Project Information:
Project Name:
Location: Supervisor :
Company name : Date:
Task Description:
Before work starts, the following must be in place
Induction Supervision Test Certificates Communication in same language Method Statement Risk Assessment Permit To Work Area Lighting
SELECT HAZARDS SELECT CONTROLS
( Tick to identify the controls in place)
Fall from height Training Access Ladder Access Handrail Edge Protection Secure Ladder Adequate Work Platform Guards for Openings Safety Harness Life Lines
Others( Specify)
Manual Handling Training Check Weight Mechanical Aids Access Route Team Lifting Wrong method Right Method
Power tools Training Color code inspection tag Check Cable Wheel guards Safe plug & sockets Cable Protection Proper Scaffold Cable Overhead Rotatory part guards
Scaffold Scaffold Tag Edge Protection Check Overhead works Access Ladder Adequate Work Platform Weather condition Out riggers Ladder 3 feet above platform Safety Harness
SELECT HAZARDS SELECT CONTROLS
( Tick to identify the controls in place)
Risk Assessment
Lifting Plan Tag Lines Lifting points / hooks Banks man Load stability Check Lifting gear Examination /Inspection Sharp edges protected
Lifting operations Weather/ Wind Speed Ground conditions Exclusion zone Communication Loading/ unloading vehicles Spreader Beams Check Ground conditions Check outriggers Others
Fire Fire Extinguisher Fire Hose Fire Exit Assembly point others
Slip/Trip Clean before you go Barricade the waste Waste Management Clean Access Housekeeping Clean liquid spillage Access signs Maintain access/ Egress
PPE
Safety Harness
Safety Helmet Coveralls Hi vis Jacket Safety Shoe Face Shield Ear Protection
Dust mask Respiratory Equipment Life line/ harness anchorage Hand Gloves Goggles/ Glass
Pre start Briefing done by: Signature:
Reviewed By HSE Manager/ In charge: Signature:
1. Project Information:
Project Name: Checklist No.:
Sub-Contractor/Company:
Date:
2. Task Details:
Description of Task:
Location / Area :
Number of Workers:
Task Duration:
Time (from): _______Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites:
Checks Yes-No-NA Checks Yes-No-NA
Safety induction done. ☐ ☐ ☐
Safety tool box talk done. ☐ ☐ ☐
Method statement/Risk assessment in place. ☐ ☐ ☐
Training on Risk Assessment/ Method Statement done ☐ ☐ ☐
Job Safety Analysis done. ☐ ☐ ☐
3 Month Safety Look Ahead in place ☐ ☐ ☐
Permit to Work obtained ☐ ☐ ☐
Site Supervisor available ☐ ☐ ☐
PPE Available ☐ ☐ ☐
Working area is well lighted ☐ ☐ ☐
Tools and equipment inspected and tagged ☐ ☐ ☐
Unsafe conditions rectified ☐ ☐ ☐
Pre-Start Checks completed ☐ ☐ ☐
Emergency procedures communicated ☐ ☐ ☐
Unauthorized workers are cleared from the area.
☐ ☐ ☐
Other ( Specify): ☐ ☐ ☐
4. Acknowledgement by Sub-Contractor:
☐ Acknowledge that all above precautions/ controls measures have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
Signature: Date /Time
Project Information
Project Name: Store No.
Location: Contact Person:
Company Name: Arabtec Construction LLC. Date:
Sr. Description Yes No N/A Comments
1. Is access to stores are restricted to authorized personnel only?
2. Are there clear spaces around racks and stacks of stored materials and are adequate gangways provided between them?
3. Are stacks and storage kept clear of light fittings and hot surfaces?
4. Are all stocks of flammable liquids kept in purpose-built flammable storage liquid stores?
5. Are storage areas generally cleaned and tidy?
6. Are flammable liquids kept away from all possible sources of ignition?
7. Emergency exit signs are available in right locations
8. Smoke detectors/fire alarm are visible and accessible.
9. Fire extinguishers are available are serviced regularly
10. Are free standing shelves and cupboards secured for stability?
11. Are heavy items stored at a suitable height?
12. Are chemical containers used for storage suitable and clearly labelled?
13. Is there adequate light in the storage area?
14. Are all small loose items secured in appropriate storage?
15. Are warning notices, prohibiting smoking and naked lights prominently displayed?
16. Others if any:
Remarks:
Inspected by: Signature:
Reviewed by Project Manager/HSE Manager Signature:
Project Information:
Project Name:
Location: Supervisor :
Company name : Date:
Task Description:
Before work starts, the following must be in place
Induction Supervision Test Certificates Communication in same language Method Statement Risk Assessment Permit To Work Area Lighting
SELECT HAZARDS SELECT CONTROLS
( Tick to identify the controls in place)
Fall from height Training Access Ladder Access Handrail Edge Protection Secure Ladder Adequate Work Platform Guards for Openings Safety Harness Life Lines
Others( Specify)
Manual Handling Training Check Weight Mechanical Aids Access Route Team Lifting Wrong method Right Method
Power tools Training Color code inspection tag Check Cable Wheel guards Safe plug & sockets Cable Protection Proper Scaffold Cable Overhead Rotatory part guards
Scaffold Scaffold Tag Edge Protection Check Overhead works Access Ladder Adequate Work Platform Weather condition Out riggers Ladder 3 feet above platform Safety Harness
SELECT HAZARDS SELECT CONTROLS
( Tick to identify the controls in place)
Risk Assessment
Lifting Plan Tag Lines Lifting points / hooks Banks man Load stability Check Lifting gear Examination /Inspection Sharp edges protected
Lifting operations Weather/ Wind Speed Ground conditions Exclusion zone Communication Loading/ unloading vehicles Spreader Beams Check Ground conditions Check outriggers Others
Fire Fire Extinguisher Fire Hose Fire Exit Assembly point others
Slip/Trip Clean before you go Barricade the waste Waste Management Clean Access Housekeeping Clean liquid spillage Access signs Maintain access/ Egress
PPE
Safety Harness
Safety Helmet Coveralls Hi vis Jacket Safety Shoe Face Shield Ear Protection
Dust mask Respiratory Equipment Life line/ harness anchorage Hand Gloves Goggles/ Glass
Pre start Briefing done by: Signature:
Reviewed By HSE Manager/ In charge: Signature:
1. Project Information:
Project Name: Checklist No.:
Sub-Contractor/Company:
Date:
2. Task Details:
Description of Task:
Location / Area :
Number of Workers:
Task Duration:
Time (from): _______Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites:
Checks Yes-No-NA Checks Yes-No-NA
Safety induction done. ☐ ☐ ☐
Safety tool box talk done. ☐ ☐ ☐
Method statement/Risk assessment in place. ☐ ☐ ☐
Training on Risk Assessment/ Method Statement done ☐ ☐ ☐
Job Safety Analysis done. ☐ ☐ ☐
3 Month Safety Look Ahead in place ☐ ☐ ☐
Permit to Work obtained ☐ ☐ ☐
Site Supervisor available ☐ ☐ ☐
PPE Available ☐ ☐ ☐
Working area is well lighted ☐ ☐ ☐
Tools and equipment inspected and tagged ☐ ☐ ☐
Unsafe conditions rectified ☐ ☐ ☐
Pre-Start Checks completed ☐ ☐ ☐
Emergency procedures communicated ☐ ☐ ☐
Unauthorized workers are cleared from the area.
☐ ☐ ☐
Other ( Specify): ☐ ☐ ☐
4. Acknowledgement by Sub-Contractor:
☐ Acknowledge that all above precautions/ controls measures have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
Signature: Date /Time
Project Information
Project Name: Store No.
Location: Contact Person:
Company Name: Arabtec Construction LLC. Date:
Sr. Description Yes No N/A Comments
1. Is access to stores are restricted to authorized personnel only?
2. Are there clear spaces around racks and stacks of stored materials and are adequate gangways provided between them?
3. Are stacks and storage kept clear of light fittings and hot surfaces?
4. Are all stocks of flammable liquids kept in purpose-built flammable storage liquid stores?
5. Are storage areas generally cleaned and tidy?
6. Are flammable liquids kept away from all possible sources of ignition?
7. Emergency exit signs are available in right locations
8. Smoke detectors/fire alarm are visible and accessible.
9. Fire extinguishers are available are serviced regularly
10. Are free standing shelves and cupboards secured for stability?
11. Are heavy items stored at a suitable height?
12. Are chemical containers used for storage suitable and clearly labelled?
13. Is there adequate light in the storage area?
14. Are all small loose items secured in appropriate storage?
15. Are warning notices, prohibiting smoking and naked lights prominently displayed?
16. Others if any:
Remarks:
Inspected by: Signature:
Reviewed by Project Manager/HSE Manager Signature:
PROJECT:
LOCATION: DATE:
I (name)_____________________________________would like provide my statement as follows on.
I hereby acknowledge that the above statement are true to the best of my recollection, and that these are my very own written down by m myself s others _________Name and Signature________
Name : ____________________________ Signature: ______________________
Position: _________________________________________Date:_________________
1. Project Information:
Project Name: Click here to enter text.
Report No.: Click here to enter text.
Project Location: Click here to enter text.
Property No.: Click here to enter text.
☐ Fatality ☐ Major Injury ☐ Minor Injury ☐ Property Damage ☐ Environmental ☐ Other
2. Describe the Incident in detail:
Answer who, what, why, where, when & how in this section: (Attach additional pages if required)
3. Incident Root Causes:
Describe direct, indirect & root cause: (Attach additional pages if required)
4. Key Corrections Taken Immediately after the Incident:
Attach additional pages if more space is required:
5. Key Corrective Actions to Prevent Recurrence:
Describe the corrective actions with timeframe: (Attach additional pages if required)
Corporate Office Remarks:
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
3. Control Measures: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Method statement & Risk assessment developed, approved & communicated? ☐ ☐ ☐
Availability of rescue procedure and equipment? ☐ ☐ ☐
Operatives are trained and competent? ☐ ☐ ☐
Workplace appropriately illuminated ☐ ☐ ☐
Any high risk activity associated that requires PTW (i.e. hot work, CSE)? ☐ ☐ ☐
Forced ventilation provided? ☐ ☐ ☐
Are all necessary Permit approved and displayed at work location? ☐ ☐ ☐
Means of communication available? (Mobile, radio etc.) ☐ ☐ ☐
Safe access / Working Platform provided? ☐ ☐ ☐
Mandatory/specific good condition PPEs are available ☐ ☐ ☐
Availability of barricades/protection to prevent unauthorized or accidental entry? ☐ ☐ ☐
Life Line provided? ☐ ☐ ☐
Warning signs posted? ☐ ☐ ☐
Fall Protection equipment (e.g. full body harness) available? ☐ ☐ ☐
Availability of Fall protection arrangement? ☐ ☐ ☐
Other(s): ☐ ☐ ☐
Adequate Lighting provided? ☐ ☐ ☐
☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Location / Area :
Panel No : Voltage:
Permit Validity:
Time (from): _______Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
No: Checks Yes-No-NA Checks Yes-No-NA
ENERGIZATION (“Power On”) ISOLATION (“Power Off”)
1. Safety tool box briefing done. ☐ ☐ ☐
Method statement/Risk assessment in place. ☐ ☐ ☐
2. Authorized personnel / operators available. ☐ ☐ ☐
Authorized personnel / operators available. ☐ ☐ ☐
3. Method statement/Risk assessment in place. ☐ ☐ ☐
Adjacent live areas protected. ☐ ☐ ☐
4. Safety Barriers in place and safety signage Displayed. ☐ ☐ ☐
PPE available, high voltage rubber gloves, Safety goggles and floor mat. ☐ ☐ ☐
5. Working area is well lighted. ☐ ☐ ☐
Isolation/Lock-out in place. ☐ ☐ ☐
6. Electrical instruments are available for any Purpose. ☐ ☐ ☐
Electrical circuits “proved” by calibrated Instrument and found out to be no power. ☐ ☐ ☐
7. Correct PPE available, high voltage rubber Gloves, safety goggles and floor mat. ☐ ☐ ☐
Unauthorized workers are cleared from the Area. ☐ ☐ ☐
8. Approved WIR for installation, testing and Termination are attached to the permit. ☐ ☐ ☐
Standby operatives in the event of contact With live circuits. ☐ ☐ ☐
9. Emergency light (Flashlight) available. ☐ ☐ ☐
Emergency light (Flashlight) available. ☐ ☐ ☐
10. Is live work absolutely necessary? ☐ ☐ ☐
Emergency response plan available ☐ ☐ ☐
11. Unauthorized workers are cleared from the area.
☐ ☐ ☐
Other ( Specify): ☒ ☐ ☐
12. Power cable route from panel board to plant & equipment has been checked ☐ ☐ ☐
13 Emergency response plan available ☐ ☐ ☐
14 Other ( Specify): ☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
Project Information
Project Name:
Date: Location:
Sr. Equipment type / Name Registration No & Exp Date Company Name
Operator Name / Mb. No Operator Third party competency certificate expiry date Operator License expiry date Equipment & Plant 3rd Party Inspection Certificate expiry date SWL / Capacity Signalman /Rigger name & TPC Exp Comment
1
2
3
4
5
6
7
8
9
10.
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge: Signature:
Accommodation Name: Date :
Accommodation Location: Time :
SN Description Yes NO N/A Observation Control
Measures Due Date
ACCESS AND EGRESS
1 Is there segregation between vehicles/ pedestrians
2 Is entry to inside camp restricted to workforce only? How is this controlled
3 Is the entrance well lit
4 Is the entrance free from water pooling
GENERAL HOUSEKEEPING
1 Are there adequate dustbins available? Are they covered
2 Is garbage disposed of on a regular basis?
3 Are toilets wash areas cleaned regular?
4 Is there adequate water for toilet and bath
5 Are water tanks kept covered at all times
6 Is soap and hand towels available?
7 Is bathroom area cleaned on a regular basis and kept dry and non-slippery
8 Is the water tank cleaned on a regular basis
9 Is the laundry area electrical & connections/ wires are in good condition.
10 Is the laundry area kept clean and dry
11 Is the tumble dryer filters cleaned frequently to prevent overheating
SEPTIC TANKS
1 Is the camp on main drainage?
2 If not are septic tanks provided?
3 Are septic tanks fitted with overflow alarm if not how are they prevented from overflowing
4 If septic tank in ground is it in a membrane?
5 If above ground is it protected from being hit by vehicular traffic?
FOOD PREPARATION AREA
1 Is the area kept clean and tidy
2 Are food preparation areas cleaned and free from cracks
3 Are signs for "No smoking" being posted
4 Food waste storage area is cleaned, odour free. Flies area controlled
5 Floor drains are provided in sink area
6 All refrigerators and freezers are working at correct temperatures Refrigerators 1c0 to 4c0
Freezers -14c0 to -18c0
7 Are there temp gauges fitted?
8 Are these temperatures recorded?
9 The Dining and Kitchen areas have an overall clean, tidy and well maintained appearance
10 LPG cylinders are of good conditions (free of damages)
11 Is storage of LPG satisfactory under shed & outside kitchens with no flammable materials nearby
12 Are Piping not perished
13 Are firefighting equipment provided in kitchen area?
LIVING QUARTERS
1 Are Ventilation working well
2 Is lighting suitable
3 Are Emergency numbers being posted in each room
4 Are emergency procedures posted in each room
5 Are Electrical sockets in good condition not damaged & no bare wires are placed in sockets
6 Are sockets overloaded
7 ELCB is provided checks carried out and recorded by
INCIDENT INVESTIGATION REPORT
(To be submitted to the HSEQ Corporate Office within 7 days of incident.)
1. Project Information:
Project Name: Click here to enter text.
Report No.: Click here to enter text.
Project Location: Click here to enter text.
Property No.: Click here to enter text.
☐ Fatality ☐ Major Incident ☐ Minor Incident
2. Describe the Incident in detail:
Answer who, what, why, where, when & how in this section: (Attach additional pages if required)
Click here to enter text.
☐ Photos Attached
3. Incident Root Causes:
Describe direct, indirect & root cause: (Attach additional pages if required)
Click here to enter text.
4. Key Corrective Actions to Prevent Recurrence:
Describe the corrective actions with timeframe: (Attach additional pages if required)
Click here to enter text.
5. Key Corrections Taken Immediately after the Incident:
Attach additional pages if more space is required:
Click here to enter text.
6. Witnesses:
I declare that I witnessed the incident and the information provided above is true, correct and complete.
No. Name Designation Signature Date
1. Click here to enter text.
Click here to enter text.
Click here to enter text.
2. Click here to enter text.
Click here to enter text.
Click here to enter text.
7. Incident Information:
Initial Incident Report No.: Click here to enter text.
Date Reported: Click here to enter text.
Date of Incident: Click here to enter text.
Time of Incident: Click here to enter text.
Type of Incident: ☐ Near Miss
☐ Major Environmental Incident
☐ Serious Dangerous Occurrence
☐ Equipment / Property Damage
☐ Medical Treatment Case (MTC)
☐ Restricted Work Case (RWC)
☐ Lost Workday Case (LWC)
☐ Serious Occupational Illness/Disease
☐ Class 1 Injuries
☐ Permanent Partial Disability (PPD)
☐ Permanent Total Disability (PTD)
☐ Fatality (F)
Recordkeeping: ☐ Reportable ☐ Recordable
Incident Location on Site: Click here to enter text.
Applicable Reports: ☐ Police
☐ Medical
☐ Other (Specify)
Click here to enter text.
Attached: ☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
8. Injured Person’s Personal Details:
In case of an incident with more than one injured person, complete the information for each person using separate forms.
Name: Click here to enter text.
Occupation: Click here to enter text.
Company: Click here to enter text.
MB / Oracle No.: Click here to enter text.
Nationality: Click here to enter text.
Date of Birth: Click here to enter text.
Passport Number: Click here to enter text.
Length of Service: Click here to enter text.
Gender: ☐ Male ☐ Female
Labour Card No.: Click here to enter text.
9. Incident Causes Details: To be supported with factual evidence
Immediate Cause
(Unsafe Acts) ☐ Failure to secure
☐ Failure to warn
☐ Removing / Defeating Safety Devices
☐
HSE INDUCTION
(Workers)
Name: _________________________________ Trade: ____________________________
M.B. No./Company Name : ________________
Date of Joining: __________________________
SL. N SUBJECT ON INDUCTION PREVIOUS SAFETY EXPOSURE FURTHER SAFETY TRAINING NEED ANALYSIS
1. Introduction Safety Requirements
2. Working Safety is of Primary Importance
3. General Safety Rules
4. Basic Safety Requirements
5. House Keeping
6. Health, Hygiene & Welfare Facilities
7. Fire Extinguisher / Fire Fighting
8. Emergency Procedure
9. Safety Violations & Penalty
10. Safety Award
11. Manual Handling
Induction Given By: Name: ___________________________
Designation: ___________________________
1st Warning 0 Ref. No. ______________
2nd Warning 0
3rd Warning 0
4th Warning 0 Date: ________________
Employee’s Name : ______________________________________ M.B No. : __________
Occupation : _____________________________________________________________________
Location / Project Site: _____________________________________________________________________
You have committed the following HSE violation/s:
………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………….….
The employee is hereby warned that if the violation is repeated further disciplinary action can be
taken as per the company Code of Conduct.
ORIGINATOR APPROVED BY (MANAGER IN CHARGE / ARABTEC HSEQ & ORG. RISK Manager)
Name: _______________________________ Name: _____________________________
Designation: _______________________________ Designation: _____________________________
Signature:
_______________________________ Signature:
_____________________________
Employee Acknowledgement:
I the undersigned have received this Safety warning letter / disciplinary notice and I admit that I have understood the contents.
0 Received on: ………………………….. (Date) Signature: ………………………………..…..
Project Information
Project Name: Porta Cabin No:
Location: Contact Person:
Company Name: Date :
Sr. Description Yes No N/A Comments
1. Emergency exit signs are available in right locations
2. Fire alarms and fire extinguishers are visible and accessible.
3. Fire doors (e.g. in stairways) are kept closed unless equipped with automatic closing device
4. Fire extinguishers are serviced regularly
5. Corridors and stairways are kept free of obstruction
6. Fire escape/ evacuation plan available and posted
7. First aid box available
8. Floor surfaces are kept dry and free of slip hazards
9. Electrical cords and plugs are in good condition with proper Grounding
10. Kitchen equipment checked
11. Fire blanket available in the pantry
12. Heat detector available in the pantry
13. Toilets floor clean and dry
14. Are staff trained to use Fire Extinguishers
15. Hand wash/ soap solution available in the toilet
16. Civil Defense or Authority approval
17. Others if any:
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
MEDICAL REPORT FORM
Day _____________
Date ____________
Time ____________
To: _________________________________________________________________________________________________________
Dear Sir,
We would kindly request you to give necessary treatment to our following employee who had met with an accident and provide us with your diagnosis.
Name of injured __________________________________________________________ Age ( ) years.
Occupation __________________________________________________________ M.B. No. _______________________________
Date of Accident ____________________________________________ Time of Accident __________________________________
Place of Accident (Project Name) _______________________________ Location _________________________________________
Nature of Accident ____________________________________________________________________________________________
____________________________________________________________________________________________________________
____________________________________________________________________________________________________________
____________________________________________________________________________________________________________
First Aider Name: ________________________________ SE Manager/Incharge: ________________________________
Signature: ________________________________ Signature: ________________________________
(If Medical Certificate is attached, this portion is not required.)
MEDICAL REPORT
Nature and extent of Accident / Injury____________________________________________________________________________
____________________________________________________________________________________________________________
____________________________________________________________________________________________________________
____________________________________________________________________________________________________________
Fit for duty___________________________________________________________________________________________________
Unfit for duty_________________________________________________________________________________________________
Remarks_____________________________________________________________________________________________________
____________________________________________________________________________________________________________
Signature of Medical Officer Date _______________
Project Information
Project Name:
Company Name: Date :
ID NO TYPE OF LIFTING GEARS LOCATION VISUAL INSPECTION THIRD PARTY INSPECTION VALID TILL MONTHLY COLOUR CODE
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
FULL BODY HARNESS INSPECTION RECORD Form # HSEQ - FBHIR Rev 2.docxDwarika Bhushan Sharma
Harness Checklist
Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Remarks
Shoulder Straps
Chest & Back Straps
Waist Straps
Back D-Ring
Shoulder Adjustment
Legible Label
Shoulder Straps
Chest & Back Straps
Waist Straps
Leg Straps
Cuts
Burns
Holes
Deterioration
Corrosive/ worn out
Color code
Others (Specify)
Project Information
Project Name: Location:
Company name : Date:
Remarks:
Inspector Name: Signature:
Reviewed By HSE Manager / Incharge Signature:
Project Information
Project Name:
Location:
Company Name: Date :
Sl. No Description Yes No N/A Comments
1. Properly stored, labeled, ventilated, isolated, Log and suitable signs displayed.
2. Material Data Safety Sheet (MSDS) available, and communicated to concerned personnel.
3. Adequate/ Sufficient firefighting equipment are in place.
4. Emergency escape and breathing apparatus available, tested and in good condition.
5. Hazardous substances containers/drums have eligible labeling and protected from leakages or spillage.
6. Personnel must be trained in chemical handling.
7. Emergency control plan must be made available, spillage control kits must be available.
8. Empty hazardous substances containers, drums and receptacles should be properly maintained and controlled.
9. Expired chemicals are logged, segregated and disposed properly
10. Others Specify
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
Project Information
Project Name: Concrete Pump Reg. No:
Location: Operators Name:
Company Name: Date :
Sr. Description Yes No N/A Comments
1. Concrete Pump 3rd Party Certificate & Registration
2. Sonographic test of all pipes
3. Calibration of all the pressure gauges
4. Operator’s Competency Certificate & Driver’s License
5. Safe distance from the edge of the excavation
6. Outrigger pads are free from damage
7. Outriggers are level
8. Reverse alarm and beacon light are operational
9. Whip arrester on the pipes and pump
10. Safe access for concrete mixer to the area (In/Out)
11. Area properly barricaded and signage posted
12. Hydraulic Oil / Diesel Leakage
13. Extension Pipeline - Free from damage
14. Extension Pipeline -Locking pin in every connection
15. Extension Pipeline - Adequately supported & secured
16. Spillage control measure in place
17. Other accessories e.g. spider pacing boom 3rd party certificate
18. Static pumps positioned properly
19. Static pumps – concrete pipes fixed on structure as per design
20. Concrete pipes coupler pins provided
21. Concrete pipes on floor – away from scaffolds/ formworks
22. Competent banks man and supervision provided
23. Others (Specify)
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
Noted by Project Leader Signature:
Project Behavioral Observation Form
Process Observed
Works Package
Subcontractor / CName
Date _ _ /_ _ /_ _ Time from ______ to ______ Duration Mins _____
Checklist attached ☐
Video ☐
Photo (s) ☐
Observation Summary (Ref checklist for details)
Safe ☐
Unsafe Acts ☐
Safe ☐
Unsafe conditions ☐
Status:
A. All activities conducted in a safe manner ☐
No negative observations
B. Generally conducted in a safe manner ☐
Some aspects of the process require improvement
C. Partially conducted in a safe manner ☐
One aspect of a task needs improvement
D. Some individual lapses ☐
One person working unsafely part of the time
E. Generally conducted in unsafe manner ☐
More than one person working unsafely
ATC Engineer-in-charge Supervisor
Follow up Action
☐
Analysed by HSE Manager and responsible person _________________
☐
Reported / shown to team observed
☐
Recommended Action
☐
Follow up recommendation
SR. TITLE YES NO N/A Comments
1 FIRE PROTECTION EQUIPMENT
1.1 Are adequate fire-fighting equipment and sufficient extinguishing agents available and operative at all times?
1.2 Have workers been oriented on their correct use and operation?
1.3 Are portable fire extinguishers of sufficient capacity (at least 20 lbs.) and type available and strategically positioned near hazardous work such that the travel distance to the nearest unit is no greater than 15 meters?
1.4 Are regular checks undertaken to make sure that the equipment is not missing or damaged?
1.5 Is a fully operational yard hydrant/Fire Hose reel system available prior to start of construction (excluding foundation work) and during the entire construction period?
Where street hydrants are not available, are temporary hydrants provided?
1.6 Is a waterline extended as soon as possible behind construction to supplement the Fire Extinguishers placed throughout the construction area?
1.7 Are permanent standpipes extended as close as possible behind construction to allow use in case of fire?
1.8 Are fully operative standpipes (wet risers) installed up to one level below the highest current work level and are sealed by temporary end caps?
1.9 (The following is a less stringent alternative to Item 8 above)
Where construction involves buildings more than 23 meters high, are fully operative standpipes (wet risers) available not less than
3 levels below the highest level under construction.
Where the provision of wet risers does not impede structural work, are they provided to the level below the highest level under construction?
1.10 Are the cabinets containing hose reels and portable fire extinguishers inspected at regular intervals but at least twice a week by competent persons?
1.11 Are hydrants and standpipes including fire water supply system designed and installed in compliance with UAE Fire and Life safety COP and according to the relevant internationally recognized codes and standards, e.g., NFPA, FM, etc.?
1.12 Is the fire water supply at the site available at the required volume and pressure?
1.13 Is storage of any material within 3 meters of fire hydrants/Fire Hose reels strictly prohibited? Is access to the outlets unobstructed?
2 COMPARTEMENTATION / SEGMENTATION YES NO N/A COMMENTS
2.1 Are fire compartments as required by local regulations installed as soon as possible after the removal of formwork?
2.2 Are openings for lift shafts, service ducts and other voids provisionally closed as soon as possible but not later than at the commencement of fit-out work?
3 FIRE PREVENTION : HOT WORK MANAGEMENT YES NO N/A COMMENTS
3.1 Is a “permit to work” system being implemented for all parties engaged in “hot work” of any kind such as but not limited to
– grinding, cutting or welding operations,
– use of blow lamps and torches,
– application of hot bitumen
or any other heat-pro
Issue Date: _______________ Permit No: ____________
Permit Requested By: __________________ Company Name: ________________ Permit Accepted By: __________________ Company Name: ________________
Validity From: __________ To: __________
1. Job Location: _____________________________________________________________
2. Job Description: __________________________________________________________
________________________________________________________________________________________________________________________________________________
3 Tools & Materials to be used:
❑Explosive Device ❑Sandblaster ❑Jack hammers
❑Hand Tools ❑Drill ❑Jack hammers
❑Powered Excavation Equipment ❑Powered cutting Saw ❑Ladder/Scaffolding
❑Air Heater ❑LPG Gas ❑Others
4- Details of potential hazards:
❑Falling from height ❑ Material Fall down ❑Skin Exposures
❑Electrocuted ❑ Slip and trip ❑Burn out due to fire/acid etc.
❑Exposure to Eye ❑ Inhalation of any Gas ❑Breathing Problem ❑Others
5- Details of precaution need to be taken:
❑Caution Signage to be placed ❑Proper fixture an erection of Scaffolding/Ladder
❑Excavated Area fencing ❑Electrical Isolation
❑Fire water supply isolation ❑Fire water tanker to be provided
❑Fire Extinguishers to be provided ❑Exhaust fan to be provided
❑Informed security Et Help Desk ❑Other
6- Details of protective equipment to be used or worn:
❑Safety Shoes
❑Safety Helmet
❑Face Shield/Goggle/Glasses
❑Gloves (As per work)
❑Safety harness/Belt/Lifeline
❑Uniform ❑Respiratory Equipment/Dust Mask
❑Chemical Suite/Apron
❑Ear protection
❑Fire Blanket/Protection Sheet
❑Rubber Mat/Ground Fault Interrupter
❑Other
7- Signature of Permit Requestor:
Contact No:-
8- Signature of PTW Acceptor:
Contact No:-
9- Signature of Permit Issuer/HSE Representative:
10- Signature of handover of responsibility between shifts, if needed.
11- Declaration by competent person in -charge of work that work is completed.
12- Signature of Maintenance / works representative ensuring that the work is
completed, site has been checked and that equipment and place may be reinstated / left
Safely isolated.
13- Signature of person issuing the permit / HSE representative which confirms that the
Site has been left in safe condition and the permit is cancelled.
14- Signature of the management representative signing off the permit to work.
REMARKS:-
Operation “Blue Star” is the only event in the history of Independent India where the state went into war with its own people. Even after about 40 years it is not clear if it was culmination of states anger over people of the region, a political game of power or start of dictatorial chapter in the democratic setup.
The people of Punjab felt alienated from main stream due to denial of their just demands during a long democratic struggle since independence. As it happen all over the word, it led to militant struggle with great loss of lives of military, police and civilian personnel. Killing of Indira Gandhi and massacre of innocent Sikhs in Delhi and other India cities was also associated with this movement.
PROJECT:
LOCATION: DATE:
I (name)_____________________________________would like provide my statement as follows on.
I hereby acknowledge that the above statement are true to the best of my recollection, and that these are my very own written down by m myself s others _________Name and Signature________
Name : ____________________________ Signature: ______________________
Position: _________________________________________Date:_________________
1. Project Information:
Project Name: Click here to enter text.
Report No.: Click here to enter text.
Project Location: Click here to enter text.
Property No.: Click here to enter text.
☐ Fatality ☐ Major Injury ☐ Minor Injury ☐ Property Damage ☐ Environmental ☐ Other
2. Describe the Incident in detail:
Answer who, what, why, where, when & how in this section: (Attach additional pages if required)
3. Incident Root Causes:
Describe direct, indirect & root cause: (Attach additional pages if required)
4. Key Corrections Taken Immediately after the Incident:
Attach additional pages if more space is required:
5. Key Corrective Actions to Prevent Recurrence:
Describe the corrective actions with timeframe: (Attach additional pages if required)
Corporate Office Remarks:
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
3. Control Measures: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Method statement & Risk assessment developed, approved & communicated? ☐ ☐ ☐
Availability of rescue procedure and equipment? ☐ ☐ ☐
Operatives are trained and competent? ☐ ☐ ☐
Workplace appropriately illuminated ☐ ☐ ☐
Any high risk activity associated that requires PTW (i.e. hot work, CSE)? ☐ ☐ ☐
Forced ventilation provided? ☐ ☐ ☐
Are all necessary Permit approved and displayed at work location? ☐ ☐ ☐
Means of communication available? (Mobile, radio etc.) ☐ ☐ ☐
Safe access / Working Platform provided? ☐ ☐ ☐
Mandatory/specific good condition PPEs are available ☐ ☐ ☐
Availability of barricades/protection to prevent unauthorized or accidental entry? ☐ ☐ ☐
Life Line provided? ☐ ☐ ☐
Warning signs posted? ☐ ☐ ☐
Fall Protection equipment (e.g. full body harness) available? ☐ ☐ ☐
Availability of Fall protection arrangement? ☐ ☐ ☐
Other(s): ☐ ☐ ☐
Adequate Lighting provided? ☐ ☐ ☐
☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Location / Area :
Panel No : Voltage:
Permit Validity:
Time (from): _______Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
No: Checks Yes-No-NA Checks Yes-No-NA
ENERGIZATION (“Power On”) ISOLATION (“Power Off”)
1. Safety tool box briefing done. ☐ ☐ ☐
Method statement/Risk assessment in place. ☐ ☐ ☐
2. Authorized personnel / operators available. ☐ ☐ ☐
Authorized personnel / operators available. ☐ ☐ ☐
3. Method statement/Risk assessment in place. ☐ ☐ ☐
Adjacent live areas protected. ☐ ☐ ☐
4. Safety Barriers in place and safety signage Displayed. ☐ ☐ ☐
PPE available, high voltage rubber gloves, Safety goggles and floor mat. ☐ ☐ ☐
5. Working area is well lighted. ☐ ☐ ☐
Isolation/Lock-out in place. ☐ ☐ ☐
6. Electrical instruments are available for any Purpose. ☐ ☐ ☐
Electrical circuits “proved” by calibrated Instrument and found out to be no power. ☐ ☐ ☐
7. Correct PPE available, high voltage rubber Gloves, safety goggles and floor mat. ☐ ☐ ☐
Unauthorized workers are cleared from the Area. ☐ ☐ ☐
8. Approved WIR for installation, testing and Termination are attached to the permit. ☐ ☐ ☐
Standby operatives in the event of contact With live circuits. ☐ ☐ ☐
9. Emergency light (Flashlight) available. ☐ ☐ ☐
Emergency light (Flashlight) available. ☐ ☐ ☐
10. Is live work absolutely necessary? ☐ ☐ ☐
Emergency response plan available ☐ ☐ ☐
11. Unauthorized workers are cleared from the area.
☐ ☐ ☐
Other ( Specify): ☒ ☐ ☐
12. Power cable route from panel board to plant & equipment has been checked ☐ ☐ ☐
13 Emergency response plan available ☐ ☐ ☐
14 Other ( Specify): ☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
Project Information
Project Name:
Date: Location:
Sr. Equipment type / Name Registration No & Exp Date Company Name
Operator Name / Mb. No Operator Third party competency certificate expiry date Operator License expiry date Equipment & Plant 3rd Party Inspection Certificate expiry date SWL / Capacity Signalman /Rigger name & TPC Exp Comment
1
2
3
4
5
6
7
8
9
10.
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge: Signature:
Accommodation Name: Date :
Accommodation Location: Time :
SN Description Yes NO N/A Observation Control
Measures Due Date
ACCESS AND EGRESS
1 Is there segregation between vehicles/ pedestrians
2 Is entry to inside camp restricted to workforce only? How is this controlled
3 Is the entrance well lit
4 Is the entrance free from water pooling
GENERAL HOUSEKEEPING
1 Are there adequate dustbins available? Are they covered
2 Is garbage disposed of on a regular basis?
3 Are toilets wash areas cleaned regular?
4 Is there adequate water for toilet and bath
5 Are water tanks kept covered at all times
6 Is soap and hand towels available?
7 Is bathroom area cleaned on a regular basis and kept dry and non-slippery
8 Is the water tank cleaned on a regular basis
9 Is the laundry area electrical & connections/ wires are in good condition.
10 Is the laundry area kept clean and dry
11 Is the tumble dryer filters cleaned frequently to prevent overheating
SEPTIC TANKS
1 Is the camp on main drainage?
2 If not are septic tanks provided?
3 Are septic tanks fitted with overflow alarm if not how are they prevented from overflowing
4 If septic tank in ground is it in a membrane?
5 If above ground is it protected from being hit by vehicular traffic?
FOOD PREPARATION AREA
1 Is the area kept clean and tidy
2 Are food preparation areas cleaned and free from cracks
3 Are signs for "No smoking" being posted
4 Food waste storage area is cleaned, odour free. Flies area controlled
5 Floor drains are provided in sink area
6 All refrigerators and freezers are working at correct temperatures Refrigerators 1c0 to 4c0
Freezers -14c0 to -18c0
7 Are there temp gauges fitted?
8 Are these temperatures recorded?
9 The Dining and Kitchen areas have an overall clean, tidy and well maintained appearance
10 LPG cylinders are of good conditions (free of damages)
11 Is storage of LPG satisfactory under shed & outside kitchens with no flammable materials nearby
12 Are Piping not perished
13 Are firefighting equipment provided in kitchen area?
LIVING QUARTERS
1 Are Ventilation working well
2 Is lighting suitable
3 Are Emergency numbers being posted in each room
4 Are emergency procedures posted in each room
5 Are Electrical sockets in good condition not damaged & no bare wires are placed in sockets
6 Are sockets overloaded
7 ELCB is provided checks carried out and recorded by
INCIDENT INVESTIGATION REPORT
(To be submitted to the HSEQ Corporate Office within 7 days of incident.)
1. Project Information:
Project Name: Click here to enter text.
Report No.: Click here to enter text.
Project Location: Click here to enter text.
Property No.: Click here to enter text.
☐ Fatality ☐ Major Incident ☐ Minor Incident
2. Describe the Incident in detail:
Answer who, what, why, where, when & how in this section: (Attach additional pages if required)
Click here to enter text.
☐ Photos Attached
3. Incident Root Causes:
Describe direct, indirect & root cause: (Attach additional pages if required)
Click here to enter text.
4. Key Corrective Actions to Prevent Recurrence:
Describe the corrective actions with timeframe: (Attach additional pages if required)
Click here to enter text.
5. Key Corrections Taken Immediately after the Incident:
Attach additional pages if more space is required:
Click here to enter text.
6. Witnesses:
I declare that I witnessed the incident and the information provided above is true, correct and complete.
No. Name Designation Signature Date
1. Click here to enter text.
Click here to enter text.
Click here to enter text.
2. Click here to enter text.
Click here to enter text.
Click here to enter text.
7. Incident Information:
Initial Incident Report No.: Click here to enter text.
Date Reported: Click here to enter text.
Date of Incident: Click here to enter text.
Time of Incident: Click here to enter text.
Type of Incident: ☐ Near Miss
☐ Major Environmental Incident
☐ Serious Dangerous Occurrence
☐ Equipment / Property Damage
☐ Medical Treatment Case (MTC)
☐ Restricted Work Case (RWC)
☐ Lost Workday Case (LWC)
☐ Serious Occupational Illness/Disease
☐ Class 1 Injuries
☐ Permanent Partial Disability (PPD)
☐ Permanent Total Disability (PTD)
☐ Fatality (F)
Recordkeeping: ☐ Reportable ☐ Recordable
Incident Location on Site: Click here to enter text.
Applicable Reports: ☐ Police
☐ Medical
☐ Other (Specify)
Click here to enter text.
Attached: ☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
8. Injured Person’s Personal Details:
In case of an incident with more than one injured person, complete the information for each person using separate forms.
Name: Click here to enter text.
Occupation: Click here to enter text.
Company: Click here to enter text.
MB / Oracle No.: Click here to enter text.
Nationality: Click here to enter text.
Date of Birth: Click here to enter text.
Passport Number: Click here to enter text.
Length of Service: Click here to enter text.
Gender: ☐ Male ☐ Female
Labour Card No.: Click here to enter text.
9. Incident Causes Details: To be supported with factual evidence
Immediate Cause
(Unsafe Acts) ☐ Failure to secure
☐ Failure to warn
☐ Removing / Defeating Safety Devices
☐
HSE INDUCTION
(Workers)
Name: _________________________________ Trade: ____________________________
M.B. No./Company Name : ________________
Date of Joining: __________________________
SL. N SUBJECT ON INDUCTION PREVIOUS SAFETY EXPOSURE FURTHER SAFETY TRAINING NEED ANALYSIS
1. Introduction Safety Requirements
2. Working Safety is of Primary Importance
3. General Safety Rules
4. Basic Safety Requirements
5. House Keeping
6. Health, Hygiene & Welfare Facilities
7. Fire Extinguisher / Fire Fighting
8. Emergency Procedure
9. Safety Violations & Penalty
10. Safety Award
11. Manual Handling
Induction Given By: Name: ___________________________
Designation: ___________________________
1st Warning 0 Ref. No. ______________
2nd Warning 0
3rd Warning 0
4th Warning 0 Date: ________________
Employee’s Name : ______________________________________ M.B No. : __________
Occupation : _____________________________________________________________________
Location / Project Site: _____________________________________________________________________
You have committed the following HSE violation/s:
………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………….….
The employee is hereby warned that if the violation is repeated further disciplinary action can be
taken as per the company Code of Conduct.
ORIGINATOR APPROVED BY (MANAGER IN CHARGE / ARABTEC HSEQ & ORG. RISK Manager)
Name: _______________________________ Name: _____________________________
Designation: _______________________________ Designation: _____________________________
Signature:
_______________________________ Signature:
_____________________________
Employee Acknowledgement:
I the undersigned have received this Safety warning letter / disciplinary notice and I admit that I have understood the contents.
0 Received on: ………………………….. (Date) Signature: ………………………………..…..
Project Information
Project Name: Porta Cabin No:
Location: Contact Person:
Company Name: Date :
Sr. Description Yes No N/A Comments
1. Emergency exit signs are available in right locations
2. Fire alarms and fire extinguishers are visible and accessible.
3. Fire doors (e.g. in stairways) are kept closed unless equipped with automatic closing device
4. Fire extinguishers are serviced regularly
5. Corridors and stairways are kept free of obstruction
6. Fire escape/ evacuation plan available and posted
7. First aid box available
8. Floor surfaces are kept dry and free of slip hazards
9. Electrical cords and plugs are in good condition with proper Grounding
10. Kitchen equipment checked
11. Fire blanket available in the pantry
12. Heat detector available in the pantry
13. Toilets floor clean and dry
14. Are staff trained to use Fire Extinguishers
15. Hand wash/ soap solution available in the toilet
16. Civil Defense or Authority approval
17. Others if any:
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
MEDICAL REPORT FORM
Day _____________
Date ____________
Time ____________
To: _________________________________________________________________________________________________________
Dear Sir,
We would kindly request you to give necessary treatment to our following employee who had met with an accident and provide us with your diagnosis.
Name of injured __________________________________________________________ Age ( ) years.
Occupation __________________________________________________________ M.B. No. _______________________________
Date of Accident ____________________________________________ Time of Accident __________________________________
Place of Accident (Project Name) _______________________________ Location _________________________________________
Nature of Accident ____________________________________________________________________________________________
____________________________________________________________________________________________________________
____________________________________________________________________________________________________________
____________________________________________________________________________________________________________
First Aider Name: ________________________________ SE Manager/Incharge: ________________________________
Signature: ________________________________ Signature: ________________________________
(If Medical Certificate is attached, this portion is not required.)
MEDICAL REPORT
Nature and extent of Accident / Injury____________________________________________________________________________
____________________________________________________________________________________________________________
____________________________________________________________________________________________________________
____________________________________________________________________________________________________________
Fit for duty___________________________________________________________________________________________________
Unfit for duty_________________________________________________________________________________________________
Remarks_____________________________________________________________________________________________________
____________________________________________________________________________________________________________
Signature of Medical Officer Date _______________
Project Information
Project Name:
Company Name: Date :
ID NO TYPE OF LIFTING GEARS LOCATION VISUAL INSPECTION THIRD PARTY INSPECTION VALID TILL MONTHLY COLOUR CODE
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
☐ OK ☐ Not OK
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
FULL BODY HARNESS INSPECTION RECORD Form # HSEQ - FBHIR Rev 2.docxDwarika Bhushan Sharma
Harness Checklist
Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Sl. No
………. Remarks
Shoulder Straps
Chest & Back Straps
Waist Straps
Back D-Ring
Shoulder Adjustment
Legible Label
Shoulder Straps
Chest & Back Straps
Waist Straps
Leg Straps
Cuts
Burns
Holes
Deterioration
Corrosive/ worn out
Color code
Others (Specify)
Project Information
Project Name: Location:
Company name : Date:
Remarks:
Inspector Name: Signature:
Reviewed By HSE Manager / Incharge Signature:
Project Information
Project Name:
Location:
Company Name: Date :
Sl. No Description Yes No N/A Comments
1. Properly stored, labeled, ventilated, isolated, Log and suitable signs displayed.
2. Material Data Safety Sheet (MSDS) available, and communicated to concerned personnel.
3. Adequate/ Sufficient firefighting equipment are in place.
4. Emergency escape and breathing apparatus available, tested and in good condition.
5. Hazardous substances containers/drums have eligible labeling and protected from leakages or spillage.
6. Personnel must be trained in chemical handling.
7. Emergency control plan must be made available, spillage control kits must be available.
8. Empty hazardous substances containers, drums and receptacles should be properly maintained and controlled.
9. Expired chemicals are logged, segregated and disposed properly
10. Others Specify
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
Project Information
Project Name: Concrete Pump Reg. No:
Location: Operators Name:
Company Name: Date :
Sr. Description Yes No N/A Comments
1. Concrete Pump 3rd Party Certificate & Registration
2. Sonographic test of all pipes
3. Calibration of all the pressure gauges
4. Operator’s Competency Certificate & Driver’s License
5. Safe distance from the edge of the excavation
6. Outrigger pads are free from damage
7. Outriggers are level
8. Reverse alarm and beacon light are operational
9. Whip arrester on the pipes and pump
10. Safe access for concrete mixer to the area (In/Out)
11. Area properly barricaded and signage posted
12. Hydraulic Oil / Diesel Leakage
13. Extension Pipeline - Free from damage
14. Extension Pipeline -Locking pin in every connection
15. Extension Pipeline - Adequately supported & secured
16. Spillage control measure in place
17. Other accessories e.g. spider pacing boom 3rd party certificate
18. Static pumps positioned properly
19. Static pumps – concrete pipes fixed on structure as per design
20. Concrete pipes coupler pins provided
21. Concrete pipes on floor – away from scaffolds/ formworks
22. Competent banks man and supervision provided
23. Others (Specify)
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
Noted by Project Leader Signature:
Project Behavioral Observation Form
Process Observed
Works Package
Subcontractor / CName
Date _ _ /_ _ /_ _ Time from ______ to ______ Duration Mins _____
Checklist attached ☐
Video ☐
Photo (s) ☐
Observation Summary (Ref checklist for details)
Safe ☐
Unsafe Acts ☐
Safe ☐
Unsafe conditions ☐
Status:
A. All activities conducted in a safe manner ☐
No negative observations
B. Generally conducted in a safe manner ☐
Some aspects of the process require improvement
C. Partially conducted in a safe manner ☐
One aspect of a task needs improvement
D. Some individual lapses ☐
One person working unsafely part of the time
E. Generally conducted in unsafe manner ☐
More than one person working unsafely
ATC Engineer-in-charge Supervisor
Follow up Action
☐
Analysed by HSE Manager and responsible person _________________
☐
Reported / shown to team observed
☐
Recommended Action
☐
Follow up recommendation
SR. TITLE YES NO N/A Comments
1 FIRE PROTECTION EQUIPMENT
1.1 Are adequate fire-fighting equipment and sufficient extinguishing agents available and operative at all times?
1.2 Have workers been oriented on their correct use and operation?
1.3 Are portable fire extinguishers of sufficient capacity (at least 20 lbs.) and type available and strategically positioned near hazardous work such that the travel distance to the nearest unit is no greater than 15 meters?
1.4 Are regular checks undertaken to make sure that the equipment is not missing or damaged?
1.5 Is a fully operational yard hydrant/Fire Hose reel system available prior to start of construction (excluding foundation work) and during the entire construction period?
Where street hydrants are not available, are temporary hydrants provided?
1.6 Is a waterline extended as soon as possible behind construction to supplement the Fire Extinguishers placed throughout the construction area?
1.7 Are permanent standpipes extended as close as possible behind construction to allow use in case of fire?
1.8 Are fully operative standpipes (wet risers) installed up to one level below the highest current work level and are sealed by temporary end caps?
1.9 (The following is a less stringent alternative to Item 8 above)
Where construction involves buildings more than 23 meters high, are fully operative standpipes (wet risers) available not less than
3 levels below the highest level under construction.
Where the provision of wet risers does not impede structural work, are they provided to the level below the highest level under construction?
1.10 Are the cabinets containing hose reels and portable fire extinguishers inspected at regular intervals but at least twice a week by competent persons?
1.11 Are hydrants and standpipes including fire water supply system designed and installed in compliance with UAE Fire and Life safety COP and according to the relevant internationally recognized codes and standards, e.g., NFPA, FM, etc.?
1.12 Is the fire water supply at the site available at the required volume and pressure?
1.13 Is storage of any material within 3 meters of fire hydrants/Fire Hose reels strictly prohibited? Is access to the outlets unobstructed?
2 COMPARTEMENTATION / SEGMENTATION YES NO N/A COMMENTS
2.1 Are fire compartments as required by local regulations installed as soon as possible after the removal of formwork?
2.2 Are openings for lift shafts, service ducts and other voids provisionally closed as soon as possible but not later than at the commencement of fit-out work?
3 FIRE PREVENTION : HOT WORK MANAGEMENT YES NO N/A COMMENTS
3.1 Is a “permit to work” system being implemented for all parties engaged in “hot work” of any kind such as but not limited to
– grinding, cutting or welding operations,
– use of blow lamps and torches,
– application of hot bitumen
or any other heat-pro
Issue Date: _______________ Permit No: ____________
Permit Requested By: __________________ Company Name: ________________ Permit Accepted By: __________________ Company Name: ________________
Validity From: __________ To: __________
1. Job Location: _____________________________________________________________
2. Job Description: __________________________________________________________
________________________________________________________________________________________________________________________________________________
3 Tools & Materials to be used:
❑Explosive Device ❑Sandblaster ❑Jack hammers
❑Hand Tools ❑Drill ❑Jack hammers
❑Powered Excavation Equipment ❑Powered cutting Saw ❑Ladder/Scaffolding
❑Air Heater ❑LPG Gas ❑Others
4- Details of potential hazards:
❑Falling from height ❑ Material Fall down ❑Skin Exposures
❑Electrocuted ❑ Slip and trip ❑Burn out due to fire/acid etc.
❑Exposure to Eye ❑ Inhalation of any Gas ❑Breathing Problem ❑Others
5- Details of precaution need to be taken:
❑Caution Signage to be placed ❑Proper fixture an erection of Scaffolding/Ladder
❑Excavated Area fencing ❑Electrical Isolation
❑Fire water supply isolation ❑Fire water tanker to be provided
❑Fire Extinguishers to be provided ❑Exhaust fan to be provided
❑Informed security Et Help Desk ❑Other
6- Details of protective equipment to be used or worn:
❑Safety Shoes
❑Safety Helmet
❑Face Shield/Goggle/Glasses
❑Gloves (As per work)
❑Safety harness/Belt/Lifeline
❑Uniform ❑Respiratory Equipment/Dust Mask
❑Chemical Suite/Apron
❑Ear protection
❑Fire Blanket/Protection Sheet
❑Rubber Mat/Ground Fault Interrupter
❑Other
7- Signature of Permit Requestor:
Contact No:-
8- Signature of PTW Acceptor:
Contact No:-
9- Signature of Permit Issuer/HSE Representative:
10- Signature of handover of responsibility between shifts, if needed.
11- Declaration by competent person in -charge of work that work is completed.
12- Signature of Maintenance / works representative ensuring that the work is
completed, site has been checked and that equipment and place may be reinstated / left
Safely isolated.
13- Signature of person issuing the permit / HSE representative which confirms that the
Site has been left in safe condition and the permit is cancelled.
14- Signature of the management representative signing off the permit to work.
REMARKS:-
Operation “Blue Star” is the only event in the history of Independent India where the state went into war with its own people. Even after about 40 years it is not clear if it was culmination of states anger over people of the region, a political game of power or start of dictatorial chapter in the democratic setup.
The people of Punjab felt alienated from main stream due to denial of their just demands during a long democratic struggle since independence. As it happen all over the word, it led to militant struggle with great loss of lives of military, police and civilian personnel. Killing of Indira Gandhi and massacre of innocent Sikhs in Delhi and other India cities was also associated with this movement.
Model Attribute Check Company Auto PropertyCeline George
In Odoo, the multi-company feature allows you to manage multiple companies within a single Odoo database instance. Each company can have its own configurations while still sharing common resources such as products, customers, and suppliers.
A Strategic Approach: GenAI in EducationPeter Windle
Artificial Intelligence (AI) technologies such as Generative AI, Image Generators and Large Language Models have had a dramatic impact on teaching, learning and assessment over the past 18 months. The most immediate threat AI posed was to Academic Integrity with Higher Education Institutes (HEIs) focusing their efforts on combating the use of GenAI in assessment. Guidelines were developed for staff and students, policies put in place too. Innovative educators have forged paths in the use of Generative AI for teaching, learning and assessments leading to pockets of transformation springing up across HEIs, often with little or no top-down guidance, support or direction.
This Gasta posits a strategic approach to integrating AI into HEIs to prepare staff, students and the curriculum for an evolving world and workplace. We will highlight the advantages of working with these technologies beyond the realm of teaching, learning and assessment by considering prompt engineering skills, industry impact, curriculum changes, and the need for staff upskilling. In contrast, not engaging strategically with Generative AI poses risks, including falling behind peers, missed opportunities and failing to ensure our graduates remain employable. The rapid evolution of AI technologies necessitates a proactive and strategic approach if we are to remain relevant.
Instructions for Submissions thorugh G- Classroom.pptxJheel Barad
This presentation provides a briefing on how to upload submissions and documents in Google Classroom. It was prepared as part of an orientation for new Sainik School in-service teacher trainees. As a training officer, my goal is to ensure that you are comfortable and proficient with this essential tool for managing assignments and fostering student engagement.
Unit 8 - Information and Communication Technology (Paper I).pdfThiyagu K
This slides describes the basic concepts of ICT, basics of Email, Emerging Technology and Digital Initiatives in Education. This presentations aligns with the UGC Paper I syllabus.
Introduction to AI for Nonprofits with Tapp NetworkTechSoup
Dive into the world of AI! Experts Jon Hill and Tareq Monaur will guide you through AI's role in enhancing nonprofit websites and basic marketing strategies, making it easy to understand and apply.
Palestine last event orientationfvgnh .pptxRaedMohamed3
An EFL lesson about the current events in Palestine. It is intended to be for intermediate students who wish to increase their listening skills through a short lesson in power point.
How to Make a Field invisible in Odoo 17Celine George
It is possible to hide or invisible some fields in odoo. Commonly using “invisible” attribute in the field definition to invisible the fields. This slide will show how to make a field invisible in odoo 17.
Biological screening of herbal drugs: Introduction and Need for
Phyto-Pharmacological Screening, New Strategies for evaluating
Natural Products, In vitro evaluation techniques for Antioxidants, Antimicrobial and Anticancer drugs. In vivo evaluation techniques
for Anti-inflammatory, Antiulcer, Anticancer, Wound healing, Antidiabetic, Hepatoprotective, Cardio protective, Diuretics and
Antifertility, Toxicity studies as per OECD guidelines
2024.06.01 Introducing a competency framework for languag learning materials ...Sandy Millin
http://sandymillin.wordpress.com/iateflwebinar2024
Published classroom materials form the basis of syllabuses, drive teacher professional development, and have a potentially huge influence on learners, teachers and education systems. All teachers also create their own materials, whether a few sentences on a blackboard, a highly-structured fully-realised online course, or anything in between. Despite this, the knowledge and skills needed to create effective language learning materials are rarely part of teacher training, and are mostly learnt by trial and error.
Knowledge and skills frameworks, generally called competency frameworks, for ELT teachers, trainers and managers have existed for a few years now. However, until I created one for my MA dissertation, there wasn’t one drawing together what we need to know and do to be able to effectively produce language learning materials.
This webinar will introduce you to my framework, highlighting the key competencies I identified from my research. It will also show how anybody involved in language teaching (any language, not just English!), teacher training, managing schools or developing language learning materials can benefit from using the framework.
The Roman Empire A Historical Colossus.pdfkaushalkr1407
The Roman Empire, a vast and enduring power, stands as one of history's most remarkable civilizations, leaving an indelible imprint on the world. It emerged from the Roman Republic, transitioning into an imperial powerhouse under the leadership of Augustus Caesar in 27 BCE. This transformation marked the beginning of an era defined by unprecedented territorial expansion, architectural marvels, and profound cultural influence.
The empire's roots lie in the city of Rome, founded, according to legend, by Romulus in 753 BCE. Over centuries, Rome evolved from a small settlement to a formidable republic, characterized by a complex political system with elected officials and checks on power. However, internal strife, class conflicts, and military ambitions paved the way for the end of the Republic. Julius Caesar’s dictatorship and subsequent assassination in 44 BCE created a power vacuum, leading to a civil war. Octavian, later Augustus, emerged victorious, heralding the Roman Empire’s birth.
Under Augustus, the empire experienced the Pax Romana, a 200-year period of relative peace and stability. Augustus reformed the military, established efficient administrative systems, and initiated grand construction projects. The empire's borders expanded, encompassing territories from Britain to Egypt and from Spain to the Euphrates. Roman legions, renowned for their discipline and engineering prowess, secured and maintained these vast territories, building roads, fortifications, and cities that facilitated control and integration.
The Roman Empire’s society was hierarchical, with a rigid class system. At the top were the patricians, wealthy elites who held significant political power. Below them were the plebeians, free citizens with limited political influence, and the vast numbers of slaves who formed the backbone of the economy. The family unit was central, governed by the paterfamilias, the male head who held absolute authority.
Culturally, the Romans were eclectic, absorbing and adapting elements from the civilizations they encountered, particularly the Greeks. Roman art, literature, and philosophy reflected this synthesis, creating a rich cultural tapestry. Latin, the Roman language, became the lingua franca of the Western world, influencing numerous modern languages.
Roman architecture and engineering achievements were monumental. They perfected the arch, vault, and dome, constructing enduring structures like the Colosseum, Pantheon, and aqueducts. These engineering marvels not only showcased Roman ingenuity but also served practical purposes, from public entertainment to water supply.