SlideShare a Scribd company logo
MONITERING AND SAFETY
ASPECTS IN UNDERGROUND
STRUCTURES
SOURABHJAIN
1
NECESSITYOFGEOTECHNICAL
INSTRUMENTATION
FINDING OUT THE ENGINEERING PROPERTIES OF THE
SOIL.
MODIFYING THE ENGINEERING PROPERTIES OF THE SOIL
TO THE DESIRED LEVEL.
DESIGN OF THE STRUCTURE BASED ON THE PROPERTIES.
MONITORING THE GEOTECHNICAL CONDITIONS OR
BEHAVIOR OF THE STRUCTURE DURING THE
CONSTRUCTION PROCESS.
CHANGES IN THE DESIGN BASED ON THE BEHAVIOR.
SOURABHJAIN
2
IMPORTANCE OFMONITERING INSTRUMENTS
TO OBSERVE THE BEHAVIOR OF THE STRUCTURE
MONITORING INSTRUMENTS ARE REQUIRED .
INSTRUMENTATION IS A TOOL TO ASSIST WITH THESE
OBSERVATIONS. THEY ARE OUR EYES AND EARS INSIDE
THE ROCK.
INSTRUMENTATION IS USED TO MEASURE THE RESPONSE
(DEFORMATION, STRESS ETC.) OF SOIL OR ROCK TO
CHANGES IN LOADING OR SUPPORT ARRANGEMENTS,
AND FROM THE MEASUREMENTS TAKEN, THE NEED FOR
MODIFICATIONS TO THE LOADING OR SUPPORT
ARRANGEMENTS IS DETERMINED.
SOURABHJAIN
3
PURPOSE OFGOOD INSTRUMENTATION
SITE INVESTIGATION.
DESIGN VERIFICATION
CONSTRUCTION CONTROL
SAFETY
LEGAL PROTECTION
PERFORMANCE
SOURABHJAIN
4
SITE INVESTIGATION.
Instruments are used to characterize and determine initial site
conditions.
Common parameters of interest in a site investigation are pore
pressure, permeability of soil, slope stability etc.
SOURABHJAIN
5
DESIGNVERIFICATION
Instruments are used to verify design assumptions.
Instrumentation data from the initial stage of a project may show the
need or provide the opportunity to modify the design in later stages.
For example, data obtained from NATM shotcrete cells in the initial
stretch of tunnel is used to revise the thickness of shotcrete in the
later stages.
SOURABHJAIN
6
CONSTRUCTION CONTROL
Instruments are installed to monitor the effects of construction.
Instrument data helps the engineer to determine how fast construction
can proceed without adverse effects on the foundation soil and
construction materials used.
For example, in tunnel construction, the data obtained from the load
cells helps the geotechnical engineer to know if the stresses in the
excavated tunnel have been stabilized and how fast he can proceed
with further excavation.
SOURABHJAIN
7
SAFETY
Instruments can provide early warning of impending failure.
In case of metro railway tunnels instruments provide early
warning through real time monitoring systems available on the
internet for any excessive and undue ground movements
affecting the adjoining premises, structure and utilities like the
railways, power lines, water lines etc.
within the zone of influence of the excavations or tunnels. This
allows for implementation of preventive remedial actions well
within time.
SOURABHJAIN
8
LEGALPROTECTION
Instruments provide designers and contractors the basis of a
legal defence should resident and owners of adjacent properties
blame construction for damage to their property and life.
This aspect gains prominence in constructions in populated
areas such as for underground metro railways
SOURABHJAIN
9
PERFORMANCE
Instruments are used to monitor the in-service performance of
a structure.
For example, monitoring leakage, pore water pressure and
deformation can provide an indication of the perform bolts and
movements within a tunnel can provide an indication of the
stability of tunnel.
SOURABHJAIN
10
MONITERING EQUIPMENTS
SOURABHJAIN
11
ROOF TO FLOOR CONVERGENCE MEASUREMENT
Used to measure deformation in tunnels by measuring contraction ( or elongation )
Procedure : Measurements are taken by simply stretching the telescopic rod
between the reference points, and reading the graduations on the rod. These
indicators are useful for understanding the roof to floor closure in the advance
galleries at various stages of extraction.
TELESCOPIC
CONVERGENCE ROD
SOURABHJAIN
12
Chart Type Convergence
Recorder
SOURABHJAIN
13
REMOTE CONVERGENCE
INDICATOR
• For monitoring convergence in
roof
• Sensor – Vibrating wire type or
Potentiometric type
• Needs laying of wire from
instrument location to
measurement site
• Fails immediately with the
failure of immediate roof
SOURABHJAIN
14
STRATAMONITORING BYTELLTALES
• Tell tale is strata – extensometer.
• It provides pre-emptive warning of roof-falling.
• The dual-height tell tale provides an immediate visible
warning, distinguishing between movement above and below
rock-bolted height.
TYPES
• Single height tell tale
• Dual height tell tale
• Three point tell tale
• Four point tell tale
• Rotary tell tale
SOURABHJAIN
15
SINGLE HEIGHTTELLTALE
• It comprises a strata movement indicator usually with color
bands and/or graduations.
• a mechanical tell tale consists of a strata movement indicator
positioned in the mouth of a drilled hole and attached to an
anchor installed up the hole
SOURABHJAIN
16
Dual height tell tale
• Dual Height tell tale is
designed to be installed
for monitoring the
bolted strata.
• They have two
versions – one for dry
drill holes and the
other for watery drill
holes.
• This is designed to be
installed following the
installation of roof bolt
reinforcement.
SOURABHJAIN
17
SAFETYMONITORING
SOURABHJAIN
18
ACTION LEVELS
• GREEN 0 - 25 mm
• YELLOW 25 - 50 mm
• RED 50 mm +
ACTIONS
• GREEN No action required, continue routine monitoring
• YELLOW Identify height of softening [HOS].
If HOS is above bolts, install longer
reinforcement.
If below top of bolts, install additional standard
length reinforcement to increase density of
support.
• RED Restrict access.
Investigate.
Install longer reinforcement
SOURABHJAIN
19
RotaryTell tale Extensometer
• It is useful where the conventional method of Roof support system is
not convenient or possible.
• Movement of the strata is indicated with a magnification of 1:15.
• It gives visual indication to a workman regarding the status of Roof
stability.
• Rapid and simple to install.
• Rotary type are useful for variable depth.
SOURABHJAIN
20
MAGNETEXTENSOMETER
• The Magnet
Extensometer consists of
a series of magnets that
are installed with an
access pipe.
• The magnets are
anchored at specified
depths.
• Measurements are taken
by lowering a probe
through the access pipe
to detect the depth of the
magnets.
SOURABHJAIN
21
VIBRATING WIRE LOAD CELLS
• The load cell is a transducer working
on vibrating-wire principle.
• It has three stretched wires housed in
a metal cylinder, which are plucked
by an electric pulse of high energy.
• Changes in the load exerted on the
cell cause changes in the length of the
wire, resulting in variations of
frequency of vibration of the wire.
• As the load increases the frequency
decreases accordingly and vice-versa.
• This frequency is measured by a
digital read-out unit, and is converted
into load using calibration charts.
Efficacy and adequacy of the support
system can be inferred on the basis of
these load cells.
SOURABHJAIN
22
ROCKBOLTLOAD CELL
• The load cell is a transducer working on vibrating-wire
principle.
• The load cells should be installed under the roof bolts using
specially prepared steel seating arrangement .
• The load cells should be installed at the junctions to understand
the change in load over the roof bolt during the operation.
SOURABHJAIN
23
Mechanical Load Cell
• Load cell consists of an elastic disc element sandwiched
between two plates.
• The disc deflects under load and changes distance between
plates.
• The deflection is measured with a dial gauge or suitable
electronic transduced.
• It has limited application due to nonlinear calibration curve
and restricted application.
SOURABHJAIN
24
STRESS CELL
• Principle : These are used for measuring unidirectional stress
change in the pillar. It consists essentially of a wire tensioned
across a steel cylinder (38 mm diameter). As the stress within
the rock/coal changes, the cylinder deforms, causing tension in
the wire to change.
• Procedure : A bore hole of 38 mm diameter is required for
installing the stress meters, preferably at mid height of the
pillar either horizontally or slightly rising/dipping according to
dip of the seam. The stress meter along with wedge and platen
assembly is set in the borehole with the help of special
installation tools, at a depth of about 4 to 9 m.
SOURABHJAIN
25
Safety aspects
SOURABHJAIN
26
Scope and application
The rule applies to construction of underground tunnels, shafts,
chambers, and passageways. It also applies to cut-and-cover
excavations, both those physically connected to tunnels and those that
create conditions characteristic of underground construction. Hazards
common to such work include reduced natural ventilation and light,
difficult or limited access and egress, exposure to air contaminants,
fire, and explosion
SOURABHJAIN
27
Provisions of the
standard
• The standard gives employers the flexibility to select from a variety
of appropriate and effective methods of controlling workplace
hazards
• In underground construction. It includes a safety program focusing
on instructing workers in topics appropriate to specific jobsites
• And it gives specific duties and responsibilities to a “competent
person.”
SOURABHJAIN
28
Competent person
• A “competent person” is one capable of identifying existing and
predictable workplace hazards who is authorized to take corrective
• action to eliminate them
• Duties of competent person
• Monitoring air
• Inspecting the work area for ground stability
• Inspecting all drilling equipment prior to each use
• Inspecting hauling equipment before each shift and visually
checking all hoisting machinery, equipment, anchorages, and rope at
the beginning of each shift and during hoisting
SOURABHJAIN
29
Safety instruction
• Employers must ensure that workers are instructed on
the recognition
• and avoidance of hazards associated with underground
construction.
• Instruction must include the following topics that are
appropriate to
• each jobsite:
• Air monitoring
• Ventilation and illumination
• Communications
• Flood control
• Mechanical and personal protective equipment
• Explosives: fire prevention and protection
• Emergency procedures: evacuation plans and check-
in/check- out procedures
SOURABHJAIN
30
Access and egress
• Employers must provide safe access to and egress from all
workstations and prevent unauthorized underground entry. Completed
• Unused sections of an underground work area must be barricaded.
• Unused openings must be covered, fenced off, or posted with warning
• signs indicating “Keep Out” or other appropriate language
SOURABHJAIN
31
Check-in/check-out
• Employers must maintain a check-in/check-out procedure that
ensures above-ground personnel can maintain an accurate
count of people who are underground, in case of an
emergency. At least one
• Designated person must be on duty at the surface whenever
anyone is working underground. That person is responsible for
securing
• Immediate aid in case of an emergency
SOURABHJAIN
32
Gassy operations
• • Using more-stringent ventilation requirements
• • Using only diesel equipment approved for use in gassy operations
• • Posting each entrance with warning signs and prohibiting smoking
and personal sources of ignition
• • Maintaining a fire watch when hot work is performed
• • Suspending all operations in the affected area until all special
requirements are met or the operation is declassified
• Additional air monitoring is also required during gassy conditions
SOURABHJAIN
33
SPECIALAIRMONITORING
REQUIREMENTS
• The employer must assign a "competent person" to perform air
monitoring. If this individual determines that air contaminants may
present a danger to life at any time, the employer must
immediately take all necessary precautions and post a notice at all
entrances to the underground site about the hazardous condition
and his responsible for checking air quality
test for oxygen first
testing for methane and other flammable gases
hydrogen sulfide levels
SOURABHJAIN
34
Illumination
• As in all construction operations, the rule requires that proper
illumination be provided during tunneling operations, as
specified
• When explosives are being handled, acceptable portable
lighting equipment must be used within 50 feet of any
underground heading
SOURABHJAIN
35
Fire prevention and control
• open flames and fires are prohibited in all underground
construction activities, except for hot-work operations.
• Smoking is allowed only in areas free of fire and explosion hazards.
• Employers must post signs prohibiting smoking and open flames
where such hazards exist
• Gases such as acetylene, liquefied petroleum, and methyl acetylene
propadiene (stabilized), may be used underground only for hot-
work operations.
• Leaks and spills of flammable or combustible fluids must be cleaned
up immediately.
SOURABHJAIN
36
Safety provisions
• —IS: 4756:- 1978 – Safety Code for Tunnelling work
• —IS: 3764 –1966 – Safety Code for Excavation work
• —IS: 4081-1986 – Safety Code for Blasting and Related drilling
operations
• —IS: 4138-1977 – Safety Code for Working on Compressed Air
• —IS: 7293-1974 – Safety Code for Working with Construction
Machinery
• —IS: 5878 (Various parts) – Codes of practices relating to
tunnelling and underground excavations
• —Indian Explosive Act -1988
• —Indian Explosive Rules -1983
SOURABHJAIN
37
Lighting:
SOURABHJAIN
38
• Minimum 50 lux at headings during drilling, mucking 70 m.
and scaling.
• Minimum 30 lux for trolley track working area.
• Minimum 10 lux for other areas inside the tunnel or on
approach cut/roads.
• Emergency lights (battery operated) at the working faces and
at regular interval along the tunnel.
• Proper earthling and grounding of all electrical apparatus.
SOURABHJAIN
39
Medical facilities:
• First Aid box with experienced first aid attendant with his
distinguishing badge on each shift.
• Stretchers in every shift at portal.
SOURABHJAIN
40
Protective wear:
• Helmet, steel tow safety shop, gum boots for each worker.
• Sign boards 1x1.5m in size to be displayed at the approach
“Construction AREA, HELMET required beyond this point”
SOURABHJAIN
41
Notices and signs:
SOURABHJAIN
42
Telephone System:
• For communication between control locations inside tunnel
and portal (when more than 500m)
SOURABHJAIN
43
Ventilation
• Essential to make working space safe for workers by keeping
the air fresh and repairable and by eliminating harmful and
obnoxious dust, dynamite fumes and other gases. Mechanical
ventilation must be used for long tunnels.
SOURABHJAIN
44
• It is essential to ensure
• Temp < 40 C dry and < 29 C wet at the working place.
• Concentration of gases in side the tunnel by volume
a) Oxygen not less than 19.5%
b) Carbon monoxide not more than 0.005%
c) Carbon Dioxide not more than 0.5%
d) Hydrogen Sulphide not more than 0.001%
SOURABHJAIN
45
Sanitation and Drinking
Water
• Sanitation - Unless the worksite is within 500 m of the portal of
the tunnel, sanitation facilities shall be provided close by.
• Drinking Water- Drinking water, at least 5 litre per person
employed in the shift, shall he provided near the portal and
also inside the longer tunnels.
• Washing and cleaning facilities shall be provided for all
workers near the portal.
SOURABHJAIN
46
Risk register
SOURABHJAIN
47
Emergency Planning &
Mitigation of Risk
• to ensure safety of tunnel workers and other stakeholders
• A culture of safety can be enhanced by in-house training,
communication through toolbox meetings and display of
procedures and escape plans on notice boards.
• table top exercise and regular drills shall be conducted once in
every six months.
• Accountability for safety performance must be appropriately
allocated through the entire safety management process, in
particular to the emergency plan
SOURABHJAIN
48
SOURABHJAIN
49
SOURABHJAIN
50
Safety measures for blasting
• Based on IS :4081- 1986.
• No metals except approved metal truck bodies shall be
allowed to come in contact with cases of explosives.
• Blasting caps, electric blasting caps or primers shall not be
stored in the same box, container or room with other
explosives.
• Smoking shall be prohibited in the storage area of explosives
and in its vicinity.
• Packages containing explosives shall not be allowed to remain
in the sun.
• Explosives shall not be carried in the pockets or folds of
clothing by any person.
SOURABHJAIN
51
• All electrical wiring and equipment of storage area shall be
adequately insulated and protected against mechanical
damage to prevent short-circuiting.
• Children and unauthorized or unnecessary persons shall not
be present where explosives are being handled or used.
SOURABHJAIN
52
Safety measures for drilling
• No drilling shall be started until previous holes in the blasted
area are flushed with air and water.
• While planning drilling operations for blasting purposes,
consideration must be given to the nature of stratum and the
overburden with a view to avoiding the possibilities of land-
slides after blasting.
• The position of all holes to be drilled shall be marked out with
white paint.
• The face of rock shall be carefully examined before drilling, to
determine the possible presence of unfired explosive.
• The diameter of the bore of each hole shall be greater than
the outside diameter of the cartridges of explosive.
SOURABHJAIN
53
• explosives shall not be forced down a bore hole or on
obstruction in a bore hole.
• A bore hole near another hole loaded with explosives shall
not be sprung.
• No holes shall be loaded except those to be fired on the next
round of blasting and after blasting.
• Drilling shall not be resumed after blasts have been fired until
a thorough examination has been made.
SOURABHJAIN
54
SOURABHJAIN
55

More Related Content

What's hot

Safety management plan by DGMS
Safety management plan by DGMSSafety management plan by DGMS
Safety management plan by DGMS
Krishna Deo Prasad
 
Mine legislation safety&amp;hazardous
Mine legislation safety&amp;hazardousMine legislation safety&amp;hazardous
Mine legislation safety&amp;hazardous
Jignesh Ruperi
 
Drilling in mining
Drilling in miningDrilling in mining
Drilling in mining
Eder Reyes
 
Metal Mines Blasting
Metal Mines BlastingMetal Mines Blasting
Metal Mines Blasting
partha sharma
 
Explosives and blasting in underground coal mining
Explosives and blasting in underground coal mining Explosives and blasting in underground coal mining
Explosives and blasting in underground coal mining
Volvo Group
 
Mine illumination
Mine illuminationMine illumination
Mine illumination
Pranjal Sao
 
Mines vocational training rules 1966 short answer notes
Mines vocational training rules 1966 short answer notesMines vocational training rules 1966 short answer notes
Mines vocational training rules 1966 short answer notes
Mines Group Vocational Training Society
 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesories
Safdar Ali
 
Openpit fundamentals
Openpit fundamentalsOpenpit fundamentals
Openpit fundamentals
VR M
 
Drilling equipments
Drilling equipmentsDrilling equipments
Drilling equipments
Jagriti Mandal
 
Mining Machinery Learning Material
Mining Machinery Learning MaterialMining Machinery Learning Material
Mining Machinery Learning Material
Bhaskar Naidu
 
Illumination In opencast mining the needs
Illumination In opencast mining  the needs Illumination In opencast mining  the needs
Illumination In opencast mining the needs
Arunachalam Iyer
 
BENCH & ROAD STANDARS IN OPENCAST MINES.pptx
BENCH & ROAD STANDARS IN OPENCAST MINES.pptxBENCH & ROAD STANDARS IN OPENCAST MINES.pptx
BENCH & ROAD STANDARS IN OPENCAST MINES.pptx
Mines Group Vocational Training Society
 
Inundation
InundationInundation
Inundation
VR M
 
Shrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat StopingShrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat Stoping
Geology Department, Faculty of Science, Tanta University
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
Jyoti Khatiwada
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall Mining
VR M
 
Rock burst presentation
Rock burst presentationRock burst presentation
Rock burst presentation
Saqib Ahmad Saki
 
Rescue apparatus and Rescue Operations.
Rescue apparatus and Rescue Operations.Rescue apparatus and Rescue Operations.
Rescue apparatus and Rescue Operations.
waseem khan
 
Mine Opening and Development
Mine Opening and DevelopmentMine Opening and Development
Mine Opening and Development
Anurag Jha
 

What's hot (20)

Safety management plan by DGMS
Safety management plan by DGMSSafety management plan by DGMS
Safety management plan by DGMS
 
Mine legislation safety&amp;hazardous
Mine legislation safety&amp;hazardousMine legislation safety&amp;hazardous
Mine legislation safety&amp;hazardous
 
Drilling in mining
Drilling in miningDrilling in mining
Drilling in mining
 
Metal Mines Blasting
Metal Mines BlastingMetal Mines Blasting
Metal Mines Blasting
 
Explosives and blasting in underground coal mining
Explosives and blasting in underground coal mining Explosives and blasting in underground coal mining
Explosives and blasting in underground coal mining
 
Mine illumination
Mine illuminationMine illumination
Mine illumination
 
Mines vocational training rules 1966 short answer notes
Mines vocational training rules 1966 short answer notesMines vocational training rules 1966 short answer notes
Mines vocational training rules 1966 short answer notes
 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesories
 
Openpit fundamentals
Openpit fundamentalsOpenpit fundamentals
Openpit fundamentals
 
Drilling equipments
Drilling equipmentsDrilling equipments
Drilling equipments
 
Mining Machinery Learning Material
Mining Machinery Learning MaterialMining Machinery Learning Material
Mining Machinery Learning Material
 
Illumination In opencast mining the needs
Illumination In opencast mining  the needs Illumination In opencast mining  the needs
Illumination In opencast mining the needs
 
BENCH & ROAD STANDARS IN OPENCAST MINES.pptx
BENCH & ROAD STANDARS IN OPENCAST MINES.pptxBENCH & ROAD STANDARS IN OPENCAST MINES.pptx
BENCH & ROAD STANDARS IN OPENCAST MINES.pptx
 
Inundation
InundationInundation
Inundation
 
Shrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat StopingShrinkage and Vertical Crater Retreat Stoping
Shrinkage and Vertical Crater Retreat Stoping
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall Mining
 
Rock burst presentation
Rock burst presentationRock burst presentation
Rock burst presentation
 
Rescue apparatus and Rescue Operations.
Rescue apparatus and Rescue Operations.Rescue apparatus and Rescue Operations.
Rescue apparatus and Rescue Operations.
 
Mine Opening and Development
Mine Opening and DevelopmentMine Opening and Development
Mine Opening and Development
 

Similar to Monitering and safety aspects in underground structures

Dam safety & Safety Devices
Dam safety & Safety DevicesDam safety & Safety Devices
Dam safety & Safety Devices
Tushar Dholakia
 
summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...
Neha Singh
 
Oil pipiline stress monitoring
Oil pipiline  stress monitoringOil pipiline  stress monitoring
Oil pipiline stress monitoring
Juan David Betancur
 
Solutions for the hydraulics industry
Solutions for the hydraulics industrySolutions for the hydraulics industry
Solutions for the hydraulics industry
Christian Holder
 
BALLUFF - Solutions for Hydraulic Systems
BALLUFF - Solutions for Hydraulic SystemsBALLUFF - Solutions for Hydraulic Systems
BALLUFF - Solutions for Hydraulic Systems
Bernd Schneider
 
7436 1
7436 17436 1
Excavation eschenasy
Excavation eschenasyExcavation eschenasy
Excavation eschenasy
q q
 
Instrumentation & Structural Monitoring of Dams
Instrumentation & Structural Monitoring of DamsInstrumentation & Structural Monitoring of Dams
Instrumentation & Structural Monitoring of Dams
Encardio Rite Electronics Private Limited
 
2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines
Specialized Carriers & Rigging Association
 
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
Britt Bettell
 
7500
75007500
Deck Machineries College of Maritime Education
Deck Machineries College of Maritime EducationDeck Machineries College of Maritime Education
Deck Machineries College of Maritime Education
melvincentmendigorin1
 
A-Guide-on-Structural-Hea.9331849.powerpoint.pptx
A-Guide-on-Structural-Hea.9331849.powerpoint.pptxA-Guide-on-Structural-Hea.9331849.powerpoint.pptx
A-Guide-on-Structural-Hea.9331849.powerpoint.pptx
Azeem Muhammed
 
OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolition
Hni Amiera
 
UNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdfUNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdf
PinakRay1
 
TS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.pptTS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.ppt
ajith30276
 
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra PradeshHT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
Mohit Bathineni
 
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEMROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
Vineeshkumar K V
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt
Muhammed Sulfeek
 
7436 2
7436 27436 2

Similar to Monitering and safety aspects in underground structures (20)

Dam safety & Safety Devices
Dam safety & Safety DevicesDam safety & Safety Devices
Dam safety & Safety Devices
 
summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...
 
Oil pipiline stress monitoring
Oil pipiline  stress monitoringOil pipiline  stress monitoring
Oil pipiline stress monitoring
 
Solutions for the hydraulics industry
Solutions for the hydraulics industrySolutions for the hydraulics industry
Solutions for the hydraulics industry
 
BALLUFF - Solutions for Hydraulic Systems
BALLUFF - Solutions for Hydraulic SystemsBALLUFF - Solutions for Hydraulic Systems
BALLUFF - Solutions for Hydraulic Systems
 
7436 1
7436 17436 1
7436 1
 
Excavation eschenasy
Excavation eschenasyExcavation eschenasy
Excavation eschenasy
 
Instrumentation & Structural Monitoring of Dams
Instrumentation & Structural Monitoring of DamsInstrumentation & Structural Monitoring of Dams
Instrumentation & Structural Monitoring of Dams
 
2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines
 
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
 
7500
75007500
7500
 
Deck Machineries College of Maritime Education
Deck Machineries College of Maritime EducationDeck Machineries College of Maritime Education
Deck Machineries College of Maritime Education
 
A-Guide-on-Structural-Hea.9331849.powerpoint.pptx
A-Guide-on-Structural-Hea.9331849.powerpoint.pptxA-Guide-on-Structural-Hea.9331849.powerpoint.pptx
A-Guide-on-Structural-Hea.9331849.powerpoint.pptx
 
OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolition
 
UNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdfUNIT 3 Part B - Safety in Special Construction Operations.pdf
UNIT 3 Part B - Safety in Special Construction Operations.pdf
 
TS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.pptTS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.ppt
 
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra PradeshHT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
 
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEMROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt
 
7436 2
7436 27436 2
7436 2
 

More from Sourabh Jain

Advance traffic management system: nagpur (india)
Advance traffic management system: nagpur (india)Advance traffic management system: nagpur (india)
Advance traffic management system: nagpur (india)
Sourabh Jain
 
Applications of rock classifications
Applications of rock classifications Applications of rock classifications
Applications of rock classifications
Sourabh Jain
 
Applications of lidar technology
Applications of lidar technologyApplications of lidar technology
Applications of lidar technology
Sourabh Jain
 
Rail rapid transit system (india)
Rail rapid transit system (india)Rail rapid transit system (india)
Rail rapid transit system (india)
Sourabh Jain
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
Sourabh Jain
 
GIS for traffic management system
GIS for traffic management systemGIS for traffic management system
GIS for traffic management system
Sourabh Jain
 
Reinforced fly ash sub bases in rural roads
Reinforced fly ash sub bases in rural roadsReinforced fly ash sub bases in rural roads
Reinforced fly ash sub bases in rural roads
Sourabh Jain
 
Network analysis for shortest optimum path
Network analysis for shortest optimum pathNetwork analysis for shortest optimum path
Network analysis for shortest optimum path
Sourabh Jain
 
Analysis on quality of roads using geoinformatics
Analysis on quality of roads using geoinformaticsAnalysis on quality of roads using geoinformatics
Analysis on quality of roads using geoinformatics
Sourabh Jain
 

More from Sourabh Jain (9)

Advance traffic management system: nagpur (india)
Advance traffic management system: nagpur (india)Advance traffic management system: nagpur (india)
Advance traffic management system: nagpur (india)
 
Applications of rock classifications
Applications of rock classifications Applications of rock classifications
Applications of rock classifications
 
Applications of lidar technology
Applications of lidar technologyApplications of lidar technology
Applications of lidar technology
 
Rail rapid transit system (india)
Rail rapid transit system (india)Rail rapid transit system (india)
Rail rapid transit system (india)
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
GIS for traffic management system
GIS for traffic management systemGIS for traffic management system
GIS for traffic management system
 
Reinforced fly ash sub bases in rural roads
Reinforced fly ash sub bases in rural roadsReinforced fly ash sub bases in rural roads
Reinforced fly ash sub bases in rural roads
 
Network analysis for shortest optimum path
Network analysis for shortest optimum pathNetwork analysis for shortest optimum path
Network analysis for shortest optimum path
 
Analysis on quality of roads using geoinformatics
Analysis on quality of roads using geoinformaticsAnalysis on quality of roads using geoinformatics
Analysis on quality of roads using geoinformatics
 

Recently uploaded

Hematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood CountHematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood Count
shahdabdulbaset
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
mamamaam477
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
amsjournal
 
gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))
shivani5543
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
RamonNovais6
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
Mahmoud Morsy
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 

Recently uploaded (20)

Hematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood CountHematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood Count
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
 
gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 

Monitering and safety aspects in underground structures

  • 1. MONITERING AND SAFETY ASPECTS IN UNDERGROUND STRUCTURES SOURABHJAIN 1
  • 2. NECESSITYOFGEOTECHNICAL INSTRUMENTATION FINDING OUT THE ENGINEERING PROPERTIES OF THE SOIL. MODIFYING THE ENGINEERING PROPERTIES OF THE SOIL TO THE DESIRED LEVEL. DESIGN OF THE STRUCTURE BASED ON THE PROPERTIES. MONITORING THE GEOTECHNICAL CONDITIONS OR BEHAVIOR OF THE STRUCTURE DURING THE CONSTRUCTION PROCESS. CHANGES IN THE DESIGN BASED ON THE BEHAVIOR. SOURABHJAIN 2
  • 3. IMPORTANCE OFMONITERING INSTRUMENTS TO OBSERVE THE BEHAVIOR OF THE STRUCTURE MONITORING INSTRUMENTS ARE REQUIRED . INSTRUMENTATION IS A TOOL TO ASSIST WITH THESE OBSERVATIONS. THEY ARE OUR EYES AND EARS INSIDE THE ROCK. INSTRUMENTATION IS USED TO MEASURE THE RESPONSE (DEFORMATION, STRESS ETC.) OF SOIL OR ROCK TO CHANGES IN LOADING OR SUPPORT ARRANGEMENTS, AND FROM THE MEASUREMENTS TAKEN, THE NEED FOR MODIFICATIONS TO THE LOADING OR SUPPORT ARRANGEMENTS IS DETERMINED. SOURABHJAIN 3
  • 4. PURPOSE OFGOOD INSTRUMENTATION SITE INVESTIGATION. DESIGN VERIFICATION CONSTRUCTION CONTROL SAFETY LEGAL PROTECTION PERFORMANCE SOURABHJAIN 4
  • 5. SITE INVESTIGATION. Instruments are used to characterize and determine initial site conditions. Common parameters of interest in a site investigation are pore pressure, permeability of soil, slope stability etc. SOURABHJAIN 5
  • 6. DESIGNVERIFICATION Instruments are used to verify design assumptions. Instrumentation data from the initial stage of a project may show the need or provide the opportunity to modify the design in later stages. For example, data obtained from NATM shotcrete cells in the initial stretch of tunnel is used to revise the thickness of shotcrete in the later stages. SOURABHJAIN 6
  • 7. CONSTRUCTION CONTROL Instruments are installed to monitor the effects of construction. Instrument data helps the engineer to determine how fast construction can proceed without adverse effects on the foundation soil and construction materials used. For example, in tunnel construction, the data obtained from the load cells helps the geotechnical engineer to know if the stresses in the excavated tunnel have been stabilized and how fast he can proceed with further excavation. SOURABHJAIN 7
  • 8. SAFETY Instruments can provide early warning of impending failure. In case of metro railway tunnels instruments provide early warning through real time monitoring systems available on the internet for any excessive and undue ground movements affecting the adjoining premises, structure and utilities like the railways, power lines, water lines etc. within the zone of influence of the excavations or tunnels. This allows for implementation of preventive remedial actions well within time. SOURABHJAIN 8
  • 9. LEGALPROTECTION Instruments provide designers and contractors the basis of a legal defence should resident and owners of adjacent properties blame construction for damage to their property and life. This aspect gains prominence in constructions in populated areas such as for underground metro railways SOURABHJAIN 9
  • 10. PERFORMANCE Instruments are used to monitor the in-service performance of a structure. For example, monitoring leakage, pore water pressure and deformation can provide an indication of the perform bolts and movements within a tunnel can provide an indication of the stability of tunnel. SOURABHJAIN 10
  • 12. ROOF TO FLOOR CONVERGENCE MEASUREMENT Used to measure deformation in tunnels by measuring contraction ( or elongation ) Procedure : Measurements are taken by simply stretching the telescopic rod between the reference points, and reading the graduations on the rod. These indicators are useful for understanding the roof to floor closure in the advance galleries at various stages of extraction. TELESCOPIC CONVERGENCE ROD SOURABHJAIN 12
  • 14. REMOTE CONVERGENCE INDICATOR • For monitoring convergence in roof • Sensor – Vibrating wire type or Potentiometric type • Needs laying of wire from instrument location to measurement site • Fails immediately with the failure of immediate roof SOURABHJAIN 14
  • 15. STRATAMONITORING BYTELLTALES • Tell tale is strata – extensometer. • It provides pre-emptive warning of roof-falling. • The dual-height tell tale provides an immediate visible warning, distinguishing between movement above and below rock-bolted height. TYPES • Single height tell tale • Dual height tell tale • Three point tell tale • Four point tell tale • Rotary tell tale SOURABHJAIN 15
  • 16. SINGLE HEIGHTTELLTALE • It comprises a strata movement indicator usually with color bands and/or graduations. • a mechanical tell tale consists of a strata movement indicator positioned in the mouth of a drilled hole and attached to an anchor installed up the hole SOURABHJAIN 16
  • 17. Dual height tell tale • Dual Height tell tale is designed to be installed for monitoring the bolted strata. • They have two versions – one for dry drill holes and the other for watery drill holes. • This is designed to be installed following the installation of roof bolt reinforcement. SOURABHJAIN 17
  • 19. ACTION LEVELS • GREEN 0 - 25 mm • YELLOW 25 - 50 mm • RED 50 mm + ACTIONS • GREEN No action required, continue routine monitoring • YELLOW Identify height of softening [HOS]. If HOS is above bolts, install longer reinforcement. If below top of bolts, install additional standard length reinforcement to increase density of support. • RED Restrict access. Investigate. Install longer reinforcement SOURABHJAIN 19
  • 20. RotaryTell tale Extensometer • It is useful where the conventional method of Roof support system is not convenient or possible. • Movement of the strata is indicated with a magnification of 1:15. • It gives visual indication to a workman regarding the status of Roof stability. • Rapid and simple to install. • Rotary type are useful for variable depth. SOURABHJAIN 20
  • 21. MAGNETEXTENSOMETER • The Magnet Extensometer consists of a series of magnets that are installed with an access pipe. • The magnets are anchored at specified depths. • Measurements are taken by lowering a probe through the access pipe to detect the depth of the magnets. SOURABHJAIN 21
  • 22. VIBRATING WIRE LOAD CELLS • The load cell is a transducer working on vibrating-wire principle. • It has three stretched wires housed in a metal cylinder, which are plucked by an electric pulse of high energy. • Changes in the load exerted on the cell cause changes in the length of the wire, resulting in variations of frequency of vibration of the wire. • As the load increases the frequency decreases accordingly and vice-versa. • This frequency is measured by a digital read-out unit, and is converted into load using calibration charts. Efficacy and adequacy of the support system can be inferred on the basis of these load cells. SOURABHJAIN 22
  • 23. ROCKBOLTLOAD CELL • The load cell is a transducer working on vibrating-wire principle. • The load cells should be installed under the roof bolts using specially prepared steel seating arrangement . • The load cells should be installed at the junctions to understand the change in load over the roof bolt during the operation. SOURABHJAIN 23
  • 24. Mechanical Load Cell • Load cell consists of an elastic disc element sandwiched between two plates. • The disc deflects under load and changes distance between plates. • The deflection is measured with a dial gauge or suitable electronic transduced. • It has limited application due to nonlinear calibration curve and restricted application. SOURABHJAIN 24
  • 25. STRESS CELL • Principle : These are used for measuring unidirectional stress change in the pillar. It consists essentially of a wire tensioned across a steel cylinder (38 mm diameter). As the stress within the rock/coal changes, the cylinder deforms, causing tension in the wire to change. • Procedure : A bore hole of 38 mm diameter is required for installing the stress meters, preferably at mid height of the pillar either horizontally or slightly rising/dipping according to dip of the seam. The stress meter along with wedge and platen assembly is set in the borehole with the help of special installation tools, at a depth of about 4 to 9 m. SOURABHJAIN 25
  • 27. Scope and application The rule applies to construction of underground tunnels, shafts, chambers, and passageways. It also applies to cut-and-cover excavations, both those physically connected to tunnels and those that create conditions characteristic of underground construction. Hazards common to such work include reduced natural ventilation and light, difficult or limited access and egress, exposure to air contaminants, fire, and explosion SOURABHJAIN 27
  • 28. Provisions of the standard • The standard gives employers the flexibility to select from a variety of appropriate and effective methods of controlling workplace hazards • In underground construction. It includes a safety program focusing on instructing workers in topics appropriate to specific jobsites • And it gives specific duties and responsibilities to a “competent person.” SOURABHJAIN 28
  • 29. Competent person • A “competent person” is one capable of identifying existing and predictable workplace hazards who is authorized to take corrective • action to eliminate them • Duties of competent person • Monitoring air • Inspecting the work area for ground stability • Inspecting all drilling equipment prior to each use • Inspecting hauling equipment before each shift and visually checking all hoisting machinery, equipment, anchorages, and rope at the beginning of each shift and during hoisting SOURABHJAIN 29
  • 30. Safety instruction • Employers must ensure that workers are instructed on the recognition • and avoidance of hazards associated with underground construction. • Instruction must include the following topics that are appropriate to • each jobsite: • Air monitoring • Ventilation and illumination • Communications • Flood control • Mechanical and personal protective equipment • Explosives: fire prevention and protection • Emergency procedures: evacuation plans and check- in/check- out procedures SOURABHJAIN 30
  • 31. Access and egress • Employers must provide safe access to and egress from all workstations and prevent unauthorized underground entry. Completed • Unused sections of an underground work area must be barricaded. • Unused openings must be covered, fenced off, or posted with warning • signs indicating “Keep Out” or other appropriate language SOURABHJAIN 31
  • 32. Check-in/check-out • Employers must maintain a check-in/check-out procedure that ensures above-ground personnel can maintain an accurate count of people who are underground, in case of an emergency. At least one • Designated person must be on duty at the surface whenever anyone is working underground. That person is responsible for securing • Immediate aid in case of an emergency SOURABHJAIN 32
  • 33. Gassy operations • • Using more-stringent ventilation requirements • • Using only diesel equipment approved for use in gassy operations • • Posting each entrance with warning signs and prohibiting smoking and personal sources of ignition • • Maintaining a fire watch when hot work is performed • • Suspending all operations in the affected area until all special requirements are met or the operation is declassified • Additional air monitoring is also required during gassy conditions SOURABHJAIN 33
  • 34. SPECIALAIRMONITORING REQUIREMENTS • The employer must assign a "competent person" to perform air monitoring. If this individual determines that air contaminants may present a danger to life at any time, the employer must immediately take all necessary precautions and post a notice at all entrances to the underground site about the hazardous condition and his responsible for checking air quality test for oxygen first testing for methane and other flammable gases hydrogen sulfide levels SOURABHJAIN 34
  • 35. Illumination • As in all construction operations, the rule requires that proper illumination be provided during tunneling operations, as specified • When explosives are being handled, acceptable portable lighting equipment must be used within 50 feet of any underground heading SOURABHJAIN 35
  • 36. Fire prevention and control • open flames and fires are prohibited in all underground construction activities, except for hot-work operations. • Smoking is allowed only in areas free of fire and explosion hazards. • Employers must post signs prohibiting smoking and open flames where such hazards exist • Gases such as acetylene, liquefied petroleum, and methyl acetylene propadiene (stabilized), may be used underground only for hot- work operations. • Leaks and spills of flammable or combustible fluids must be cleaned up immediately. SOURABHJAIN 36
  • 37. Safety provisions • —IS: 4756:- 1978 – Safety Code for Tunnelling work • —IS: 3764 –1966 – Safety Code for Excavation work • —IS: 4081-1986 – Safety Code for Blasting and Related drilling operations • —IS: 4138-1977 – Safety Code for Working on Compressed Air • —IS: 7293-1974 – Safety Code for Working with Construction Machinery • —IS: 5878 (Various parts) – Codes of practices relating to tunnelling and underground excavations • —Indian Explosive Act -1988 • —Indian Explosive Rules -1983 SOURABHJAIN 37
  • 39. • Minimum 50 lux at headings during drilling, mucking 70 m. and scaling. • Minimum 30 lux for trolley track working area. • Minimum 10 lux for other areas inside the tunnel or on approach cut/roads. • Emergency lights (battery operated) at the working faces and at regular interval along the tunnel. • Proper earthling and grounding of all electrical apparatus. SOURABHJAIN 39
  • 40. Medical facilities: • First Aid box with experienced first aid attendant with his distinguishing badge on each shift. • Stretchers in every shift at portal. SOURABHJAIN 40
  • 41. Protective wear: • Helmet, steel tow safety shop, gum boots for each worker. • Sign boards 1x1.5m in size to be displayed at the approach “Construction AREA, HELMET required beyond this point” SOURABHJAIN 41
  • 43. Telephone System: • For communication between control locations inside tunnel and portal (when more than 500m) SOURABHJAIN 43
  • 44. Ventilation • Essential to make working space safe for workers by keeping the air fresh and repairable and by eliminating harmful and obnoxious dust, dynamite fumes and other gases. Mechanical ventilation must be used for long tunnels. SOURABHJAIN 44
  • 45. • It is essential to ensure • Temp < 40 C dry and < 29 C wet at the working place. • Concentration of gases in side the tunnel by volume a) Oxygen not less than 19.5% b) Carbon monoxide not more than 0.005% c) Carbon Dioxide not more than 0.5% d) Hydrogen Sulphide not more than 0.001% SOURABHJAIN 45
  • 46. Sanitation and Drinking Water • Sanitation - Unless the worksite is within 500 m of the portal of the tunnel, sanitation facilities shall be provided close by. • Drinking Water- Drinking water, at least 5 litre per person employed in the shift, shall he provided near the portal and also inside the longer tunnels. • Washing and cleaning facilities shall be provided for all workers near the portal. SOURABHJAIN 46
  • 48. Emergency Planning & Mitigation of Risk • to ensure safety of tunnel workers and other stakeholders • A culture of safety can be enhanced by in-house training, communication through toolbox meetings and display of procedures and escape plans on notice boards. • table top exercise and regular drills shall be conducted once in every six months. • Accountability for safety performance must be appropriately allocated through the entire safety management process, in particular to the emergency plan SOURABHJAIN 48
  • 51. Safety measures for blasting • Based on IS :4081- 1986. • No metals except approved metal truck bodies shall be allowed to come in contact with cases of explosives. • Blasting caps, electric blasting caps or primers shall not be stored in the same box, container or room with other explosives. • Smoking shall be prohibited in the storage area of explosives and in its vicinity. • Packages containing explosives shall not be allowed to remain in the sun. • Explosives shall not be carried in the pockets or folds of clothing by any person. SOURABHJAIN 51
  • 52. • All electrical wiring and equipment of storage area shall be adequately insulated and protected against mechanical damage to prevent short-circuiting. • Children and unauthorized or unnecessary persons shall not be present where explosives are being handled or used. SOURABHJAIN 52
  • 53. Safety measures for drilling • No drilling shall be started until previous holes in the blasted area are flushed with air and water. • While planning drilling operations for blasting purposes, consideration must be given to the nature of stratum and the overburden with a view to avoiding the possibilities of land- slides after blasting. • The position of all holes to be drilled shall be marked out with white paint. • The face of rock shall be carefully examined before drilling, to determine the possible presence of unfired explosive. • The diameter of the bore of each hole shall be greater than the outside diameter of the cartridges of explosive. SOURABHJAIN 53
  • 54. • explosives shall not be forced down a bore hole or on obstruction in a bore hole. • A bore hole near another hole loaded with explosives shall not be sprung. • No holes shall be loaded except those to be fired on the next round of blasting and after blasting. • Drilling shall not be resumed after blasts have been fired until a thorough examination has been made. SOURABHJAIN 54