow paint to dry.” The paint 
        will dry in exactly the same amount of time 
        regardless of whether it dries on a workday, a 
              dl      f h h       d             kd
        weekend or holiday.  If it takes one day to dry, the 
        duration should be entered as  1 ed (for 1 elapsed
        duration should be entered as “1 ed” (for 1 elapsed
        day). 




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   25
Editing Tasks and Durations                                       XP
      in Other Views
      in Other Views
      • Anything changed in one view is automatically 
        changed in all the other views.
        changed in all the other views
      • You can use the View Bar to quickly switch between 
        views.
        views
      • The way data is displayed differs by view and often 
        satisfies different communication and reporting 
        satisfies different communication and reporting
        needs as the project develops.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   26
Editing Tasks and Durations                                       XP
      in Other Views Cont. d
      in Other Views Cont ’d
      • Regardless of the view used, you can edit any task by 
        double clicking it to open its Task Information dialog 
        double‐clicking it to open its Task Information dialog
        box.
      • As you work with Project 2010, you will become
        As you work with Project 2010, you will become 
        more familiar with each view and learn which is the 
        best representation of the data for different 
        purposes.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   27
Entering Recurring Tasks                                          XP

      • A recurring task is a task that repeats at a regular 
        interval.  
      • A status meeting is a good example of a recurring 
        task that needs to be scheduled for each week or 
        other regular intervals in the project.
          h         l         l     h
      • In Project 2010, you can define a recurring task one 
        time using the Recurring Task Information dialog box.
        time using the Recurring Task Information dialog box
      • Project 2010 then handles the details of scheduling 
                      p                               p j
        the task at specified interval for the entire project or 
        for the time period you specify.
      • You can also change the calendar used on the 
        recurring task in the Calendar section.
                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   28
Recurring Task Information Dialog 
                                       XP
      Box




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                              29
Entering Milestones                                               XP

      • A milestone is a task that marks a significant point in 
        time or a progress checkpoint.
        time or a progress checkpoint
      • It has a zero duration and is therefore a symbolic task 
        that is used mainly to communicate progress or to 
        that is used mainly to communicate progress or to
        mark the end of a significant phase of the project.
      • Examples include the signing of a contract or the 
              p                 g g
        announcement of a new product.
                                                   p j
      • Milestones can also be used to motivate project 
        participants by recognizing accomplishments.



                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   30
Milestones                                                        XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   31
Understanding Task Dependencies
                                    XP

      • Four task dependencies define the relationships 
        between tasks in a project.
        between tasks in a project




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                              32
Understanding Task Dependencies 
                                    XP
      Cont. d
      Cont ’d
      • By linking tasks in finish‐to‐start relationships, you 
        establish the required sequence of tasks.
        establish the required sequence of tasks
      • Project 2010 uses these relationships to set start and 
        finish dates for each task.
        finish dates for each task.
      • Most dependencies are Finish‐to‐Start (FS), meaning 
        a certain task (the predecessor) must finish before 
                       (     p            )
        another task (the successor) can start.
                           p         p j           g
      • In order to use important project management 
        techniques such as critical path analysis, you must 
        determine task dependencies.

                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                              33
Creating Task Dependencies                                        XP

      • Project 2010 makes it easy to create, and remove, FS 
        relationships between tasks by providing the Link 
                   p                  yp        g
        Tasks and Unlink Tasks buttons on the Standard 
        toolbar.
      • Task dependencies also can be established in the 
            kd      d       l       b      bl h d     h
        graphical views.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   34
Creating Task Dependencies Cont.XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                              35
Slack Times                                                       XP

      • Total slack is the amount of time by which an activity 
        may be delayed from its scheduled Start date without 
        may be delayed from its scheduled Start date without
        the delay setting back the entire project.
      • Free slack is the amount of time by which an activity
        Free slack is the amount of time by which an activity 
        may be delayed without delaying the early start of 
        any immediately following tasks.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   36
Critical and Non‐Critical Tasks                                   XP

      • In the Network Diagram view, the critical tasks—
        tasks that are on the critical path—are displayed 
                                       p              p y
        within a red border.
      • A task that is not on the critical path is a non‐critical 
        task, that is, it doesn’t necessarily have to start on its 
            k h           d    ’           l h
        currently scheduled Start date in order for the overall 
        project to be completed on time.
        project to be completed on time.
      • The Network Diagram is used mainly to view and 
        analyze the critical path.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   37
Creating Dependencies using the                                   XP
      Network Diagram view
      Network Diagram view




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   38
Entering Lag and Lead Times                                       XP

      • When a project is scheduled from a Start date, lag 
        and lead times refer to an amount of time that the 
        second task of a relationship is moved backward 
        (lead) or forward (lag) in time.
      • Lead time moves the second task backward in time 
            d              h         d kb k         d
        so that the two tasks overlap.  
      • Lag time is the opposite of lead time It moves the
        Lag time is the opposite of lead time.  It moves the 
        second task forward in time so that the tasks are 
        further separated.  




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   39
Lag and Lead Time from Start Date
                                      XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                              40
Entering Lag and Lead Times Cont.’d                                   XP

      • Project 2010 combines the concepts of lag and lead 
        times into one term, lag time.  
                            , g
      • When a project is scheduled from a Start date, 
        positive lag time moves the second task forward in 
        time.
             – Positive lag time is the traditional definition of lag time in 
               general project management discussions.
               general project management discussions.
      • Negative lag time moves the second task backward 
        in time so that the tasks overlap.  
             – Negative lag time is called lead time in general project 
               management discussions.



                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                       41
Negative and Positive Lag Time                                    XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   42
Check for Lag Time Effects Cont.                                      XP

      • Confusing negative and positive lag times is easy, 
        especially when examining them for both a project 
          p       y               g                 p j
        that is scheduled from a Start date and one 
        scheduled from a Finish date.
      • Remember:b
             – Positive lag time always increases the amount of time 
               between tasks.
               between tasks.
             – Negative lag time always causes the tasks to overlap.
             – This rule holds true regardless of whether the project is 
               scheduled from the Start date or the Finish date.
                 h d l df       th St t d t       th Fi i h d t




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                       43
Check for Lag Time Effects                                        XP

      • Once the tasks, durations, and relationships are 
        entered, you should check the Project Information
        entered you should check the Project Information
        dialog box to verify the project’s calculated Finish 
        date if the project is scheduled from a Start date, or 
                     p j
        calculated Start date if the project is scheduled from 
        a Finish date.
      • When a project is scheduled from a Start date, 
        applying negative lag time to task dependencies that 
        are on the critical path is a common way to shorten 
                th iti l th i                       t h t
        the critical path because it allows tasks to overlap.


                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   44
Check for Lag Time Effects Cont.’dXP
      • When you apply negative lag time, the second task is 
        allowed to start before the first task is completely 
        allowed to start before the first task is completely
        finished.
      • When a project is scheduled from a Finish date, all
        When a project is scheduled from a Finish date, all 
        tasks have as late as possible schedules and lag time 
        affects the first task rather than the second.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                              45
Lag Time From a Finish Date                                       XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   46
Creating a Work Breakdown Structure 
                                        XP
      with Summary Tasks
      with Summary Tasks
      • A very important strategy for managing projects well 
        is to organize the work that needs to be done in a 
                g
        logical manner.
      • A work breakdown structure (WBS) is an outcome‐
        oriented analysis of the work involved in a project 
                d     l     f h      k     l d
        that defines the total scope of the project.
             – A WBS is a foundation document in project management
               A WBS is a foundation document in project management 
               because it provides the basis for planning and managing 
               project schedules, costs, and changes.
             – The WBS provides a hierarchy similar to an organizational
               The WBS provides a hierarchy, similar to an organizational 
               chart, to group project work logically.



                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   47
Creating a Work Breakdown Structure 
                                        XP
      with Summary Tasks Cont. d
      with Summary Tasks Cont ’d
      • In order to use a WBS in Project 2010, you must 
        organize tasks into summary tasks (groups of tasks 
          g                         y      (g p
        that logically belong together).
      • When developing a new, large project, some project 
        managers prefer to start with broad groupings of 
                       f             hb d               f
        summary tasks and then break them down into 
        smaller tasks.
        smaller tasks.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                              48
Creating a Work Breakdown Structure 
                                        XP
      with Summary Tasks Cont. d
      with Summary Tasks Cont ’d
      • Planning a project by starting with broad categories 
        of tasks is called the top‐down method of creating a 
                                 p                         g
        WBS.
      • Other project managers prefer to list all of the 
        individual tasks, and then collect them into logical 
          d d l k            d h      ll    h         l    l
        groupings using the bottom‐up method.
      • Once you have indentified your summary tasks you
        Once you have indentified your summary tasks, you 
        use Outdenting and Indenting in Project 2010 to 
        create the summary tasks.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                              49
Outdenting and Indenting Tasks                                    XP

      • Use the Outdent button and the Indent button on the 
        Formatting toolbar to create your WBS.
        Formatting toolbar to create your WBS
      • Outdenting moves a task to the left (a higher level in 
        the WBS), and indenting moves a task to the right (a 
                 ),            g                       g (
        lower level in the WBS).
      • Projects can have several levels in the WBS.
      • Many projects have at least three levels, and some 
        large projects have more.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   50
Creating a Summary Task                                           XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   51
Displaying Outline Numbers                                        XP

      • Tasks and subtasks are organized in an outline, with 
        tasks in a hierarchy, when you have created summary 
        tasks in a hierarchy when you have created summary
        tasks.
      • In Project 2010, you can view built‐in outline
        In Project 2010, you can view built in outline 
        numbers, which will display in the Task name cells for 
        all tasks.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   52
Displaying Outline Numbers                                        XP
      Cont. d
      Cont ’d




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   53
Project Summary Task                                              XP

      • Many Project Managers like to create a Project 
        Summary Task which allows them to see how the 
        Summary Task which allows them to see how the
        start and finish dates change as they enter and edit 
        tasks, durations, and dependencies.
                                 p




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   54
Project Summary Task Cont.’d                                      XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   55
Expanding and Collapsing Tasks                                    XP

      • Once your project has been organized into summary 
        tasks, you can easily expand (show) and collapse
        tasks you can easily expand (show) and collapse
        (hide) the individual tasks within each phase.




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   56
Using WBS Codes                                                   XP

      • Many people like to number tasks in their WBS to 
        show the logical groupings of work.
        show the logical groupings of work
      • Using outline numbers or special work breakdown 
        structure (WBS) code is a way to use an 
        structure (WBS) code is a way to use an
        alphanumeric code to represent each task’s position 
        within the hierarchical structure of the project.
      • A WBS code helps identify and group project tasks for 
        project communication, documentation, or 
        accounting purposes.



                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   57
Creating WBS Codes                                                XP




                                       http://www.learningquotient.in
New Perspectives on Microsoft Project 2010                                   58

Ms project 2010 tutorial 2

  • 1.
    Tutorial 2:  Creating a Project Schedule Creatinga Project Sched le Microsoft Project 2010 ® http://www.learningquotient.in
  • 2.
    In Tutorial Section 2.1  XP you will: you will: • Start a new project • Examine scheduling defaults h d l d f l • Change a project and task calendar • Enter and edit tasks and durations • Enter and edit recurring tasks and milestones Enter and edit recurring tasks and milestones • Enter lag and lead times http://www.learningquotient.in New Perspectives on Microsoft Project 2010 2
  • 3.
    In Tutorial Section 2.2 XP you will: you will: • Enter and edit task dependencies • View project statistics • Show the project summary • Review project statistics • Create and manipulate summary tasks Create and manipulate summary tasks • Develop a work breakdown structure http://www.learningquotient.in New Perspectives on Microsoft Project 2010 3
  • 4.
    XP • By default, the new project file is scheduled from a  project Start date project Start date • All tasks are scheduled to begin as soon as possible • Project 2010 calculates the project’s Finish date Project 2010 calculates the project s Finish date  based on the:  – Tasks – Durations – Dependencies http://www.learningquotient.in New Perspectives on Microsoft Project 2010 4
  • 5.
    Project Information Dialog Box XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 5
  • 6.
    Scheduling a Project from a Finish  XP Date • When a project is scheduled from a Finish date, such  as a conference, all tasks are scheduled to begin as  as a conference all tasks are scheduled to begin as late as possible. • Project 2010 calculates the project’s Start date based Project 2010 calculates the project s Start date based  on the tasks, durations and dependencies. • The default is for all tasks and the project to start as  p j late as possible. y pp y • To schedule from a Finish Date, you apply this setting  g as soon as the project is created. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 6
  • 7.
    Project Scheduled From Finish Date XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 7
  • 8.
    The Task Information Dialog Box XP • The Task Information dialog box is a comprehensive  collection of all of the information about each task  collection of all of the information about each task organized into six categories: – General – Predecessors – Resources – Advanced – Notes – Custom Fields ld • The Task Information dialog box is another view by  which you can examine and enter data about a task. which you can examine and enter data about a task http://www.learningquotient.in New Perspectives on Microsoft Project 2010 8
  • 9.
    The Task Information Dialog Box XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 9
  • 10.
    Constraints using Task Information XP • How the project is originally scheduled (from a Start  date or from a Finish date) determines the initial  ) Constraint types (as soon as possible or as late as  possible). • The initial Constraint type has a tremendous impact  h l h d on the calculated start and finish dates for each task  entered into the project. entered into the project. • Always take the time to examine the Project  Information dialog box before starting a new project. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 10
  • 11.
    Examining Project Calendars XP • By default, the entire project, each task, and each  resource is scheduled according to the Standard  calendar. • The Standard calendar specifies that Monday through  Friday are working days with 8 hours of work completed  Friday are working days with 8 hours of work completed each day. • Saturday and Sunday are designated as nonworking days. • The Calendar can be modified to identify holidays or  other nonworking days or times in which work should not  be scheduled.   be scheduled • You can also create unique calendars for tasks and  resources that do not follow the working and nonworking  times specified by the Standard calendar. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 11
  • 12.
    Change Time for a Work Week XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 12
  • 13.
    Creating a Task Calendar XP • An individual task calendar can be created for any An individual task calendar can be created for any  task that does not follow the working and  nonworking times specified by the project calendar.  • An individual resource calendar can be created for a  resource that does not follow the working and  nonworking times specified by the project calendar.  nonworking times specified by the project calendar • By default, all tasks and resource assignments inherit  p j y p y g the project calendar unless you specify something  else.  http://www.learningquotient.in New Perspectives on Microsoft Project 2010 13
  • 14.
    Changing the Calendar for a Task XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 14
  • 15.
    Applying a Task Calendar to a Task XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 15
  • 16.
    Entering Tasks and Durations  XP in the Entry Table in the Entry Table • Entering tasks and durations is probably the single  most important effort in developing a useful project  p p g p j file. • If tasks are omitted or durations underestimated, the  value of the project’s scheduling and cost  l f h ’ h d l d information is compromised and the success of the  project might be jeopardized. project might be jeopardized. • Often you will need to change an existing task or  insert, delete, or move a task. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 16
  • 17.
    Editing Tasks and Durations  XP in the Entry Table in the Entry Table • Project 2010 makes it very easy to edit an existing  p j project. • Many of the editing skills that you gained when  editing a spreadsheet will apply to a project table. • To change an existing entry, you first navigate to the  cell.  Once there, you have several options: –R t Retype the entry th t – Edit the entry directly in the cell – Edit an entry in the Entry bar y y http://www.learningquotient.in New Perspectives on Microsoft Project 2010 17
  • 18.
    Entering and Editing Tasks XP in the Entry Table in the Entry Table http://www.learningquotient.in New Perspectives on Microsoft Project 2010 18
  • 19.
    To Delete a Task XP • If you want to delete an entire task row in Project  2010, you must select the entire row, then press the  2010 you must select the entire row then press the Delete key. • Project 2010 includes a Smart Tag to allow you to Project 2010 includes a Smart Tag to allow you to  specify what you want to delete. • A list arrow appears when you place the pointer over  pp y p p the Smart Tag. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 19
  • 20.
    Smart Tag Selection for Task  XP Deletion http://www.learningquotient.in New Perspectives on Microsoft Project 2010 20
  • 21.
    Copy, Paste and Move XP • Copying, pasting, and moving tasks are important  task editing skills.   task editing skills • Project 2010 offers a variety of tools that you can use  to accomplish these common tasks, including: to accomplish these common tasks, including: – Menu bar options – Toolbar buttons – Quick keystrokes – Right‐click shortcut menus http://www.learningquotient.in New Perspectives on Microsoft Project 2010 21
  • 22.
    Fill Handle XP • If several task durations are the same, you can use  either the copy and paste features to quickly enter  either the copy and paste features to quickly enter the durations or the fill handle to populate cells. • If you have used the fill handle in Excel or another If you have used the fill handle in Excel or another  spreadsheet program, you will find it a very similar  process in Project 2010. • The fill handle is a small square that appears in the  lower corner of the selected cell. • When you drag a fill handle, the contents of the  active cell are copied. • You can also use the fill handle to fill task names. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 22
  • 23.
    Fill Handle XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 23
  • 24.
    Working with Duration Units of  XP Measure • Entering and editing durations involves  understanding the units of measure available for  understanding the units of measure available for them. • The default unit of measure is day, and therefore The default unit of measure is day, and therefore  “day” does not need to be entered. • To use any other unit, you must type the  y ,y yp abbreviation. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 24
  • 25.
    Units of Measure Abbreviations XP • Elapsed refers to clock time rather than working  time. • An example is the task “Allow paint to dry.” The paint  will dry in exactly the same amount of time  regardless of whether it dries on a workday, a  dl f h h d kd weekend or holiday.  If it takes one day to dry, the  duration should be entered as  1 ed (for 1 elapsed duration should be entered as “1 ed” (for 1 elapsed day).  http://www.learningquotient.in New Perspectives on Microsoft Project 2010 25
  • 26.
    Editing Tasks and Durations XP in Other Views in Other Views • Anything changed in one view is automatically  changed in all the other views. changed in all the other views • You can use the View Bar to quickly switch between  views. views • The way data is displayed differs by view and often  satisfies different communication and reporting  satisfies different communication and reporting needs as the project develops. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 26
  • 27.
    Editing Tasks and Durations  XP in Other Views Cont. d in Other Views Cont ’d • Regardless of the view used, you can edit any task by  double clicking it to open its Task Information dialog  double‐clicking it to open its Task Information dialog box. • As you work with Project 2010, you will become As you work with Project 2010, you will become  more familiar with each view and learn which is the  best representation of the data for different  purposes. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 27
  • 28.
    Entering Recurring Tasks XP • A recurring task is a task that repeats at a regular  interval.   • A status meeting is a good example of a recurring  task that needs to be scheduled for each week or  other regular intervals in the project. h l l h • In Project 2010, you can define a recurring task one  time using the Recurring Task Information dialog box. time using the Recurring Task Information dialog box • Project 2010 then handles the details of scheduling  p p j the task at specified interval for the entire project or  for the time period you specify. • You can also change the calendar used on the  recurring task in the Calendar section. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 28
  • 29.
    Recurring Task Information Dialog  XP Box http://www.learningquotient.in New Perspectives on Microsoft Project 2010 29
  • 30.
    Entering Milestones XP • A milestone is a task that marks a significant point in  time or a progress checkpoint. time or a progress checkpoint • It has a zero duration and is therefore a symbolic task  that is used mainly to communicate progress or to  that is used mainly to communicate progress or to mark the end of a significant phase of the project. • Examples include the signing of a contract or the  p g g announcement of a new product. p j • Milestones can also be used to motivate project  participants by recognizing accomplishments. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 30
  • 31.
    Milestones XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 31
  • 32.
    Understanding Task Dependencies XP • Four task dependencies define the relationships  between tasks in a project. between tasks in a project http://www.learningquotient.in New Perspectives on Microsoft Project 2010 32
  • 33.
    Understanding Task Dependencies  XP Cont. d Cont ’d • By linking tasks in finish‐to‐start relationships, you  establish the required sequence of tasks. establish the required sequence of tasks • Project 2010 uses these relationships to set start and  finish dates for each task. finish dates for each task. • Most dependencies are Finish‐to‐Start (FS), meaning  a certain task (the predecessor) must finish before  ( p ) another task (the successor) can start. p p j g • In order to use important project management  techniques such as critical path analysis, you must  determine task dependencies. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 33
  • 34.
    Creating Task Dependencies XP • Project 2010 makes it easy to create, and remove, FS  relationships between tasks by providing the Link  p yp g Tasks and Unlink Tasks buttons on the Standard  toolbar. • Task dependencies also can be established in the  kd d l b bl h d h graphical views. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 34
  • 35.
    Creating Task Dependencies Cont.XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 35
  • 36.
    Slack Times XP • Total slack is the amount of time by which an activity  may be delayed from its scheduled Start date without  may be delayed from its scheduled Start date without the delay setting back the entire project. • Free slack is the amount of time by which an activity Free slack is the amount of time by which an activity  may be delayed without delaying the early start of  any immediately following tasks. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 36
  • 37.
    Critical and Non‐Critical Tasks XP • In the Network Diagram view, the critical tasks— tasks that are on the critical path—are displayed  p p y within a red border. • A task that is not on the critical path is a non‐critical  task, that is, it doesn’t necessarily have to start on its  k h d ’ l h currently scheduled Start date in order for the overall  project to be completed on time. project to be completed on time. • The Network Diagram is used mainly to view and  analyze the critical path. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 37
  • 38.
    Creating Dependencies using the  XP Network Diagram view Network Diagram view http://www.learningquotient.in New Perspectives on Microsoft Project 2010 38
  • 39.
    Entering Lag and Lead Times XP • When a project is scheduled from a Start date, lag  and lead times refer to an amount of time that the  second task of a relationship is moved backward  (lead) or forward (lag) in time. • Lead time moves the second task backward in time  d h d kb k d so that the two tasks overlap.   • Lag time is the opposite of lead time It moves the Lag time is the opposite of lead time.  It moves the  second task forward in time so that the tasks are  further separated.   http://www.learningquotient.in New Perspectives on Microsoft Project 2010 39
  • 40.
    Lag and Lead Time from Start Date XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 40
  • 41.
    Entering Lag and Lead Times Cont.’d XP • Project 2010 combines the concepts of lag and lead  times into one term, lag time.   , g • When a project is scheduled from a Start date,  positive lag time moves the second task forward in  time. – Positive lag time is the traditional definition of lag time in  general project management discussions. general project management discussions. • Negative lag time moves the second task backward  in time so that the tasks overlap.   – Negative lag time is called lead time in general project  management discussions. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 41
  • 42.
    Negative and Positive Lag Time XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 42
  • 43.
    Check for Lag Time Effects Cont. XP • Confusing negative and positive lag times is easy,  especially when examining them for both a project  p y g p j that is scheduled from a Start date and one  scheduled from a Finish date. • Remember:b – Positive lag time always increases the amount of time  between tasks. between tasks. – Negative lag time always causes the tasks to overlap. – This rule holds true regardless of whether the project is  scheduled from the Start date or the Finish date. h d l df th St t d t th Fi i h d t http://www.learningquotient.in New Perspectives on Microsoft Project 2010 43
  • 44.
    Check for Lag Time Effects XP • Once the tasks, durations, and relationships are  entered, you should check the Project Information entered you should check the Project Information dialog box to verify the project’s calculated Finish  date if the project is scheduled from a Start date, or  p j calculated Start date if the project is scheduled from  a Finish date. • When a project is scheduled from a Start date,  applying negative lag time to task dependencies that  are on the critical path is a common way to shorten  th iti l th i t h t the critical path because it allows tasks to overlap. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 44
  • 45.
    Check for Lag Time Effects Cont.’dXP • When you apply negative lag time, the second task is  allowed to start before the first task is completely  allowed to start before the first task is completely finished. • When a project is scheduled from a Finish date, all When a project is scheduled from a Finish date, all  tasks have as late as possible schedules and lag time  affects the first task rather than the second. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 45
  • 46.
    Lag Time From a Finish Date XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 46
  • 47.
    Creating a Work Breakdown Structure  XP with Summary Tasks with Summary Tasks • A very important strategy for managing projects well  is to organize the work that needs to be done in a  g logical manner. • A work breakdown structure (WBS) is an outcome‐ oriented analysis of the work involved in a project  d l f h k l d that defines the total scope of the project. – A WBS is a foundation document in project management A WBS is a foundation document in project management  because it provides the basis for planning and managing  project schedules, costs, and changes. – The WBS provides a hierarchy similar to an organizational The WBS provides a hierarchy, similar to an organizational  chart, to group project work logically. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 47
  • 48.
    Creating a Work Breakdown Structure  XP with Summary Tasks Cont. d with Summary Tasks Cont ’d • In order to use a WBS in Project 2010, you must  organize tasks into summary tasks (groups of tasks  g y (g p that logically belong together). • When developing a new, large project, some project  managers prefer to start with broad groupings of  f hb d f summary tasks and then break them down into  smaller tasks. smaller tasks. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 48
  • 49.
    Creating a Work Breakdown Structure  XP with Summary Tasks Cont. d with Summary Tasks Cont ’d • Planning a project by starting with broad categories  of tasks is called the top‐down method of creating a  p g WBS. • Other project managers prefer to list all of the  individual tasks, and then collect them into logical  d d l k d h ll h l l groupings using the bottom‐up method. • Once you have indentified your summary tasks you Once you have indentified your summary tasks, you  use Outdenting and Indenting in Project 2010 to  create the summary tasks. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 49
  • 50.
    Outdenting and Indenting Tasks XP • Use the Outdent button and the Indent button on the  Formatting toolbar to create your WBS. Formatting toolbar to create your WBS • Outdenting moves a task to the left (a higher level in  the WBS), and indenting moves a task to the right (a  ), g g ( lower level in the WBS). • Projects can have several levels in the WBS. • Many projects have at least three levels, and some  large projects have more. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 50
  • 51.
    Creating a Summary Task XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 51
  • 52.
    Displaying Outline Numbers XP • Tasks and subtasks are organized in an outline, with  tasks in a hierarchy, when you have created summary  tasks in a hierarchy when you have created summary tasks. • In Project 2010, you can view built‐in outline In Project 2010, you can view built in outline  numbers, which will display in the Task name cells for  all tasks. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 52
  • 53.
    Displaying Outline Numbers  XP Cont. d Cont ’d http://www.learningquotient.in New Perspectives on Microsoft Project 2010 53
  • 54.
    Project Summary Task XP • Many Project Managers like to create a Project  Summary Task which allows them to see how the  Summary Task which allows them to see how the start and finish dates change as they enter and edit  tasks, durations, and dependencies. p http://www.learningquotient.in New Perspectives on Microsoft Project 2010 54
  • 55.
    Project Summary Task Cont.’d XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 55
  • 56.
    Expanding and Collapsing Tasks XP • Once your project has been organized into summary  tasks, you can easily expand (show) and collapse tasks you can easily expand (show) and collapse (hide) the individual tasks within each phase. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 56
  • 57.
    Using WBS Codes XP • Many people like to number tasks in their WBS to  show the logical groupings of work. show the logical groupings of work • Using outline numbers or special work breakdown  structure (WBS) code is a way to use an  structure (WBS) code is a way to use an alphanumeric code to represent each task’s position  within the hierarchical structure of the project. • A WBS code helps identify and group project tasks for  project communication, documentation, or  accounting purposes. http://www.learningquotient.in New Perspectives on Microsoft Project 2010 57
  • 58.
    Creating WBS Codes XP http://www.learningquotient.in New Perspectives on Microsoft Project 2010 58