SlideShare a Scribd company logo
Pipe Network Distribution
Md. Mehedi Hassan Masum
Lecturer
Department of Civil Engineering
Port City International University
Department of CEN, PCIU
Department of CE, CUET2
Introduction Result & Discussion Conclusion
Analysis of pipe Network
The following are the most common methods used to analyze the
Grid-system networks:
1.Hardy Cross method.
2.Computer programs (WaterCAD, Epanet, WaterGEMs etc.)
Department of CE, CUET3
Introduction Result & Discussion Conclusion
Hardy Cross Method
Assumptions
1. Water is withdrawn from nodes only, not directly from
pipes.
2. The discharge entering the system will have (+) value, and
the discharge leaving the system will have (-) value.
3. Usually neglect minor losses.
4. Assume flows for each individual pipe in the network.
5. At any junction (node) discharge input is equal to output.
6. Around any loop in the grid, the sum of head losses must
equal to zero
Department of CE, CUET4
Introduction Result & Discussion Conclusion
Hardy Cross Method
Steps
1. Assume values of Q to satisfy 𝑄 = 0.
2. Calculate 𝐻𝑓 from Q using ℎ 𝑓 = 𝐾1 𝑄2
.
3. If ℎ 𝑓 = 0, then the solution is correct.
4. If ℎ 𝑓 ≠ 0, then apply a correction factor, ∆𝑄, to all
Q and repeat from step (2).
5. For practical purposes, the calculation is usually
terminated when ℎ 𝑓< 0.01 m or ∆𝑄 < 1 L/s.
Department of CE, CUET5
Introduction Result & Discussion Conclusion
Hardy Cross Method
Steps
A reasonably efficient value of ∆𝑄 for rapid convergence is
given by;
∆𝑄 = −
𝐻𝐿
2
𝐻𝐿
𝑄
N.B. Head loss can be calculated using the Darcy-Weisbach
equation
ℎ 𝑓 = 𝜆
𝐿
𝐷
𝑉2
2𝑔
= 𝜆
𝐿
𝐷
𝑄2
2𝑔𝐴2
= 𝐾1 𝑄2
Department of CE, CUET6
Introduction Result & Discussion Conclusion
Computer Programs
𝐸𝑃𝐴𝑁𝐸𝑇 𝑊𝑎𝑡𝑒𝑟𝐺𝐸𝑀
Department of CE, CUET7
Introduction Result & Discussion Conclusion
Pipe Network System
𝐶𝑉
𝑆𝐶
𝐵
𝑆𝑀
𝑀
M : Mains
SM : Sub Main
B : Branch
SC :Service Connection
CV :CUTOFF Valve
Department of CE, CUET8
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 01: 𝑃𝑙𝑎𝑛 𝑜𝑓 𝑎 𝑝𝑜𝑤𝑒𝑟 𝑝𝑙𝑎𝑛𝑡
Department of CE, CUET9
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 02: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚
Department of CE, CUET10
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 03: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚
𝑊𝑇 − 1𝑊𝑇 − 2
Department of CE, CUET11
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 04: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑊𝑇 − 1)
Department of CE, CUET12
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 05: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑊𝑇 − 2)
Department of CE, CUET13
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 06: 𝐿𝑜𝑜𝑝 𝑠𝑒𝑙𝑒𝑐𝑡𝑒𝑑 𝑓𝑜𝑟 𝑎𝑛𝑎𝑙𝑦𝑠𝑖𝑠
Department of CE, CUET14
Introduction Result & Discussion Conclusion
Initial Assumptions
47.12 𝑙/𝑠𝑒𝑐
20𝑙/𝑠𝑒𝑐
10 𝑙/𝑠𝑒𝑐
10𝑙/𝑠𝑒𝑐
10 𝑙/𝑠𝑒𝑐
20 𝑙/𝑠𝑒𝑐
𝐴 𝐵
𝐶
𝐷
Department of CE, CUET15
Pipe name Dia (m)
Length
(m)
hf (m) Q (L/sec) hf/Q
AB 0.15 219.512 0.305773 -10 -30.5773
BC 0.2 60.98 0.08063 -20 -4.03149
CD 0.2 219.51 0.533681 27.12 19.67849
DA 0.15 115.85 0.161375 10 16.13754
Sum 1.081459 1.207208
First Trial
= -0.44792
Introduction Result & Discussion Conclusion
Department of CE, CUET16
Pipe name Dia (m)
Length
(m)
hf (m) Q (L/sec) hf/Q
AB 0.15 219.512 0.23807 -8.82374 -26.9806
BC 0.2 60.98 0.070918 -18.7568 -3.78089
CD 0.2 219.51 0.58373 28.36318 20.58055
DA 0.15 115.85 0.203993 11.24318 18.14373
Sum 1.096711 7.962748
First Trial
= -0.06887
Introduction Result & Discussion Conclusion
Department of CE, CUET17
Introduction Result & Discussion Conclusion
Final Discharge
47.12 𝑙/𝑠𝑒𝑐
18.76𝑙/𝑠𝑒𝑐
8.82 𝑙/𝑠𝑒𝑐
11.24𝑙/𝑠𝑒𝑐
9.94 𝑙/𝑠𝑒𝑐
20.06 𝑙/𝑠𝑒𝑐
𝐴 𝐵
𝐶
𝐷
Sewer Network Distribution
Department of CE, CUET
Md. Mehedi Hassan Masum
Lecturer
Department of Civil Engineering
Port City International University
Department of CE, CUET19
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 01: 𝑃𝑙𝑎𝑛 𝑜𝑓 𝑎 𝑝𝑜𝑤𝑒𝑟 𝑝𝑙𝑎𝑛𝑡
Department of CE, CUET20
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 03: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚
Department of CE, CUET21
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 04: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑃 − 1)
Department of CE, CUET22
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 05: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑃 − 2)
Department of CE, CUET23
Introduction Result & Discussion Conclusion
𝐹𝑖𝑔 06: 𝐿𝑜𝑜𝑝 𝑠𝑒𝑙𝑒𝑐𝑡𝑒𝑑 𝑓𝑜𝑟 𝑎𝑛𝑎𝑙𝑦𝑠𝑖𝑠
Department of CE, CUET24
Introduction Result & Discussion Conclusion
Pipe
Sub-
Area
Population
Per capita
consumpti
on (lpcd)
Water
Demand
(m3/day)
Peak
factor
% of
wastewater
Total
wastewater
(m3/day)
P1
A1 432 135 58.32 2.50 70 102.06
A2 768 135 103.68 2.50 70 181.44
A9 384 135 51.84 3.00 90 139.97
P2
A3 768 135 103.68 2.50 70 181.44
A4 768 135 103.68 2.50 70 181.44
P3
A5 1152 135 155.52 2.50 70 272.16
A6 1152 135 155.52 2.50 70 272.16
A7 1152 135 155.52 2.50 70 272.16
A8 300 100 30.00 3.00 90 81.00
Total 917.76 23.50 1683.83
Table: Wastewater Generation from household
Department of CE, CUET25
Introduction Result & Discussion Conclusion
Table: Wastewater Generation from household
Pipe Sub-Area Area (sq.m) Area (ha)
Peak
infiltration
factor
(m3/ha-day)
Infiltration , I
(m3/day)
P1
A1 7432.2400 0.7432
8.7500 22.6962
A2 7618.0460 0.7618
A9 10888.2316 1.0888
P2
A3 7543.7236 0.7544
8.7500 13.1690
A4 7506.5624 0.7507
P3
A5 7580.8848 0.7581
8.7500 24.8097
A6 7618.0460 0.7618
A7 7432.2400 0.7432
A8 5722.8248 0.5723
Total 69342.7992 6.9343 60.6749
Department of CE, CUET26
Introduction Result & Discussion Conclusion
Total Wastewater Generation
Total wastewater generation =
1683.73+60.6749 = 1744.59 𝑚3/𝑑𝑎𝑦
Department of CE, CUET27
Department of CE, CUET28

More Related Content

What's hot

sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenance
Manish Goyal
 
Design of sewers
Design of sewersDesign of sewers
Design of sewers
AnkitTurambekar
 
hydro chapter_4_b_pipe_network_by louy Al hami
hydro  chapter_4_b_pipe_network_by louy Al hami hydro  chapter_4_b_pipe_network_by louy Al hami
hydro chapter_4_b_pipe_network_by louy Al hami
Louy Alhamy
 
Water supply appurtenances
Water supply appurtenancesWater supply appurtenances
Water supply appurtenances
Ajay B.K
 
Water distribution System In Water Supply Schemes
Water distribution System In Water Supply Schemes Water distribution System In Water Supply Schemes
Water distribution System In Water Supply Schemes
Vaibhav Kambale
 
Gradually varied flow
Gradually varied flowGradually varied flow
Gradually varied flow
GAJA GOVIND BABU
 
L 9 pumping stations
L 9 pumping stationsL 9 pumping stations
L 9 pumping stations
Dr. shrikant jahagirdar
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
Damalla Rams
 
Pipe network analysis with examples
Pipe network analysis with examplesPipe network analysis with examples
Pipe network analysis with examples
Mohsin Siddique
 
Water and waste water oep
Water and waste water oep Water and waste water oep
Water and waste water oep
nemilgandhi
 
Collection and estimation of sewage
Collection and estimation of sewageCollection and estimation of sewage
Collection and estimation of sewage
Bibhabasu Mohanty
 
Water hammer in pipe_AMIT
Water hammer in pipe_AMITWater hammer in pipe_AMIT
Water hammer in pipe_AMIT
Amit Sharma
 
Flow Through Pipes - Hydraulics
Flow Through Pipes - HydraulicsFlow Through Pipes - Hydraulics
Flow Through Pipes - Hydraulics
Engr. M Jalal Sarwar
 
Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]
Prakash Kumar Sekar
 
Quantity of Water
Quantity of WaterQuantity of Water
Quantity of Water
ChandanGupta201
 
MAINTENANCE OF SEWAGE SYSTEM.pptx
MAINTENANCE OF SEWAGE SYSTEM.pptxMAINTENANCE OF SEWAGE SYSTEM.pptx
MAINTENANCE OF SEWAGE SYSTEM.pptx
muthunayake1
 
Introduction, water demand
Introduction, water demandIntroduction, water demand
Introduction, water demand
GARRE RAVI KUMAR
 
Water distribution system design report
Water distribution system design reportWater distribution system design report
Water distribution system design report
Muhammad Magsi
 
Intake structures-Introduction
Intake structures-IntroductionIntake structures-Introduction
Intake structures-Introduction
Deepak Paithankar
 
L 24 filtration
L 24 filtrationL 24 filtration
L 24 filtration
Dr. shrikant jahagirdar
 

What's hot (20)

sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenance
 
Design of sewers
Design of sewersDesign of sewers
Design of sewers
 
hydro chapter_4_b_pipe_network_by louy Al hami
hydro  chapter_4_b_pipe_network_by louy Al hami hydro  chapter_4_b_pipe_network_by louy Al hami
hydro chapter_4_b_pipe_network_by louy Al hami
 
Water supply appurtenances
Water supply appurtenancesWater supply appurtenances
Water supply appurtenances
 
Water distribution System In Water Supply Schemes
Water distribution System In Water Supply Schemes Water distribution System In Water Supply Schemes
Water distribution System In Water Supply Schemes
 
Gradually varied flow
Gradually varied flowGradually varied flow
Gradually varied flow
 
L 9 pumping stations
L 9 pumping stationsL 9 pumping stations
L 9 pumping stations
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 
Pipe network analysis with examples
Pipe network analysis with examplesPipe network analysis with examples
Pipe network analysis with examples
 
Water and waste water oep
Water and waste water oep Water and waste water oep
Water and waste water oep
 
Collection and estimation of sewage
Collection and estimation of sewageCollection and estimation of sewage
Collection and estimation of sewage
 
Water hammer in pipe_AMIT
Water hammer in pipe_AMITWater hammer in pipe_AMIT
Water hammer in pipe_AMIT
 
Flow Through Pipes - Hydraulics
Flow Through Pipes - HydraulicsFlow Through Pipes - Hydraulics
Flow Through Pipes - Hydraulics
 
Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]
 
Quantity of Water
Quantity of WaterQuantity of Water
Quantity of Water
 
MAINTENANCE OF SEWAGE SYSTEM.pptx
MAINTENANCE OF SEWAGE SYSTEM.pptxMAINTENANCE OF SEWAGE SYSTEM.pptx
MAINTENANCE OF SEWAGE SYSTEM.pptx
 
Introduction, water demand
Introduction, water demandIntroduction, water demand
Introduction, water demand
 
Water distribution system design report
Water distribution system design reportWater distribution system design report
Water distribution system design report
 
Intake structures-Introduction
Intake structures-IntroductionIntake structures-Introduction
Intake structures-Introduction
 
L 24 filtration
L 24 filtrationL 24 filtration
L 24 filtration
 

Similar to L 5 pipe_network_analysis

L 6 sewer_design
L 6 sewer_designL 6 sewer_design
L 6 sewer_design
MEHEDIMASUM2
 
Comparison of MOC and Lax FDE for simulating transients in Pipe Flows
Comparison of  MOC and Lax FDE for simulating transients in Pipe FlowsComparison of  MOC and Lax FDE for simulating transients in Pipe Flows
Comparison of MOC and Lax FDE for simulating transients in Pipe Flows
IRJET Journal
 
A suggestion of optimization process for water pipe networks design
A suggestion of optimization process for water pipe networks designA suggestion of optimization process for water pipe networks design
A suggestion of optimization process for water pipe networks design
Medhat Elzahar
 
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...
IAEME Publication
 
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...
Naimesh Rama
 
FYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdfFYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdf
sauravdesignnedits
 
L 7 plumbing_design
L 7 plumbing_designL 7 plumbing_design
L 7 plumbing_design
MEHEDIMASUM2
 
SEM IV 15 Civil Engineering syllabus.pdf
SEM IV 15 Civil Engineering syllabus.pdfSEM IV 15 Civil Engineering syllabus.pdf
SEM IV 15 Civil Engineering syllabus.pdf
gopalkumar91649
 
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...
IOSR Journals
 
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
Hossam Shafiq I
 
A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...
IJEECSIAES
 
A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...
nooriasukmaningtyas
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...
IAEME Publication
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...
IAEME Publication
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...
IAEME Publication
 
Design of a Subsequent Water Detection System Controlled by the Microcontroller
Design of a Subsequent Water Detection System Controlled by the MicrocontrollerDesign of a Subsequent Water Detection System Controlled by the Microcontroller
Design of a Subsequent Water Detection System Controlled by the Microcontroller
Nooria Sukmaningtyas
 
Load flow studies
Load flow studiesLoad flow studies
Load flow studies
Darshil Shah
 
report.pdf
report.pdfreport.pdf
report.pdf
KarnaPatel17
 
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...
AnweshBussa
 
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...
Hossam Shafiq I
 

Similar to L 5 pipe_network_analysis (20)

L 6 sewer_design
L 6 sewer_designL 6 sewer_design
L 6 sewer_design
 
Comparison of MOC and Lax FDE for simulating transients in Pipe Flows
Comparison of  MOC and Lax FDE for simulating transients in Pipe FlowsComparison of  MOC and Lax FDE for simulating transients in Pipe Flows
Comparison of MOC and Lax FDE for simulating transients in Pipe Flows
 
A suggestion of optimization process for water pipe networks design
A suggestion of optimization process for water pipe networks designA suggestion of optimization process for water pipe networks design
A suggestion of optimization process for water pipe networks design
 
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...
CREATING A NEW CRITICAL DEPTH EQUATION FOR GRADUALLY VARIED FLOW IN CIRCULAR ...
 
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...
IMPROVED MPPT METHOD TO INCREASE ACCURACY & SPEED IN PHOTOVOLTAIC UNDER VARIA...
 
FYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdfFYP Review 3 Presentation about EV c.pdf
FYP Review 3 Presentation about EV c.pdf
 
L 7 plumbing_design
L 7 plumbing_designL 7 plumbing_design
L 7 plumbing_design
 
SEM IV 15 Civil Engineering syllabus.pdf
SEM IV 15 Civil Engineering syllabus.pdfSEM IV 15 Civil Engineering syllabus.pdf
SEM IV 15 Civil Engineering syllabus.pdf
 
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...
Optimization of Threshold Voltage for 65nm PMOS Transistor using Silvaco TCAD...
 
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
13 Fundamentals of Signal Timing and Design: Pretimed Signal (Traffic Enginee...
 
A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...
 
A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...A simple faulted phase-based fault distance estimation algorithm for a loop d...
A simple faulted phase-based fault distance estimation algorithm for a loop d...
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...
 
Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...Effect of inertia weight functions of pso in optimization of water distributi...
Effect of inertia weight functions of pso in optimization of water distributi...
 
Design of a Subsequent Water Detection System Controlled by the Microcontroller
Design of a Subsequent Water Detection System Controlled by the MicrocontrollerDesign of a Subsequent Water Detection System Controlled by the Microcontroller
Design of a Subsequent Water Detection System Controlled by the Microcontroller
 
Load flow studies
Load flow studiesLoad flow studies
Load flow studies
 
report.pdf
report.pdfreport.pdf
report.pdf
 
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...
proposedfaultdetectiononoverheadtransmissionlineusingparticleswarmoptimizatio...
 
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...
5-Modal Split & Traffic Assignment-( Transportation and Traffic Engineering D...
 

More from MEHEDIMASUM2

L 4 pump_capacity
L 4 pump_capacityL 4 pump_capacity
L 4 pump_capacity
MEHEDIMASUM2
 
L 2 wastewater_treatment
L 2 wastewater_treatmentL 2 wastewater_treatment
L 2 wastewater_treatment
MEHEDIMASUM2
 
L 1 organogram_demand calculation
L 1 organogram_demand calculationL 1 organogram_demand calculation
L 1 organogram_demand calculation
MEHEDIMASUM2
 
L 8 septic_tank
L 8 septic_tankL 8 septic_tank
L 8 septic_tank
MEHEDIMASUM2
 
L 3 well_design
L 3 well_designL 3 well_design
L 3 well_design
MEHEDIMASUM2
 
L6 infiltrationr rate calculation
L6 infiltrationr rate calculationL6 infiltrationr rate calculation
L6 infiltrationr rate calculation
MEHEDIMASUM2
 
L5 infiltration
L5 infiltrationL5 infiltration
L5 infiltration
MEHEDIMASUM2
 
L3 evaporation
L3 evaporationL3 evaporation
L3 evaporation
MEHEDIMASUM2
 
L2 precipitation
L2 precipitationL2 precipitation
L2 precipitation
MEHEDIMASUM2
 
L4 stream flow
L4 stream flowL4 stream flow
L4 stream flow
MEHEDIMASUM2
 
L8 unit hydrograph
L8 unit hydrographL8 unit hydrograph
L8 unit hydrograph
MEHEDIMASUM2
 
L7 hydrograph
L7 hydrographL7 hydrograph
L7 hydrograph
MEHEDIMASUM2
 
L1 introduction
L1 introductionL1 introduction
L1 introduction
MEHEDIMASUM2
 

More from MEHEDIMASUM2 (13)

L 4 pump_capacity
L 4 pump_capacityL 4 pump_capacity
L 4 pump_capacity
 
L 2 wastewater_treatment
L 2 wastewater_treatmentL 2 wastewater_treatment
L 2 wastewater_treatment
 
L 1 organogram_demand calculation
L 1 organogram_demand calculationL 1 organogram_demand calculation
L 1 organogram_demand calculation
 
L 8 septic_tank
L 8 septic_tankL 8 septic_tank
L 8 septic_tank
 
L 3 well_design
L 3 well_designL 3 well_design
L 3 well_design
 
L6 infiltrationr rate calculation
L6 infiltrationr rate calculationL6 infiltrationr rate calculation
L6 infiltrationr rate calculation
 
L5 infiltration
L5 infiltrationL5 infiltration
L5 infiltration
 
L3 evaporation
L3 evaporationL3 evaporation
L3 evaporation
 
L2 precipitation
L2 precipitationL2 precipitation
L2 precipitation
 
L4 stream flow
L4 stream flowL4 stream flow
L4 stream flow
 
L8 unit hydrograph
L8 unit hydrographL8 unit hydrograph
L8 unit hydrograph
 
L7 hydrograph
L7 hydrographL7 hydrograph
L7 hydrograph
 
L1 introduction
L1 introductionL1 introduction
L1 introduction
 

Recently uploaded

Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 

Recently uploaded (20)

Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 

L 5 pipe_network_analysis

  • 1. Pipe Network Distribution Md. Mehedi Hassan Masum Lecturer Department of Civil Engineering Port City International University Department of CEN, PCIU
  • 2. Department of CE, CUET2 Introduction Result & Discussion Conclusion Analysis of pipe Network The following are the most common methods used to analyze the Grid-system networks: 1.Hardy Cross method. 2.Computer programs (WaterCAD, Epanet, WaterGEMs etc.)
  • 3. Department of CE, CUET3 Introduction Result & Discussion Conclusion Hardy Cross Method Assumptions 1. Water is withdrawn from nodes only, not directly from pipes. 2. The discharge entering the system will have (+) value, and the discharge leaving the system will have (-) value. 3. Usually neglect minor losses. 4. Assume flows for each individual pipe in the network. 5. At any junction (node) discharge input is equal to output. 6. Around any loop in the grid, the sum of head losses must equal to zero
  • 4. Department of CE, CUET4 Introduction Result & Discussion Conclusion Hardy Cross Method Steps 1. Assume values of Q to satisfy 𝑄 = 0. 2. Calculate 𝐻𝑓 from Q using ℎ 𝑓 = 𝐾1 𝑄2 . 3. If ℎ 𝑓 = 0, then the solution is correct. 4. If ℎ 𝑓 ≠ 0, then apply a correction factor, ∆𝑄, to all Q and repeat from step (2). 5. For practical purposes, the calculation is usually terminated when ℎ 𝑓< 0.01 m or ∆𝑄 < 1 L/s.
  • 5. Department of CE, CUET5 Introduction Result & Discussion Conclusion Hardy Cross Method Steps A reasonably efficient value of ∆𝑄 for rapid convergence is given by; ∆𝑄 = − 𝐻𝐿 2 𝐻𝐿 𝑄 N.B. Head loss can be calculated using the Darcy-Weisbach equation ℎ 𝑓 = 𝜆 𝐿 𝐷 𝑉2 2𝑔 = 𝜆 𝐿 𝐷 𝑄2 2𝑔𝐴2 = 𝐾1 𝑄2
  • 6. Department of CE, CUET6 Introduction Result & Discussion Conclusion Computer Programs 𝐸𝑃𝐴𝑁𝐸𝑇 𝑊𝑎𝑡𝑒𝑟𝐺𝐸𝑀
  • 7. Department of CE, CUET7 Introduction Result & Discussion Conclusion Pipe Network System 𝐶𝑉 𝑆𝐶 𝐵 𝑆𝑀 𝑀 M : Mains SM : Sub Main B : Branch SC :Service Connection CV :CUTOFF Valve
  • 8. Department of CE, CUET8 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 01: 𝑃𝑙𝑎𝑛 𝑜𝑓 𝑎 𝑝𝑜𝑤𝑒𝑟 𝑝𝑙𝑎𝑛𝑡
  • 9. Department of CE, CUET9 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 02: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚
  • 10. Department of CE, CUET10 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 03: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 𝑊𝑇 − 1𝑊𝑇 − 2
  • 11. Department of CE, CUET11 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 04: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑊𝑇 − 1)
  • 12. Department of CE, CUET12 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 05: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑊𝑇 − 2)
  • 13. Department of CE, CUET13 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 06: 𝐿𝑜𝑜𝑝 𝑠𝑒𝑙𝑒𝑐𝑡𝑒𝑑 𝑓𝑜𝑟 𝑎𝑛𝑎𝑙𝑦𝑠𝑖𝑠
  • 14. Department of CE, CUET14 Introduction Result & Discussion Conclusion Initial Assumptions 47.12 𝑙/𝑠𝑒𝑐 20𝑙/𝑠𝑒𝑐 10 𝑙/𝑠𝑒𝑐 10𝑙/𝑠𝑒𝑐 10 𝑙/𝑠𝑒𝑐 20 𝑙/𝑠𝑒𝑐 𝐴 𝐵 𝐶 𝐷
  • 15. Department of CE, CUET15 Pipe name Dia (m) Length (m) hf (m) Q (L/sec) hf/Q AB 0.15 219.512 0.305773 -10 -30.5773 BC 0.2 60.98 0.08063 -20 -4.03149 CD 0.2 219.51 0.533681 27.12 19.67849 DA 0.15 115.85 0.161375 10 16.13754 Sum 1.081459 1.207208 First Trial = -0.44792 Introduction Result & Discussion Conclusion
  • 16. Department of CE, CUET16 Pipe name Dia (m) Length (m) hf (m) Q (L/sec) hf/Q AB 0.15 219.512 0.23807 -8.82374 -26.9806 BC 0.2 60.98 0.070918 -18.7568 -3.78089 CD 0.2 219.51 0.58373 28.36318 20.58055 DA 0.15 115.85 0.203993 11.24318 18.14373 Sum 1.096711 7.962748 First Trial = -0.06887 Introduction Result & Discussion Conclusion
  • 17. Department of CE, CUET17 Introduction Result & Discussion Conclusion Final Discharge 47.12 𝑙/𝑠𝑒𝑐 18.76𝑙/𝑠𝑒𝑐 8.82 𝑙/𝑠𝑒𝑐 11.24𝑙/𝑠𝑒𝑐 9.94 𝑙/𝑠𝑒𝑐 20.06 𝑙/𝑠𝑒𝑐 𝐴 𝐵 𝐶 𝐷
  • 18. Sewer Network Distribution Department of CE, CUET Md. Mehedi Hassan Masum Lecturer Department of Civil Engineering Port City International University
  • 19. Department of CE, CUET19 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 01: 𝑃𝑙𝑎𝑛 𝑜𝑓 𝑎 𝑝𝑜𝑤𝑒𝑟 𝑝𝑙𝑎𝑛𝑡
  • 20. Department of CE, CUET20 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 03: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚
  • 21. Department of CE, CUET21 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 04: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑃 − 1)
  • 22. Department of CE, CUET22 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 05: 𝑁𝑒𝑡𝑤𝑜𝑟𝑘 𝑑𝑖𝑎𝑔𝑟𝑎𝑚 (𝑃 − 2)
  • 23. Department of CE, CUET23 Introduction Result & Discussion Conclusion 𝐹𝑖𝑔 06: 𝐿𝑜𝑜𝑝 𝑠𝑒𝑙𝑒𝑐𝑡𝑒𝑑 𝑓𝑜𝑟 𝑎𝑛𝑎𝑙𝑦𝑠𝑖𝑠
  • 24. Department of CE, CUET24 Introduction Result & Discussion Conclusion Pipe Sub- Area Population Per capita consumpti on (lpcd) Water Demand (m3/day) Peak factor % of wastewater Total wastewater (m3/day) P1 A1 432 135 58.32 2.50 70 102.06 A2 768 135 103.68 2.50 70 181.44 A9 384 135 51.84 3.00 90 139.97 P2 A3 768 135 103.68 2.50 70 181.44 A4 768 135 103.68 2.50 70 181.44 P3 A5 1152 135 155.52 2.50 70 272.16 A6 1152 135 155.52 2.50 70 272.16 A7 1152 135 155.52 2.50 70 272.16 A8 300 100 30.00 3.00 90 81.00 Total 917.76 23.50 1683.83 Table: Wastewater Generation from household
  • 25. Department of CE, CUET25 Introduction Result & Discussion Conclusion Table: Wastewater Generation from household Pipe Sub-Area Area (sq.m) Area (ha) Peak infiltration factor (m3/ha-day) Infiltration , I (m3/day) P1 A1 7432.2400 0.7432 8.7500 22.6962 A2 7618.0460 0.7618 A9 10888.2316 1.0888 P2 A3 7543.7236 0.7544 8.7500 13.1690 A4 7506.5624 0.7507 P3 A5 7580.8848 0.7581 8.7500 24.8097 A6 7618.0460 0.7618 A7 7432.2400 0.7432 A8 5722.8248 0.5723 Total 69342.7992 6.9343 60.6749
  • 26. Department of CE, CUET26 Introduction Result & Discussion Conclusion Total Wastewater Generation Total wastewater generation = 1683.73+60.6749 = 1744.59 𝑚3/𝑑𝑎𝑦