SlideShare a Scribd company logo
Four Ball
Accelerated Wear Tester
Department of Mechanical Engineering
Fall Semester 2014
Mechanical System Design
CONTROLS TEAM STRUCTURES TEAM FABRICATION TEAM
Ana Dungan Whitney Stregles Daniel Griffin
Kelsey Kaht Robert Nalecz Colin Holliday
Steve Soto Riley Shay Casey Sheppard
John Willis Jordan Ansley Michael Spaulding
Ibrahim Ahmed
Background and
Design Development
Four Ball Tribometer
❖ Tests a lubricant’s extreme pressure properties under high contact
in pure sliding or pure rolling motion
❖ In this design, a ½ inch diameter ball is pressed against three
similar balls at a set force. The top ball will spin against the three
lower balls creating wear scars on the balls.
❖ The force and torque applied to the system are measured and this
data, along with the appearance of wear
scars, enables the user to conclude
which lubrication is the most efficient
Example Set-Up
Note: This is not our 4-Ball Tribometer
Objectives
Successfully design and fabricate a four ball accelerated wear
tester:
➢ Thoroughly research and develop major concepts and compare
constraints
➢ Develop a design that rotates a top ball under a force causing friction
and wear on the bottom 3 balls
➢ Develop a prototype to test major concepts
➢ Develop methods for measuring wear, torque, load, and temperature
➢ Establish a budget for the project
ASTM Standards
ASTM D2266 ASTM D4172 ASTM D5183
Value Tolerance Value Tolerance Value Tolerance
Force Applied
40 kgf 0.2 kgf 15 kgf 0.2 kgf 40 kgf Not Given
392 N 2 N 147 N 2 N 392 N Not Given
Lubricant
Temp
75 C 2 C 75 C 2 C 75 C 2 C
167 F 4 F 167 F 4 F 167 F 4 F
Speed 1200 rpm 60 rpm 1200 rpm 60 rpm 600 rpm Not Given
Duration 60 min 1 min 60 min 1 min 60 min Not Given
Oil Level very top of cup 3mm above top of balls 3mm above top of balls
[1]
Design Process
❖ The design of the 4-ball tribometer was changed several
times.
❖ The initial design involved a lever and an inline motor.
❖ The second design included the drill press that was donated to
our team and the previous lever idea.
❖ The final design utilizes a pneumatic cylinder and was
upgraded from the use of a manual regulator to the
integration of a data acquisition concept and force sensor
components to control the applied force.
Initial Design
❖ Basic Concept
➢ Not technologically advanced
❖ Inline Motor
❖ Lever Arm
➢ Strategically placed fulcrum
➢ Force applied to the bottom
❖ Wear Measurement
➢ Microscope and Volume Displacement
Second Design
❖ Lever arm design incorporated onto
the drill press
❖ Existing platform mount retains
translating shaft
❖ Two Cups Inside One Another
➢ Increase Repeatability
❖ Weights used to apply load
❖ Wear Measurement via Camera
Second Milestone Design
❖ Air cylinder with manual
regulator to apply force from the
top
❖ Thrust bearing under the cup for
self-alignment
❖ Fixed bottom plate for improved
repeatability and accuracy
❖ Force sensors implemented on
the cup
❖ Wear measurement camera
❖ Hot plate for heating the
Concerns After Milestone Two
❖ Pneumatic Cylinder:
➢ Manual Air Regulation Accuracy
➢ Air Cleaning
❖ Data:
➢ No Way to Directly Calculate
Normal Load
➢ Controlling Motor Speed
❖ Cup:
➢ Dual Cup Design for Repeatability
Created an Extra Moment to
Consider
❖ Force Application:
➢ Not Constant Over Time
➢ Weights Capability to Fall
Decreased Safety Factor
❖ Heating and Cooling:
➢ Overheating would lead to
welding of balls
➢ Maintaining the temperature at
the standard without
overheating
❖ Safety:
➢ Temperature Intensity and Ball
Controlling Applied Force
❖ Manual Regulator
➢ Budget-friendly
➢ Not accurate
➢ Needs to be controlled better
❖ Controls Loop
➢ Continuously checks and displays data
➢ Maintains desired force output
➢ Costly
Final Re-Design Concepts
Design Changes:
❖ Added Filter to the Pneumatic Cylinder
❖ Added Electronic P-Valve
➢ Controls loop feeds data to constantly regulate pressure
❖ Redesigned for Addition of Axial Transducer
➢ Input Data relays to the DAQ for direct normal force measurement
❖ Self-Alignment Plate Design for the Axial Transducer
❖ Replacement 3-Phase Motor to Allow for the Addition of Variable Speed Drive
❖ Added Heating Elements and Temperature Controller
❖ Added Auto-Stop Controlled by the Temperature Controller
Final Design
❖ Drill press was further modified
❖ Pneumatic cylinder added to apply force
❖ Axial Transducer incorporated for direct
force measurement
❖ Auto-Stop Controller incorporated for
increased safety
❖ Addition of plate to platform for mounting
cup and axial transducer
Theoretical Testing
and Equations
Theoretical Testing
❖ Finite Element Analyses (FEA) were performed to determine the
theoretical stresses and deformation results based on the designed
components under the standard conditions determined.
❖ Theoretical Calculations were used to determine the dimensions of the air
cylinder
Given:
➢ Lever Arm Length= 4 in.
➢ Bore Size= 7/16 in.
➢ Gear Ratio= 13:1
➢ Pinion Diameter= I in.
➢ From ASTM D2266 Standards, Applied Force= 88.18
lbf
Collet FEA
Thermal FEA
Thermal analysis
determined that no
insulation is necessary.
Theoretical Calculations
❖ Tangential Force at Pinion:
➢ By considering the relationship between
forces and the mechanical advantage of
the gear ratio, Ft was calculated.
❖ The Moment about Pinion, M :
Theoretical Calculations
❖ Required Force Output from Air Cylinder:
➢ Using the Equation for Moment at the End of a
Rotating Rod as a Result from the Air Cylinder
Force, FA:
➢ Working Area of Cylinder, A:
❖ Required Internal Pressure of 7/16 in. Bore Air
Cylinder:
➢ From Pascal’s Law, P:
Budget
Budget
❖ The initial budget presentation was
estimated at $1,575.31
❖ The budget was re-presented based off
of the concerns presented by Dr. Vlcek
and Dr. Molina at $3,538.70
Original Total Budget:
$1,575.31
Proposed New Budget:
$3,538.70
Difference:
$1,963.39
Force Components Budget
Control’s Budget
Fabrication Components Budget
Final Budget
Technical Drawings
Components Designed by the Group:
❖ Chuck/Collet Set-Up:
➢ Chuck
➢ Stopper
❖ Cup Set-Up:
➢ Cap
➢ Retainer
➢ Cup
Stopper
**Note: All Dimensions are in Inches
Chuck
**Note: All Dimensions are in Inches
Cap
**Note: All Dimensions are in Inches
Retainer
**Note: All Dimensions are in Inches
Cup
**Note: All Dimensions are in Inches
Centering
Plate
**Note: All Dimensions are in Inches
Fabrication Issues
❖ Collet Design Problem 1: Threads caused DA collet to become
non-concentric
➢ Solution: Eliminated threads that tighten down on collet
❖ Collet Design Problem 2: Not enough friction to keep DA
collet from turning during operation
➢ Solution: Use dowel to hold collet in place with a hex cap
screw that will pull DA collet into chuck
Fabrication Images
Cup/Transducer/Plate Assembly
Cup/Transducer/Plate Assembly
Pneumatic Piston Set-Up
Chuck Set-Up
Instrumentation/Controls
Review:
❖ Block Diagram
❖ Temperature
❖ Torque
❖ RPM
❖ DAQ
❖ Power Supplies
Instrumentation and Controls
Recent Additions:
❖ Axial Force
❖ New Motor
❖ RPM Control
❖ Emergency Stop
Instrumentation block diagram
Instrumentation and Controls
Force/Torque Controls
Torque Transducer
Force Controller
Pressure Valve
DAQ
❖ Single Phase Induction Motor
❖ No Control Available
❖ Encoder would be counting
total revolutions
Original RPM Controls
New RPM Control
❖ New 3 Phase, ½ hp motor
will reach speed specified in
standards
➢VFD controller will
maintain constant RPM AC Motor 0.5 HP
Emergency Stop
❖ Arduino
controller and
programming
were used to
implement this
feature Arduino Controller
Measuring Torque and Axial Force
❖ Thrust and torque load cell
simplifies torque and axial
force measurement
❖ No longer rely on calculated
axial force and torque
Thrust and Torque Load Cell
Force/Torque Controls
Temperature Controls
Temperature sensor Temperature controller Temperature actuator
Temperature Controls
❖ Torque and Thrust Biaxial Sensor
❖ Thermocouple
❖ Microcontroller
❖ Power Relay
❖ Miniature Relay
Power Supply Controls
Power Supply Controls
Calibration and Testing
❖ Signal Conditioning
❖ Force
❖ Temperature
❖ Auto-shutoff
❖ RPM
Calibration and Testing
❖ Signal Conditioning
➢ Built three inverted op-amp circuits to amplify
temperature, torque, and force signals
❖ Force Sensor
➢ Calibrated by using calibration charts
➢ Tested by listening to pressure change as actuator
or valve is activated by controller
Calibration and Testing
❖ Temperature
➢ Tested by boiling
water and
observing heating
element activation
Calibration and Testing
❖ Auto-shutoff
➢ Tested auto-start by observing activation of
drill
➢ Tested auto-stop by boiling water and
observing deactivation of drill
❖ RPM
➢ Ordered three-phase motor and VFD controller
➢ Encoder temporarily set-up for RPM counting
until new motor arrives
Results
The Results of the tribometer were unfortunately not
able to be recorded due to the DAQ set-up being
incomplete.
Summary
❖ Completed:
➢ Concept Development
➢ Multiple Design Changes
➢ Final Design Approval
➢ All Fabrication
❖ Incomplete:
➢ Three Phase Motor
➢ VFD Controller
➢ Auto-Stop Controller
➢ DAQ Output Results
➢ Final Set-Up and Wire
Organization
References
[1] ASTM Standards:
ASTM D2266-01(2008), Standard Test Method for Wear Preventive Characteristics of
Lubricating Grease (Four-Ball Method), ASTM International, West Conshohocken, PA, 2008,
www.astm.org
ASTM D4172-94(2010), Standard Test Method for Wear Preventive Characteristics of
Lubricating Fluid (Four-Ball Method), ASTM International, West Conshohocken, PA, 2010,
www.astm.org
ASTM D5183-05(2011), Standard Test Method for Determination of the Coefficient of
Friction of Lubricants Using the Four-Ball Wear Test Machine, ASTM International, West
Conshohocken, PA, 2011, www.astm.org
Gantt
Timeline
Concept Comparison Results
Comparison Constraints: Ease of Use, Cost, Size, Safety,
Accuracy, Maintenance, Repeatability
Table 1: Concept Comparison Group Totals
QFD
Air Cylinder Set-Up
Figure 15: Air Cylinder Model (Side View)
Air Cylinder Set-Up
Figure 16: Air Cylinder Detail Drawing
Air Cylinder Set-Up
Table 3&4: Air Cylinder Calculations and Possible Scenarios
Rough Calculations
Total Needed Downward Force 150 lb
Tang. Force from Pinion (1" Diam) 11.53 lb
Moment Produced at Pinion 5.765 lb*in
Rack/Pinion Gear Ratio 13:01
Air Cylinder Set-Up
Table 5: Air Cylinder Details
Air Cylinder Set-Up
Table 6: Air Cylinder Set-Up Parts List
Temperature Measurement
ASTM D2266, D4172, and
D5183 Standards require a
lubricant temperature of 75℃
maintained within 2℃.
Figure 18: Omega Thermocouple [3]
Temperature Measurement
LabVIEW writes Excel file
that contains time and
temperature data.
Figure 19: Temperature Output
Temperature Measurement
Manufacturer Price Specifications Quantity
Omega $35.00 -200 to 1250 ℃
1McMaster-Carr $35.00 -200 to 1250 ℃
TEMPCO $35.00 -200 to 1250 ℃
Table 9: Thermocouple Manufacturer Comparisons
Temperature Control
PID control provides more
accuracy
Figure 20: AUTONICS temperature
controller [4]
Temperature Control
Manufacturer Price Specifications Quantity
AUTONICS $143.00 +/- 1 ℃
1
Omega $195.00 +/-0.5 ℃
Table 10: Temperature Controller Manufacturer Comparisons
Heating
Manufacturer Price Specifications Quantity
Omega $25.00 10W/in2
2
McMaster-Carr $26.00 10W/in2
Table 11: Heating Element Manufacturer Comparisons
RPM Measurement
Real time RPM:
❖ LabVIEW program
creates Excel file
❖ Excel file contains time,
encoder counts, and
RPM
Encoder
Figure 23: Encoder Motion
Schematicω = (θ2-θ1)/( T2-T1)
RPM Measurement
The max RPM required
by the three standards
used is up to 1200 rpm
and the smallest
accuracy required is ±60
rpm.
Figure 24: Karlsson Robotics Rotary
Encoder [7]
RPM Measurement
Figure 28: Display of LabVIEW Data
RPM Measurement
Manufacturer Price Specifications Quantity
Karlsson Robotics $50.00 up to 6,000 RPM
1
Automation Direct $90.00 up to 5,000 RPM
Table 13: Rotary Encoder Manufacturer Comparison
Data Acquisition
❖ Sampling rate is an
important factor for
DAQ selection.
❖ Digital counter required
for easier RPM
measurement.
Figure 30: National Instruments DAQ [8]
Data Acquisition
Manufacturer Price Specifications Quantity
National Instruments $300.00 48 kS/s
1
LabJack $114.00 50 kS/s
Table 14: DAQ Manufacturer Comparison
Power
❖5 Volts provided to the
encoder and force sensors
by a DC power supply.
Figure 34: Power Supply [11]
Power
Manufacturer Price Specifications Quantity
TDK-Lambda $18.00 5V
1
CUI $28.00 5 V
Table 16: DC Power Supply Manufacturer Comparison

More Related Content

What's hot

Artificial Lift Products from Evolution Oil Tools
Artificial Lift Products from Evolution Oil ToolsArtificial Lift Products from Evolution Oil Tools
Artificial Lift Products from Evolution Oil Tools
Geoffrey Brennan
 
Gas Turbine PGT25 DLE Single Gas With Centrifugal Compressor PCL 603PS
Gas Turbine PGT25 DLE Single Gas With Centrifugal Compressor PCL 603PSGas Turbine PGT25 DLE Single Gas With Centrifugal Compressor PCL 603PS
Gas Turbine PGT25 DLE Single Gas With Centrifugal Compressor PCL 603PSJamie Boyd
 
Prvs 2. asme section i fired vessel rev4
Prvs   2. asme section i fired vessel rev4Prvs   2. asme section i fired vessel rev4
Prvs 2. asme section i fired vessel rev4
David Alexandre
 
20130601 - Work carried out on 21G72
20130601 - Work carried out on 21G7220130601 - Work carried out on 21G72
20130601 - Work carried out on 21G72Joe Edwards
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
Manohar Tatwawadi
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergencies
Manohar Tatwawadi
 
Automatic Pneumatic Double Bumper
Automatic Pneumatic Double BumperAutomatic Pneumatic Double Bumper
Automatic Pneumatic Double Bumper
SandeepIlangovan
 
4736 4740.output
4736 4740.output4736 4740.output
4736 4740.output
j1075017
 
Focus areas in economic operation of DG sets
Focus areas in economic operation of DG setsFocus areas in economic operation of DG sets
Focus areas in economic operation of DG setsD.Pawan Kumar
 
Surge Control for Parallel Centrifugal Compressor Operations
Surge Control for Parallel Centrifugal Compressor OperationsSurge Control for Parallel Centrifugal Compressor Operations
Surge Control for Parallel Centrifugal Compressor Operations
Vijay Sarathy
 
Work carried out on 21G20 in March 2013 - Copy
Work carried out on 21G20 in March 2013 - CopyWork carried out on 21G20 in March 2013 - Copy
Work carried out on 21G20 in March 2013 - CopyJoe Edwards
 
Brochure Fire-Fighting 05-2015
Brochure Fire-Fighting 05-2015Brochure Fire-Fighting 05-2015
Brochure Fire-Fighting 05-2015jan visser
 
Major drilling-rotary-rc-brochure
Major drilling-rotary-rc-brochureMajor drilling-rotary-rc-brochure
Major drilling-rotary-rc-brochure
JulioColque5
 
Presentation on Meter Regulating Skid(MRS)
Presentation on Meter Regulating Skid(MRS)Presentation on Meter Regulating Skid(MRS)
Presentation on Meter Regulating Skid(MRS)
harsitatpug
 
Reavell 20 100 hp water cooled reciprocating compressor
Reavell 20 100 hp water cooled reciprocating compressorReavell 20 100 hp water cooled reciprocating compressor
Reavell 20 100 hp water cooled reciprocating compressor
Mazen Rabah
 
well pad operations - PCP
well pad operations - PCPwell pad operations - PCP
well pad operations - PCP
Afsal Ameen c
 
Progressive Cavity Pump (PCP) Petroleum Production Engineering
Progressive Cavity Pump (PCP) Petroleum Production EngineeringProgressive Cavity Pump (PCP) Petroleum Production Engineering
Progressive Cavity Pump (PCP) Petroleum Production Engineering
Muhammad Hanif
 

What's hot (18)

Artificial Lift Products from Evolution Oil Tools
Artificial Lift Products from Evolution Oil ToolsArtificial Lift Products from Evolution Oil Tools
Artificial Lift Products from Evolution Oil Tools
 
Gas Turbine PGT25 DLE Single Gas With Centrifugal Compressor PCL 603PS
Gas Turbine PGT25 DLE Single Gas With Centrifugal Compressor PCL 603PSGas Turbine PGT25 DLE Single Gas With Centrifugal Compressor PCL 603PS
Gas Turbine PGT25 DLE Single Gas With Centrifugal Compressor PCL 603PS
 
Prvs 2. asme section i fired vessel rev4
Prvs   2. asme section i fired vessel rev4Prvs   2. asme section i fired vessel rev4
Prvs 2. asme section i fired vessel rev4
 
20130601 - Work carried out on 21G72
20130601 - Work carried out on 21G7220130601 - Work carried out on 21G72
20130601 - Work carried out on 21G72
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergencies
 
Automatic Pneumatic Double Bumper
Automatic Pneumatic Double BumperAutomatic Pneumatic Double Bumper
Automatic Pneumatic Double Bumper
 
4736 4740.output
4736 4740.output4736 4740.output
4736 4740.output
 
Focus areas in economic operation of DG sets
Focus areas in economic operation of DG setsFocus areas in economic operation of DG sets
Focus areas in economic operation of DG sets
 
Surge Control for Parallel Centrifugal Compressor Operations
Surge Control for Parallel Centrifugal Compressor OperationsSurge Control for Parallel Centrifugal Compressor Operations
Surge Control for Parallel Centrifugal Compressor Operations
 
Work carried out on 21G20 in March 2013 - Copy
Work carried out on 21G20 in March 2013 - CopyWork carried out on 21G20 in March 2013 - Copy
Work carried out on 21G20 in March 2013 - Copy
 
job des
job desjob des
job des
 
Brochure Fire-Fighting 05-2015
Brochure Fire-Fighting 05-2015Brochure Fire-Fighting 05-2015
Brochure Fire-Fighting 05-2015
 
Major drilling-rotary-rc-brochure
Major drilling-rotary-rc-brochureMajor drilling-rotary-rc-brochure
Major drilling-rotary-rc-brochure
 
Presentation on Meter Regulating Skid(MRS)
Presentation on Meter Regulating Skid(MRS)Presentation on Meter Regulating Skid(MRS)
Presentation on Meter Regulating Skid(MRS)
 
Reavell 20 100 hp water cooled reciprocating compressor
Reavell 20 100 hp water cooled reciprocating compressorReavell 20 100 hp water cooled reciprocating compressor
Reavell 20 100 hp water cooled reciprocating compressor
 
well pad operations - PCP
well pad operations - PCPwell pad operations - PCP
well pad operations - PCP
 
Progressive Cavity Pump (PCP) Petroleum Production Engineering
Progressive Cavity Pump (PCP) Petroleum Production EngineeringProgressive Cavity Pump (PCP) Petroleum Production Engineering
Progressive Cavity Pump (PCP) Petroleum Production Engineering
 

Viewers also liked

power generation from speed breaker
power generation from speed breakerpower generation from speed breaker
power generation from speed breaker
DXVICKY
 
Rack and pinion gear design project.
Rack and pinion gear design project.Rack and pinion gear design project.
Rack and pinion gear design project.Waqas Ali Tunio
 
Rack and pinion
Rack and pinionRack and pinion
Presentacion Congreso Polymat 2013 Huatulco, Oaxaca, Mexico
Presentacion Congreso Polymat 2013 Huatulco, Oaxaca, MexicoPresentacion Congreso Polymat 2013 Huatulco, Oaxaca, Mexico
Presentacion Congreso Polymat 2013 Huatulco, Oaxaca, Mexico
Fernando Chinas
 
Rack and pinion
Rack and pinionRack and pinion
Rack and pinion
ROBOTIX רובוטיקס
 
The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )
Kamel Elsayed
 
Preparation Of Specimen For Microscopic Examination
Preparation Of Specimen For Microscopic ExaminationPreparation Of Specimen For Microscopic Examination
Preparation Of Specimen For Microscopic Examination
PATEL DEEP
 
Fluid pwr
Fluid pwrFluid pwr
S3 Individual Presentation - LAPTOP Acer Aspire
S3 Individual Presentation - LAPTOP Acer AspireS3 Individual Presentation - LAPTOP Acer Aspire
S3 Individual Presentation - LAPTOP Acer Aspire
no suhaila
 
Energy policy : New Zealand
Energy policy : New ZealandEnergy policy : New Zealand
Energy policy : New Zealandpnnazz
 
Rack and pinion presentation
Rack and pinion presentationRack and pinion presentation
Rack and pinion presentation
Rajdeep Das
 
2012 rack and pinion (1)
2012 rack and pinion (1)2012 rack and pinion (1)
2012 rack and pinion (1)Luke jackson
 
3: Energy Management In Water Supply Systems - Pumping Operations
3: Energy Management In Water Supply Systems - Pumping Operations3: Energy Management In Water Supply Systems - Pumping Operations
3: Energy Management In Water Supply Systems - Pumping Operations
Alliance To Save Energy
 
Design improvement-of-the-existing-car-jack-design---24-pages
Design improvement-of-the-existing-car-jack-design---24-pagesDesign improvement-of-the-existing-car-jack-design---24-pages
Design improvement-of-the-existing-car-jack-design---24-pagesJorge Flórido
 
power generation through speed breaker
power generation through speed breakerpower generation through speed breaker
power generation through speed breakerShifa Nadeem
 
pnuematic valve symbols
pnuematic valve symbolspnuematic valve symbols
pnuematic valve symbolsTaliya Hemanth
 
Sem 2 bs1 cold water supply 1
Sem 2 bs1 cold water supply   1Sem 2 bs1 cold water supply   1
Sem 2 bs1 cold water supply 1
Est
 
S3 Lec 7 (air flow rate)
S3 Lec 7 (air flow rate)S3 Lec 7 (air flow rate)
S3 Lec 7 (air flow rate)
no suhaila
 
Hydraulics training
Hydraulics trainingHydraulics training
Hydraulics training
Sunil Dewalekar
 

Viewers also liked (20)

power generation from speed breaker
power generation from speed breakerpower generation from speed breaker
power generation from speed breaker
 
Rack and pinion gear design project.
Rack and pinion gear design project.Rack and pinion gear design project.
Rack and pinion gear design project.
 
Rack and pinion
Rack and pinionRack and pinion
Rack and pinion
 
Presentacion Congreso Polymat 2013 Huatulco, Oaxaca, Mexico
Presentacion Congreso Polymat 2013 Huatulco, Oaxaca, MexicoPresentacion Congreso Polymat 2013 Huatulco, Oaxaca, Mexico
Presentacion Congreso Polymat 2013 Huatulco, Oaxaca, Mexico
 
Final project
Final projectFinal project
Final project
 
Rack and pinion
Rack and pinionRack and pinion
Rack and pinion
 
The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )
 
Preparation Of Specimen For Microscopic Examination
Preparation Of Specimen For Microscopic ExaminationPreparation Of Specimen For Microscopic Examination
Preparation Of Specimen For Microscopic Examination
 
Fluid pwr
Fluid pwrFluid pwr
Fluid pwr
 
S3 Individual Presentation - LAPTOP Acer Aspire
S3 Individual Presentation - LAPTOP Acer AspireS3 Individual Presentation - LAPTOP Acer Aspire
S3 Individual Presentation - LAPTOP Acer Aspire
 
Energy policy : New Zealand
Energy policy : New ZealandEnergy policy : New Zealand
Energy policy : New Zealand
 
Rack and pinion presentation
Rack and pinion presentationRack and pinion presentation
Rack and pinion presentation
 
2012 rack and pinion (1)
2012 rack and pinion (1)2012 rack and pinion (1)
2012 rack and pinion (1)
 
3: Energy Management In Water Supply Systems - Pumping Operations
3: Energy Management In Water Supply Systems - Pumping Operations3: Energy Management In Water Supply Systems - Pumping Operations
3: Energy Management In Water Supply Systems - Pumping Operations
 
Design improvement-of-the-existing-car-jack-design---24-pages
Design improvement-of-the-existing-car-jack-design---24-pagesDesign improvement-of-the-existing-car-jack-design---24-pages
Design improvement-of-the-existing-car-jack-design---24-pages
 
power generation through speed breaker
power generation through speed breakerpower generation through speed breaker
power generation through speed breaker
 
pnuematic valve symbols
pnuematic valve symbolspnuematic valve symbols
pnuematic valve symbols
 
Sem 2 bs1 cold water supply 1
Sem 2 bs1 cold water supply   1Sem 2 bs1 cold water supply   1
Sem 2 bs1 cold water supply 1
 
S3 Lec 7 (air flow rate)
S3 Lec 7 (air flow rate)S3 Lec 7 (air flow rate)
S3 Lec 7 (air flow rate)
 
Hydraulics training
Hydraulics trainingHydraulics training
Hydraulics training
 

Similar to Milestone 3

Engine Introduction.pptx
Engine Introduction.pptxEngine Introduction.pptx
Engine Introduction.pptx
Sujit Regmi
 
Engine Introduction.pptx
Engine Introduction.pptxEngine Introduction.pptx
Engine Introduction.pptx
Sujit Regmi
 
eti_03_EngineTestingOverview.pdf
eti_03_EngineTestingOverview.pdfeti_03_EngineTestingOverview.pdf
eti_03_EngineTestingOverview.pdf
AlemuAsefa1
 
Final Animal Loading Device Presentation
Final Animal Loading Device PresentationFinal Animal Loading Device Presentation
Final Animal Loading Device PresentationBolt Zhang
 
3rd unit content.pptx
3rd unit content.pptx3rd unit content.pptx
3rd unit content.pptx
MohamedAboulazm2
 
Combi Systems: Lessons Learned from the Field
Combi Systems: Lessons Learned from the FieldCombi Systems: Lessons Learned from the Field
Combi Systems: Lessons Learned from the Field
Center for Energy and Environment
 
Testing of Mixed Flow Vertical Turbine Pump
Testing of Mixed Flow Vertical Turbine PumpTesting of Mixed Flow Vertical Turbine Pump
Testing of Mixed Flow Vertical Turbine Pump
IRJET Journal
 
Improving Energy Efficiency of Pumps and Fans
Improving Energy Efficiency of Pumps and FansImproving Energy Efficiency of Pumps and Fans
Improving Energy Efficiency of Pumps and Fans
eecfncci
 
Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014
Ray Beebe
 
FINAL-Fan-Laws-Part-1-091621.pptx
FINAL-Fan-Laws-Part-1-091621.pptxFINAL-Fan-Laws-Part-1-091621.pptx
FINAL-Fan-Laws-Part-1-091621.pptx
PhongHoangLe
 
Energy audit & conservation studies for industries
Energy audit & conservation studies for industriesEnergy audit & conservation studies for industries
Energy audit & conservation studies for industries
ravindradatar
 
4-electricalsubmersibleumps.pdfeeeeeeeee
4-electricalsubmersibleumps.pdfeeeeeeeee4-electricalsubmersibleumps.pdfeeeeeeeee
4-electricalsubmersibleumps.pdfeeeeeeeee
shakermahoud
 
Ais 041(rev.1)
Ais 041(rev.1)Ais 041(rev.1)
Ais 041(rev.1)
Dhruv Upadhaya
 
Bubble injection inside cooling system
Bubble injection inside cooling systemBubble injection inside cooling system
Bubble injection inside cooling system
Shamil Pc
 
Engineered Spring Supports (Practical, Hands-on Approach) Webinar
Engineered Spring Supports (Practical, Hands-on Approach) WebinarEngineered Spring Supports (Practical, Hands-on Approach) Webinar
Engineered Spring Supports (Practical, Hands-on Approach) Webinar
Piping Technology & Products, Inc.
 
ECM Motor and Pump Basics - Grundfos
ECM Motor and Pump Basics - GrundfosECM Motor and Pump Basics - Grundfos
ECM Motor and Pump Basics - Grundfos
ArcticEnergyAlliance
 
Motorcycle Engine Design
Motorcycle Engine DesignMotorcycle Engine Design
Motorcycle Engine Design
BoxuanSong
 
Volvo ECR88 Compact Excavator Service Repair Manual Instant Download.pdf
Volvo ECR88 Compact Excavator Service Repair Manual Instant Download.pdfVolvo ECR88 Compact Excavator Service Repair Manual Instant Download.pdf
Volvo ECR88 Compact Excavator Service Repair Manual Instant Download.pdf
f8iosedkdm3e
 

Similar to Milestone 3 (20)

Engine Introduction.pptx
Engine Introduction.pptxEngine Introduction.pptx
Engine Introduction.pptx
 
Engine Introduction.pptx
Engine Introduction.pptxEngine Introduction.pptx
Engine Introduction.pptx
 
eti_03_EngineTestingOverview.pdf
eti_03_EngineTestingOverview.pdfeti_03_EngineTestingOverview.pdf
eti_03_EngineTestingOverview.pdf
 
Final Animal Loading Device Presentation
Final Animal Loading Device PresentationFinal Animal Loading Device Presentation
Final Animal Loading Device Presentation
 
3rd unit content.pptx
3rd unit content.pptx3rd unit content.pptx
3rd unit content.pptx
 
Combi Systems: Lessons Learned from the Field
Combi Systems: Lessons Learned from the FieldCombi Systems: Lessons Learned from the Field
Combi Systems: Lessons Learned from the Field
 
Project List
Project ListProject List
Project List
 
Testing of Mixed Flow Vertical Turbine Pump
Testing of Mixed Flow Vertical Turbine PumpTesting of Mixed Flow Vertical Turbine Pump
Testing of Mixed Flow Vertical Turbine Pump
 
Improving Energy Efficiency of Pumps and Fans
Improving Energy Efficiency of Pumps and FansImproving Energy Efficiency of Pumps and Fans
Improving Energy Efficiency of Pumps and Fans
 
Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014
 
FINAL-Fan-Laws-Part-1-091621.pptx
FINAL-Fan-Laws-Part-1-091621.pptxFINAL-Fan-Laws-Part-1-091621.pptx
FINAL-Fan-Laws-Part-1-091621.pptx
 
Energy audit & conservation studies for industries
Energy audit & conservation studies for industriesEnergy audit & conservation studies for industries
Energy audit & conservation studies for industries
 
4-electricalsubmersibleumps.pdfeeeeeeeee
4-electricalsubmersibleumps.pdfeeeeeeeee4-electricalsubmersibleumps.pdfeeeeeeeee
4-electricalsubmersibleumps.pdfeeeeeeeee
 
Ais 041(rev.1)
Ais 041(rev.1)Ais 041(rev.1)
Ais 041(rev.1)
 
Bubble injection inside cooling system
Bubble injection inside cooling systemBubble injection inside cooling system
Bubble injection inside cooling system
 
Engineered Spring Supports (Practical, Hands-on Approach) Webinar
Engineered Spring Supports (Practical, Hands-on Approach) WebinarEngineered Spring Supports (Practical, Hands-on Approach) Webinar
Engineered Spring Supports (Practical, Hands-on Approach) Webinar
 
ECM Motor and Pump Basics - Grundfos
ECM Motor and Pump Basics - GrundfosECM Motor and Pump Basics - Grundfos
ECM Motor and Pump Basics - Grundfos
 
Motorcycle Engine Design
Motorcycle Engine DesignMotorcycle Engine Design
Motorcycle Engine Design
 
Pipininspect
PipininspectPipininspect
Pipininspect
 
Volvo ECR88 Compact Excavator Service Repair Manual Instant Download.pdf
Volvo ECR88 Compact Excavator Service Repair Manual Instant Download.pdfVolvo ECR88 Compact Excavator Service Repair Manual Instant Download.pdf
Volvo ECR88 Compact Excavator Service Repair Manual Instant Download.pdf
 

Milestone 3

  • 1. Four Ball Accelerated Wear Tester Department of Mechanical Engineering Fall Semester 2014 Mechanical System Design CONTROLS TEAM STRUCTURES TEAM FABRICATION TEAM Ana Dungan Whitney Stregles Daniel Griffin Kelsey Kaht Robert Nalecz Colin Holliday Steve Soto Riley Shay Casey Sheppard John Willis Jordan Ansley Michael Spaulding Ibrahim Ahmed
  • 3. Four Ball Tribometer ❖ Tests a lubricant’s extreme pressure properties under high contact in pure sliding or pure rolling motion ❖ In this design, a ½ inch diameter ball is pressed against three similar balls at a set force. The top ball will spin against the three lower balls creating wear scars on the balls. ❖ The force and torque applied to the system are measured and this data, along with the appearance of wear scars, enables the user to conclude which lubrication is the most efficient
  • 4. Example Set-Up Note: This is not our 4-Ball Tribometer
  • 5. Objectives Successfully design and fabricate a four ball accelerated wear tester: ➢ Thoroughly research and develop major concepts and compare constraints ➢ Develop a design that rotates a top ball under a force causing friction and wear on the bottom 3 balls ➢ Develop a prototype to test major concepts ➢ Develop methods for measuring wear, torque, load, and temperature ➢ Establish a budget for the project
  • 6. ASTM Standards ASTM D2266 ASTM D4172 ASTM D5183 Value Tolerance Value Tolerance Value Tolerance Force Applied 40 kgf 0.2 kgf 15 kgf 0.2 kgf 40 kgf Not Given 392 N 2 N 147 N 2 N 392 N Not Given Lubricant Temp 75 C 2 C 75 C 2 C 75 C 2 C 167 F 4 F 167 F 4 F 167 F 4 F Speed 1200 rpm 60 rpm 1200 rpm 60 rpm 600 rpm Not Given Duration 60 min 1 min 60 min 1 min 60 min Not Given Oil Level very top of cup 3mm above top of balls 3mm above top of balls [1]
  • 7. Design Process ❖ The design of the 4-ball tribometer was changed several times. ❖ The initial design involved a lever and an inline motor. ❖ The second design included the drill press that was donated to our team and the previous lever idea. ❖ The final design utilizes a pneumatic cylinder and was upgraded from the use of a manual regulator to the integration of a data acquisition concept and force sensor components to control the applied force.
  • 8. Initial Design ❖ Basic Concept ➢ Not technologically advanced ❖ Inline Motor ❖ Lever Arm ➢ Strategically placed fulcrum ➢ Force applied to the bottom ❖ Wear Measurement ➢ Microscope and Volume Displacement
  • 9. Second Design ❖ Lever arm design incorporated onto the drill press ❖ Existing platform mount retains translating shaft ❖ Two Cups Inside One Another ➢ Increase Repeatability ❖ Weights used to apply load ❖ Wear Measurement via Camera
  • 10. Second Milestone Design ❖ Air cylinder with manual regulator to apply force from the top ❖ Thrust bearing under the cup for self-alignment ❖ Fixed bottom plate for improved repeatability and accuracy ❖ Force sensors implemented on the cup ❖ Wear measurement camera ❖ Hot plate for heating the
  • 11. Concerns After Milestone Two ❖ Pneumatic Cylinder: ➢ Manual Air Regulation Accuracy ➢ Air Cleaning ❖ Data: ➢ No Way to Directly Calculate Normal Load ➢ Controlling Motor Speed ❖ Cup: ➢ Dual Cup Design for Repeatability Created an Extra Moment to Consider ❖ Force Application: ➢ Not Constant Over Time ➢ Weights Capability to Fall Decreased Safety Factor ❖ Heating and Cooling: ➢ Overheating would lead to welding of balls ➢ Maintaining the temperature at the standard without overheating ❖ Safety: ➢ Temperature Intensity and Ball
  • 12. Controlling Applied Force ❖ Manual Regulator ➢ Budget-friendly ➢ Not accurate ➢ Needs to be controlled better ❖ Controls Loop ➢ Continuously checks and displays data ➢ Maintains desired force output ➢ Costly
  • 13. Final Re-Design Concepts Design Changes: ❖ Added Filter to the Pneumatic Cylinder ❖ Added Electronic P-Valve ➢ Controls loop feeds data to constantly regulate pressure ❖ Redesigned for Addition of Axial Transducer ➢ Input Data relays to the DAQ for direct normal force measurement ❖ Self-Alignment Plate Design for the Axial Transducer ❖ Replacement 3-Phase Motor to Allow for the Addition of Variable Speed Drive ❖ Added Heating Elements and Temperature Controller ❖ Added Auto-Stop Controlled by the Temperature Controller
  • 14. Final Design ❖ Drill press was further modified ❖ Pneumatic cylinder added to apply force ❖ Axial Transducer incorporated for direct force measurement ❖ Auto-Stop Controller incorporated for increased safety ❖ Addition of plate to platform for mounting cup and axial transducer
  • 16. Theoretical Testing ❖ Finite Element Analyses (FEA) were performed to determine the theoretical stresses and deformation results based on the designed components under the standard conditions determined. ❖ Theoretical Calculations were used to determine the dimensions of the air cylinder Given: ➢ Lever Arm Length= 4 in. ➢ Bore Size= 7/16 in. ➢ Gear Ratio= 13:1 ➢ Pinion Diameter= I in. ➢ From ASTM D2266 Standards, Applied Force= 88.18 lbf
  • 18. Thermal FEA Thermal analysis determined that no insulation is necessary.
  • 19. Theoretical Calculations ❖ Tangential Force at Pinion: ➢ By considering the relationship between forces and the mechanical advantage of the gear ratio, Ft was calculated. ❖ The Moment about Pinion, M :
  • 20. Theoretical Calculations ❖ Required Force Output from Air Cylinder: ➢ Using the Equation for Moment at the End of a Rotating Rod as a Result from the Air Cylinder Force, FA: ➢ Working Area of Cylinder, A: ❖ Required Internal Pressure of 7/16 in. Bore Air Cylinder: ➢ From Pascal’s Law, P:
  • 22. Budget ❖ The initial budget presentation was estimated at $1,575.31 ❖ The budget was re-presented based off of the concerns presented by Dr. Vlcek and Dr. Molina at $3,538.70 Original Total Budget: $1,575.31 Proposed New Budget: $3,538.70 Difference: $1,963.39
  • 27. Technical Drawings Components Designed by the Group: ❖ Chuck/Collet Set-Up: ➢ Chuck ➢ Stopper ❖ Cup Set-Up: ➢ Cap ➢ Retainer ➢ Cup
  • 30. Cap **Note: All Dimensions are in Inches
  • 32. Cup **Note: All Dimensions are in Inches
  • 34. Fabrication Issues ❖ Collet Design Problem 1: Threads caused DA collet to become non-concentric ➢ Solution: Eliminated threads that tighten down on collet ❖ Collet Design Problem 2: Not enough friction to keep DA collet from turning during operation ➢ Solution: Use dowel to hold collet in place with a hex cap screw that will pull DA collet into chuck
  • 41. Review: ❖ Block Diagram ❖ Temperature ❖ Torque ❖ RPM ❖ DAQ ❖ Power Supplies Instrumentation and Controls Recent Additions: ❖ Axial Force ❖ New Motor ❖ RPM Control ❖ Emergency Stop
  • 43. Force/Torque Controls Torque Transducer Force Controller Pressure Valve DAQ
  • 44. ❖ Single Phase Induction Motor ❖ No Control Available ❖ Encoder would be counting total revolutions Original RPM Controls
  • 45. New RPM Control ❖ New 3 Phase, ½ hp motor will reach speed specified in standards ➢VFD controller will maintain constant RPM AC Motor 0.5 HP
  • 46. Emergency Stop ❖ Arduino controller and programming were used to implement this feature Arduino Controller
  • 47. Measuring Torque and Axial Force ❖ Thrust and torque load cell simplifies torque and axial force measurement ❖ No longer rely on calculated axial force and torque Thrust and Torque Load Cell
  • 49. Temperature Controls Temperature sensor Temperature controller Temperature actuator
  • 51. ❖ Torque and Thrust Biaxial Sensor ❖ Thermocouple ❖ Microcontroller ❖ Power Relay ❖ Miniature Relay Power Supply Controls
  • 53. Calibration and Testing ❖ Signal Conditioning ❖ Force ❖ Temperature ❖ Auto-shutoff ❖ RPM
  • 54. Calibration and Testing ❖ Signal Conditioning ➢ Built three inverted op-amp circuits to amplify temperature, torque, and force signals ❖ Force Sensor ➢ Calibrated by using calibration charts ➢ Tested by listening to pressure change as actuator or valve is activated by controller
  • 55. Calibration and Testing ❖ Temperature ➢ Tested by boiling water and observing heating element activation
  • 56. Calibration and Testing ❖ Auto-shutoff ➢ Tested auto-start by observing activation of drill ➢ Tested auto-stop by boiling water and observing deactivation of drill ❖ RPM ➢ Ordered three-phase motor and VFD controller ➢ Encoder temporarily set-up for RPM counting until new motor arrives
  • 57. Results The Results of the tribometer were unfortunately not able to be recorded due to the DAQ set-up being incomplete.
  • 58. Summary ❖ Completed: ➢ Concept Development ➢ Multiple Design Changes ➢ Final Design Approval ➢ All Fabrication ❖ Incomplete: ➢ Three Phase Motor ➢ VFD Controller ➢ Auto-Stop Controller ➢ DAQ Output Results ➢ Final Set-Up and Wire Organization
  • 59. References [1] ASTM Standards: ASTM D2266-01(2008), Standard Test Method for Wear Preventive Characteristics of Lubricating Grease (Four-Ball Method), ASTM International, West Conshohocken, PA, 2008, www.astm.org ASTM D4172-94(2010), Standard Test Method for Wear Preventive Characteristics of Lubricating Fluid (Four-Ball Method), ASTM International, West Conshohocken, PA, 2010, www.astm.org ASTM D5183-05(2011), Standard Test Method for Determination of the Coefficient of Friction of Lubricants Using the Four-Ball Wear Test Machine, ASTM International, West Conshohocken, PA, 2011, www.astm.org
  • 61. Concept Comparison Results Comparison Constraints: Ease of Use, Cost, Size, Safety, Accuracy, Maintenance, Repeatability Table 1: Concept Comparison Group Totals
  • 62. QFD
  • 63. Air Cylinder Set-Up Figure 15: Air Cylinder Model (Side View)
  • 64. Air Cylinder Set-Up Figure 16: Air Cylinder Detail Drawing
  • 65. Air Cylinder Set-Up Table 3&4: Air Cylinder Calculations and Possible Scenarios Rough Calculations Total Needed Downward Force 150 lb Tang. Force from Pinion (1" Diam) 11.53 lb Moment Produced at Pinion 5.765 lb*in Rack/Pinion Gear Ratio 13:01
  • 66. Air Cylinder Set-Up Table 5: Air Cylinder Details
  • 67. Air Cylinder Set-Up Table 6: Air Cylinder Set-Up Parts List
  • 68. Temperature Measurement ASTM D2266, D4172, and D5183 Standards require a lubricant temperature of 75℃ maintained within 2℃. Figure 18: Omega Thermocouple [3]
  • 69. Temperature Measurement LabVIEW writes Excel file that contains time and temperature data. Figure 19: Temperature Output
  • 70. Temperature Measurement Manufacturer Price Specifications Quantity Omega $35.00 -200 to 1250 ℃ 1McMaster-Carr $35.00 -200 to 1250 ℃ TEMPCO $35.00 -200 to 1250 ℃ Table 9: Thermocouple Manufacturer Comparisons
  • 71. Temperature Control PID control provides more accuracy Figure 20: AUTONICS temperature controller [4]
  • 72. Temperature Control Manufacturer Price Specifications Quantity AUTONICS $143.00 +/- 1 ℃ 1 Omega $195.00 +/-0.5 ℃ Table 10: Temperature Controller Manufacturer Comparisons
  • 73. Heating Manufacturer Price Specifications Quantity Omega $25.00 10W/in2 2 McMaster-Carr $26.00 10W/in2 Table 11: Heating Element Manufacturer Comparisons
  • 74. RPM Measurement Real time RPM: ❖ LabVIEW program creates Excel file ❖ Excel file contains time, encoder counts, and RPM Encoder Figure 23: Encoder Motion Schematicω = (θ2-θ1)/( T2-T1)
  • 75. RPM Measurement The max RPM required by the three standards used is up to 1200 rpm and the smallest accuracy required is ±60 rpm. Figure 24: Karlsson Robotics Rotary Encoder [7]
  • 76. RPM Measurement Figure 28: Display of LabVIEW Data
  • 77. RPM Measurement Manufacturer Price Specifications Quantity Karlsson Robotics $50.00 up to 6,000 RPM 1 Automation Direct $90.00 up to 5,000 RPM Table 13: Rotary Encoder Manufacturer Comparison
  • 78. Data Acquisition ❖ Sampling rate is an important factor for DAQ selection. ❖ Digital counter required for easier RPM measurement. Figure 30: National Instruments DAQ [8]
  • 79. Data Acquisition Manufacturer Price Specifications Quantity National Instruments $300.00 48 kS/s 1 LabJack $114.00 50 kS/s Table 14: DAQ Manufacturer Comparison
  • 80. Power ❖5 Volts provided to the encoder and force sensors by a DC power supply. Figure 34: Power Supply [11]
  • 81. Power Manufacturer Price Specifications Quantity TDK-Lambda $18.00 5V 1 CUI $28.00 5 V Table 16: DC Power Supply Manufacturer Comparison