SlideShare a Scribd company logo
The Enigma of the Leaning Tower of Pisa
‘?’
Basic facts about the structure
• Height of the structure: 60 meters
• Diameter of the foundation: 19.6
meters
• Inclination of the tower: 5.5° to
the south
• Estimated weight of the structure:
14,500 tons
Cross section through the tower
.
Soil Profile beneath the tower
Construction timeline
• Construction work began on 9th August, 1173
• About quarter construction was achieved by
1178.
• There was then a halt in the construction for
unknown reasons, but had the construction
continued any further, the foundation would
have experienced a bearing capacity failure.
• The work recommenced in the year 1272.
.
• In year 1278, the tower’s construction was
completed up-to the seventh cornice & then
there was again a halt due to the military
action.
• Next recommencement was in 1360 and the
whole construction was finished in 1370.
• It took nearly 200 years to finish the
construction with two intervals of nearly 100
years each which gave the soil to gain
strength.
Unpleasant Surprise
• In 1838 an architect, Allesandro
Della Gherardesca excavated a
walk-way around the foundation
of the tower known as Catino.
• It was intended to expose
foundation steps and column
plinths.
• As the excavation was under the
water table, it caused an inflow
of water which gave the tower
an additional tilt of nearly half
degree to the south.
History of Tilting
• The commission for the stabilization was headed by Prof.
John B. Burland.
• Due to the absence of any documentary evidence all the
clues for the history of tilt were to be inferred from the
adjustments made to the masonry.
• He put himself in the place of a mason and asked himself,
“What is the most practical thing to do when you arrive
at a given floor and find that the tower is out-of-the
plumb.”
• A widely accepted hypothesis is that the masons would
always try to keep the masonry layers horizontal.
Shape of the axis of the tower deduced from relative
inclination of masonry layers
Temporary stabilization of the tower
• There were two distinct problems that
threatened the stability of the tower:
1. Strength of the masonry.
2. Stability of foundation against overturning.
Temporary stabilization of the masonry
• On the south side of the tower, due to the change in
the cross section the masonry blocks were stressed.
The exact assessment of stresses was not possible
but its effect would have been catastrophic.
• This problem was tackled by using plastic covered
steel tendons which were bound around the first
cornice upto the second floor which helped in
reducing the crack sizes and prevented the tower to
fail due to buckling.
Temporary stabilization of the masonry with light
circumferential pre-tensioning
Temporary Stabilization for the possible
overturning failure
• This was achieved by placing the counter weight
on the northern side of the tower is four phases
so that the response of the tower could be
recorded.
• Such solution would not have been considered if
it had not been recognized that the leaning
instability rather than the bearing capacity failure
was controlling the behavior of the tower or the
north side of the foundation was settling.
Counterweight installation to prevent the
overturning of tower
Observed change of inclination of the tower during
application of the counter-weight
Choosing the suitable and Permanent
Stabilization
• For bureaucratic and financial reasons the temporary
stabilization took longer than expected.
• Because of the severe restraints that have been
discussed already measures involving application of
concentrated loads to the masonry or underpinning
operations beneath the south side of the foundation
were ruled out.
• Moreover aesthetic and conservation considerations
required that the stabilization effect should have an
absolute minimal appearance.
The three possible approaches for the
permanent stabilization
After careful consideration of number of possible
approaches the commission chose to study three in
detail:
• Construction of the ground pressing concrete slab to
the north of the tower which was to be connected with
the post-tensioned concrete ring to be placed around
the periphery of the foundation.
• Consolidation of the Pancone clayby means of carefully
devised electro-osmosis.
• The technique of soil extraction which was at that time
already in practice in Mexico to reduce differential
settlement of number of buildings.
Approach #1: Ground pressing slab
• ✗ Numeric modeling of the ground pressing
slab showed that the tower’s response was
uncertain and if anyhow it gave positive
results the results were not large enough and
the settlements were huge & it required costly
civil engineering to proceed with.
• RULED OUT.
Approach #2: Electro-osmosis
• ✗ Full scale model showed that the ground
conditions at Pisa were not fit for this method.
• RULED OUT
Approach #3: Soil Extraction
• ✔ This method was best suited and was finally
adopted for the final large scale work.
• In this method small amounts of soil from
predefined locations are removed with the
help of inclined drills.
• This leaves a cavity at the drilled location and
which is gradually filled with the soil in
immediate vicinity of the cavity due to the
overburden pressure.
Schematic representation of the under-
excavation process
Change in the North-South inclination after the
permanent stabilization
References
• The Enigma of the Leaning Tower of Pisa, Prof. John
B. Burland, 1998
• http://casehistories.geoengineer.org
• http://home.eng.iastate.edu/

More Related Content

What's hot

Modes of failure of retaining walls
Modes of failure of retaining wallsModes of failure of retaining walls
Modes of failure of retaining wallsRitesh Chinchawade
 
Analysis and design of reinforced concrete stepped cantilever retaining wall
Analysis and design of reinforced concrete stepped cantilever retaining wallAnalysis and design of reinforced concrete stepped cantilever retaining wall
Analysis and design of reinforced concrete stepped cantilever retaining wall
eSAT Journals
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
KHUSHBU SHAH
 
3.bearing capacity of soil
3.bearing capacity of soil3.bearing capacity of soil
3.bearing capacity of soil
Amynaah Amye
 
Presentation on Slab, Beam & Column
Presentation on Slab, Beam & ColumnPresentation on Slab, Beam & Column
Presentation on Slab, Beam & Column
মু সা
 
RETAINING WALL
RETAINING WALLRETAINING WALL
RETAINING WALL
Yash Patel
 
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
Muhammad Irfan
 
Comlumns
ComlumnsComlumns
Retaining walls and slope stabilisation methods
Retaining walls and slope stabilisation methodsRetaining walls and slope stabilisation methods
Retaining walls and slope stabilisation methods
Alen James
 
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...Review of Causes of Foundation Failures and Their Possible Preventive and Rem...
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...
THE NORTHCAP UNIVERSITY
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Make Mannan
 
Case study on pile foundation review
Case study on pile foundation reviewCase study on pile foundation review
Case study on pile foundation review
Rajankumar416
 
Combined & Eccentric Footing
Combined & Eccentric FootingCombined & Eccentric Footing
Combined & Eccentric Footing
Parth Patil
 
Design of staircases
Design of staircasesDesign of staircases
Design of staircases
Jayvant Choudhary
 
dampness in structure by umar khan
dampness in structure by umar khandampness in structure by umar khan
dampness in structure by umar khan
engnr_umar
 
Foundation
FoundationFoundation
Foundation
bakht zamin
 
Details of Construction presentation ,single & combined footing
Details of Construction presentation ,single &  combined footingDetails of Construction presentation ,single &  combined footing
Details of Construction presentation ,single & combined footing
arnob293
 

What's hot (20)

Final booklet
Final bookletFinal booklet
Final booklet
 
Modes of failure of retaining walls
Modes of failure of retaining wallsModes of failure of retaining walls
Modes of failure of retaining walls
 
Deep foundation
Deep foundationDeep foundation
Deep foundation
 
Analysis and design of reinforced concrete stepped cantilever retaining wall
Analysis and design of reinforced concrete stepped cantilever retaining wallAnalysis and design of reinforced concrete stepped cantilever retaining wall
Analysis and design of reinforced concrete stepped cantilever retaining wall
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 
3.bearing capacity of soil
3.bearing capacity of soil3.bearing capacity of soil
3.bearing capacity of soil
 
Presentation on Slab, Beam & Column
Presentation on Slab, Beam & ColumnPresentation on Slab, Beam & Column
Presentation on Slab, Beam & Column
 
RETAINING WALL
RETAINING WALLRETAINING WALL
RETAINING WALL
 
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
 
Comlumns
ComlumnsComlumns
Comlumns
 
Retaining walls and slope stabilisation methods
Retaining walls and slope stabilisation methodsRetaining walls and slope stabilisation methods
Retaining walls and slope stabilisation methods
 
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...Review of Causes of Foundation Failures and Their Possible Preventive and Rem...
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Case study on pile foundation review
Case study on pile foundation reviewCase study on pile foundation review
Case study on pile foundation review
 
Combined & Eccentric Footing
Combined & Eccentric FootingCombined & Eccentric Footing
Combined & Eccentric Footing
 
Design of staircases
Design of staircasesDesign of staircases
Design of staircases
 
dampness in structure by umar khan
dampness in structure by umar khandampness in structure by umar khan
dampness in structure by umar khan
 
Advancement in retaining wall
Advancement  in retaining wallAdvancement  in retaining wall
Advancement in retaining wall
 
Foundation
FoundationFoundation
Foundation
 
Details of Construction presentation ,single & combined footing
Details of Construction presentation ,single &  combined footingDetails of Construction presentation ,single &  combined footing
Details of Construction presentation ,single & combined footing
 

Viewers also liked

LEANING TOWER OF PISA, ITALY
LEANING TOWER OF PISA, ITALYLEANING TOWER OF PISA, ITALY
LEANING TOWER OF PISA, ITALY
Ayaz Ahmed
 
Beauty of Italy
Beauty of ItalyBeauty of Italy
Beauty of Italy
Nubia **
 
The Leaning Tower Of Pisa
The Leaning Tower Of PisaThe Leaning Tower Of Pisa
The Leaning Tower Of Pisa
Alfia Mironova
 
The Origin Of The Wonderful Leaning Tower Of Pisa
The Origin Of The Wonderful Leaning Tower Of PisaThe Origin Of The Wonderful Leaning Tower Of Pisa
The Origin Of The Wonderful Leaning Tower Of Pisa
Kenny Slaught
 
Tower of pisa2
Tower of pisa2Tower of pisa2
Tower of pisa2LidiaGon
 
The Leaning Tower of Pisa
The Leaning Tower of PisaThe Leaning Tower of Pisa
The Leaning Tower of Pisa
kakapo1
 

Viewers also liked (7)

VFT to Pisa
VFT to PisaVFT to Pisa
VFT to Pisa
 
LEANING TOWER OF PISA, ITALY
LEANING TOWER OF PISA, ITALYLEANING TOWER OF PISA, ITALY
LEANING TOWER OF PISA, ITALY
 
Beauty of Italy
Beauty of ItalyBeauty of Italy
Beauty of Italy
 
The Leaning Tower Of Pisa
The Leaning Tower Of PisaThe Leaning Tower Of Pisa
The Leaning Tower Of Pisa
 
The Origin Of The Wonderful Leaning Tower Of Pisa
The Origin Of The Wonderful Leaning Tower Of PisaThe Origin Of The Wonderful Leaning Tower Of Pisa
The Origin Of The Wonderful Leaning Tower Of Pisa
 
Tower of pisa2
Tower of pisa2Tower of pisa2
Tower of pisa2
 
The Leaning Tower of Pisa
The Leaning Tower of PisaThe Leaning Tower of Pisa
The Leaning Tower of Pisa
 

Similar to Leaning tower of Pisa

Leaning Tower of Pisa.pptx
Leaning Tower of Pisa.pptxLeaning Tower of Pisa.pptx
Leaning Tower of Pisa.pptx
VISHVACHAUDHARY2
 
Soil properties and its importance in construction
Soil properties and its importance in constructionSoil properties and its importance in construction
Soil properties and its importance in construction
Venkatesh Yadav
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
Shivananda Roy
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
Andhra University
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
BirukYared3
 
Retrofitting case study of RCC structure
Retrofitting case study of RCC structureRetrofitting case study of RCC structure
Retrofitting case study of RCC structure
Manish Sharma
 
Turning torso
Turning torsoTurning torso
Turning torso
Miral Hadakia
 
Design And Construction Of Cantilevered Retaining Walls
Design And Construction Of Cantilevered Retaining WallsDesign And Construction Of Cantilevered Retaining Walls
Design And Construction Of Cantilevered Retaining Walls
Kumar Aman
 
Walkie Talkie.pptx
Walkie Talkie.pptxWalkie Talkie.pptx
Walkie Talkie.pptx
Vigneshwarsankar2
 
structure analysis by PUC GRP 3
structure analysis by PUC GRP 3structure analysis by PUC GRP 3
structure analysis by PUC GRP 3
promitchowdhury1
 
Deep excavations
Deep excavationsDeep excavations
Deep excavations
Bhargava Ram
 
Micropile
MicropileMicropile
Micropile
Sameer Thaiyam
 
Temporary Tie Backs in the Building Construction by Bill Morales MSc CCE
Temporary Tie Backs in the Building Construction by Bill Morales MSc CCETemporary Tie Backs in the Building Construction by Bill Morales MSc CCE
Temporary Tie Backs in the Building Construction by Bill Morales MSc CCEBill Morales MSc
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
Dave Chinmyee
 
S8 trabajo muros de contención-re2
 S8   trabajo muros de contención-re2 S8   trabajo muros de contención-re2
S8 trabajo muros de contención-re2
VITORINOCHAVEZMONTER
 

Similar to Leaning tower of Pisa (20)

Leaning Tower of Pisa.pptx
Leaning Tower of Pisa.pptxLeaning Tower of Pisa.pptx
Leaning Tower of Pisa.pptx
 
Soil properties and its importance in construction
Soil properties and its importance in constructionSoil properties and its importance in construction
Soil properties and its importance in construction
 
Engineering failures
Engineering failuresEngineering failures
Engineering failures
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
Pile foundation
Pile foundation Pile foundation
Pile foundation
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 
Retrofitting case study of RCC structure
Retrofitting case study of RCC structureRetrofitting case study of RCC structure
Retrofitting case study of RCC structure
 
Turning torso
Turning torsoTurning torso
Turning torso
 
Taiyaba rashid jmi
Taiyaba rashid jmiTaiyaba rashid jmi
Taiyaba rashid jmi
 
Pisaaaa
PisaaaaPisaaaa
Pisaaaa
 
Design And Construction Of Cantilevered Retaining Walls
Design And Construction Of Cantilevered Retaining WallsDesign And Construction Of Cantilevered Retaining Walls
Design And Construction Of Cantilevered Retaining Walls
 
Walkie Talkie.pptx
Walkie Talkie.pptxWalkie Talkie.pptx
Walkie Talkie.pptx
 
Pisa
PisaPisa
Pisa
 
Pisa
PisaPisa
Pisa
 
structure analysis by PUC GRP 3
structure analysis by PUC GRP 3structure analysis by PUC GRP 3
structure analysis by PUC GRP 3
 
Deep excavations
Deep excavationsDeep excavations
Deep excavations
 
Micropile
MicropileMicropile
Micropile
 
Temporary Tie Backs in the Building Construction by Bill Morales MSc CCE
Temporary Tie Backs in the Building Construction by Bill Morales MSc CCETemporary Tie Backs in the Building Construction by Bill Morales MSc CCE
Temporary Tie Backs in the Building Construction by Bill Morales MSc CCE
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
S8 trabajo muros de contención-re2
 S8   trabajo muros de contención-re2 S8   trabajo muros de contención-re2
S8 trabajo muros de contención-re2
 

Recently uploaded

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 

Recently uploaded (20)

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 

Leaning tower of Pisa

  • 1. The Enigma of the Leaning Tower of Pisa ‘?’
  • 2. Basic facts about the structure • Height of the structure: 60 meters • Diameter of the foundation: 19.6 meters • Inclination of the tower: 5.5° to the south • Estimated weight of the structure: 14,500 tons
  • 3. Cross section through the tower .
  • 5. Construction timeline • Construction work began on 9th August, 1173 • About quarter construction was achieved by 1178. • There was then a halt in the construction for unknown reasons, but had the construction continued any further, the foundation would have experienced a bearing capacity failure. • The work recommenced in the year 1272.
  • 6. . • In year 1278, the tower’s construction was completed up-to the seventh cornice & then there was again a halt due to the military action. • Next recommencement was in 1360 and the whole construction was finished in 1370. • It took nearly 200 years to finish the construction with two intervals of nearly 100 years each which gave the soil to gain strength.
  • 7. Unpleasant Surprise • In 1838 an architect, Allesandro Della Gherardesca excavated a walk-way around the foundation of the tower known as Catino. • It was intended to expose foundation steps and column plinths. • As the excavation was under the water table, it caused an inflow of water which gave the tower an additional tilt of nearly half degree to the south.
  • 8. History of Tilting • The commission for the stabilization was headed by Prof. John B. Burland. • Due to the absence of any documentary evidence all the clues for the history of tilt were to be inferred from the adjustments made to the masonry. • He put himself in the place of a mason and asked himself, “What is the most practical thing to do when you arrive at a given floor and find that the tower is out-of-the plumb.” • A widely accepted hypothesis is that the masons would always try to keep the masonry layers horizontal.
  • 9. Shape of the axis of the tower deduced from relative inclination of masonry layers
  • 10. Temporary stabilization of the tower • There were two distinct problems that threatened the stability of the tower: 1. Strength of the masonry. 2. Stability of foundation against overturning.
  • 11. Temporary stabilization of the masonry • On the south side of the tower, due to the change in the cross section the masonry blocks were stressed. The exact assessment of stresses was not possible but its effect would have been catastrophic. • This problem was tackled by using plastic covered steel tendons which were bound around the first cornice upto the second floor which helped in reducing the crack sizes and prevented the tower to fail due to buckling.
  • 12. Temporary stabilization of the masonry with light circumferential pre-tensioning
  • 13. Temporary Stabilization for the possible overturning failure • This was achieved by placing the counter weight on the northern side of the tower is four phases so that the response of the tower could be recorded. • Such solution would not have been considered if it had not been recognized that the leaning instability rather than the bearing capacity failure was controlling the behavior of the tower or the north side of the foundation was settling.
  • 14. Counterweight installation to prevent the overturning of tower
  • 15. Observed change of inclination of the tower during application of the counter-weight
  • 16. Choosing the suitable and Permanent Stabilization • For bureaucratic and financial reasons the temporary stabilization took longer than expected. • Because of the severe restraints that have been discussed already measures involving application of concentrated loads to the masonry or underpinning operations beneath the south side of the foundation were ruled out. • Moreover aesthetic and conservation considerations required that the stabilization effect should have an absolute minimal appearance.
  • 17. The three possible approaches for the permanent stabilization After careful consideration of number of possible approaches the commission chose to study three in detail: • Construction of the ground pressing concrete slab to the north of the tower which was to be connected with the post-tensioned concrete ring to be placed around the periphery of the foundation. • Consolidation of the Pancone clayby means of carefully devised electro-osmosis. • The technique of soil extraction which was at that time already in practice in Mexico to reduce differential settlement of number of buildings.
  • 18. Approach #1: Ground pressing slab • ✗ Numeric modeling of the ground pressing slab showed that the tower’s response was uncertain and if anyhow it gave positive results the results were not large enough and the settlements were huge & it required costly civil engineering to proceed with. • RULED OUT.
  • 19. Approach #2: Electro-osmosis • ✗ Full scale model showed that the ground conditions at Pisa were not fit for this method. • RULED OUT
  • 20. Approach #3: Soil Extraction • ✔ This method was best suited and was finally adopted for the final large scale work. • In this method small amounts of soil from predefined locations are removed with the help of inclined drills. • This leaves a cavity at the drilled location and which is gradually filled with the soil in immediate vicinity of the cavity due to the overburden pressure.
  • 21. Schematic representation of the under- excavation process
  • 22. Change in the North-South inclination after the permanent stabilization
  • 23. References • The Enigma of the Leaning Tower of Pisa, Prof. John B. Burland, 1998 • http://casehistories.geoengineer.org • http://home.eng.iastate.edu/