SlideShare a Scribd company logo
©-Peninsula v1 Form LPC – Lifting Plan Checklist Page 1 of 5
Lifting Plan Checklist and Method Statement (Mobile Cranes)
Site or Contract: ………………………………….Managed or Contract lift; ………………….…
Task description: ………………………………….….
Date planned for lift: ………………………………….
Use this checklist before carrying out a lifting operation. It is based on requirements set out in
British Standard 7121-1:2016 Code of practice for safe use of cranes. If you are using a contractor
expect them to ask for the information set out in Section A. Require the contractor to supply you
with the information as in Sections Band C before the lifting operation takes place.
Section A: PRE-PLANNING
For completion before a lifting operation under your control and supply to the crane operating
company before a crane is ordered.
1. The load to be lifted;
Size
Shape
Lifting eyes, lifting points
Centre of gravity and stability
Location
2. Access route for crane and space
available at planned operating position.
3. Crane position before, during and after
the lift.
(see sketch plan overleaf)
4. Maximum load to be lifted in tonnes.
5. Lifting accessories and attachments.
Specify their weight if not included
above.
6. Expected operating radius in meters.
7. Lift height required, in meters.
8. Presence of overhead cables and other
hazards that could affect the lifting
operation.
9. Ground conditions - foundations,
made-up ground, impact loading, etc.
10. Crane configuration and arrangements
for erection and dismantling
11. Crane to be used and configuration
12. Maximum permissible motion speeds,
acceleration and deceleration
©-Peninsula v1 Form LPC – Lifting Plan Checklist Page 2 of 5
13. Other factors taken into account.
Sketch plan.
Site access for crane and position of crane before, during and after the lifting operation. Show crane safety
working zone and any exclusion zones.
Completed by: on date
©-Peninsula v1 Form LPC – Lifting Plan Checklist Page 3 of 5
Section B: CRANE ON SITE
To be completed by the appointed person in control of the lifting operation before the lift begins.
Crane Details
Type of Crane Size of Crane
Identification No
Hire Company if applicable
Thorough Examination of Lifting Accessories?
Valid only if completed within the last 6 months.
Thorough Examination of Lifting Equipment?
Valid only if completed within the last 12 months.
SWL Indicator Functional?
Weekly Inspection Book in Cab?
Is the crane of the correct size and type?
Driver, Operator Details
Driver, Operator name
CPCS Card No
Or other qualification
Crane Position
Adequate and suitable base? All outriggers fully extended?
Adequate packing under outriggers? Position of outriggers satisfactory?
Lifting Gear
Type Identification No
SWL Test Certificate in place No
Visual Check
(i.e. general condition)
Can the lift proceed in safety?
Comments;
Completed by on-
©-Peninsula v1 Form LPC – Lifting Plan Checklist Page 4 of 5
Section C: METHOD STATEMENT & AUTHORISATION OF LIFTING
OPERATION
Task to be carried out.
Where the work is expected to take
more than a day specify the
configuration of the crane at the end
of each day’s work.
Explain the control measures required
to eliminate or minimise risk to those
involved.
Explain the steps required to eliminate
risk to other people e.g. road closures
and segregation zones.
Pre work checks of crane, site, and
load.
Task allocation to named people;
 Appointed person in control of
lifting operation.
 Crane supervisor.
 Crane operator.
 Slingers – signalers.
 Others
Confirmation of load details; weight,
dimensions, CoG.
Lifting points and lifting method
including accessories to be used and
their configuration.
Pickup and landing points
Height and radius of lift
Model and configuration of crane.
Configuration of outriggers and
ground supports
Overhead and underground hazards
©-Peninsula v1 Form LPC – Lifting Plan Checklist Page 5 of 5
Sequence of lifting operations
Control measures to eliminate or
minimise risk.
Environmental limitations – wind
speed, sea state etc.
Access to attach and remove slings and
lifting accessories.
Measures to ensure that the load
remains stable once slings and
attachments have been removed.
Arrangements for working at height
and rescue plans – if applicable.
Method of communication e.g. hand
signals, radio, etc.
PROVISION OF AUTHORITY -
Authorisation commences (date and time)
Authorisation issued by
Name
Signature
The person givingthis authorisationconfirms thatthe operator, slingers, signalers, supervisorsand others
involved in this lifting operation have taken part in a team briefing at which this method statement was
explained and they were given all necessary information and made aware of specific hazards i.e. position
of load, loads to be lifted, any excavation, soft ground, overhead cables, etc.
Accepted by Crane Driver
Name
Signature
THIS AUTHORISATION IS VALID UNTIL -

More Related Content

What's hot

SAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEASAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEA
ANA ISABEL R.R.
 
313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet
Phạm Thành
 
Lifting Operation.ppt
Lifting Operation.pptLifting Operation.ppt
Lifting Operation.ppt
ballabammoune1
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
Simba Zhao
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
DrValliammaishanmuga
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatYousif Fikry
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
VasudevaRajuDantulur1
 
Rigging and lifting
Rigging and liftingRigging and lifting
Rigging and lifting
Asghar Yaghouti
 
Signalman training
Signalman trainingSignalman training
Signalman training
Rob Cowden
 
Lifting Presentation.
Lifting Presentation.Lifting Presentation.
Lifting Presentation.paul doherty
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates
Dwarika Bhushan Sharma
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
Lift Plan
Lift PlanLift Plan
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Gaurav Singh Rajput
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
Dwarika Bhushan Sharma
 
Hoisting and Rigging Safety
Hoisting and Rigging SafetyHoisting and Rigging Safety
Hoisting and Rigging Safety
NickHawkins19
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 

What's hot (20)

SAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEASAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEA
 
313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet313440656 crane-lifting-calculation-sheet
313440656 crane-lifting-calculation-sheet
 
Lifting Operation.ppt
Lifting Operation.pptLifting Operation.ppt
Lifting Operation.ppt
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boat
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Rigging and lifting
Rigging and liftingRigging and lifting
Rigging and lifting
 
Signalman training
Signalman trainingSignalman training
Signalman training
 
Lifting Presentation.
Lifting Presentation.Lifting Presentation.
Lifting Presentation.
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
Lift Plan
Lift PlanLift Plan
Lift Plan
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 
Basic Rigging
Basic RiggingBasic Rigging
Basic Rigging
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
 
Hoisting and Rigging Safety
Hoisting and Rigging SafetyHoisting and Rigging Safety
Hoisting and Rigging Safety
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
Safety know your crane
Safety   know your craneSafety   know your crane
Safety know your crane
 

Similar to 10. lifting-plan-checklist-and-method-statement-2

Pr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionPr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning execution
Sergio Augusto Esteves
 
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
Specialized Carriers & Rigging Association
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
dinesh622857
 
Const cranes 9 3 10
Const cranes 9 3 10Const cranes 9 3 10
Const cranes 9 3 10
vtsiri
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sitesPrastowo Priyatmoko
 
Crane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas ArlingtonCrane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas Arlington
Atlantic Training, LLC.
 
2017 cranes_hoists_and_elevators_ codes_regulations.pdf
2017 cranes_hoists_and_elevators_ codes_regulations.pdf2017 cranes_hoists_and_elevators_ codes_regulations.pdf
2017 cranes_hoists_and_elevators_ codes_regulations.pdf
albertmunoz998
 
Abs 1975 single point moorings
Abs 1975 single point mooringsAbs 1975 single point moorings
Abs 1975 single point moorings
Ignacio Santana
 
Liffting supervisor
Liffting supervisorLiffting supervisor
Liffting supervisor
muhammad nazeer taj tanoli
 
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGAIZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
ssuser9df777
 
const_cranes_090310 (1).ppt
const_cranes_090310 (1).pptconst_cranes_090310 (1).ppt
const_cranes_090310 (1).ppt
Ronald Aranha
 
22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates
Dwarika Bhushan Sharma
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptx
AizazFarhat3
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
shahriermahmud13
 
24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates
Dwarika Bhushan Sharma
 
Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
Muhammad Saqib
 
Rigging Course .pdf
Rigging Course                       .pdfRigging Course                       .pdf
Rigging Course .pdf
Muhammad Saqib
 

Similar to 10. lifting-plan-checklist-and-method-statement-2 (20)

SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
 
Pr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionPr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning execution
 
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
2016 CRW - An inside look at Kiewit's Crane & Rigging Management System
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
 
Const cranes 9 3 10
Const cranes 9 3 10Const cranes 9 3 10
Const cranes 9 3 10
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites
 
Crane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas ArlingtonCrane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas Arlington
 
2017 cranes_hoists_and_elevators_ codes_regulations.pdf
2017 cranes_hoists_and_elevators_ codes_regulations.pdf2017 cranes_hoists_and_elevators_ codes_regulations.pdf
2017 cranes_hoists_and_elevators_ codes_regulations.pdf
 
Abs 1975 single point moorings
Abs 1975 single point mooringsAbs 1975 single point moorings
Abs 1975 single point moorings
 
Paul CV 2017-2
Paul CV  2017-2Paul CV  2017-2
Paul CV 2017-2
 
Liffting supervisor
Liffting supervisorLiffting supervisor
Liffting supervisor
 
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGAIZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
 
const_cranes_090310 (1).ppt
const_cranes_090310 (1).pptconst_cranes_090310 (1).ppt
const_cranes_090310 (1).ppt
 
22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptx
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
 
24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates
 
Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
 
Rigging Course .pdf
Rigging Course                       .pdfRigging Course                       .pdf
Rigging Course .pdf
 

More from Sergio Augusto Esteves

Cartazes covid19-v25-02-2020 unidadessaude
Cartazes covid19-v25-02-2020 unidadessaudeCartazes covid19-v25-02-2020 unidadessaude
Cartazes covid19-v25-02-2020 unidadessaude
Sergio Augusto Esteves
 
Pick carry-cranes-risk-assessment
Pick carry-cranes-risk-assessmentPick carry-cranes-risk-assessment
Pick carry-cranes-risk-assessment
Sergio Augusto Esteves
 
0505 breaker heavy -110230v
0505 breaker   heavy -110230v0505 breaker   heavy -110230v
0505 breaker heavy -110230v
Sergio Augusto Esteves
 
0316 sawbench 110230v
0316 sawbench   110230v0316 sawbench   110230v
0316 sawbench 110230v
Sergio Augusto Esteves
 
0308 circular saw 110230v
0308 circular saw  110230v0308 circular saw  110230v
0308 circular saw 110230v
Sergio Augusto Esteves
 

More from Sergio Augusto Esteves (6)

Cartazes covid19-v25-02-2020 unidadessaude
Cartazes covid19-v25-02-2020 unidadessaudeCartazes covid19-v25-02-2020 unidadessaude
Cartazes covid19-v25-02-2020 unidadessaude
 
Pick carry-cranes-risk-assessment
Pick carry-cranes-risk-assessmentPick carry-cranes-risk-assessment
Pick carry-cranes-risk-assessment
 
0505 breaker heavy -110230v
0505 breaker   heavy -110230v0505 breaker   heavy -110230v
0505 breaker heavy -110230v
 
0316 sawbench 110230v
0316 sawbench   110230v0316 sawbench   110230v
0316 sawbench 110230v
 
0306 jigsaw 110230v
0306 jigsaw  110230v0306 jigsaw  110230v
0306 jigsaw 110230v
 
0308 circular saw 110230v
0308 circular saw  110230v0308 circular saw  110230v
0308 circular saw 110230v
 

Recently uploaded

Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 

Recently uploaded (20)

Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 

10. lifting-plan-checklist-and-method-statement-2

  • 1. ©-Peninsula v1 Form LPC – Lifting Plan Checklist Page 1 of 5 Lifting Plan Checklist and Method Statement (Mobile Cranes) Site or Contract: ………………………………….Managed or Contract lift; ………………….… Task description: ………………………………….…. Date planned for lift: …………………………………. Use this checklist before carrying out a lifting operation. It is based on requirements set out in British Standard 7121-1:2016 Code of practice for safe use of cranes. If you are using a contractor expect them to ask for the information set out in Section A. Require the contractor to supply you with the information as in Sections Band C before the lifting operation takes place. Section A: PRE-PLANNING For completion before a lifting operation under your control and supply to the crane operating company before a crane is ordered. 1. The load to be lifted; Size Shape Lifting eyes, lifting points Centre of gravity and stability Location 2. Access route for crane and space available at planned operating position. 3. Crane position before, during and after the lift. (see sketch plan overleaf) 4. Maximum load to be lifted in tonnes. 5. Lifting accessories and attachments. Specify their weight if not included above. 6. Expected operating radius in meters. 7. Lift height required, in meters. 8. Presence of overhead cables and other hazards that could affect the lifting operation. 9. Ground conditions - foundations, made-up ground, impact loading, etc. 10. Crane configuration and arrangements for erection and dismantling 11. Crane to be used and configuration 12. Maximum permissible motion speeds, acceleration and deceleration
  • 2. ©-Peninsula v1 Form LPC – Lifting Plan Checklist Page 2 of 5 13. Other factors taken into account. Sketch plan. Site access for crane and position of crane before, during and after the lifting operation. Show crane safety working zone and any exclusion zones. Completed by: on date
  • 3. ©-Peninsula v1 Form LPC – Lifting Plan Checklist Page 3 of 5 Section B: CRANE ON SITE To be completed by the appointed person in control of the lifting operation before the lift begins. Crane Details Type of Crane Size of Crane Identification No Hire Company if applicable Thorough Examination of Lifting Accessories? Valid only if completed within the last 6 months. Thorough Examination of Lifting Equipment? Valid only if completed within the last 12 months. SWL Indicator Functional? Weekly Inspection Book in Cab? Is the crane of the correct size and type? Driver, Operator Details Driver, Operator name CPCS Card No Or other qualification Crane Position Adequate and suitable base? All outriggers fully extended? Adequate packing under outriggers? Position of outriggers satisfactory? Lifting Gear Type Identification No SWL Test Certificate in place No Visual Check (i.e. general condition) Can the lift proceed in safety? Comments; Completed by on-
  • 4. ©-Peninsula v1 Form LPC – Lifting Plan Checklist Page 4 of 5 Section C: METHOD STATEMENT & AUTHORISATION OF LIFTING OPERATION Task to be carried out. Where the work is expected to take more than a day specify the configuration of the crane at the end of each day’s work. Explain the control measures required to eliminate or minimise risk to those involved. Explain the steps required to eliminate risk to other people e.g. road closures and segregation zones. Pre work checks of crane, site, and load. Task allocation to named people;  Appointed person in control of lifting operation.  Crane supervisor.  Crane operator.  Slingers – signalers.  Others Confirmation of load details; weight, dimensions, CoG. Lifting points and lifting method including accessories to be used and their configuration. Pickup and landing points Height and radius of lift Model and configuration of crane. Configuration of outriggers and ground supports Overhead and underground hazards
  • 5. ©-Peninsula v1 Form LPC – Lifting Plan Checklist Page 5 of 5 Sequence of lifting operations Control measures to eliminate or minimise risk. Environmental limitations – wind speed, sea state etc. Access to attach and remove slings and lifting accessories. Measures to ensure that the load remains stable once slings and attachments have been removed. Arrangements for working at height and rescue plans – if applicable. Method of communication e.g. hand signals, radio, etc. PROVISION OF AUTHORITY - Authorisation commences (date and time) Authorisation issued by Name Signature The person givingthis authorisationconfirms thatthe operator, slingers, signalers, supervisorsand others involved in this lifting operation have taken part in a team briefing at which this method statement was explained and they were given all necessary information and made aware of specific hazards i.e. position of load, loads to be lifted, any excavation, soft ground, overhead cables, etc. Accepted by Crane Driver Name Signature THIS AUTHORISATION IS VALID UNTIL -