PROJECT COST MANAGEMENT
 A project consists of number of activities. Each of these activities consumes
resources. Resources cost money.
 PROJECT COST MANAGEMENT deals with controlling cost of the resources
needed to complete project activities.
1
STEPS IN PROJECT COST MANAGEMENT
1. Resources planning schedule
2. Cost planning
3. Cost budgeting
4. Cost control
2
1: Resources planning schedule
 These schedules shows the quantity requirement of each of the resources
either on weekly basis or on a monthly basis.
 Resources schedules such as material schedule , labour schedule, staff
schedule , equipment and plant schedule , subcontractor or specialist.
3
2: COST PLANNING
 It aims at ascertaining cost before many of decisions are made related to
design of facility.
 The essential components of cost planning are the project schedules and
estimates.
4
3: COST BUDGETING
 It is the process of allocating the overall cost estimate to individual work
items of the project.
 Work items are group of similar activities taken from bill of quantities.
 For example: concreting a different grades can be grouped under one
common head “CONCRETE”.
5
4: COST CONTROL
 The aim of cost control is to ensure that the final cost of project doesn’t
exceed to planned cost.
 The steps of cost control are :
-observe the cost expended for an item
-comparing it with available standards
-compute the variance between the observed cost and standard cost.
6
Collection of cost related information
 Labour cost
 Material cost
 Plant and equipment cost
 Subcontractor cost
 Overhead cost
7
COST CODES
 It is the standardization of letters, number, words or symbols for
representation of various items of works.
 It is the code assigned to an activity for which a particular cost is incurred.
 They are allocated by planning department depending on the nature of
activity at site.
 The number of cost codes should neither be too large nor too small.
 They are also called cost heads.
8
COST STATEMENT
1. Cost codes are alloted.
2. Collection of cost related information .
3. Determination of provision for expenses.
4. Determination of deferred expenses
5. Compilation of above costs in the given formats, finalizing total cost code
wise, and arriving at project cost.
9
A typical cost statement
10
VALUE MANAGEMENT IN CONSTRUCTION
 Value engineering is defined as systematic objective and analytical approach
to effectively identify unnecessary costs in construction.
 It is also known as value management or value analysis.
 Value index = worth / cost
11
Value index can be increased by :
 Improving the utility with no change in cost.
 Retaining the same utility for less cost.
 Combining improved utility and less cost.
12
Steps in application of value engineering
1. Different plant and non plant structures are compared with respect to their
cost .
2. Various elements and materials aspects are analysed cost wise.
3. A “FAST” diagram is constructed.
4. All the possible alternatives are then generated to cater to the functions
identified in previous step.
5. The identified alternative are then evaluated in two stages
13
6. The criteria with the highest mean value is rated as first and vice versa.
7. The weights of each criteria is then obtained by evaluation matrix.
8. The alternatives are evaluated against each of the performance criteria.
9. The ranks given are multiplied by corresponding weights of criteria and
receptioning scores are calculated.
10. The alternative with the highest score is thus selected.
14
THANK YOU
15

Cost & value management

  • 1.
    PROJECT COST MANAGEMENT A project consists of number of activities. Each of these activities consumes resources. Resources cost money.  PROJECT COST MANAGEMENT deals with controlling cost of the resources needed to complete project activities. 1
  • 2.
    STEPS IN PROJECTCOST MANAGEMENT 1. Resources planning schedule 2. Cost planning 3. Cost budgeting 4. Cost control 2
  • 3.
    1: Resources planningschedule  These schedules shows the quantity requirement of each of the resources either on weekly basis or on a monthly basis.  Resources schedules such as material schedule , labour schedule, staff schedule , equipment and plant schedule , subcontractor or specialist. 3
  • 4.
    2: COST PLANNING It aims at ascertaining cost before many of decisions are made related to design of facility.  The essential components of cost planning are the project schedules and estimates. 4
  • 5.
    3: COST BUDGETING It is the process of allocating the overall cost estimate to individual work items of the project.  Work items are group of similar activities taken from bill of quantities.  For example: concreting a different grades can be grouped under one common head “CONCRETE”. 5
  • 6.
    4: COST CONTROL The aim of cost control is to ensure that the final cost of project doesn’t exceed to planned cost.  The steps of cost control are : -observe the cost expended for an item -comparing it with available standards -compute the variance between the observed cost and standard cost. 6
  • 7.
    Collection of costrelated information  Labour cost  Material cost  Plant and equipment cost  Subcontractor cost  Overhead cost 7
  • 8.
    COST CODES  Itis the standardization of letters, number, words or symbols for representation of various items of works.  It is the code assigned to an activity for which a particular cost is incurred.  They are allocated by planning department depending on the nature of activity at site.  The number of cost codes should neither be too large nor too small.  They are also called cost heads. 8
  • 9.
    COST STATEMENT 1. Costcodes are alloted. 2. Collection of cost related information . 3. Determination of provision for expenses. 4. Determination of deferred expenses 5. Compilation of above costs in the given formats, finalizing total cost code wise, and arriving at project cost. 9
  • 10.
    A typical coststatement 10
  • 11.
    VALUE MANAGEMENT INCONSTRUCTION  Value engineering is defined as systematic objective and analytical approach to effectively identify unnecessary costs in construction.  It is also known as value management or value analysis.  Value index = worth / cost 11
  • 12.
    Value index canbe increased by :  Improving the utility with no change in cost.  Retaining the same utility for less cost.  Combining improved utility and less cost. 12
  • 13.
    Steps in applicationof value engineering 1. Different plant and non plant structures are compared with respect to their cost . 2. Various elements and materials aspects are analysed cost wise. 3. A “FAST” diagram is constructed. 4. All the possible alternatives are then generated to cater to the functions identified in previous step. 5. The identified alternative are then evaluated in two stages 13
  • 14.
    6. The criteriawith the highest mean value is rated as first and vice versa. 7. The weights of each criteria is then obtained by evaluation matrix. 8. The alternatives are evaluated against each of the performance criteria. 9. The ranks given are multiplied by corresponding weights of criteria and receptioning scores are calculated. 10. The alternative with the highest score is thus selected. 14
  • 15.