The Carlstar Group, LLC
Human Resources Deparment
To: Johanna Kempski Date: 4-15-16
From: Michael Coulombe
Subject: Project Accomplishments
Project: West Trimmer Guard
Issue: Safety
Problem:
 Welding slag is not contained, workers are subject to being hit by red hot welding slag.
Design Requirements:
 Orientation of trimmer dictates multi-axis movement of guard
o Solution- create guard that moves down then follows trimmer out to collect slag
o Linear bearings used on either side to accommodate this motion, as well as
support weight of guard
o Lifting frame was designed to be sturdy, built with two bearing supports to
counter moment created by own weight
 Sourced parts, specified springs, communicated with all involved parties
 Given minimal time as it was a safety issue
o Given Friday, it was modeled by Monday
o Worked with the machine shop until completion
 Fixed safety issue of having red hot welding slag projected about the work space
Project: Line 3 Kicker
Issue: Safety
Problem:
 Operator was using broom to eject stuck rim band in roll 2 when the broom got wedge
and hit the operator in the face.
 Operator sustained only minor injuries, but it could cause much more serious injuries.
Design Requirements:
 Must guide wheel out of rolls once open so the rim does not fall and get stuck
 Kickers exist on rolls 1 of both line 1 and line 2, line 3 has a much smaller width then
lines 1 and 2.
o Design must fit within the envelope of roll 2 of line 3
o Limits materials to use
 Hot rolled bar was used, material on hand
 Extensive measurements were taken
o Needs to accommodate from a 4” to 6” width and 10” to 16” diameter.
o All applicable rims were measured, and attachments were made for each rim
 Design is fully functioning, and alleviated operator from using a broom handle to
dislodge stuck wheels.
Project: Line 1, Roll 2 Kicker
Issue: Safety
Problem:
 Operator uses broom handle to eject stuck wheels, operators previously injured from
doing this
Design Requirements:
 Since a kicker is on roll 1, the design was based around that
 After measuring, it was found that the line tapers, getting narrower with each roll
o Every component must be changed to reflect this
o The design needs to incorporate as many off the shelf components as possible
 Design process was carried out in solid works where interactions/fitments can be seen
o A bell crank system was designed to allow necessary articulation of the kicker
arm to work with all diameters of rims ran on the line
o A new mounting system was configured after talking with maintenance, this
allowed them to take out the air cylinder without having to take the whole
mechanism out.
 Design is fully functioning, and eliminated necessity for operator to remove stuck rims.
Project: Die Rack Move
Issue: Future State
Problem:
 Die racks were all over stamping building, needed to be condensed and arranged to
accept future state layout
Design Requirements:
 Used AutoCad/Solidworks to optimize layout
o Forklift access had to be accounted for
o Maximum shelf space was thought of to ensure all dies had shelf space
 Since die racks were against a wall shared with the office, safety needed to be
addressed
o Die racks had steel tube welded to the back, and tops to prevent dies from being
pushed through
 Bending calculations were carried out to size tubing appropriately
 Length of material was calculated so appropriate amount of material was
ordered
Project: Valve Hole Pierce Machine
Issue: Existing Equipment Failure
Problem:
 Existing clutch/flywheel style press had broken beyond repair
Design Requirements:
 Air was initially to be used instead of hydraulic power
o Force calculations were prepared to redesign top arm, as well as size air cylinder
 It was found that too big of an air cylinder was needed, and our existing
air compressors would not support this
 All Existing drawings were compiled; it was determined what was missing
o Measured or created drawings of missing components
 Calculations were carried out for force required of worst case (biggest valve hole,
thickest material)
o A hydraulic cylinder was sized, worked with Bernell to get correct cylinder
o Also worked with Bernell to size an appropriate hydraulic power unit, added
chiller to prolong life of equipment and reduce operating temperatures.
 After safety check was done, unit was put into production
Project: Center Press
Issue: No Positive Stop
Problem:
 Aligning adds and extra step to the assembly process
o Requires extra FTE, and adds extra time to the assembly process
Design Requirements:
 Data from Aiken shows that a having a positive stop reduces run out
o Need to incorporate positive stop in current presses to eliminate aligners
 Each of the 5 lines has a different press
o System needs to be able to be used on every line for every assembled wheel
 Identified shut heights for each press
o Identified and specified all parameters necessary for new press concept
 Modeled initial design so Engineering department had a visual idea
o Moved forward with concept
 Concentric ring fixtures were design to fit all rims, and be easily removable by operator
for ease of change over
o Centers were grouped in families so upper and lower tooling could be made
 Elevator system designed to allow the widest wheel to fit on smallest shut height
o Acme threaded rods were used, torque calculations were carried out to ensure
an appropriate sized motor was used to power the threaded rods
 A chain drive system was developed in order to power and sync both rods
 Required angular contact ball bearings to account for axial loads in both
up and down directions.
 Ratchet system was developed to work in positive stop system
o This allows the wheel to be taken in and out with no obstruction from the lower
die
 Necessary for small shut heights
 Test runs conclude that consistent run out can be had with positive stop system
o Ongoing project, further development to take place

Project List

  • 1.
    The Carlstar Group,LLC Human Resources Deparment To: Johanna Kempski Date: 4-15-16 From: Michael Coulombe Subject: Project Accomplishments Project: West Trimmer Guard Issue: Safety Problem:  Welding slag is not contained, workers are subject to being hit by red hot welding slag. Design Requirements:  Orientation of trimmer dictates multi-axis movement of guard o Solution- create guard that moves down then follows trimmer out to collect slag o Linear bearings used on either side to accommodate this motion, as well as support weight of guard o Lifting frame was designed to be sturdy, built with two bearing supports to counter moment created by own weight  Sourced parts, specified springs, communicated with all involved parties  Given minimal time as it was a safety issue o Given Friday, it was modeled by Monday o Worked with the machine shop until completion  Fixed safety issue of having red hot welding slag projected about the work space Project: Line 3 Kicker Issue: Safety Problem:  Operator was using broom to eject stuck rim band in roll 2 when the broom got wedge and hit the operator in the face.  Operator sustained only minor injuries, but it could cause much more serious injuries. Design Requirements:  Must guide wheel out of rolls once open so the rim does not fall and get stuck
  • 2.
     Kickers existon rolls 1 of both line 1 and line 2, line 3 has a much smaller width then lines 1 and 2. o Design must fit within the envelope of roll 2 of line 3 o Limits materials to use  Hot rolled bar was used, material on hand  Extensive measurements were taken o Needs to accommodate from a 4” to 6” width and 10” to 16” diameter. o All applicable rims were measured, and attachments were made for each rim  Design is fully functioning, and alleviated operator from using a broom handle to dislodge stuck wheels. Project: Line 1, Roll 2 Kicker Issue: Safety Problem:  Operator uses broom handle to eject stuck wheels, operators previously injured from doing this Design Requirements:  Since a kicker is on roll 1, the design was based around that  After measuring, it was found that the line tapers, getting narrower with each roll o Every component must be changed to reflect this o The design needs to incorporate as many off the shelf components as possible  Design process was carried out in solid works where interactions/fitments can be seen o A bell crank system was designed to allow necessary articulation of the kicker arm to work with all diameters of rims ran on the line o A new mounting system was configured after talking with maintenance, this allowed them to take out the air cylinder without having to take the whole mechanism out.  Design is fully functioning, and eliminated necessity for operator to remove stuck rims. Project: Die Rack Move Issue: Future State Problem:  Die racks were all over stamping building, needed to be condensed and arranged to accept future state layout Design Requirements:  Used AutoCad/Solidworks to optimize layout o Forklift access had to be accounted for o Maximum shelf space was thought of to ensure all dies had shelf space
  • 3.
     Since dieracks were against a wall shared with the office, safety needed to be addressed o Die racks had steel tube welded to the back, and tops to prevent dies from being pushed through  Bending calculations were carried out to size tubing appropriately  Length of material was calculated so appropriate amount of material was ordered Project: Valve Hole Pierce Machine Issue: Existing Equipment Failure Problem:  Existing clutch/flywheel style press had broken beyond repair Design Requirements:  Air was initially to be used instead of hydraulic power o Force calculations were prepared to redesign top arm, as well as size air cylinder  It was found that too big of an air cylinder was needed, and our existing air compressors would not support this  All Existing drawings were compiled; it was determined what was missing o Measured or created drawings of missing components  Calculations were carried out for force required of worst case (biggest valve hole, thickest material) o A hydraulic cylinder was sized, worked with Bernell to get correct cylinder o Also worked with Bernell to size an appropriate hydraulic power unit, added chiller to prolong life of equipment and reduce operating temperatures.  After safety check was done, unit was put into production Project: Center Press Issue: No Positive Stop Problem:  Aligning adds and extra step to the assembly process o Requires extra FTE, and adds extra time to the assembly process Design Requirements:  Data from Aiken shows that a having a positive stop reduces run out o Need to incorporate positive stop in current presses to eliminate aligners  Each of the 5 lines has a different press o System needs to be able to be used on every line for every assembled wheel  Identified shut heights for each press
  • 4.
    o Identified andspecified all parameters necessary for new press concept  Modeled initial design so Engineering department had a visual idea o Moved forward with concept  Concentric ring fixtures were design to fit all rims, and be easily removable by operator for ease of change over o Centers were grouped in families so upper and lower tooling could be made  Elevator system designed to allow the widest wheel to fit on smallest shut height o Acme threaded rods were used, torque calculations were carried out to ensure an appropriate sized motor was used to power the threaded rods  A chain drive system was developed in order to power and sync both rods  Required angular contact ball bearings to account for axial loads in both up and down directions.  Ratchet system was developed to work in positive stop system o This allows the wheel to be taken in and out with no obstruction from the lower die  Necessary for small shut heights  Test runs conclude that consistent run out can be had with positive stop system o Ongoing project, further development to take place