INDUSTRIAL
TRAINING
PRESENTATION
ECV 3901
INTRODUCTION

Name
Matric No

: Nursyafiqah Ismail
: 156275

I was undergo my industrial training for 10
weeks in a construction company named
Pembinaan Thin Chai Sdn. Bhd.
BACKGROUND OF THE
COMPANY



Incorporated in 1970 by Mr Chai Min Choo
The range of works include :
> Bridge Construction: Land & Marine
> Heavy Industrial Plant Works
> Jetty Construction
> Tunnel Lining Works
> Runway, Taxiway & Parking Apron
> Drainage & Road-works; Earthworks
> Building Works
> Water Treatment Plant, Reservoir & Dam
> Structure Works
WORK EXPERIENCES









Design analysis of fencing on parapet walls for
bridge project in Port Klang
Enhance software skills (AutoCAD) by preparing
paperwork for method of statement for “spalled
concrete on precast beams” and “launching of
T beams on Pier 8-9”
Prepare BoQ for tender and contracts
Site inspection in Gua Musang Project
and Port Klang
Order and purchase materials
Analyze the volume of ready mix concrete used
every month, to estimate the progression of
work
1.

Design analysis of fencing on
parapet walls

 Consist

of rectangular hollow section
column, beams and zinc sheet
 Subjected to wind loading
 Mostly based on BS Code and Malaysia
Meteorological Department
 Must be in line with JKR requirements
 Purpose of fencing : to provide safety for
the road users, during the demolition of
flyovers
 Difficulties

Port Klang




to get the basic wind speed in

Table provided in the BS Code is only suitable for UK
climate
Refer to Malaysia Meteorological Dept to find basic
wind speed for Port Klang (near the sea)
2. Method of statement
MoS “Patch repair of spalled concrete on precast
beam” and “modification of rib beam”.
 Steps to repair the defect occurred on the beam
 Approved by Professional Engineers before
proceed with repair process
MoS launching of T Beams
 Draw the sequence of launching T Beams by
using AutoCAD
 Take into account,
Mobilization and demobilization of crane
 Closure of Traffic
 Construct alternative road for road users, to avoid
traffic congestion during launching

3. Prepare BoQ
 Preparing

the Bill of Quantities to bid for
tenders and contracts, below are such
project :







AKLEH - Ampang KL Elevated Highway
Prai CCGT Power Plant
Construct barrage in Sg Johor

Tender documentation
4. Site Inspection – Gua Musang
 Inspect

the formwork of diaphragm wall on
Bridge 2
 Monitor concrete work of parapet walls
 Get to see the process of launching T Beam
on pier 8-9
 Update the record of diesel on site
 Update the summary record of ready mix
concrete for July 2013
Launching T Beam

Launch T beam
using corrective
method

1

Close the road

Lifting Operation by
Crane
Formwork

Pour concrete

Curing

Parapet Wall
Site Inspection

Inspect formwork of
diaphragm wall
4. Site Inspection – Port Klang
 Inspect

the work progress of bridge
construction
 Inspect the location of flyover that will be
demolish in order to construct bridge
 Problems facing :
-> the existence of electric cable which
exposes on the ground
 Report to the main contractor before
proceed to the demolition process
Skeleton structure of
Diaphragm wall

Installing the pile cap
RC Slab of Bridge

Precast Beam
5. Order/purchase materials
 Contact

the suppliers, negotiate the price of
materials
 Choose supplier with the best offer/price
 The material will be delivered to the site
CONCLUSION
THANK YOU 

Industrial training presentation

  • 1.
  • 2.
    INTRODUCTION Name Matric No : NursyafiqahIsmail : 156275 I was undergo my industrial training for 10 weeks in a construction company named Pembinaan Thin Chai Sdn. Bhd.
  • 3.
    BACKGROUND OF THE COMPANY   Incorporatedin 1970 by Mr Chai Min Choo The range of works include : > Bridge Construction: Land & Marine > Heavy Industrial Plant Works > Jetty Construction > Tunnel Lining Works > Runway, Taxiway & Parking Apron > Drainage & Road-works; Earthworks > Building Works > Water Treatment Plant, Reservoir & Dam > Structure Works
  • 4.
    WORK EXPERIENCES       Design analysisof fencing on parapet walls for bridge project in Port Klang Enhance software skills (AutoCAD) by preparing paperwork for method of statement for “spalled concrete on precast beams” and “launching of T beams on Pier 8-9” Prepare BoQ for tender and contracts Site inspection in Gua Musang Project and Port Klang Order and purchase materials Analyze the volume of ready mix concrete used every month, to estimate the progression of work
  • 5.
    1. Design analysis offencing on parapet walls  Consist of rectangular hollow section column, beams and zinc sheet  Subjected to wind loading  Mostly based on BS Code and Malaysia Meteorological Department  Must be in line with JKR requirements  Purpose of fencing : to provide safety for the road users, during the demolition of flyovers
  • 6.
     Difficulties Port Klang   toget the basic wind speed in Table provided in the BS Code is only suitable for UK climate Refer to Malaysia Meteorological Dept to find basic wind speed for Port Klang (near the sea)
  • 9.
    2. Method ofstatement MoS “Patch repair of spalled concrete on precast beam” and “modification of rib beam”.  Steps to repair the defect occurred on the beam  Approved by Professional Engineers before proceed with repair process MoS launching of T Beams  Draw the sequence of launching T Beams by using AutoCAD  Take into account, Mobilization and demobilization of crane  Closure of Traffic  Construct alternative road for road users, to avoid traffic congestion during launching 
  • 10.
    3. Prepare BoQ Preparing the Bill of Quantities to bid for tenders and contracts, below are such project :     AKLEH - Ampang KL Elevated Highway Prai CCGT Power Plant Construct barrage in Sg Johor Tender documentation
  • 11.
    4. Site Inspection– Gua Musang  Inspect the formwork of diaphragm wall on Bridge 2  Monitor concrete work of parapet walls  Get to see the process of launching T Beam on pier 8-9  Update the record of diesel on site  Update the summary record of ready mix concrete for July 2013
  • 12.
    Launching T Beam LaunchT beam using corrective method 1 Close the road Lifting Operation by Crane
  • 13.
  • 14.
  • 15.
    4. Site Inspection– Port Klang  Inspect the work progress of bridge construction  Inspect the location of flyover that will be demolish in order to construct bridge  Problems facing : -> the existence of electric cable which exposes on the ground  Report to the main contractor before proceed to the demolition process
  • 16.
    Skeleton structure of Diaphragmwall Installing the pile cap
  • 17.
    RC Slab ofBridge Precast Beam
  • 18.
    5. Order/purchase materials Contact the suppliers, negotiate the price of materials  Choose supplier with the best offer/price  The material will be delivered to the site
  • 19.
  • 21.