SlideShare a Scribd company logo
1 of 5
Download to read offline
Design of Transmission Lines in India : a Review of Multiple
Swing Angle-clearance Combinations
Dr V N Rikh, Fellow
                     Proper live metal clearances have to be maintained under various swing angles of the suspension insulator
                     strings/jumper loops on a tower, in order to ensure a reliable performance of the transmission lines. The required
                     swing angle-clearance combinations for lines of different voltages are determined on the basis of a pre-specified
                     criterion of flashover probability. These combinations decide horizontal and vertical spacing of the power
                     conductors and thereby determine the tower configuration, weight and cost. Presently three to five swing angle-
                     clearance combinations are commonly specified for Indian transmission lines of each voltage. On the other hand,
                     in many countries generally only two or three combinations are specified. Based on detailed analysis this paper
                     attempts to prove that if even two judiciously selected swing angle-clearance combinations are used, they would
                     adequately determine optimum tower configuration and the remaining extra combinations presently specified could
                     be dispensed with, without jeopardizing the reliability of the lines.

                     Keywords : Transmission line; Line insulation; Swing angle; Line metal clearances

NOTATIONS                                                                         INTRODUCTION
  C0 , C15 , C10, etc : location of critical live metal part of the               One of the most important criteria for ensuring a reliable perform-
                        phase power conductor with swing angles                   ance of transmission lines under all weather conditions, is to
                        of 0°, 15°, 30° etc                                       ensure that proper live metal (conductor to nearest earthed parts
  L0 , L15 , L30, etc : live-metal clearances specified for swing                 of the tower structure) clearances are maintained under various
                        angles of 0°, 15°, 30° etc, cm                            angles (depending on wind speeds) of swing of the suspension
  c                   : minimum clearance between the live metal                  insulator strings for a suspension tower (or the jumper loops for
                        parts phase power conductor and the nearest               a tension tower). The required live-metal clearances for different
                        (carthed) part of the tower structure or live-            angles of swing of suspension insulator strings (or jumper loops
                        metal clearance, cm                                       for tension towers) are determined on the basis of a pre-specified
  h                   : half width of the tower hamper at the critical            criterion of flashover probability. When the suspension strings,
                        point (where the clearance arc from the                   supporting the power conductors, hang vertically under ‘no-
                        swung, live metal parts touches it), cm                   wind’ conditions, the live-metal clearance is maintained at a value
  l                   : swinging length of the suspension string                  that ensures a probability of flashover across the air-gap within a
                        duly adjusted for any longitudinal (to the                pre-specified value of, say, less than 2%. As the string/conductor
                                                                                  attachment point, swings toward the tower body under the influ-
                        string axis) projection of the guard ring/
                                                                                  ence of the wind, the critical value of flashover voltage gradient
                        bandle spacer, cm
                                                                                  across the gap correspondingly increases due to faster de-ioniza-
  lo                  : length of hanger of the suspension                        tion of the air. This results in a reduced requirement of live-metal
                        string, cm                                                clearances under higher wind velocities (and consequently bigger
  r                   : transverse (to the string axis) projection, if            swing angles of the string/conductor attachment points) to ensure
                        any, of the critical point of the guard                   the same level of pre-specified flashover probability across the
                        ring/bundle spacer, cm                                    air- gap.
  α                   : angle at which the uppermost (nearest to the
                        conductor) structural member of the under-                The swing angle-clearance combinations presently adopted for
                        neath cross-arm is inclined to horizontal                 Indian transmission lines are based on the aforesaid logic.
                        plane, degrees                                            Usually three to five swing angle-clearance combinations are
                                                                                  specified for transmission lines of each voltage on the basis of
  α′                  : angle at which the nearest structural mem-                detailed analysis of prevailing weather conditions and flashover
                        ber of the tower hamper is inclined to the                characteristics of air-gaps. The values of these swing angle-
                        vertical plane, degrees
                                                                                  clearance combinations commonly specified in India1, are shown
  θ                   : angle of swing of the suspension insulator                in Table 1.
                        string or of the jumper loop of tension insu-
                        lator string, degrees                                     These combinations have yielded a reasonably satisfactory per-
  Φ                   : tan − 1 [r ⁄ √ (r2 + l2)]                                 formance of the transmission lines in this country over several
                                                                                 decades.
Dr V N Rikh resides at 188-A, Saket, Meerut 250 003.                              The 66kV, 132kV and 220kV transmission lines in India (single
This paper was received on September 26, 2003. Written discussion on this paper   circuit as well as double circuit) commonly use self-supporting
will be received until July 31, 2004.
                                                                                  barrel type towers. However, while 400kV double circuit Indian

Vol 85, May 2004                                                                                                                                   21
Table 1 Swing angle-clearance combinations adopted for Indian             On the other hand, with a given value of swing angle-clearance
        transmission lines                                                combination;
 Swing Angle, degree             Live Metal Clearance, mm                   l    An increase in the outward (towards the conductor, eg, in
                        66 kV       132 kV       220 kV         400 kV
                                                                                 the Barrel type towers)) slope α′ of the tower hamper,
                        Lines        Lines        Lines          Lines           increases the horizontal spacing while an increased inward
          0              915         1530         2130          3050             (away from the conductor, eg, in a corset type tower) slope
         15              915         1530         2130           —               α′ of the tower hamper reduces the horizontal spacing of the
         22               —           —            —            3050
                                                                                 conductors, and
         30              760         1370         1830           —          l    An increase in the upward (towards the conductor) slope α
         44               —           —            —            1860             of the uppermost member of underneath cross-arm results in
         45              610         1220         1675           —
                                                                                 an increased vertical spacing of the conductors. As per
                                                                                 prevalent design practice, a downward slope of the
lines also use barrel type towers, the 400kV single circuit lines                underneath cross-arm member is not adopted.
commonly use corset (or Wasp-waisted) type of towers.                     The effect of the slopes (towards the phase conductor/s) of the
A study of swing angle-clearance combinations adopted in other            tower hamper as well as that of the nearest member of underneath
countries reveals that, in many countries, generally only two and         cross arm, on the horizontal and vertical conductor spacings, is
sometimes a maximum of three, combinations are specified for              illustrated for a Barrel type tower in Figure 1.
designing tower configuration. This paper therefore attempts to           In case of a corset type tower, the slope of Tower Hamper is away
analyze the impact of each of the combinations (shown in Table            from the (outer) phase conductor/s and its effect on the horizontal
1) on the tower configuration for Indian transmission lines, and          conductor can be visualized from a typical Figure 2. As the corset
determine whether all these combinations play a critical role in          type tower is used for single circuit lines (usually of 400kV), there
determining tower configuration/s or some of these (combina-              is no vertical formation of the conductors.
tions) could be dispensed with, without jeopardizing reliability of
the transmission lines.                                                   IMPACT OF SWING ANGLE-CLEARANCE
                                                                          COMBINATIONS ON THE TOWER CONFIGURATION
PARAMETERS AFFECTING TOWER
CONFIGURATION                                                             As explained above, for any given values of α and α′, each
                                                                          swing angle-clearance combination will require certain mini-
The swing angle-clearance combinations, along with the follow-            mum values of horizontal and vertical spacings of the power
ing two important design parameters help determine the horizon-
tal, as well as the vertical, spacing of the power conductors and,
in turn, help decide the configuration, dimensions and therefore
the weight/cost of the towers;
  l    The slope α and α′ (to the vertical plane) of the outermost
       (nearest to the conductor) structural member of the tower
       hamper, and
  l    The slope α (to the horizontal plane) of the uppermost
       (nearest to the conductor) structural member of the
       underneath cross-arm.
The values of α and α′ are determined in the process of economic
optimization of tower configuration.
For any given values of α′,
  l    An increase in (inward) swing-angle, θ, of the insulator string
       (or, jumper loop, for a tension tower) requires a
       corresponding increase in the horizontal spacing of the phase
       conductor/s maintain the specified live-metal clearance,
       Similarly, any increase in the live-metal clearance, c, requires
       a corresponding increase in the horizontal spacing.
  l    The requirement of vertical spacing of the phase conductors
       , however, decreases with any increase in (inward)
       swing-angle, θ, of the insulator string (or, jumper loop, for a
       tension tower), though an increase in the live-metal clearance
       c, still requires a corresponding increase in the vertical         Figure 1 Effect of tower hamper and X-arm slopes on conductor spacings
       spacing.                                                                   for barrel type tower


22                                                                                                                            IE(I) Journal-ID

                                                                            Cv = (√ 2 + r2) cos (θ ± Φ + sin (θ ± Φ tan α +
                                                                                                                                         
                                                                                  
                                                                                  l                                      
                                                                                                                   c sec α + l0 (2)
                                                                          Using these expressions, the requirement of horizontal spacings
                                                                          for each specified swing angle (with corresponding live metal
                                                                          clearance) for the aforesaid range of α′, are shown in the follow-
                                                                          ing figures :
                                                                            l     Figure 3(a) - 66kV lines (barrel type towers)
                                                                            l     Figure 3(b) - 132kV lines (barrel type towers)
                                                                            l     Figure 3(c) - 220 kV lines (barrel type towers)
                                                                            l     Figure 3(d) - 400 kV double circuit lines with barrel type
                                                                                  towers
                                                                            l     Figure 3(e) - 400 kV single circuit lines with corset type
                                                                                  towers




Figure 2 Effect of slope of tower hamper on conductor spacing, Ch , for
         corset type tower                                                Figure 3(a) Variation of horizontal spacing, Ch , with the slope of Tower
                                                                                     Hamper (66 kV lines)
conductors. If the horizontal and vertical spacing requirements
for each of the three (or four) swing angle-clearance combinations
specified for the lines of a particular voltage (eg, 66kV) as above
are determined, it can be seen that only one of the combinations
(generally, with higher swing angle) will be critical for the re-
quirement of (maximum) horizontal spacing while some other
combination (generally with lower seing angle) will be critical for
the vertical spacing, for the given values of α and α′. Thus, for
the selected values of α and α′, only two combinations would
normally be critical for fixing tower configuration while the
remaining combinations, will require spacings which are less than
the critical values and thus play no part in deciding the tower
configuration.                                                            Figure 3(b) Variation of horizontal spacing, Ch , with the slope of Tower
                                                                                     Hamper (132 kV lines)
The commonly used, practical value of α is between 0° and +15°
while the value of α′ may range between +5° and +20° for Barrel
type towers and between 0° and −20° for corset type tower. If the
critically of all the swing angle-clearance combinations (specified
for a particular line voltage) could be examined over the aforesaid
practical range of α and α′, it will reveal whether all the specified
combination do play a determining role for tower configuration
or one/two of them, are not critical and could be dispensed with.
Considering a typical case of suspension tower, it can be shown
that the horizontal and vertical spacings of the phase conductors
are given by :
                                                               
  Ch = 2 [(√ 2 + r2) sin (θ ± Φ) + cos (θ ± Φ) tan α′ +
           
           l                                                           Figure 3(c) Variation of horizontal spacing, Ch , with the slope of Tower
                                  l0 tan α′ + c sec α′ + h] (1)                      Hamper (220 kV lines)


Vol 85, May 2004                                                                                                                                      23
Figure 3(d) Variation of horizontal spacing, Ch , with the slope of Tower
                                                                            Figure 4(b) Variation of vertical spacing, Cv, with the slope of
           Hamper (400 kv line — barrel type tower)
                                                                                       underneath X-arm for (132 kV lines)




Figure 3(e) Variation of horizontal spacing, Ch , with the slope of Tower
           Hamper (400 kV line — corset type tower)
                                                                            Figure 4(c) Variation of vertical spacing, Cv, with the slope of
Similarly, the requirement of vertical spacings for each specified                     underneath X-arm for (220 kV lines)
swing angle of α, are shown in the following Figures (there being
no vertical spacing for a corset type tower):
  l     Figure 4(a) - 66kV lines (barrel type towers)
  l     Figure 4(b) - 132 kV lines (barrel type towers)
  l     Figure 4(c) - 220 kV lines (barrel type towers)
  l     Figure 4(d) - 400 kV double circuit lines with barrel type
        towers
The aforesaid analysis is based on the values of relevant dimen-
sions as shown in Table 2.

                                                                            Figure 4(d) Variation of vertical spacing, Cv, with the slope of
                                                                                       underneath X-arm for (400 kV lines — barrel type tower)

                                                                            Table 2 Typical values of relevant dimensions
                                                                                          Item                     Typical Value for Line Voltage

                                                                                                                66 kV     132 kV     220 kV    400 kV
                                                                             Swing length of suspension          97         163        234      385
                                                                             string, l, cm
                                                                             Transverse projection of guard      10         12          15       20
                                                                             ring, r, cm
                                                                             Hanger length of suspension          5          5          10       35
                                                                             string, l0, cm
Figure 4(a) Variation of vertical spacing, Cv, with the slope of             Critical half-width of tower        50         75          85      100
           underneath X-arm for (66 kV lines)                                hamper, h, cm


24                                                                                                                                   IE(I) Journal-ID
CRITICALITY OF SPECIFIED SWING                                              angle-clearance combinations could adequately determine the
ANGLE-CLEARANCE COMBINATIONS                                                optimum tower configurations, as the other specified combina-
A close examination of the Figures 3 and 4 reveals the following            tions do not play any role in affecting tower configuration :
facts in respect of swing angle-clearance combinations (denoted             66 kV lines on barrel type towers:
only by corresponding Swing angles in the following paragraphs)               l      Swing angle = 45°, Live metal clearance = 610 mm
specified for the Indian transmission lines of different voltages:
                                                                              l      Swing angle = 15°, Live metal clearance = 915 mm
66kV lines [Figures 3(a) and 4(a)]:
                                                                            132 kV lines on barrel type towers :
  l    For deciding horizontal spacing, the swing angle of 45° is
       critical for the entire range of α′ except for α′ in a small range     l      Swing angle - 45°, Live metal clearance = 1220 mm
       of 18° to 20° where a 30° swing angle requires only a                  l      Swing angle = 15°, Live metal clearance = 1530 mm
       marginally (less than 1%) higher value of horizontal spacing.        220 kV lines on barrel type towers:
  l    For deciding vertical spacing, the swing angle of 15° is               l      Swing angle = 45°, Live metal clearance = 1675 mm
       critical for the entire range of α expect for α in a small range
       of 5° to 7° where 15° swing angle requires a marginally (less
                                                                              l      Swing angle = 15°, Live metal clearance = 2130 mm
       that 3%) higher value of horizontal spacing.                         400 kV DC lines on barrel type towers:
132 kV lines [Figures 3(b) and 4(b)]:                                         l      Swing angle = 22°, Live metal clearance = 3050 mm
  l    For deciding horizontal spacing, the swing angle of 45° is             l      Swing angle = 0°, Live metal clearance = 3050 mm
       critical for the entire range of α′.                                 400 kV SC lines on corset type towers :
  l    For deciding vertical spacing, the swing angle of 15° is               l      Swing angle = 44°, Live metal clearance = 1840 mm
       critical for the entire range of α expect for α in a small range
                                                                            CONCLUSIONS
       of 5° to 7° where 0° swing angle requires a marginally (less
       than 2%) higher value of horizontal spacing.                         On the basis of aforesaid analysis, it can be seen that a maximum
                                                                            of two swing angle-clearance combinations, if judiciously
220 kV lines [Figures 3(c) and 4(c)]:
                                                                            selected, could completely and adequately determine optimum
  l    For deciding horizontal spacing, the swing angle of 45° is           tower configuration for a pre-specified level of performance
       critical for the entire range of α′.                                 (flashover probability) of the transmission lines and the remain-
  l    For deciding vertical spacing, the swing angle of 15° is             ing (one or two) presently specified combinations could be dis-
       critical for the entire range of α expect for α in a small range     pensed with, without jeopardizing the reliability of the lines.
       of 5° to 7° where 0° swing angle requires a marginally (less         The analysis presented in this paper is based on the configuration
       than 1.5%) higher value of horizontal spacing.                       of a suspension tower. However, it can be shown that similar
400 kV double circuit lines on barrel type of tower [Figures 3(d)           results would be obtained for tension towers also.
and 4(d)]:                                                                  This analysis is also based on the presumptions that :
  l    For deciding horizontal spacing, the swing angle of 22° is             l      Live metal clearances presently specified with different
       critical for the entire range of α′.                                          swing angle (for different voltage lines) are properly
  l    For deciding vertical spacing, the swing angle of 0° is critical              co-coordinated for the pre-specified level of flashover
                                                                                     probability.
       for most of the range of α expect for α′ in a small range of
       16° to 20° where 22° swing angle requires a marginally (less           l      66 kV SC/DC lines, 132 kV SC/DC lines, 220 kV SC/DC
       than 1.5%) higher value of horizontal spacing.                                lines and 400 kV DC lines use standard barrel type towers
                                                                                     and 400 kV SC lines use corset type towers.
400 kV single circuit lines on corset type tower [Figure 3(e)]
  l    For deciding horizontal spacing, the swing angle of 44° is
                                                                              l      The values of α′ and α are within the practical range assumed
       critical for the entire range of α′ except for α′ in a small range            in the analysis.
       of 0° to − 3° where a 22° swing angle requires only a                REFERENCES
       marginally (less than 0.5%) higher value of horizontal               1. ‘Transmission Line Manual.’ (Book) Publication No 268, Central Board of
       spacing.                                                             Irrigation and Power, New Delhi.
                                                                            2. S S Murthy and A R Santhakumar. ‘Transmission Line Structures.’ (Book)
OBSERVATIONS                                                                McGraw-Hill Book Company, Singapore 1990.
On the basis of criticality of specified swing angle-clearance              3. V N Rikh. ‘Economic Stranding and Size of ACSR for H V Power Lines.’
combinations on Indian transmission lines as explained above and            Journal of The Institution of Engineers (India), part EL-3, vol 53, February 1973,
                                                                            pp 127-134.
acknowledging that a marginal reduction of less that 3% in the
                                                                            4. IS802 (Part 1/Sec 1) : 199, Indian Standard on ‘Use of Structural Steel in
spacings will not materially/practically affect the performance of          Overhead Transmission Line Towers-Code of Practice.’ Bureau of Indian Stand-
the transmission lines, it can be noted that the following swing            ards, New Delhi.




Vol 85, May 2004                                                                                                                                          25

More Related Content

What's hot

Sag in overhead transmission line, sag calculation & string chart
Sag in overhead transmission line, sag   calculation & string chartSag in overhead transmission line, sag   calculation & string chart
Sag in overhead transmission line, sag calculation & string chartvishalgohel12195
 
A mini project on the transmission tower
A mini project on the transmission towerA mini project on the transmission tower
A mini project on the transmission towernaqeeb04
 
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINESSAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINESPower System Operation
 
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...Thorne & Derrick International
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design conceptKumar VEL
 
Principles of power systems v. k. mehta and r. mehta
Principles of power systems v. k. mehta and r. mehtaPrinciples of power systems v. k. mehta and r. mehta
Principles of power systems v. k. mehta and r. mehtaManoj Chowdary
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and detailsMahesh Sontyal
 
UNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAINUNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAINPremanandDesai
 
Sag tension calcs-ohl-tutorial
Sag tension calcs-ohl-tutorialSag tension calcs-ohl-tutorial
Sag tension calcs-ohl-tutorialAzira Muda
 
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Gensol Engineering Limited
 
Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationAmeen San
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parametersfiraoltemesgen1
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission linesfiraoltemesgen1
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission lineFazlur Rahman
 

What's hot (20)

Sag in overhead transmission line, sag calculation & string chart
Sag in overhead transmission line, sag   calculation & string chartSag in overhead transmission line, sag   calculation & string chart
Sag in overhead transmission line, sag calculation & string chart
 
A mini project on the transmission tower
A mini project on the transmission towerA mini project on the transmission tower
A mini project on the transmission tower
 
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINESSAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
 
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
 
Sag and tension
Sag and tensionSag and tension
Sag and tension
 
Transmisiion line design concept
Transmisiion line design conceptTransmisiion line design concept
Transmisiion line design concept
 
Principles of power systems v. k. mehta and r. mehta
Principles of power systems v. k. mehta and r. mehtaPrinciples of power systems v. k. mehta and r. mehta
Principles of power systems v. k. mehta and r. mehta
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
 
Ehv line design
Ehv line designEhv line design
Ehv line design
 
UNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAINUNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAIN
 
Sag tension calcs-ohl-tutorial
Sag tension calcs-ohl-tutorialSag tension calcs-ohl-tutorial
Sag tension calcs-ohl-tutorial
 
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
 
Poles and towers
Poles and towersPoles and towers
Poles and towers
 
Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss Calculation
 
Underground cables vs overhead lines
Underground cables vs overhead linesUnderground cables vs overhead lines
Underground cables vs overhead lines
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
 
Over head power lines
Over head power linesOver head power lines
Over head power lines
 
Selection of transmission voltage
Selection of transmission voltageSelection of transmission voltage
Selection of transmission voltage
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission lines
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
 

Viewers also liked (8)

Jacobs Recent changes to transmission line design standards and the impact on...
Jacobs Recent changes to transmission line design standards and the impact on...Jacobs Recent changes to transmission line design standards and the impact on...
Jacobs Recent changes to transmission line design standards and the impact on...
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Copy of stub setting 1
Copy of stub setting 1Copy of stub setting 1
Copy of stub setting 1
 
Copy of stub setting 2
Copy of stub setting 2Copy of stub setting 2
Copy of stub setting 2
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of stub setting 3
Copy of stub setting 3Copy of stub setting 3
Copy of stub setting 3
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
02 1 synchronous-machines
02 1 synchronous-machines02 1 synchronous-machines
02 1 synchronous-machines
 

Similar to Swing angle

Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.pptssuserc3b807
 
transmission line tower design
transmission line tower designtransmission line tower design
transmission line tower designkunalbhattgecd
 
Strain gauge loadcell ppt
Strain gauge loadcell pptStrain gauge loadcell ppt
Strain gauge loadcell pptmaneeb
 
main content
main contentmain content
main contentRaj Kumar
 
ESA Module 1 Part-B ME832. by Dr. Mohammed Imran
ESA Module 1 Part-B ME832. by Dr. Mohammed ImranESA Module 1 Part-B ME832. by Dr. Mohammed Imran
ESA Module 1 Part-B ME832. by Dr. Mohammed ImranMohammed Imran
 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptAshish585772
 
Alternator / Synchronous Generator
Alternator / Synchronous GeneratorAlternator / Synchronous Generator
Alternator / Synchronous GeneratorRidwanul Hoque
 
Incomplete PPT on first topic.pptx [Autosaved] [Autosaved].ppt
Incomplete PPT on first topic.pptx [Autosaved] [Autosaved].pptIncomplete PPT on first topic.pptx [Autosaved] [Autosaved].ppt
Incomplete PPT on first topic.pptx [Autosaved] [Autosaved].pptShubhobrataRudr
 
INTRODUCTION TO STRAIN GAUGES
INTRODUCTION TO STRAIN GAUGESINTRODUCTION TO STRAIN GAUGES
INTRODUCTION TO STRAIN GAUGESSACHINNikam39
 
Experimental stress analysis BE notes by mohammed imran
Experimental stress analysis BE notes by mohammed imranExperimental stress analysis BE notes by mohammed imran
Experimental stress analysis BE notes by mohammed imranMohammed Imran
 
Transmission & distribution of electrical power
Transmission & distribution of electrical powerTransmission & distribution of electrical power
Transmission & distribution of electrical powerpriyanka1432
 
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...IJCSIS Research Publications
 
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONSUNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONSPremanandDesai
 
3.1 Overhead Line Insulators,Underground Cables (1).pptx
3.1 Overhead Line Insulators,Underground Cables (1).pptx3.1 Overhead Line Insulators,Underground Cables (1).pptx
3.1 Overhead Line Insulators,Underground Cables (1).pptxBalaMurugan992669
 

Similar to Swing angle (20)

Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.ppt
 
Tower design
Tower designTower design
Tower design
 
transmission line tower design
transmission line tower designtransmission line tower design
transmission line tower design
 
Strain gauge loadcell ppt
Strain gauge loadcell pptStrain gauge loadcell ppt
Strain gauge loadcell ppt
 
main content
main contentmain content
main content
 
ESA Module 1 Part-B ME832. by Dr. Mohammed Imran
ESA Module 1 Part-B ME832. by Dr. Mohammed ImranESA Module 1 Part-B ME832. by Dr. Mohammed Imran
ESA Module 1 Part-B ME832. by Dr. Mohammed Imran
 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.ppt
 
Ce31533536
Ce31533536Ce31533536
Ce31533536
 
Alternator / Synchronous Generator
Alternator / Synchronous GeneratorAlternator / Synchronous Generator
Alternator / Synchronous Generator
 
Generators [compatibility mode]
Generators [compatibility mode]Generators [compatibility mode]
Generators [compatibility mode]
 
Incomplete PPT on first topic.pptx [Autosaved] [Autosaved].ppt
Incomplete PPT on first topic.pptx [Autosaved] [Autosaved].pptIncomplete PPT on first topic.pptx [Autosaved] [Autosaved].ppt
Incomplete PPT on first topic.pptx [Autosaved] [Autosaved].ppt
 
INTRODUCTION TO STRAIN GAUGES
INTRODUCTION TO STRAIN GAUGESINTRODUCTION TO STRAIN GAUGES
INTRODUCTION TO STRAIN GAUGES
 
Experimental stress analysis BE notes by mohammed imran
Experimental stress analysis BE notes by mohammed imranExperimental stress analysis BE notes by mohammed imran
Experimental stress analysis BE notes by mohammed imran
 
Generator ppt 1
Generator ppt 1Generator ppt 1
Generator ppt 1
 
Transmission & distribution of electrical power
Transmission & distribution of electrical powerTransmission & distribution of electrical power
Transmission & distribution of electrical power
 
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...
 
1228808532(2)
1228808532(2)1228808532(2)
1228808532(2)
 
Perfiles
PerfilesPerfiles
Perfiles
 
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONSUNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
 
3.1 Overhead Line Insulators,Underground Cables (1).pptx
3.1 Overhead Line Insulators,Underground Cables (1).pptx3.1 Overhead Line Insulators,Underground Cables (1).pptx
3.1 Overhead Line Insulators,Underground Cables (1).pptx
 

More from Lahmeyer International, UAE

Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01Lahmeyer International, UAE
 
Design of transmission lines in india a review of multiple swing angle
Design of transmission lines in india  a review of multiple swing angleDesign of transmission lines in india  a review of multiple swing angle
Design of transmission lines in india a review of multiple swing angleLahmeyer International, UAE
 
Counter mesaures aginst liquefaction induced settlemnt for ohl
Counter mesaures aginst liquefaction induced settlemnt for ohlCounter mesaures aginst liquefaction induced settlemnt for ohl
Counter mesaures aginst liquefaction induced settlemnt for ohlLahmeyer International, UAE
 

More from Lahmeyer International, UAE (20)

Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01Techniquescontrolledblasting 091217003405-phpapp01
Techniquescontrolledblasting 091217003405-phpapp01
 
AP88 & AP91 shifting proposal
AP88 & AP91 shifting proposalAP88 & AP91 shifting proposal
AP88 & AP91 shifting proposal
 
Design of transmission lines in india a review of multiple swing angle
Design of transmission lines in india  a review of multiple swing angleDesign of transmission lines in india  a review of multiple swing angle
Design of transmission lines in india a review of multiple swing angle
 
Guide to sampling concrete
Guide to sampling concreteGuide to sampling concrete
Guide to sampling concrete
 
Guide to sampling concrete
Guide to sampling concreteGuide to sampling concrete
Guide to sampling concrete
 
Use of bentonite
Use of bentoniteUse of bentonite
Use of bentonite
 
Gb137
Gb137Gb137
Gb137
 
Ohl project risk register
Ohl project risk registerOhl project risk register
Ohl project risk register
 
Ohl project risk register
Ohl project risk registerOhl project risk register
Ohl project risk register
 
Counter mesaures aginst liquefaction induced settlemnt for ohl
Counter mesaures aginst liquefaction induced settlemnt for ohlCounter mesaures aginst liquefaction induced settlemnt for ohl
Counter mesaures aginst liquefaction induced settlemnt for ohl
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Copy of stub setting 1
Copy of stub setting 1Copy of stub setting 1
Copy of stub setting 1
 
Copy of stub setting
Copy of stub settingCopy of stub setting
Copy of stub setting
 
Copy of prop setting calculations final
Copy of prop setting calculations finalCopy of prop setting calculations final
Copy of prop setting calculations final
 
Copy of stub setting 3
Copy of stub setting 3Copy of stub setting 3
Copy of stub setting 3
 
Copy of stub setting 2
Copy of stub setting 2Copy of stub setting 2
Copy of stub setting 2
 

Recently uploaded

HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 

Recently uploaded (20)

HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 

Swing angle

  • 1. Design of Transmission Lines in India : a Review of Multiple Swing Angle-clearance Combinations Dr V N Rikh, Fellow Proper live metal clearances have to be maintained under various swing angles of the suspension insulator strings/jumper loops on a tower, in order to ensure a reliable performance of the transmission lines. The required swing angle-clearance combinations for lines of different voltages are determined on the basis of a pre-specified criterion of flashover probability. These combinations decide horizontal and vertical spacing of the power conductors and thereby determine the tower configuration, weight and cost. Presently three to five swing angle- clearance combinations are commonly specified for Indian transmission lines of each voltage. On the other hand, in many countries generally only two or three combinations are specified. Based on detailed analysis this paper attempts to prove that if even two judiciously selected swing angle-clearance combinations are used, they would adequately determine optimum tower configuration and the remaining extra combinations presently specified could be dispensed with, without jeopardizing the reliability of the lines. Keywords : Transmission line; Line insulation; Swing angle; Line metal clearances NOTATIONS INTRODUCTION C0 , C15 , C10, etc : location of critical live metal part of the One of the most important criteria for ensuring a reliable perform- phase power conductor with swing angles ance of transmission lines under all weather conditions, is to of 0°, 15°, 30° etc ensure that proper live metal (conductor to nearest earthed parts L0 , L15 , L30, etc : live-metal clearances specified for swing of the tower structure) clearances are maintained under various angles of 0°, 15°, 30° etc, cm angles (depending on wind speeds) of swing of the suspension c : minimum clearance between the live metal insulator strings for a suspension tower (or the jumper loops for parts phase power conductor and the nearest a tension tower). The required live-metal clearances for different (carthed) part of the tower structure or live- angles of swing of suspension insulator strings (or jumper loops metal clearance, cm for tension towers) are determined on the basis of a pre-specified h : half width of the tower hamper at the critical criterion of flashover probability. When the suspension strings, point (where the clearance arc from the supporting the power conductors, hang vertically under ‘no- swung, live metal parts touches it), cm wind’ conditions, the live-metal clearance is maintained at a value l : swinging length of the suspension string that ensures a probability of flashover across the air-gap within a duly adjusted for any longitudinal (to the pre-specified value of, say, less than 2%. As the string/conductor attachment point, swings toward the tower body under the influ- string axis) projection of the guard ring/ ence of the wind, the critical value of flashover voltage gradient bandle spacer, cm across the gap correspondingly increases due to faster de-ioniza- lo : length of hanger of the suspension tion of the air. This results in a reduced requirement of live-metal string, cm clearances under higher wind velocities (and consequently bigger r : transverse (to the string axis) projection, if swing angles of the string/conductor attachment points) to ensure any, of the critical point of the guard the same level of pre-specified flashover probability across the ring/bundle spacer, cm air- gap. α : angle at which the uppermost (nearest to the conductor) structural member of the under- The swing angle-clearance combinations presently adopted for neath cross-arm is inclined to horizontal Indian transmission lines are based on the aforesaid logic. plane, degrees Usually three to five swing angle-clearance combinations are specified for transmission lines of each voltage on the basis of α′ : angle at which the nearest structural mem- detailed analysis of prevailing weather conditions and flashover ber of the tower hamper is inclined to the characteristics of air-gaps. The values of these swing angle- vertical plane, degrees clearance combinations commonly specified in India1, are shown θ : angle of swing of the suspension insulator in Table 1. string or of the jumper loop of tension insu- lator string, degrees These combinations have yielded a reasonably satisfactory per- Φ : tan − 1 [r ⁄ √ (r2 + l2)] formance of the transmission lines in this country over several  decades. Dr V N Rikh resides at 188-A, Saket, Meerut 250 003. The 66kV, 132kV and 220kV transmission lines in India (single This paper was received on September 26, 2003. Written discussion on this paper circuit as well as double circuit) commonly use self-supporting will be received until July 31, 2004. barrel type towers. However, while 400kV double circuit Indian Vol 85, May 2004 21
  • 2. Table 1 Swing angle-clearance combinations adopted for Indian On the other hand, with a given value of swing angle-clearance transmission lines combination; Swing Angle, degree Live Metal Clearance, mm l An increase in the outward (towards the conductor, eg, in 66 kV 132 kV 220 kV 400 kV the Barrel type towers)) slope α′ of the tower hamper, Lines Lines Lines Lines increases the horizontal spacing while an increased inward 0 915 1530 2130 3050 (away from the conductor, eg, in a corset type tower) slope 15 915 1530 2130 — α′ of the tower hamper reduces the horizontal spacing of the 22 — — — 3050 conductors, and 30 760 1370 1830 — l An increase in the upward (towards the conductor) slope α 44 — — — 1860 of the uppermost member of underneath cross-arm results in 45 610 1220 1675 — an increased vertical spacing of the conductors. As per prevalent design practice, a downward slope of the lines also use barrel type towers, the 400kV single circuit lines underneath cross-arm member is not adopted. commonly use corset (or Wasp-waisted) type of towers. The effect of the slopes (towards the phase conductor/s) of the A study of swing angle-clearance combinations adopted in other tower hamper as well as that of the nearest member of underneath countries reveals that, in many countries, generally only two and cross arm, on the horizontal and vertical conductor spacings, is sometimes a maximum of three, combinations are specified for illustrated for a Barrel type tower in Figure 1. designing tower configuration. This paper therefore attempts to In case of a corset type tower, the slope of Tower Hamper is away analyze the impact of each of the combinations (shown in Table from the (outer) phase conductor/s and its effect on the horizontal 1) on the tower configuration for Indian transmission lines, and conductor can be visualized from a typical Figure 2. As the corset determine whether all these combinations play a critical role in type tower is used for single circuit lines (usually of 400kV), there determining tower configuration/s or some of these (combina- is no vertical formation of the conductors. tions) could be dispensed with, without jeopardizing reliability of the transmission lines. IMPACT OF SWING ANGLE-CLEARANCE COMBINATIONS ON THE TOWER CONFIGURATION PARAMETERS AFFECTING TOWER CONFIGURATION As explained above, for any given values of α and α′, each swing angle-clearance combination will require certain mini- The swing angle-clearance combinations, along with the follow- mum values of horizontal and vertical spacings of the power ing two important design parameters help determine the horizon- tal, as well as the vertical, spacing of the power conductors and, in turn, help decide the configuration, dimensions and therefore the weight/cost of the towers; l The slope α and α′ (to the vertical plane) of the outermost (nearest to the conductor) structural member of the tower hamper, and l The slope α (to the horizontal plane) of the uppermost (nearest to the conductor) structural member of the underneath cross-arm. The values of α and α′ are determined in the process of economic optimization of tower configuration. For any given values of α′, l An increase in (inward) swing-angle, θ, of the insulator string (or, jumper loop, for a tension tower) requires a corresponding increase in the horizontal spacing of the phase conductor/s maintain the specified live-metal clearance, Similarly, any increase in the live-metal clearance, c, requires a corresponding increase in the horizontal spacing. l The requirement of vertical spacing of the phase conductors , however, decreases with any increase in (inward) swing-angle, θ, of the insulator string (or, jumper loop, for a tension tower), though an increase in the live-metal clearance c, still requires a corresponding increase in the vertical Figure 1 Effect of tower hamper and X-arm slopes on conductor spacings spacing. for barrel type tower 22 IE(I) Journal-ID
  • 3. Cv = (√ 2 + r2) cos (θ ± Φ + sin (θ ± Φ tan α +   l   c sec α + l0 (2) Using these expressions, the requirement of horizontal spacings for each specified swing angle (with corresponding live metal clearance) for the aforesaid range of α′, are shown in the follow- ing figures : l Figure 3(a) - 66kV lines (barrel type towers) l Figure 3(b) - 132kV lines (barrel type towers) l Figure 3(c) - 220 kV lines (barrel type towers) l Figure 3(d) - 400 kV double circuit lines with barrel type towers l Figure 3(e) - 400 kV single circuit lines with corset type towers Figure 2 Effect of slope of tower hamper on conductor spacing, Ch , for corset type tower Figure 3(a) Variation of horizontal spacing, Ch , with the slope of Tower Hamper (66 kV lines) conductors. If the horizontal and vertical spacing requirements for each of the three (or four) swing angle-clearance combinations specified for the lines of a particular voltage (eg, 66kV) as above are determined, it can be seen that only one of the combinations (generally, with higher swing angle) will be critical for the re- quirement of (maximum) horizontal spacing while some other combination (generally with lower seing angle) will be critical for the vertical spacing, for the given values of α and α′. Thus, for the selected values of α and α′, only two combinations would normally be critical for fixing tower configuration while the remaining combinations, will require spacings which are less than the critical values and thus play no part in deciding the tower configuration. Figure 3(b) Variation of horizontal spacing, Ch , with the slope of Tower Hamper (132 kV lines) The commonly used, practical value of α is between 0° and +15° while the value of α′ may range between +5° and +20° for Barrel type towers and between 0° and −20° for corset type tower. If the critically of all the swing angle-clearance combinations (specified for a particular line voltage) could be examined over the aforesaid practical range of α and α′, it will reveal whether all the specified combination do play a determining role for tower configuration or one/two of them, are not critical and could be dispensed with. Considering a typical case of suspension tower, it can be shown that the horizontal and vertical spacings of the phase conductors are given by :   Ch = 2 [(√ 2 + r2) sin (θ ± Φ) + cos (θ ± Φ) tan α′ +  l   Figure 3(c) Variation of horizontal spacing, Ch , with the slope of Tower l0 tan α′ + c sec α′ + h] (1) Hamper (220 kV lines) Vol 85, May 2004 23
  • 4. Figure 3(d) Variation of horizontal spacing, Ch , with the slope of Tower Figure 4(b) Variation of vertical spacing, Cv, with the slope of Hamper (400 kv line — barrel type tower) underneath X-arm for (132 kV lines) Figure 3(e) Variation of horizontal spacing, Ch , with the slope of Tower Hamper (400 kV line — corset type tower) Figure 4(c) Variation of vertical spacing, Cv, with the slope of Similarly, the requirement of vertical spacings for each specified underneath X-arm for (220 kV lines) swing angle of α, are shown in the following Figures (there being no vertical spacing for a corset type tower): l Figure 4(a) - 66kV lines (barrel type towers) l Figure 4(b) - 132 kV lines (barrel type towers) l Figure 4(c) - 220 kV lines (barrel type towers) l Figure 4(d) - 400 kV double circuit lines with barrel type towers The aforesaid analysis is based on the values of relevant dimen- sions as shown in Table 2. Figure 4(d) Variation of vertical spacing, Cv, with the slope of underneath X-arm for (400 kV lines — barrel type tower) Table 2 Typical values of relevant dimensions Item Typical Value for Line Voltage 66 kV 132 kV 220 kV 400 kV Swing length of suspension 97 163 234 385 string, l, cm Transverse projection of guard 10 12 15 20 ring, r, cm Hanger length of suspension 5 5 10 35 string, l0, cm Figure 4(a) Variation of vertical spacing, Cv, with the slope of Critical half-width of tower 50 75 85 100 underneath X-arm for (66 kV lines) hamper, h, cm 24 IE(I) Journal-ID
  • 5. CRITICALITY OF SPECIFIED SWING angle-clearance combinations could adequately determine the ANGLE-CLEARANCE COMBINATIONS optimum tower configurations, as the other specified combina- A close examination of the Figures 3 and 4 reveals the following tions do not play any role in affecting tower configuration : facts in respect of swing angle-clearance combinations (denoted 66 kV lines on barrel type towers: only by corresponding Swing angles in the following paragraphs) l Swing angle = 45°, Live metal clearance = 610 mm specified for the Indian transmission lines of different voltages: l Swing angle = 15°, Live metal clearance = 915 mm 66kV lines [Figures 3(a) and 4(a)]: 132 kV lines on barrel type towers : l For deciding horizontal spacing, the swing angle of 45° is critical for the entire range of α′ except for α′ in a small range l Swing angle - 45°, Live metal clearance = 1220 mm of 18° to 20° where a 30° swing angle requires only a l Swing angle = 15°, Live metal clearance = 1530 mm marginally (less than 1%) higher value of horizontal spacing. 220 kV lines on barrel type towers: l For deciding vertical spacing, the swing angle of 15° is l Swing angle = 45°, Live metal clearance = 1675 mm critical for the entire range of α expect for α in a small range of 5° to 7° where 15° swing angle requires a marginally (less l Swing angle = 15°, Live metal clearance = 2130 mm that 3%) higher value of horizontal spacing. 400 kV DC lines on barrel type towers: 132 kV lines [Figures 3(b) and 4(b)]: l Swing angle = 22°, Live metal clearance = 3050 mm l For deciding horizontal spacing, the swing angle of 45° is l Swing angle = 0°, Live metal clearance = 3050 mm critical for the entire range of α′. 400 kV SC lines on corset type towers : l For deciding vertical spacing, the swing angle of 15° is l Swing angle = 44°, Live metal clearance = 1840 mm critical for the entire range of α expect for α in a small range CONCLUSIONS of 5° to 7° where 0° swing angle requires a marginally (less than 2%) higher value of horizontal spacing. On the basis of aforesaid analysis, it can be seen that a maximum of two swing angle-clearance combinations, if judiciously 220 kV lines [Figures 3(c) and 4(c)]: selected, could completely and adequately determine optimum l For deciding horizontal spacing, the swing angle of 45° is tower configuration for a pre-specified level of performance critical for the entire range of α′. (flashover probability) of the transmission lines and the remain- l For deciding vertical spacing, the swing angle of 15° is ing (one or two) presently specified combinations could be dis- critical for the entire range of α expect for α in a small range pensed with, without jeopardizing the reliability of the lines. of 5° to 7° where 0° swing angle requires a marginally (less The analysis presented in this paper is based on the configuration than 1.5%) higher value of horizontal spacing. of a suspension tower. However, it can be shown that similar 400 kV double circuit lines on barrel type of tower [Figures 3(d) results would be obtained for tension towers also. and 4(d)]: This analysis is also based on the presumptions that : l For deciding horizontal spacing, the swing angle of 22° is l Live metal clearances presently specified with different critical for the entire range of α′. swing angle (for different voltage lines) are properly l For deciding vertical spacing, the swing angle of 0° is critical co-coordinated for the pre-specified level of flashover probability. for most of the range of α expect for α′ in a small range of 16° to 20° where 22° swing angle requires a marginally (less l 66 kV SC/DC lines, 132 kV SC/DC lines, 220 kV SC/DC than 1.5%) higher value of horizontal spacing. lines and 400 kV DC lines use standard barrel type towers and 400 kV SC lines use corset type towers. 400 kV single circuit lines on corset type tower [Figure 3(e)] l For deciding horizontal spacing, the swing angle of 44° is l The values of α′ and α are within the practical range assumed critical for the entire range of α′ except for α′ in a small range in the analysis. of 0° to − 3° where a 22° swing angle requires only a REFERENCES marginally (less than 0.5%) higher value of horizontal 1. ‘Transmission Line Manual.’ (Book) Publication No 268, Central Board of spacing. Irrigation and Power, New Delhi. 2. S S Murthy and A R Santhakumar. ‘Transmission Line Structures.’ (Book) OBSERVATIONS McGraw-Hill Book Company, Singapore 1990. On the basis of criticality of specified swing angle-clearance 3. V N Rikh. ‘Economic Stranding and Size of ACSR for H V Power Lines.’ combinations on Indian transmission lines as explained above and Journal of The Institution of Engineers (India), part EL-3, vol 53, February 1973, pp 127-134. acknowledging that a marginal reduction of less that 3% in the 4. IS802 (Part 1/Sec 1) : 199, Indian Standard on ‘Use of Structural Steel in spacings will not materially/practically affect the performance of Overhead Transmission Line Towers-Code of Practice.’ Bureau of Indian Stand- the transmission lines, it can be noted that the following swing ards, New Delhi. Vol 85, May 2004 25