SlideShare a Scribd company logo
TRANSFORMER TESTING
Insulation Resistance
Shanid Pazhamkavil
INSULATION RESISTANCE TESTING
• Insulation resistance measurements are performed to verify
that the state of dryness of the insulation of the various
windings and the core are of acceptable values.
• Insulation resistance testing may also reveal important
information about concealed damage of bushings.
• Insulation resistance is the volume and surface resistivity of
the insulation involved.
• Insulation resistance of transformers and reactors are
measured using Insulation Tester and the values expressed in
Mega Ohms/Giga ohms.
• The output voltage from the insulation tester is DC.
• The value of insulation resistance (IR value) depends on the
design (voltage class, type etc.), temperature of oil , dryness
of internal parts, cleanliness of parts (especially bushing
porcelains, terminals), condition of oil, atmospheric
conditions (humidity) etc.
• IR value varies with voltage applied for measurement and
hence comparison may always be done with measurements
carried out at same voltages.
• IR value is inversely proportional to the temperature.
TESTING & ANALYSIS
• Before starting the measurement, the temperature of the oil in
Transformer must be noted; which shall be almost the same as the
reference ambient temperature.
• Measurements are made at 15TH ,60TH & 600TH Seconds
• Ensure that the measured value at 60th seconds is not less than
2000 Meg. Ohm.
• Polarization Index (PI) value, which is the ratio of 600th to 60th
seconds.
• PI value gives a rough guide to the condition of the insulation
properties; especially the dryness of the windings and internal
parts of the Transformer.
• PI value <1.0 indicates bad/ unsatisfactory, >= 1 .3satisfactory,
>= 1.5 good and >= 2.0 very good conditions of the dryness /
insulation properties inside the transformer.
• The new generation Insulation testers have inbuilt provisions for discharging
the voltages through the testing equipment itself, which takes place within a
few seconds after switching off. However ,as the voltage generated for
measurement is of the tune of 500V ~ 5000V, earthing may be done
externally before removing the connections as a safety precaution
Insulation Resistance of Winding
Aim
c) To determine the insulation resistance of individual winding
to Earth and between windings.
d) To evaluate the condition of the Transformer insulation.
Test preparation
• Insulation Tester (Megger) must be of 5kV range having valid
calibration.
• The earthing of the main body / tank, core /clamp etc.,
cleanliness & dryness of the bushing porcelains/ terminals
and tightness of the connection are checked.
• The temperature of the oil inside the transformer (OTI
reading) is noted.
• Care may be taken to see that test leads do not touch among
themselves and with Transformer body.
Test procedure
• Terminals of all HV bushings and HVN bushing are shorted
together as shown in the figure. Similarly all terminals of LV
bushings are shorted together.
• The test voltage is selected per the requirement considering
the voltage class of the testing specimen
• IR values of individual winding to Earth and between windings
are measured at 15th ,60th and 600th seconds.
• Compare the measured IR values with the factory results. Also
evaluate PI values.
• Connection diagram for a two winding Transformer is shown
below.
*Vector Indication may change according to vector group of transformer
*Ynd vector group is considered in above diagram
Connection Arrangement
How the instrument looks like?
Precautions/ Safety
• Transformer and the bushings under test shall be thoroughly cleaned
with dry cloth.
• During the measurement the test area shall be demarked with
warning tape.
• Megger shall be placed on a leveled platform.
• Sagging of the connection leads shall be avoided.
• Infinity and zero of the megger shall be checked prior to test.
• Sufficient time shall be given for discharge of megger before taking
the next measurement.
• The test circuit must be discharged by short-circuiting for a period
which shall be at least four times the voltage application time; if the
connection is made by bare hands. However in practice at least a
discharge time equal to the voltage application time shall be given.
• Measurement at higher voltage shall not be done while the
transformer is under vacuum.
Interpretation
• A high value of polarization index indicates the insulation is very
good. PI value <1 indicates immediate corrective action is
required.
• There are no specific absolute values of acceptable insulation
resistance; however reference should be made to previous test
history to establish a trend.

More Related Content

What's hot

Transformer basic
Transformer basicTransformer basic
Transformer basic
BHAGWAN PRASAD
 
Motor starter
Motor starterMotor starter
Motor starter
BHAGWAN PRASAD
 
Chapter 02- Breakdown in liquid dielectrics
Chapter 02- Breakdown in liquid dielectricsChapter 02- Breakdown in liquid dielectrics
Chapter 02- Breakdown in liquid dielectrics
MUET SZAB Campus Khairpur Mir's Sindh Pakistan
 
Breaker Operation & Maintenance
Breaker Operation & MaintenanceBreaker Operation & Maintenance
Breaker Operation & Maintenance
Sheikh Nazmul Islam
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
Geetesh Verma
 
Types of relay
Types of relayTypes of relay
Types of relay
Abdur rehman
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in precise
Muthar Hussain
 
Circuit protection devices perfect ppt
Circuit protection devices perfect ppt Circuit protection devices perfect ppt
Circuit protection devices perfect ppt
vikram rajpurohit
 
Power Transformer Parts And Functions
Power Transformer Parts And FunctionsPower Transformer Parts And Functions
Power Transformer Parts And Functions
Nitendra Kumar Singh
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
Dr. Selvarasu Ranganathan
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
Novia Putri
 
Introduction to electrical measurements
Introduction to electrical measurementsIntroduction to electrical measurements
Introduction to electrical measurements
parneetchowdhary1
 
measurement of high voltage and high currents
 measurement of high voltage and high currents  measurement of high voltage and high currents
measurement of high voltage and high currents
mukund mukund.m
 
Electrical instruments ppt
Electrical instruments pptElectrical instruments ppt
Electrical instruments ppt
Amey Waghmare
 
Digital multimeter
Digital multimeterDigital multimeter
Digital multimeter
Jeraldine Cabayaran
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTCRohit Dave
 
Chapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering IntroductionChapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering Introduction
MUET SZAB Campus Khairpur Mir's Sindh Pakistan
 
Three phase-circuits
Three phase-circuitsThree phase-circuits
Three phase-circuits
rsamurti
 
Transformer basics
Transformer   basicsTransformer   basics
Transformer basics
AtheenaPandian Enterprises
 

What's hot (20)

Transformer basic
Transformer basicTransformer basic
Transformer basic
 
Motor starter
Motor starterMotor starter
Motor starter
 
Chapter 02- Breakdown in liquid dielectrics
Chapter 02- Breakdown in liquid dielectricsChapter 02- Breakdown in liquid dielectrics
Chapter 02- Breakdown in liquid dielectrics
 
Breaker Operation & Maintenance
Breaker Operation & MaintenanceBreaker Operation & Maintenance
Breaker Operation & Maintenance
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 
Types of relay
Types of relayTypes of relay
Types of relay
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in precise
 
Circuit protection devices perfect ppt
Circuit protection devices perfect ppt Circuit protection devices perfect ppt
Circuit protection devices perfect ppt
 
Power Transformer Parts And Functions
Power Transformer Parts And FunctionsPower Transformer Parts And Functions
Power Transformer Parts And Functions
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
Introduction to electrical measurements
Introduction to electrical measurementsIntroduction to electrical measurements
Introduction to electrical measurements
 
measurement of high voltage and high currents
 measurement of high voltage and high currents  measurement of high voltage and high currents
measurement of high voltage and high currents
 
Electrical instruments ppt
Electrical instruments pptElectrical instruments ppt
Electrical instruments ppt
 
Lightning arrester
Lightning arresterLightning arrester
Lightning arrester
 
Digital multimeter
Digital multimeterDigital multimeter
Digital multimeter
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
 
Chapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering IntroductionChapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering Introduction
 
Three phase-circuits
Three phase-circuitsThree phase-circuits
Three phase-circuits
 
Transformer basics
Transformer   basicsTransformer   basics
Transformer basics
 

Similar to Insulation Resistance Test

'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt
Thien Phan Bản
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
srichakra kripa
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
Asha Anu Kurian
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHShankar Singh
 
Relay testing.............................
Relay testing.............................Relay testing.............................
Relay testing.............................
hiiarindam
 
Cables22-1-19.pptx
Cables22-1-19.pptxCables22-1-19.pptx
Cables22-1-19.pptx
IAIvachan
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
Nadir Baloch
 
Design, planning and layout of high voltage lab
Design, planning and layout of high voltage labDesign, planning and layout of high voltage lab
Design, planning and layout of high voltage labNidhi Maru
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptx
DrNiveditaSingh3
 
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptx
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptxHVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptx
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptx
MuthuKumar158260
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptx
RAJKIRANR3
 
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Sheikh Nazmul Islam
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
Nihal Shiroya
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
johny renoald
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
Satish Pydimarla
 
Vacuum circuit breaker selection of circuit breakers
Vacuum circuit breaker selection of circuit breakersVacuum circuit breaker selection of circuit breakers
Vacuum circuit breaker selection of circuit breakers
shubham_bharadia
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
SMRITI KESHARWANI
 
Fusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity CircuitsFusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity Circuits
TESCO - The Eastern Specialty Company
 
Module 6part1
Module 6part1Module 6part1
Module 6part1
Asha Anu Kurian
 

Similar to Insulation Resistance Test (20)

'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
Relay testing.............................
Relay testing.............................Relay testing.............................
Relay testing.............................
 
Cables22-1-19.pptx
Cables22-1-19.pptxCables22-1-19.pptx
Cables22-1-19.pptx
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Design, planning and layout of high voltage lab
Design, planning and layout of high voltage labDesign, planning and layout of high voltage lab
Design, planning and layout of high voltage lab
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptx
 
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptx
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptxHVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptx
HVE UNIT V HIGH VOLTAGES TESTING AND INSULATION COORDINATION.pptx
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptx
 
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV Switchgear
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
Testing
TestingTesting
Testing
 
Vacuum circuit breaker selection of circuit breakers
Vacuum circuit breaker selection of circuit breakersVacuum circuit breaker selection of circuit breakers
Vacuum circuit breaker selection of circuit breakers
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Fusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity CircuitsFusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity Circuits
 
Module 6part1
Module 6part1Module 6part1
Module 6part1
 

More from Shanid Pazhamkavil

Concept of renewable energy-various forms of renewable energy
Concept of renewable energy-various forms of renewable energy Concept of renewable energy-various forms of renewable energy
Concept of renewable energy-various forms of renewable energy
Shanid Pazhamkavil
 
energy efficient operation of Fans and blowers
energy efficient operation of Fans and blowersenergy efficient operation of Fans and blowers
energy efficient operation of Fans and blowers
Shanid Pazhamkavil
 
Electric motors
Electric motorsElectric motors
Electric motors
Shanid Pazhamkavil
 
Coefficient of utilization (cu)
Coefficient of utilization (cu)Coefficient of utilization (cu)
Coefficient of utilization (cu)
Shanid Pazhamkavil
 
Online detection and locating of faulty nodes using
Online detection and locating of faulty nodes using  Online detection and locating of faulty nodes using
Online detection and locating of faulty nodes using
Shanid Pazhamkavil
 
Wind energy and constructional features
Wind energy and constructional featuresWind energy and constructional features
Wind energy and constructional features
Shanid Pazhamkavil
 
Energy problem and energy auditing
Energy problem and energy auditingEnergy problem and energy auditing
Energy problem and energy auditing
Shanid Pazhamkavil
 

More from Shanid Pazhamkavil (8)

Electric motors
Electric motorsElectric motors
Electric motors
 
Concept of renewable energy-various forms of renewable energy
Concept of renewable energy-various forms of renewable energy Concept of renewable energy-various forms of renewable energy
Concept of renewable energy-various forms of renewable energy
 
energy efficient operation of Fans and blowers
energy efficient operation of Fans and blowersenergy efficient operation of Fans and blowers
energy efficient operation of Fans and blowers
 
Electric motors
Electric motorsElectric motors
Electric motors
 
Coefficient of utilization (cu)
Coefficient of utilization (cu)Coefficient of utilization (cu)
Coefficient of utilization (cu)
 
Online detection and locating of faulty nodes using
Online detection and locating of faulty nodes using  Online detection and locating of faulty nodes using
Online detection and locating of faulty nodes using
 
Wind energy and constructional features
Wind energy and constructional featuresWind energy and constructional features
Wind energy and constructional features
 
Energy problem and energy auditing
Energy problem and energy auditingEnergy problem and energy auditing
Energy problem and energy auditing
 

Recently uploaded

一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 

Recently uploaded (20)

一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 

Insulation Resistance Test

  • 2. INSULATION RESISTANCE TESTING • Insulation resistance measurements are performed to verify that the state of dryness of the insulation of the various windings and the core are of acceptable values. • Insulation resistance testing may also reveal important information about concealed damage of bushings.
  • 3. • Insulation resistance is the volume and surface resistivity of the insulation involved. • Insulation resistance of transformers and reactors are measured using Insulation Tester and the values expressed in Mega Ohms/Giga ohms. • The output voltage from the insulation tester is DC. • The value of insulation resistance (IR value) depends on the design (voltage class, type etc.), temperature of oil , dryness of internal parts, cleanliness of parts (especially bushing porcelains, terminals), condition of oil, atmospheric conditions (humidity) etc. • IR value varies with voltage applied for measurement and hence comparison may always be done with measurements carried out at same voltages. • IR value is inversely proportional to the temperature.
  • 4. TESTING & ANALYSIS • Before starting the measurement, the temperature of the oil in Transformer must be noted; which shall be almost the same as the reference ambient temperature. • Measurements are made at 15TH ,60TH & 600TH Seconds • Ensure that the measured value at 60th seconds is not less than 2000 Meg. Ohm. • Polarization Index (PI) value, which is the ratio of 600th to 60th seconds. • PI value gives a rough guide to the condition of the insulation properties; especially the dryness of the windings and internal parts of the Transformer. • PI value <1.0 indicates bad/ unsatisfactory, >= 1 .3satisfactory, >= 1.5 good and >= 2.0 very good conditions of the dryness / insulation properties inside the transformer.
  • 5. • The new generation Insulation testers have inbuilt provisions for discharging the voltages through the testing equipment itself, which takes place within a few seconds after switching off. However ,as the voltage generated for measurement is of the tune of 500V ~ 5000V, earthing may be done externally before removing the connections as a safety precaution
  • 6. Insulation Resistance of Winding Aim c) To determine the insulation resistance of individual winding to Earth and between windings. d) To evaluate the condition of the Transformer insulation. Test preparation • Insulation Tester (Megger) must be of 5kV range having valid calibration. • The earthing of the main body / tank, core /clamp etc., cleanliness & dryness of the bushing porcelains/ terminals and tightness of the connection are checked. • The temperature of the oil inside the transformer (OTI reading) is noted. • Care may be taken to see that test leads do not touch among themselves and with Transformer body.
  • 7. Test procedure • Terminals of all HV bushings and HVN bushing are shorted together as shown in the figure. Similarly all terminals of LV bushings are shorted together. • The test voltage is selected per the requirement considering the voltage class of the testing specimen • IR values of individual winding to Earth and between windings are measured at 15th ,60th and 600th seconds. • Compare the measured IR values with the factory results. Also evaluate PI values. • Connection diagram for a two winding Transformer is shown below.
  • 8. *Vector Indication may change according to vector group of transformer *Ynd vector group is considered in above diagram
  • 10. How the instrument looks like?
  • 11. Precautions/ Safety • Transformer and the bushings under test shall be thoroughly cleaned with dry cloth. • During the measurement the test area shall be demarked with warning tape. • Megger shall be placed on a leveled platform. • Sagging of the connection leads shall be avoided. • Infinity and zero of the megger shall be checked prior to test. • Sufficient time shall be given for discharge of megger before taking the next measurement. • The test circuit must be discharged by short-circuiting for a period which shall be at least four times the voltage application time; if the connection is made by bare hands. However in practice at least a discharge time equal to the voltage application time shall be given. • Measurement at higher voltage shall not be done while the transformer is under vacuum.
  • 12. Interpretation • A high value of polarization index indicates the insulation is very good. PI value <1 indicates immediate corrective action is required. • There are no specific absolute values of acceptable insulation resistance; however reference should be made to previous test history to establish a trend.