SlideShare a Scribd company logo
LIFTING WORK PERMIT
Page 1 of 2 Form # HSEQ-LWP (Rev 2 - Mar 23)
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity: Time (from): __________Hrs. Time (To): __________Hrs. Date:
Weight of Load : Max Height of Lift:
Max. Radius of Lift: Lifting Equipment ID/Registration No.:
Crane Capacity (SWL)
Lift shall not be carried out if the load chart capacity
exceeds 80% (Capacity …………)
Lifting Point Defined: ☐ Yes ☐ No Road Closure/ Isolation required: ☐ Yes ☐ No
Underground services identified (if applicable):
☐ Yes ☐ No
Load Centre of Gravity Calculated: ☐ Yes ☐ No
3. Lifting Operation Details: (To be filled by initiator/originator)
Crane Operator Contact:
Rigger-1 Contact:
Rigger-2 Contact:
Type of Lifting Crane: ☐ Mobile Crane
☐ Wheel crane ☐ Crawler Crane
☐ All Terrain
☐ Loader/Hiab Crane
☐ Excavator
☐ Elevated working Platform
☐ Mobile Concrete Pump
☐ All Winch
☐ Other :
Lifting Crane Specification: ☐ Year of make (<25 years): __________
☐ Lifting Capacity: __________
☐ No. of rope fall wraps: ___________
☐ SWL: ______________
☐ Boom Reach: __________
☐ Fly Jib Reach: ___________
☐ Other(s): _____________
Type of lifting Gear(s): ☐ Chain Sling,
No. Of Legs: ___________
Each Leg Capacity: ____________
SWL: ______________
☐ Webbing Sling, SWL: ____________
☐ Wire Rope, SWL: _____________
☐ Lifting Beam, SWL: ___________
☐ Shackle, SWL: _____________
☐ Chain Blocks, SWL: ____________
☐ Hook with latch, SWL: ___________
☐ Eye Bolt/Nut, SWL: ____________
☐ Other(s): _________________
LIFTING WORK PERMIT
Page 2 of 2 Form # HSEQ-LWP (Rev 2 - Mar 23)
4. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Risk assessment/ method statement and Lifting
Plan developed, approved and communicated?
☐ ☐ ☐
Crane outriggers fully extended and
spreading pads in place
☐ ☐ ☐
Operatives are consulted and trained? ☐ ☐ ☐ All wheels are off the ground. ☐ ☐ ☐
Provision of vigilance supervision? ☐ ☐ ☐
SWL and radius indicators in working order
with visual and audible warning
☐ ☐ ☐
Has the crane valid certification ☐ ☐ ☐ Wind indicator is fitted & in working order ☐ ☐ ☐
Has the lifting gears valid certification ☐ ☐ ☐
load(s) slung correctly by a competent
rigger
☐ ☐ ☐
Riggers/slinger competent and certified ☐ ☐ ☐ Tag-line(s) are connected with the load ☐ ☐ ☐
Correct crane selected for the load(s) and radius ☐ ☐ ☐
Suspended Load slewing path is cleared
from people and barricaded
☐ ☐ ☐
Ground suitable, even, firm and prepared ☐ ☐ ☐
Destination of load(s) is cleared and
prepared sufficiently
☐ ☐ ☐
Safe means of access/egress provided? ☐ ☐ ☐ Load rating chart for the crane is available ☐ ☐ ☐
Crane is set-up away from excavation ☐ ☐ ☐ Communication aid available (radio device) ☐ ☐ ☐
Crane swing radius area is free from overhead
cable/ structure or other cranes
☐ ☐ ☐
Has the operator have a valid 3rd
party
certificate and license?
☐ ☐ ☐
Proper barricade and signage are posted? ☐ ☐ ☐ Others (specify): ☐ ☐ ☐
5. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives,
and I consider them competent to do it safely.
Initiator/Originator
Name:
Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
6. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
7. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator: Designation:
Signature: Date /Time
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator: Designation:
Signature: Date /Time

More Related Content

What's hot

3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templates
Dwarika Bhushan Sharma
 
Hot Works Safety Training
Hot Works Safety TrainingHot Works Safety Training
Hot Works Safety Training
Gaurav Singh Rajput
 
NGI-Permit to Work
NGI-Permit to WorkNGI-Permit to Work
NGI-Permit to Worklifecombo
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdf
BalamuruganD26
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
VasudevaRajuDantulur1
 
Permit to work training
Permit to work trainingPermit to work training
Permit to work training
Karnav Rana
 
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC Rev 2.docx
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC  Rev 2.docxAUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC  Rev 2.docx
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC Rev 2.docx
Dwarika Bhushan Sharma
 
Conducting Hot Work Operations
Conducting Hot Work OperationsConducting Hot Work Operations
Conducting Hot Work Operations
Aaron Johnson
 
Permit to Work Training
Permit to Work TrainingPermit to Work Training
Permit to Work Training
SUDHEER KUMAR KALYANAM
 
Lifting plan
Lifting planLifting plan
Lifting plan
tnsv22
 
A Part 1 Safety Induction
A  Part 1 Safety InductionA  Part 1 Safety Induction
A Part 1 Safety Induction
James McCann
 
Risk assessment for testing &amp; commissioning of cranes
Risk assessment for  testing &amp; commissioning of cranesRisk assessment for  testing &amp; commissioning of cranes
Risk assessment for testing &amp; commissioning of cranes
Azmeel Contracting Company
 
Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
Sergio Augusto Esteves
 
Permit to work system
Permit to work systemPermit to work system
Permit to work system
Asif Khan
 
Job safety Analysis
Job safety Analysis Job safety Analysis
Job safety Analysis Deepu Rajan
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
Simba Zhao
 
27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates
Dwarika Bhushan Sharma
 
Lifting Equipment Inspection
Lifting Equipment InspectionLifting Equipment Inspection
Lifting Equipment Inspection
Schilling s
 

What's hot (20)

3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templates
 
Hot Works Safety Training
Hot Works Safety TrainingHot Works Safety Training
Hot Works Safety Training
 
NGI-Permit to Work
NGI-Permit to WorkNGI-Permit to Work
NGI-Permit to Work
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdf
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Permit to work training
Permit to work trainingPermit to work training
Permit to work training
 
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC Rev 2.docx
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC  Rev 2.docxAUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC  Rev 2.docx
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC Rev 2.docx
 
Conducting Hot Work Operations
Conducting Hot Work OperationsConducting Hot Work Operations
Conducting Hot Work Operations
 
Permit to Work Training
Permit to Work TrainingPermit to Work Training
Permit to Work Training
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
A Part 1 Safety Induction
A  Part 1 Safety InductionA  Part 1 Safety Induction
A Part 1 Safety Induction
 
Risk assessment for testing &amp; commissioning of cranes
Risk assessment for  testing &amp; commissioning of cranesRisk assessment for  testing &amp; commissioning of cranes
Risk assessment for testing &amp; commissioning of cranes
 
Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
 
Permit to work system
Permit to work systemPermit to work system
Permit to work system
 
Job safety Analysis
Job safety Analysis Job safety Analysis
Job safety Analysis
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
 
27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates
 
Forklift safety
Forklift safetyForklift safety
Forklift safety
 
Lifting Equipment Inspection
Lifting Equipment InspectionLifting Equipment Inspection
Lifting Equipment Inspection
 

Similar to LIFTING WORK PERMIT Form # HSEQ - LWP Rev 2.docx

MAST CLIMBER & CRADLE PERMIT Form # HSEQ - Rev 2.docx
MAST CLIMBER & CRADLE PERMIT Form # HSEQ -  Rev 2.docxMAST CLIMBER & CRADLE PERMIT Form # HSEQ -  Rev 2.docx
MAST CLIMBER & CRADLE PERMIT Form # HSEQ - Rev 2.docx
Dwarika Bhushan Sharma
 
LADDER PERMIT REV 1 MARCH 28 2018 Form # HSEQ - LP Rev 2.docx
LADDER PERMIT REV 1 MARCH 28 2018 Form # HSEQ - LP Rev 2.docxLADDER PERMIT REV 1 MARCH 28 2018 Form # HSEQ - LP Rev 2.docx
LADDER PERMIT REV 1 MARCH 28 2018 Form # HSEQ - LP Rev 2.docx
Dwarika Bhushan Sharma
 
PRESSURE TESTING PERMIT Form # HSEQ - PTP Rev 2 -.docx
PRESSURE TESTING PERMIT Form # HSEQ - PTP Rev 2 -.docxPRESSURE TESTING PERMIT Form # HSEQ - PTP Rev 2 -.docx
PRESSURE TESTING PERMIT Form # HSEQ - PTP Rev 2 -.docx
Dwarika Bhushan Sharma
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
Dwarika Bhushan Sharma
 
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docxEDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
Dwarika Bhushan Sharma
 
DE-SHUTTERING WORK PERMIT Form # HSEQ - DSWP Rev 2.docx
DE-SHUTTERING WORK PERMIT Form # HSEQ - DSWP Rev 2.docxDE-SHUTTERING WORK PERMIT Form # HSEQ - DSWP Rev 2.docx
DE-SHUTTERING WORK PERMIT Form # HSEQ - DSWP Rev 2.docx
Dwarika Bhushan Sharma
 
WAIVER FORM Form # HSEQ - WF Rev 2.docx
WAIVER FORM Form # HSEQ - WF Rev 2.docxWAIVER FORM Form # HSEQ - WF Rev 2.docx
WAIVER FORM Form # HSEQ - WF Rev 2.docx
Dwarika Bhushan Sharma
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2
Sergio Augusto Esteves
 
HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docxHOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
Dwarika Bhushan Sharma
 
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
Arber Dogani
 
COLD WORK PERMIT Form # HSEQ - CWP Rev 2.docx
COLD WORK PERMIT Form # HSEQ - CWP Rev 2.docxCOLD WORK PERMIT Form # HSEQ - CWP Rev 2.docx
COLD WORK PERMIT Form # HSEQ - CWP Rev 2.docx
Dwarika Bhushan Sharma
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
dinesh622857
 
Section 2.pdf
Section 2.pdfSection 2.pdf
Section 2.pdf
Basant Ashraf
 
TOWER CRANE INSPECTION CHECKLIST Form # HSEQ - TCI Rev 2 -.docx
TOWER CRANE INSPECTION CHECKLIST Form # HSEQ - TCI  Rev 2 -.docxTOWER CRANE INSPECTION CHECKLIST Form # HSEQ - TCI  Rev 2 -.docx
TOWER CRANE INSPECTION CHECKLIST Form # HSEQ - TCI Rev 2 -.docx
Dwarika Bhushan Sharma
 
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
Arber Dogani
 
2
22
JOB SAFETY ENVIRONMENTAL ANALYSIS Form # HSEQ - JSEA Rev 2 -.docx
JOB SAFETY ENVIRONMENTAL ANALYSIS   Form # HSEQ - JSEA Rev 2 -.docxJOB SAFETY ENVIRONMENTAL ANALYSIS   Form # HSEQ - JSEA Rev 2 -.docx
JOB SAFETY ENVIRONMENTAL ANALYSIS Form # HSEQ - JSEA Rev 2 -.docx
Dwarika Bhushan Sharma
 
JSEA JOB SAFETY ENVIRONMENTAL ANALYSIS Form # HSEQ - JSEA Rev 2 -.docx
JSEA JOB SAFETY ENVIRONMENTAL ANALYSIS   Form # HSEQ - JSEA Rev 2 -.docxJSEA JOB SAFETY ENVIRONMENTAL ANALYSIS   Form # HSEQ - JSEA Rev 2 -.docx
JSEA JOB SAFETY ENVIRONMENTAL ANALYSIS Form # HSEQ - JSEA Rev 2 -.docx
Dwarika Bhushan Sharma
 
Const cranes 9 3 10
Const cranes 9 3 10Const cranes 9 3 10
Const cranes 9 3 10
vtsiri
 
Uds v202 u2 rev 0
Uds v202  u2 rev 0Uds v202  u2 rev 0
Uds v202 u2 rev 0
Anish Dani
 

Similar to LIFTING WORK PERMIT Form # HSEQ - LWP Rev 2.docx (20)

MAST CLIMBER & CRADLE PERMIT Form # HSEQ - Rev 2.docx
MAST CLIMBER & CRADLE PERMIT Form # HSEQ -  Rev 2.docxMAST CLIMBER & CRADLE PERMIT Form # HSEQ -  Rev 2.docx
MAST CLIMBER & CRADLE PERMIT Form # HSEQ - Rev 2.docx
 
LADDER PERMIT REV 1 MARCH 28 2018 Form # HSEQ - LP Rev 2.docx
LADDER PERMIT REV 1 MARCH 28 2018 Form # HSEQ - LP Rev 2.docxLADDER PERMIT REV 1 MARCH 28 2018 Form # HSEQ - LP Rev 2.docx
LADDER PERMIT REV 1 MARCH 28 2018 Form # HSEQ - LP Rev 2.docx
 
PRESSURE TESTING PERMIT Form # HSEQ - PTP Rev 2 -.docx
PRESSURE TESTING PERMIT Form # HSEQ - PTP Rev 2 -.docxPRESSURE TESTING PERMIT Form # HSEQ - PTP Rev 2 -.docx
PRESSURE TESTING PERMIT Form # HSEQ - PTP Rev 2 -.docx
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
 
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docxEDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
EDGE PROTECTION AND FLOOR OPENINGS REMOVAL PERMIT Form # HSEQ - EPRP Rev 2.docx
 
DE-SHUTTERING WORK PERMIT Form # HSEQ - DSWP Rev 2.docx
DE-SHUTTERING WORK PERMIT Form # HSEQ - DSWP Rev 2.docxDE-SHUTTERING WORK PERMIT Form # HSEQ - DSWP Rev 2.docx
DE-SHUTTERING WORK PERMIT Form # HSEQ - DSWP Rev 2.docx
 
WAIVER FORM Form # HSEQ - WF Rev 2.docx
WAIVER FORM Form # HSEQ - WF Rev 2.docxWAIVER FORM Form # HSEQ - WF Rev 2.docx
WAIVER FORM Form # HSEQ - WF Rev 2.docx
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2
 
HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docxHOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
HOT WORK PERMIT Form # HSEQ - HWP Rev 7 -.docx
 
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
 
COLD WORK PERMIT Form # HSEQ - CWP Rev 2.docx
COLD WORK PERMIT Form # HSEQ - CWP Rev 2.docxCOLD WORK PERMIT Form # HSEQ - CWP Rev 2.docx
COLD WORK PERMIT Form # HSEQ - CWP Rev 2.docx
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
 
Section 2.pdf
Section 2.pdfSection 2.pdf
Section 2.pdf
 
TOWER CRANE INSPECTION CHECKLIST Form # HSEQ - TCI Rev 2 -.docx
TOWER CRANE INSPECTION CHECKLIST Form # HSEQ - TCI  Rev 2 -.docxTOWER CRANE INSPECTION CHECKLIST Form # HSEQ - TCI  Rev 2 -.docx
TOWER CRANE INSPECTION CHECKLIST Form # HSEQ - TCI Rev 2 -.docx
 
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
 
2
22
2
 
JOB SAFETY ENVIRONMENTAL ANALYSIS Form # HSEQ - JSEA Rev 2 -.docx
JOB SAFETY ENVIRONMENTAL ANALYSIS   Form # HSEQ - JSEA Rev 2 -.docxJOB SAFETY ENVIRONMENTAL ANALYSIS   Form # HSEQ - JSEA Rev 2 -.docx
JOB SAFETY ENVIRONMENTAL ANALYSIS Form # HSEQ - JSEA Rev 2 -.docx
 
JSEA JOB SAFETY ENVIRONMENTAL ANALYSIS Form # HSEQ - JSEA Rev 2 -.docx
JSEA JOB SAFETY ENVIRONMENTAL ANALYSIS   Form # HSEQ - JSEA Rev 2 -.docxJSEA JOB SAFETY ENVIRONMENTAL ANALYSIS   Form # HSEQ - JSEA Rev 2 -.docx
JSEA JOB SAFETY ENVIRONMENTAL ANALYSIS Form # HSEQ - JSEA Rev 2 -.docx
 
Const cranes 9 3 10
Const cranes 9 3 10Const cranes 9 3 10
Const cranes 9 3 10
 
Uds v202 u2 rev 0
Uds v202  u2 rev 0Uds v202  u2 rev 0
Uds v202 u2 rev 0
 

More from Dwarika Bhushan Sharma

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
Dwarika Bhushan Sharma
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
Dwarika Bhushan Sharma
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
Dwarika Bhushan Sharma
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
Dwarika Bhushan Sharma
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
Dwarika Bhushan Sharma
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
Dwarika Bhushan Sharma
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
Dwarika Bhushan Sharma
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
Dwarika Bhushan Sharma
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
Dwarika Bhushan Sharma
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
Dwarika Bhushan Sharma
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
Dwarika Bhushan Sharma
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
Dwarika Bhushan Sharma
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
Dwarika Bhushan Sharma
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
Dwarika Bhushan Sharma
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
Dwarika Bhushan Sharma
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
Dwarika Bhushan Sharma
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
Dwarika Bhushan Sharma
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
Dwarika Bhushan Sharma
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
Dwarika Bhushan Sharma
 
MEDICAL REPORT FORM Form # HSEQ - MRF Rev 3 -.docx
MEDICAL REPORT FORM Form # HSEQ - MRF Rev 3 -.docxMEDICAL REPORT FORM Form # HSEQ - MRF Rev 3 -.docx
MEDICAL REPORT FORM Form # HSEQ - MRF Rev 3 -.docx
Dwarika Bhushan Sharma
 

More from Dwarika Bhushan Sharma (20)

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
 
MEDICAL REPORT FORM Form # HSEQ - MRF Rev 3 -.docx
MEDICAL REPORT FORM Form # HSEQ - MRF Rev 3 -.docxMEDICAL REPORT FORM Form # HSEQ - MRF Rev 3 -.docx
MEDICAL REPORT FORM Form # HSEQ - MRF Rev 3 -.docx
 

Recently uploaded

一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 

Recently uploaded (20)

一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 

LIFTING WORK PERMIT Form # HSEQ - LWP Rev 2.docx

  • 1. LIFTING WORK PERMIT Page 1 of 2 Form # HSEQ-LWP (Rev 2 - Mar 23) 1. Project Information: (To be filled by initiator/originator) Project Name: Permit No.: Project Location: Requesting Contractor/Company 2. Permit Issuance Details: (To be filled by initiator/originator) THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE Description of Task: Detail of Surroundings: Permit Validity: Time (from): __________Hrs. Time (To): __________Hrs. Date: Weight of Load : Max Height of Lift: Max. Radius of Lift: Lifting Equipment ID/Registration No.: Crane Capacity (SWL) Lift shall not be carried out if the load chart capacity exceeds 80% (Capacity …………) Lifting Point Defined: ☐ Yes ☐ No Road Closure/ Isolation required: ☐ Yes ☐ No Underground services identified (if applicable): ☐ Yes ☐ No Load Centre of Gravity Calculated: ☐ Yes ☐ No 3. Lifting Operation Details: (To be filled by initiator/originator) Crane Operator Contact: Rigger-1 Contact: Rigger-2 Contact: Type of Lifting Crane: ☐ Mobile Crane ☐ Wheel crane ☐ Crawler Crane ☐ All Terrain ☐ Loader/Hiab Crane ☐ Excavator ☐ Elevated working Platform ☐ Mobile Concrete Pump ☐ All Winch ☐ Other : Lifting Crane Specification: ☐ Year of make (<25 years): __________ ☐ Lifting Capacity: __________ ☐ No. of rope fall wraps: ___________ ☐ SWL: ______________ ☐ Boom Reach: __________ ☐ Fly Jib Reach: ___________ ☐ Other(s): _____________ Type of lifting Gear(s): ☐ Chain Sling, No. Of Legs: ___________ Each Leg Capacity: ____________ SWL: ______________ ☐ Webbing Sling, SWL: ____________ ☐ Wire Rope, SWL: _____________ ☐ Lifting Beam, SWL: ___________ ☐ Shackle, SWL: _____________ ☐ Chain Blocks, SWL: ____________ ☐ Hook with latch, SWL: ___________ ☐ Eye Bolt/Nut, SWL: ____________ ☐ Other(s): _________________
  • 2. LIFTING WORK PERMIT Page 2 of 2 Form # HSEQ-LWP (Rev 2 - Mar 23) 4. Prerequisites: (To be filled by initiator/originator and verified by Evaluator) Checks Yes-No-NA Checks Yes-No-NA Risk assessment/ method statement and Lifting Plan developed, approved and communicated? ☐ ☐ ☐ Crane outriggers fully extended and spreading pads in place ☐ ☐ ☐ Operatives are consulted and trained? ☐ ☐ ☐ All wheels are off the ground. ☐ ☐ ☐ Provision of vigilance supervision? ☐ ☐ ☐ SWL and radius indicators in working order with visual and audible warning ☐ ☐ ☐ Has the crane valid certification ☐ ☐ ☐ Wind indicator is fitted & in working order ☐ ☐ ☐ Has the lifting gears valid certification ☐ ☐ ☐ load(s) slung correctly by a competent rigger ☐ ☐ ☐ Riggers/slinger competent and certified ☐ ☐ ☐ Tag-line(s) are connected with the load ☐ ☐ ☐ Correct crane selected for the load(s) and radius ☐ ☐ ☐ Suspended Load slewing path is cleared from people and barricaded ☐ ☐ ☐ Ground suitable, even, firm and prepared ☐ ☐ ☐ Destination of load(s) is cleared and prepared sufficiently ☐ ☐ ☐ Safe means of access/egress provided? ☐ ☐ ☐ Load rating chart for the crane is available ☐ ☐ ☐ Crane is set-up away from excavation ☐ ☐ ☐ Communication aid available (radio device) ☐ ☐ ☐ Crane swing radius area is free from overhead cable/ structure or other cranes ☐ ☐ ☐ Has the operator have a valid 3rd party certificate and license? ☐ ☐ ☐ Proper barricade and signage are posted? ☐ ☐ ☐ Others (specify): ☐ ☐ ☐ 5. Acknowledgement by Initiator and Evaluator: ☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely. Initiator/Originator Name: Designation: Signature: Date /Time: ☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity Evaluator (HSE Team): Designation: Signature: Date /Time Comments (if any): 6. Authorization (PM/CM): Name: Designation: Signature: Date /Time: 7. Completion/Cancelation of Permit: ☐ Acknowledge that the area have been restored to a safe and orderly condition. Initiator: Designation: Signature: Date /Time ☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition. Evaluator: Designation: Signature: Date /Time