Sub-Contractor Pre-Start HSE Checklist
(To be filled by Sub-Contractor before start of activity on daily basis)
Page 1 of 1 Form # HSEQ- SPSC (Rev 2 - Mar 23)
1. Project Information:
Project Name: Checklist No.:
Sub-Contractor/Company:
Date:
2. Task Details:
Description of Task:
Location / Area :
Number of Workers:
Task Duration: Time (from): _______Hrs. Time (To): __________Hrs. Date:
3. Prerequisites:
Checks Yes-No-NA Checks Yes-No-NA
Safety induction done. ☐ ☐ ☐ Safety tool box talk done. ☐ ☐ ☐
Method statement/Risk assessment
in place.
☐ ☐ ☐ Training on Risk Assessment/
Method Statement done
☐ ☐ ☐
Job Safety Analysis done. ☐ ☐ ☐ 3 Month Safety Look Ahead in place ☐ ☐ ☐
Permit to Work obtained ☐ ☐ ☐ Site Supervisor available ☐ ☐ ☐
PPE Available ☐ ☐ ☐ Working area is well lighted ☐ ☐ ☐
Tools and equipment inspected and
tagged
☐ ☐ ☐ Unsafe conditions rectified ☐ ☐ ☐
Pre-Start Checks completed ☐ ☐ ☐ Emergency procedures
communicated
☐ ☐ ☐
Unauthorized workers are cleared
from the area.
☐ ☐ ☐ Other ( Specify): ☐ ☐ ☐
4. Acknowledgement by Sub-Contractor:
☐ Acknowledge that all above precautions/ controls measures have been taken. These have also been fully explained
to the operatives, and I consider them competent to do it safely.
Initiator/Originator
Name:
Designation:
Signature: Date /Time:
Signature: Date /Time

SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx

  • 1.
    Sub-Contractor Pre-Start HSEChecklist (To be filled by Sub-Contractor before start of activity on daily basis) Page 1 of 1 Form # HSEQ- SPSC (Rev 2 - Mar 23) 1. Project Information: Project Name: Checklist No.: Sub-Contractor/Company: Date: 2. Task Details: Description of Task: Location / Area : Number of Workers: Task Duration: Time (from): _______Hrs. Time (To): __________Hrs. Date: 3. Prerequisites: Checks Yes-No-NA Checks Yes-No-NA Safety induction done. ☐ ☐ ☐ Safety tool box talk done. ☐ ☐ ☐ Method statement/Risk assessment in place. ☐ ☐ ☐ Training on Risk Assessment/ Method Statement done ☐ ☐ ☐ Job Safety Analysis done. ☐ ☐ ☐ 3 Month Safety Look Ahead in place ☐ ☐ ☐ Permit to Work obtained ☐ ☐ ☐ Site Supervisor available ☐ ☐ ☐ PPE Available ☐ ☐ ☐ Working area is well lighted ☐ ☐ ☐ Tools and equipment inspected and tagged ☐ ☐ ☐ Unsafe conditions rectified ☐ ☐ ☐ Pre-Start Checks completed ☐ ☐ ☐ Emergency procedures communicated ☐ ☐ ☐ Unauthorized workers are cleared from the area. ☐ ☐ ☐ Other ( Specify): ☐ ☐ ☐ 4. Acknowledgement by Sub-Contractor: ☐ Acknowledge that all above precautions/ controls measures have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely. Initiator/Originator Name: Designation: Signature: Date /Time: Signature: Date /Time