SlideShare a Scribd company logo
1 of 7
Download to read offline
Page 1 of 7
BPAE WIND-US LIFT PROCEDURE
CRITICAL LIFTS
Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00
Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA
.
THE PROCEDURES LISTED IN THIS SECTION IS TO BE USED IN CONJUCTION WITH THE BP ALTERNATIVE
ENERGY HSSE PLAN AND PROCEDURES.
TABLE OF CONTENTS
1.0 SCOPE ............................................................................................................... 1
2.0 DEFINITIONS ..................................................................................................... 1
3.0 GENERAL........................................................................................................... 1
4.0 REQUIRED CRITICAL LIFT PLANS ................................................................... 2
5.0 CRITICAL LIFT PLAN COMPONENTS............................................................... 2
6.0 REVIEW MEETINGS .......................................................................................... 4
7.0 REVIEW REQUIREMENT................................................................................... 4
8.0 CONTINGENCY PLAN ………………………………………………………….........4
ATTACHMENT 1: PERMIT FOR CRITICAL NONREPETITIVE LIFT ............................ 5
_____________________________________________________________________________
1.0 SCOPE
This procedure outlines the specific planning and execution requirements for lifting loads that
are considered critical to the facility or project.
2.0 DEFINITIONS
“Live Equipment” means equipment that is operating or any non-operating equipment
containing liquids and/or gases.
“Proximity” means any distance within the radius of the combined length of the crane boom
and length of the load fully extended horizontally.
“Critical Lift” - See Section 4.1
3.0 GENERAL
Page 2 of 7
BPAE WIND-US LIFT PROCEDURE
CRITICAL LIFTS
Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00
Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA
.
3.1 The Contractor and Operation Personnel shall submit a Critical Lift Plan for review and
acceptance by BP Alternative Energy Representative at least fifteen (15) working days
prior to performing any lift that is covered by this Project Procedure.
3.2 This Critical Lift Plan will be returned to the Contractor accepted, accepted with
comments, or not accepted within seven days (7) working days.
3.3 The contractor or Operation Personnel hall have critical lifts plans reviewed and
approved by a qualified engineer acceptable to state in which the work is being
preformed. All lift plans shall be complete with, details, load calculations, crane
certification and rigging. Critical Lift Plans shall be stamped by a licensed Professional
Engineer.
3.4 No lift is allowed if it exceeds 95% of the chart for any given configuration of the crane.
Site Manager Approval is required for all Critical Lifts.
3.5 Personnel are not allowed in the shadow of the boom’s arc while a critical lift is in
progress.
4.0 REQUIRED CRITICAL LIFT PLANS
4.1 Critical Lift Plans are required for all lifts with a mobile crane, where one or more of the
following conditions are present:
4.1.1 The weight of the item to be lifted exceeds 50,000 pounds;
4.1.2 The lift is within an operating facility and the weight of the item to be lifted
exceeds 20,000 pounds.
4.1.3 The total load to be lifted exceeds 75% of the chart for the lift configuration of
the crane;
OR
4.1.4 Any other lift that is deemed as a "critical lift" by BP Alternative Energy that
would impact either plant operability, environmental compliance start –up or
reputation.
4.1.5 All multi pick loads.
4.1.6 Any lift that will occur over transmission lines and substation.
5.0 CRITICAL LIFT PLAN COMPONENTS
Page 3 of 7
BPAE WIND-US LIFT PROCEDURE
CRITICAL LIFTS
Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00
Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA
.
The Critical Lift Plan shall include, as a minimum, the following:
5.1 A completed Project Critical Lift Permit. See Attachment 1.
5.2 An Elevation View showing:
5.2.1 Crane manufacturer’s document of make and model of the crane with boom,
boom length, radius and crane capacity for the configuration used.
5.2.2 Rigging accessory information to identify and show capacity of sling, shackles,
spreader beams, blocks, etc.
5.2.3 Tabulation of weights of all items that constitute load on the crane boom, lifted
load, load lines, load blocks, spreaders, slings, shackles, jib, headache ball, etc.
5.2.4 Lifted equipment information to include weight, height, and diameter, point of
support, center of gravity and degree of dress-out.
5.2.5 Calculation of tailing load.
 A horizontal loading diagram will be drawn to show the initial tailing crane
load on the elevation view.
 The equipment center of gravity is to be obtained from the vendor.
5.2.6 Any obstructions or interferences to the lift from existing equipment, structure,
etc.
5.2.7 Details of the supporting mats or foundation under the lifting crane and tailing
crane with notation indication of the bearing capacity of the sub soil and the
calculated applied load.
5.2.8 Ratio of the lifted load to each crane’s chart capacity as configured.
5.2.9 Crane boom to load clearances.
5.3 The Plan View should show, on an overlay of the area plot plan:
5.3.1 The lift and tailing crane location at the beginning of the lift, any travel and the
final location.
5.3.2 Initial horizontal position of equipment to be lifted.
5.3.3 Layout and specifics for all required matting.
Note: Crane mats are required whenever the crane outrigger or
crawler tracks soil bearing pressure is equal or greater than
2,000 pound/square foot (lb/ft2
).
5.3.4 The plot layout should show any existing area and any new construction that will
be in place when the lift occurs.
Page 4 of 7
BPAE WIND-US LIFT PROCEDURE
CRITICAL LIFTS
Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00
Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA
.
5.3.5 Special note should be made of any underground lines or if the lift will pass over
any operating condition, i.e.: pipe rack, equipment, tank, electrical, building, etc.
5.3.6 Special note should be made if any portion of the lifting configuration will, at any
time during the lift, pass within ten (10) feet of any exposed live electrical
component.
5.3.7 The area under the boom’s arc that shall be “off-limits” to all personnel not
associated with the lift.
5.4 Attachments to the rigging study should include any item that will make the review more
efficient and complete. Required items are:
5.4.1 Equipment weight information from the Equipment Manufacturer.
5.4.2 Equipment weight verification - this can be either scale weight tickets or
independently calculated weight.
5.4.3 Cut sheets from the Crane Vendor’s capacity chart indicating the appropriate
configuration.
5.4.4 Cut sheets from the manufacturer of the rigging attachments showing capacity
and weight.
5.4.5 Outrigger or crawler track soil bearing pressure chart or calculations.
6.0 REVIEW MEETINGS
At the option of BP Alternative Energy, a formal rigging review meeting may be scheduled. As
a minimum, this meeting shall be attended by the Contractor’s site representative and, where
appropriate, the rigging engineer and superintendent for the Heavy Lift Subcontractor.
7.0 EMERGENCY ACTION PLAN
The HSSE supervisor shall be notified and emergency action plan shall be reviewed prior to
the lift plan.
8.0 REVIEW REQUIREMENT
No critical lift may proceed without a Critical Lift Permit signed and accepted by BPAE
Representative.
Page 5 of 7
BPAE WIND-US LIFT PROCEDURE
CRITICAL LIFTS
Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00
Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA
.
Page 6 of 7
BPAE WIND-US LIFT PROCEDURE
CRITICAL LIFTS
Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00
Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA
.
Attachment 1
Attachment 1 is shown on the next page.
Page 7 of 7
CRITICAL LIFT PERMIT
For Critical Non-Repetitive Lift
Issue Date: / /
1. Project Name/Plant 2. Contractor 3. Lift Date and time 4. Lift Location
5. Crane Manufacturer 6. Model Number 7. Serial Number 8. Total Boom/Boom Ext and/or
Jib Lgth (ft) @ time of Lift
9. Max. radius during Lift
(pick, swing, and set)
10. Swing Dir. & Degrees of swing 11. Lift Elevation (ft)
_______Max. _______Min.
12. Boom Angle
_______Pick _______Set
13. Will Jib and/or Boom Ext be used? Yes _____ No _____
Erected Stowed
If Yes: Length (ft) ______ ______
Weight (lb) ______ ______
14. Mfg. rated capacity from chart as outlined in Blocks 8 - 13
15. Component Weights:
Jib / Boom Extension: Wt. _______
Headache Ball Size: ______ Wt. _______
Load Block Size: ______ Wt. _______
Auxiliary Boom Head: Wt. _______
Weight of Cable (Load Fall): Wt. _______
Slings, Rigging, Shackles, & Etc: Wt. _______
Lifting Beam or Bars: Wt. _______
Allowance for Unaccounted Material and Equipment Wt. _______
Other Wt. _______
Total Weight ___________
16. Load Description and Weight
17. Who determined weight of Load and Lift?
Name:
How:
18. Total Lift Load
(Block 15 + 16)
19. Load % of Crane Capacity
(Divide Block 18 by 14)
20. Rigging Safety factor 5 to 1?
Yes ______ No ______
21. Rigging accessories size and
condition:
Slings:
Shackles:
Other:
22. Tag Line Required
Yes _____ No _____
23. Parts of Wire Rope on Block and
Single-Line Capacity of Wire Rope
24. Soil Conditions? Poor______ Good _____
Calculations? Required ____ Not Required ____
Compaction? Required ____ Not Required ____
Crane Mats? Required ____ Not Required ____
25. HAZARDS:
Electrical? Yes ____ No ____ If Yes, Explain:
Rain? Yes ____ No ____ If Yes, Explain:
Overhead? Yes ____ No ____ If Yes, Explain:
Wind Speed Yes ____ No ____ If Yes, Explain:
(If wind speed > 35 mph (56 kph), lift is prohibited.)
Underground? Yes ____ No ____ If Yes, Explain:
Others? Yes ____ No ____ If Yes, Explain:
26. Inspection/Testing:
Load Test Date: _________________
Periodic Insp. Date: _____________
Test Lift:
Remote Area ______
Lift Location ______
(Block 4) ______
27. Pre-lift meeting:
To be held? yes____ no_____
Date:
28. Attach:
"Plan View"
"Elevation View"
"Other Attachments"
29. Employee Training verified.
Yes ______ No ______
30. Signatures:
Representative of company making lift Date BP Alternative Energy Construction
Manager
Date
Contractor rigging supervisor Date BP Alternative Energy Project Manager Date
Contractor Site Manager Date BP Safety Representative Date
31. Immediate Approval to Proceed with Lift.
Set up is in accordance with the lift plan without deviation and the lift may proceed.
BP Alternative Energy Rigging Consultant Date BP Alternative Energy Site Manager Date

More Related Content

What's hot

Alan McNaughton Design Portfolio 2016
Alan McNaughton Design Portfolio 2016Alan McNaughton Design Portfolio 2016
Alan McNaughton Design Portfolio 2016
Alan McNaughton
 
Mass Properties and Automotive Braking, Rev b
Mass Properties and Automotive Braking, Rev bMass Properties and Automotive Braking, Rev b
Mass Properties and Automotive Braking, Rev b
Brian Wiegand
 
Stress analysis and optimization of crankshaft under dynamic loading 2
Stress analysis and optimization of crankshaft under dynamic loading 2Stress analysis and optimization of crankshaft under dynamic loading 2
Stress analysis and optimization of crankshaft under dynamic loading 2
IAEME Publication
 
BAJA 2013 final year project report
BAJA 2013 final year project reportBAJA 2013 final year project report
BAJA 2013 final year project report
Kalyan Potukuchi
 
Baja project 2010 report by bangalore institue of tech
Baja project 2010 report by bangalore institue of techBaja project 2010 report by bangalore institue of tech
Baja project 2010 report by bangalore institue of tech
Kapil Singh
 

What's hot (20)

DESIGN, OPTIMIZATION AND FINITE ELEMENT ANALYSIS OF CRANKSHAFT
DESIGN, OPTIMIZATION AND FINITE ELEMENT ANALYSIS OF CRANKSHAFTDESIGN, OPTIMIZATION AND FINITE ELEMENT ANALYSIS OF CRANKSHAFT
DESIGN, OPTIMIZATION AND FINITE ELEMENT ANALYSIS OF CRANKSHAFT
 
C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021C3 Corvette chassis upgrade 2021
C3 Corvette chassis upgrade 2021
 
Vehicle load transfer part II 2021
Vehicle load transfer part II 2021Vehicle load transfer part II 2021
Vehicle load transfer part II 2021
 
Fpo application guide ver 11 26 11-04
Fpo application guide ver 11  26 11-04Fpo application guide ver 11  26 11-04
Fpo application guide ver 11 26 11-04
 
Vehicle load transfer part I 2021
Vehicle load transfer part I 2021Vehicle load transfer part I 2021
Vehicle load transfer part I 2021
 
Vehicle load transfer part III 2021
Vehicle load transfer part III 2021Vehicle load transfer part III 2021
Vehicle load transfer part III 2021
 
Aircraft design trends and their impact on air cargo oriented aircrafts
Aircraft design trends and their impact on air cargo oriented aircraftsAircraft design trends and their impact on air cargo oriented aircrafts
Aircraft design trends and their impact on air cargo oriented aircrafts
 
06 02-27-load-testing-handbook-2006
06 02-27-load-testing-handbook-200606 02-27-load-testing-handbook-2006
06 02-27-load-testing-handbook-2006
 
Pick carry-cranes-risk-assessment
Pick carry-cranes-risk-assessmentPick carry-cranes-risk-assessment
Pick carry-cranes-risk-assessment
 
Aw Aerospace Presentation
Aw Aerospace PresentationAw Aerospace Presentation
Aw Aerospace Presentation
 
Alan McNaughton Design Portfolio 2016
Alan McNaughton Design Portfolio 2016Alan McNaughton Design Portfolio 2016
Alan McNaughton Design Portfolio 2016
 
macine design
macine designmacine design
macine design
 
Modeling and Analysis of Car Wheel
Modeling and Analysis of Car WheelModeling and Analysis of Car Wheel
Modeling and Analysis of Car Wheel
 
2002-01-3041_Tractor_Air_Suspension_Design_and_Tuning
2002-01-3041_Tractor_Air_Suspension_Design_and_Tuning2002-01-3041_Tractor_Air_Suspension_Design_and_Tuning
2002-01-3041_Tractor_Air_Suspension_Design_and_Tuning
 
6 bar linkage mechanism for hopper tipper hoisting
6 bar linkage mechanism for  hopper tipper hoisting6 bar linkage mechanism for  hopper tipper hoisting
6 bar linkage mechanism for hopper tipper hoisting
 
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design EngineerPortfolio - Theodoros Dragonas - Mechanical Design Engineer
Portfolio - Theodoros Dragonas - Mechanical Design Engineer
 
Mass Properties and Automotive Braking, Rev b
Mass Properties and Automotive Braking, Rev bMass Properties and Automotive Braking, Rev b
Mass Properties and Automotive Braking, Rev b
 
Stress analysis and optimization of crankshaft under dynamic loading 2
Stress analysis and optimization of crankshaft under dynamic loading 2Stress analysis and optimization of crankshaft under dynamic loading 2
Stress analysis and optimization of crankshaft under dynamic loading 2
 
BAJA 2013 final year project report
BAJA 2013 final year project reportBAJA 2013 final year project report
BAJA 2013 final year project report
 
Baja project 2010 report by bangalore institue of tech
Baja project 2010 report by bangalore institue of techBaja project 2010 report by bangalore institue of tech
Baja project 2010 report by bangalore institue of tech
 

Similar to Attach f critical_lifts

Design and Model of Bucket Elevator
Design and Model of Bucket ElevatorDesign and Model of Bucket Elevator
Design and Model of Bucket Elevator
Utkarsh Amaravat
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
Minh Bui Si
 
104 AAE - Introduction to CAD (submission C) (1)
104 AAE - Introduction to CAD (submission C) (1)104 AAE - Introduction to CAD (submission C) (1)
104 AAE - Introduction to CAD (submission C) (1)
Kruti Joshi AMIMechE
 
Yale e813 glp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 glp3.5 5.5 mj lift truck (europe) service repair manualYale e813 glp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 glp3.5 5.5 mj lift truck (europe) service repair manual
fjkskekdmmenm
 
Yale e813 gdp3.5 5.5 lj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 lj lift truck (europe) service repair manualYale e813 gdp3.5 5.5 lj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 lj lift truck (europe) service repair manual
fjjsekkmdmes
 
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manualYale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
fjjskekdmnsme
 
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manualYale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
fujjsjefkskekmm
 
Yale e813 glp3.5 5.5 lj lift truck (europe) service repair manual
Yale e813 glp3.5 5.5 lj lift truck (europe) service repair manualYale e813 glp3.5 5.5 lj lift truck (europe) service repair manual
Yale e813 glp3.5 5.5 lj lift truck (europe) service repair manual
fjjskkdmnsme
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
ssuseref23d3
 

Similar to Attach f critical_lifts (20)

Basic riggingworkbook
Basic riggingworkbookBasic riggingworkbook
Basic riggingworkbook
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
 
Personnel liftingad
Personnel liftingadPersonnel liftingad
Personnel liftingad
 
Design and Model of Bucket Elevator
Design and Model of Bucket ElevatorDesign and Model of Bucket Elevator
Design and Model of Bucket Elevator
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
 
104 AAE - Introduction to CAD (submission C) (1)
104 AAE - Introduction to CAD (submission C) (1)104 AAE - Introduction to CAD (submission C) (1)
104 AAE - Introduction to CAD (submission C) (1)
 
Motorized Sccissor Lift
Motorized Sccissor Lift Motorized Sccissor Lift
Motorized Sccissor Lift
 
Abs 1975 single point moorings
Abs 1975 single point mooringsAbs 1975 single point moorings
Abs 1975 single point moorings
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
 
heavylift and rigging.pdf
heavylift and rigging.pdfheavylift and rigging.pdf
heavylift and rigging.pdf
 
Rigging Engineering Basic
Rigging Engineering BasicRigging Engineering Basic
Rigging Engineering Basic
 
Yale e813 glp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 glp3.5 5.5 mj lift truck (europe) service repair manualYale e813 glp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 glp3.5 5.5 mj lift truck (europe) service repair manual
 
Yale e813 gdp3.5 5.5 lj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 lj lift truck (europe) service repair manualYale e813 gdp3.5 5.5 lj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 lj lift truck (europe) service repair manual
 
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manualYale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
 
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manualYale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
Yale e813 gdp3.5 5.5 mj lift truck (europe) service repair manual
 
Yale e813 glp3.5 5.5 lj lift truck (europe) service repair manual
Yale e813 glp3.5 5.5 lj lift truck (europe) service repair manualYale e813 glp3.5 5.5 lj lift truck (europe) service repair manual
Yale e813 glp3.5 5.5 lj lift truck (europe) service repair manual
 
Artificial lifting method
Artificial lifting methodArtificial lifting method
Artificial lifting method
 
Launch analysis
Launch analysisLaunch analysis
Launch analysis
 
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdfPMT80 Foundation Design & Installation & Commissioning & Safety.pdf
PMT80 Foundation Design & Installation & Commissioning & Safety.pdf
 
Structures proyect
Structures proyectStructures proyect
Structures proyect
 

Recently uploaded

一比一原版犹他大学毕业证如何办理
一比一原版犹他大学毕业证如何办理一比一原版犹他大学毕业证如何办理
一比一原版犹他大学毕业证如何办理
F
 
原版定制英国赫瑞瓦特大学毕业证原件一模一样
原版定制英国赫瑞瓦特大学毕业证原件一模一样原版定制英国赫瑞瓦特大学毕业证原件一模一样
原版定制英国赫瑞瓦特大学毕业证原件一模一样
AS
 
一比一原版(UWE毕业证书)西英格兰大学毕业证原件一模一样
一比一原版(UWE毕业证书)西英格兰大学毕业证原件一模一样一比一原版(UWE毕业证书)西英格兰大学毕业证原件一模一样
一比一原版(UWE毕业证书)西英格兰大学毕业证原件一模一样
Fi
 
一比一原版帝国理工学院毕业证如何办理
一比一原版帝国理工学院毕业证如何办理一比一原版帝国理工学院毕业证如何办理
一比一原版帝国理工学院毕业证如何办理
F
 
一比一原版美国北卡罗莱纳大学毕业证如何办理
一比一原版美国北卡罗莱纳大学毕业证如何办理一比一原版美国北卡罗莱纳大学毕业证如何办理
一比一原版美国北卡罗莱纳大学毕业证如何办理
A
 
Jual obat aborsi Bekasi ( 085657271886 ) Cytote pil telat bulan penggugur kan...
Jual obat aborsi Bekasi ( 085657271886 ) Cytote pil telat bulan penggugur kan...Jual obat aborsi Bekasi ( 085657271886 ) Cytote pil telat bulan penggugur kan...
Jual obat aborsi Bekasi ( 085657271886 ) Cytote pil telat bulan penggugur kan...
ZurliaSoop
 
一比一原版澳大利亚迪肯大学毕业证如何办理
一比一原版澳大利亚迪肯大学毕业证如何办理一比一原版澳大利亚迪肯大学毕业证如何办理
一比一原版澳大利亚迪肯大学毕业证如何办理
SS
 
一比一原版田纳西大学毕业证如何办理
一比一原版田纳西大学毕业证如何办理一比一原版田纳西大学毕业证如何办理
一比一原版田纳西大学毕业证如何办理
F
 
一比一原版贝德福特大学毕业证学位证书
一比一原版贝德福特大学毕业证学位证书一比一原版贝德福特大学毕业证学位证书
一比一原版贝德福特大学毕业证学位证书
F
 
如何办理(UCLA毕业证)加州大学洛杉矶分校毕业证成绩单本科硕士学位证留信学历认证
如何办理(UCLA毕业证)加州大学洛杉矶分校毕业证成绩单本科硕士学位证留信学历认证如何办理(UCLA毕业证)加州大学洛杉矶分校毕业证成绩单本科硕士学位证留信学历认证
如何办理(UCLA毕业证)加州大学洛杉矶分校毕业证成绩单本科硕士学位证留信学历认证
hfkmxufye
 
一比一原版(毕业证书)新西兰怀特克利夫艺术设计学院毕业证原件一模一样
一比一原版(毕业证书)新西兰怀特克利夫艺术设计学院毕业证原件一模一样一比一原版(毕业证书)新西兰怀特克利夫艺术设计学院毕业证原件一模一样
一比一原版(毕业证书)新西兰怀特克利夫艺术设计学院毕业证原件一模一样
AS
 

Recently uploaded (20)

一比一原版犹他大学毕业证如何办理
一比一原版犹他大学毕业证如何办理一比一原版犹他大学毕业证如何办理
一比一原版犹他大学毕业证如何办理
 
Story Board.pptxrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrr
Story Board.pptxrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrStory Board.pptxrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrr
Story Board.pptxrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrrr
 
原版定制英国赫瑞瓦特大学毕业证原件一模一样
原版定制英国赫瑞瓦特大学毕业证原件一模一样原版定制英国赫瑞瓦特大学毕业证原件一模一样
原版定制英国赫瑞瓦特大学毕业证原件一模一样
 
一比一原版(UWE毕业证书)西英格兰大学毕业证原件一模一样
一比一原版(UWE毕业证书)西英格兰大学毕业证原件一模一样一比一原版(UWE毕业证书)西英格兰大学毕业证原件一模一样
一比一原版(UWE毕业证书)西英格兰大学毕业证原件一模一样
 
一比一原版帝国理工学院毕业证如何办理
一比一原版帝国理工学院毕业证如何办理一比一原版帝国理工学院毕业证如何办理
一比一原版帝国理工学院毕业证如何办理
 
一比一原版美国北卡罗莱纳大学毕业证如何办理
一比一原版美国北卡罗莱纳大学毕业证如何办理一比一原版美国北卡罗莱纳大学毕业证如何办理
一比一原版美国北卡罗莱纳大学毕业证如何办理
 
APNIC Policy Roundup, presented by Sunny Chendi at the 5th ICANN APAC-TWNIC E...
APNIC Policy Roundup, presented by Sunny Chendi at the 5th ICANN APAC-TWNIC E...APNIC Policy Roundup, presented by Sunny Chendi at the 5th ICANN APAC-TWNIC E...
APNIC Policy Roundup, presented by Sunny Chendi at the 5th ICANN APAC-TWNIC E...
 
Jual obat aborsi Bekasi ( 085657271886 ) Cytote pil telat bulan penggugur kan...
Jual obat aborsi Bekasi ( 085657271886 ) Cytote pil telat bulan penggugur kan...Jual obat aborsi Bekasi ( 085657271886 ) Cytote pil telat bulan penggugur kan...
Jual obat aborsi Bekasi ( 085657271886 ) Cytote pil telat bulan penggugur kan...
 
一比一原版澳大利亚迪肯大学毕业证如何办理
一比一原版澳大利亚迪肯大学毕业证如何办理一比一原版澳大利亚迪肯大学毕业证如何办理
一比一原版澳大利亚迪肯大学毕业证如何办理
 
一比一原版田纳西大学毕业证如何办理
一比一原版田纳西大学毕业证如何办理一比一原版田纳西大学毕业证如何办理
一比一原版田纳西大学毕业证如何办理
 
Research Assignment - NIST SP800 [172 A] - Presentation.pptx
Research Assignment - NIST SP800 [172 A] - Presentation.pptxResearch Assignment - NIST SP800 [172 A] - Presentation.pptx
Research Assignment - NIST SP800 [172 A] - Presentation.pptx
 
Down bad crying at the gym t shirtsDown bad crying at the gym t shirts
Down bad crying at the gym t shirtsDown bad crying at the gym t shirtsDown bad crying at the gym t shirtsDown bad crying at the gym t shirts
Down bad crying at the gym t shirtsDown bad crying at the gym t shirts
 
一比一原版贝德福特大学毕业证学位证书
一比一原版贝德福特大学毕业证学位证书一比一原版贝德福特大学毕业证学位证书
一比一原版贝德福特大学毕业证学位证书
 
20240509 QFM015 Engineering Leadership Reading List April 2024.pdf
20240509 QFM015 Engineering Leadership Reading List April 2024.pdf20240509 QFM015 Engineering Leadership Reading List April 2024.pdf
20240509 QFM015 Engineering Leadership Reading List April 2024.pdf
 
如何办理(UCLA毕业证)加州大学洛杉矶分校毕业证成绩单本科硕士学位证留信学历认证
如何办理(UCLA毕业证)加州大学洛杉矶分校毕业证成绩单本科硕士学位证留信学历认证如何办理(UCLA毕业证)加州大学洛杉矶分校毕业证成绩单本科硕士学位证留信学历认证
如何办理(UCLA毕业证)加州大学洛杉矶分校毕业证成绩单本科硕士学位证留信学历认证
 
HUMANIZE YOUR BRAND - FREE E-WORKBOOK Download Now
HUMANIZE YOUR BRAND - FREE E-WORKBOOK Download NowHUMANIZE YOUR BRAND - FREE E-WORKBOOK Download Now
HUMANIZE YOUR BRAND - FREE E-WORKBOOK Download Now
 
一比一原版(毕业证书)新西兰怀特克利夫艺术设计学院毕业证原件一模一样
一比一原版(毕业证书)新西兰怀特克利夫艺术设计学院毕业证原件一模一样一比一原版(毕业证书)新西兰怀特克利夫艺术设计学院毕业证原件一模一样
一比一原版(毕业证书)新西兰怀特克利夫艺术设计学院毕业证原件一模一样
 
Washington Football Commanders Redskins Feathers Shirt
Washington Football Commanders Redskins Feathers ShirtWashington Football Commanders Redskins Feathers Shirt
Washington Football Commanders Redskins Feathers Shirt
 
20240510 QFM016 Irresponsible AI Reading List April 2024.pdf
20240510 QFM016 Irresponsible AI Reading List April 2024.pdf20240510 QFM016 Irresponsible AI Reading List April 2024.pdf
20240510 QFM016 Irresponsible AI Reading List April 2024.pdf
 
TOP 100 Vulnerabilities Step-by-Step Guide Handbook
TOP 100 Vulnerabilities Step-by-Step Guide HandbookTOP 100 Vulnerabilities Step-by-Step Guide Handbook
TOP 100 Vulnerabilities Step-by-Step Guide Handbook
 

Attach f critical_lifts

  • 1. Page 1 of 7 BPAE WIND-US LIFT PROCEDURE CRITICAL LIFTS Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00 Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA . THE PROCEDURES LISTED IN THIS SECTION IS TO BE USED IN CONJUCTION WITH THE BP ALTERNATIVE ENERGY HSSE PLAN AND PROCEDURES. TABLE OF CONTENTS 1.0 SCOPE ............................................................................................................... 1 2.0 DEFINITIONS ..................................................................................................... 1 3.0 GENERAL........................................................................................................... 1 4.0 REQUIRED CRITICAL LIFT PLANS ................................................................... 2 5.0 CRITICAL LIFT PLAN COMPONENTS............................................................... 2 6.0 REVIEW MEETINGS .......................................................................................... 4 7.0 REVIEW REQUIREMENT................................................................................... 4 8.0 CONTINGENCY PLAN ………………………………………………………….........4 ATTACHMENT 1: PERMIT FOR CRITICAL NONREPETITIVE LIFT ............................ 5 _____________________________________________________________________________ 1.0 SCOPE This procedure outlines the specific planning and execution requirements for lifting loads that are considered critical to the facility or project. 2.0 DEFINITIONS “Live Equipment” means equipment that is operating or any non-operating equipment containing liquids and/or gases. “Proximity” means any distance within the radius of the combined length of the crane boom and length of the load fully extended horizontally. “Critical Lift” - See Section 4.1 3.0 GENERAL
  • 2. Page 2 of 7 BPAE WIND-US LIFT PROCEDURE CRITICAL LIFTS Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00 Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA . 3.1 The Contractor and Operation Personnel shall submit a Critical Lift Plan for review and acceptance by BP Alternative Energy Representative at least fifteen (15) working days prior to performing any lift that is covered by this Project Procedure. 3.2 This Critical Lift Plan will be returned to the Contractor accepted, accepted with comments, or not accepted within seven days (7) working days. 3.3 The contractor or Operation Personnel hall have critical lifts plans reviewed and approved by a qualified engineer acceptable to state in which the work is being preformed. All lift plans shall be complete with, details, load calculations, crane certification and rigging. Critical Lift Plans shall be stamped by a licensed Professional Engineer. 3.4 No lift is allowed if it exceeds 95% of the chart for any given configuration of the crane. Site Manager Approval is required for all Critical Lifts. 3.5 Personnel are not allowed in the shadow of the boom’s arc while a critical lift is in progress. 4.0 REQUIRED CRITICAL LIFT PLANS 4.1 Critical Lift Plans are required for all lifts with a mobile crane, where one or more of the following conditions are present: 4.1.1 The weight of the item to be lifted exceeds 50,000 pounds; 4.1.2 The lift is within an operating facility and the weight of the item to be lifted exceeds 20,000 pounds. 4.1.3 The total load to be lifted exceeds 75% of the chart for the lift configuration of the crane; OR 4.1.4 Any other lift that is deemed as a "critical lift" by BP Alternative Energy that would impact either plant operability, environmental compliance start –up or reputation. 4.1.5 All multi pick loads. 4.1.6 Any lift that will occur over transmission lines and substation. 5.0 CRITICAL LIFT PLAN COMPONENTS
  • 3. Page 3 of 7 BPAE WIND-US LIFT PROCEDURE CRITICAL LIFTS Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00 Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA . The Critical Lift Plan shall include, as a minimum, the following: 5.1 A completed Project Critical Lift Permit. See Attachment 1. 5.2 An Elevation View showing: 5.2.1 Crane manufacturer’s document of make and model of the crane with boom, boom length, radius and crane capacity for the configuration used. 5.2.2 Rigging accessory information to identify and show capacity of sling, shackles, spreader beams, blocks, etc. 5.2.3 Tabulation of weights of all items that constitute load on the crane boom, lifted load, load lines, load blocks, spreaders, slings, shackles, jib, headache ball, etc. 5.2.4 Lifted equipment information to include weight, height, and diameter, point of support, center of gravity and degree of dress-out. 5.2.5 Calculation of tailing load.  A horizontal loading diagram will be drawn to show the initial tailing crane load on the elevation view.  The equipment center of gravity is to be obtained from the vendor. 5.2.6 Any obstructions or interferences to the lift from existing equipment, structure, etc. 5.2.7 Details of the supporting mats or foundation under the lifting crane and tailing crane with notation indication of the bearing capacity of the sub soil and the calculated applied load. 5.2.8 Ratio of the lifted load to each crane’s chart capacity as configured. 5.2.9 Crane boom to load clearances. 5.3 The Plan View should show, on an overlay of the area plot plan: 5.3.1 The lift and tailing crane location at the beginning of the lift, any travel and the final location. 5.3.2 Initial horizontal position of equipment to be lifted. 5.3.3 Layout and specifics for all required matting. Note: Crane mats are required whenever the crane outrigger or crawler tracks soil bearing pressure is equal or greater than 2,000 pound/square foot (lb/ft2 ). 5.3.4 The plot layout should show any existing area and any new construction that will be in place when the lift occurs.
  • 4. Page 4 of 7 BPAE WIND-US LIFT PROCEDURE CRITICAL LIFTS Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00 Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA . 5.3.5 Special note should be made of any underground lines or if the lift will pass over any operating condition, i.e.: pipe rack, equipment, tank, electrical, building, etc. 5.3.6 Special note should be made if any portion of the lifting configuration will, at any time during the lift, pass within ten (10) feet of any exposed live electrical component. 5.3.7 The area under the boom’s arc that shall be “off-limits” to all personnel not associated with the lift. 5.4 Attachments to the rigging study should include any item that will make the review more efficient and complete. Required items are: 5.4.1 Equipment weight information from the Equipment Manufacturer. 5.4.2 Equipment weight verification - this can be either scale weight tickets or independently calculated weight. 5.4.3 Cut sheets from the Crane Vendor’s capacity chart indicating the appropriate configuration. 5.4.4 Cut sheets from the manufacturer of the rigging attachments showing capacity and weight. 5.4.5 Outrigger or crawler track soil bearing pressure chart or calculations. 6.0 REVIEW MEETINGS At the option of BP Alternative Energy, a formal rigging review meeting may be scheduled. As a minimum, this meeting shall be attended by the Contractor’s site representative and, where appropriate, the rigging engineer and superintendent for the Heavy Lift Subcontractor. 7.0 EMERGENCY ACTION PLAN The HSSE supervisor shall be notified and emergency action plan shall be reviewed prior to the lift plan. 8.0 REVIEW REQUIREMENT No critical lift may proceed without a Critical Lift Permit signed and accepted by BPAE Representative.
  • 5. Page 5 of 7 BPAE WIND-US LIFT PROCEDURE CRITICAL LIFTS Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00 Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA .
  • 6. Page 6 of 7 BPAE WIND-US LIFT PROCEDURE CRITICAL LIFTS Issued By: Hans.Owen@BP.com 11/19/2007 Document No.: AEPA_WND_EDOMH_GN_40_000018_00 Approval By: Tim Stastny@BP.com 11/19/2007 BPAE- EA . Attachment 1 Attachment 1 is shown on the next page.
  • 7. Page 7 of 7 CRITICAL LIFT PERMIT For Critical Non-Repetitive Lift Issue Date: / / 1. Project Name/Plant 2. Contractor 3. Lift Date and time 4. Lift Location 5. Crane Manufacturer 6. Model Number 7. Serial Number 8. Total Boom/Boom Ext and/or Jib Lgth (ft) @ time of Lift 9. Max. radius during Lift (pick, swing, and set) 10. Swing Dir. & Degrees of swing 11. Lift Elevation (ft) _______Max. _______Min. 12. Boom Angle _______Pick _______Set 13. Will Jib and/or Boom Ext be used? Yes _____ No _____ Erected Stowed If Yes: Length (ft) ______ ______ Weight (lb) ______ ______ 14. Mfg. rated capacity from chart as outlined in Blocks 8 - 13 15. Component Weights: Jib / Boom Extension: Wt. _______ Headache Ball Size: ______ Wt. _______ Load Block Size: ______ Wt. _______ Auxiliary Boom Head: Wt. _______ Weight of Cable (Load Fall): Wt. _______ Slings, Rigging, Shackles, & Etc: Wt. _______ Lifting Beam or Bars: Wt. _______ Allowance for Unaccounted Material and Equipment Wt. _______ Other Wt. _______ Total Weight ___________ 16. Load Description and Weight 17. Who determined weight of Load and Lift? Name: How: 18. Total Lift Load (Block 15 + 16) 19. Load % of Crane Capacity (Divide Block 18 by 14) 20. Rigging Safety factor 5 to 1? Yes ______ No ______ 21. Rigging accessories size and condition: Slings: Shackles: Other: 22. Tag Line Required Yes _____ No _____ 23. Parts of Wire Rope on Block and Single-Line Capacity of Wire Rope 24. Soil Conditions? Poor______ Good _____ Calculations? Required ____ Not Required ____ Compaction? Required ____ Not Required ____ Crane Mats? Required ____ Not Required ____ 25. HAZARDS: Electrical? Yes ____ No ____ If Yes, Explain: Rain? Yes ____ No ____ If Yes, Explain: Overhead? Yes ____ No ____ If Yes, Explain: Wind Speed Yes ____ No ____ If Yes, Explain: (If wind speed > 35 mph (56 kph), lift is prohibited.) Underground? Yes ____ No ____ If Yes, Explain: Others? Yes ____ No ____ If Yes, Explain: 26. Inspection/Testing: Load Test Date: _________________ Periodic Insp. Date: _____________ Test Lift: Remote Area ______ Lift Location ______ (Block 4) ______ 27. Pre-lift meeting: To be held? yes____ no_____ Date: 28. Attach: "Plan View" "Elevation View" "Other Attachments" 29. Employee Training verified. Yes ______ No ______ 30. Signatures: Representative of company making lift Date BP Alternative Energy Construction Manager Date Contractor rigging supervisor Date BP Alternative Energy Project Manager Date Contractor Site Manager Date BP Safety Representative Date 31. Immediate Approval to Proceed with Lift. Set up is in accordance with the lift plan without deviation and the lift may proceed. BP Alternative Energy Rigging Consultant Date BP Alternative Energy Site Manager Date