This document discusses how to integrate MS Project with Adept ProjectShare to enable Scrum project management. Key points include: - Defining the project scope, budget, and product backlog in ProjectShare. - Creating sprints and initial budgets in MS Project and publishing to ProjectShare. - Teams create Scrum boards in ProjectShare for each sprint to plan and track work. - Timesheets in ProjectShare import hours into MS Project to track overall progress. - Dashboards in ProjectShare provide burn down/up charts and reports to analyze progress.