SlideShare a Scribd company logo
1 of 17
Submitted by
"Mr . AMAR M.GAIKWAD"
Under the guidance of
" Prof. S.A. Joshi "
DEPARTMENT OF PETROLEUM ENGINEERING
MAEER'S
MAHARASTRA INSTITUTE OF TECHNOLOGY,PUNE
UNIVERSITY OF PUNE
2015-2016
 What is Christmas tree?
 The set of valves, spools & fittings connected
to the top of the well to isolate, direct and
control the flow wellbore fluids.
 The control valves, pressure gauges and
chokes assembled at the top of the well to
control the flow of oil and gas after the well
has been drilled and completed.
 The purpose of a production
Christmas Tree:
 The purpose of an injection
Christmas Tree: Fig. Schematic of Wellhead & Christmas Tree
 Tubing Hanger
 Tubing Head Spool
 Tree piping
 Flow line connector
 Wellhead connector
 Valves and fittings
 Choke
 Safety barrier
 Safely stop produced or injected fluid
 Injection of chemicals to well or flow line
 Allow for control of down hole valves
 Allow for electrical signals to down hole gauges
 To bleed of excessive pressure from annulus
 Regulate fluid flow through a choke
 Allow for well intervention
 API 6A: Specification for Wellhead and Christmas Tree
Equipment.
 API 17D: Design and Operation of Subsea Production
Systems-Subsea Wellhead and Tree Equipment.
 ISO 13628-4: Petroleum and natural gas industries –
Design and operation of subsea production systems.
 ISO 10423:2009: Petroleum and natural gas industries -
Drilling and production equipment - Wellhead and
Christmas tree equipment.
1. Vertical Christmas Tree
2. Horizontal Christmas Tree
l Christmas Tree
Vertical Christmas Tree Horizontal Christmas Tree
Horizontal tree Vertical tree
 Production master valve (PMV) in
horizontal bore
 Single, concentric bore
 Must pull the production tubing to retrieve
the tree
 Both barriers fail if the tree is accidentally
removed
 Designed to take the load from a BOP
(increased weight)
 Batch-wise completion possible
 Tubing hanger is installed in the tree body
instead of the wellhead.
 The Horizontal tree concept can be further
defined as –
1.“Partial Drilling HT”
2.“Full Drilling HT”
 Production master valve (PMV) in vertical
bore
 Dual bore (production + annulus)
 Must pull the tree to retrieve the production
tubing
 Requires landing string to secure well before
work over
 Primary barrier is maintained if the tree is
accidentally removed
 Not designed to take the load from a BOP
 The vertical tree concept can be further defined
as –
1.“Eccentric” production flow is routed
eccentrically (dual bore configuration)
2.“Concentric” concentrically (single bore
configuration) through the tubing hanger.
 The valves are mounted on the lateral sides, allowing for simple
well intervention and tubing recovery.
 This concept is especially beneficial for wells that need a high
number of interventions.
 Swab valves are not used in the HXT since they have electrical
submersible pumps applications.
 The key feature of the HXT is that the tubing hanger is installed
in the tree body instead of the wellhead.
 This arrangement requires the tree to be installed onto the
wellhead before completion of the well.
Fig. Partial Drilling HT Fig. Full Drilling HT
 Partial Drilling HT:
 Diana, Marshall, Madison
(ExxonMobil GOM)
 Mica (ExxonMobil GOM)
 Kizomba (ExxonMobil
Angola)
 Full Drilling HT:
 Dalia (Total Fina Elf –
Block 17 Offshore Angola)
 Ross (Talisman Energy –
North Sea UK)
 The master valves are configured above the tubing hanger in the
vertical Xmas tree (VXT).
 VXT are applied commonly and widely in subsea fields due to
their flexibility of installation and operation.
 The vertical tree concept can be further defined as –
 “Eccentric” production flow is routed eccentrically (dual bore
configuration)
 “Concentric” concentrically (single bore configuration) through
the tubing hanger.
Fig. Concentric Mono-bore VTFig. Eccentric Dual Bore VT
 Eccentric VT:-
 Zinc (ExxonMobil – GOM)
 Girossol (Total Fina Elf -
Block 17 Offshore Angola)
 Balder (ExxonMobil –
North Sea Norway)
 Blackback (ExxonMobil –
Austraila)
 Concentric VT:-
 Bongo (Shell – Nigeria)
 Mensa (BP – GOM)
 Crazy Horse (BP – GOM)
 Macaroni (Shell – GOM)
 The cost of an HXT is much higher than that of a VXT; typically the purchase
price of an HXT is five to seven times more.
 A VXT is larger and heavier, which should be considered if the installation area
of the rig is limited.
 Completion of the well is another factor in selecting an HXT or VXT. If the
well is completed but the tree has not yet been prepared, a VXT is needed. Or if
an HXT is desired, then the well must be completed after installation of the tree.
 An HXT is not recommended for use in a gas field because interventions are
rarely needed.
 For the last 20 years the Horizontal Christmas tree has been the preferred
design for deepwater fields, while in recent years the focus in the industry
is returning to the conventional Vertical Christmas tree system.
 An HXT is applied in complex reservoirs or those needing frequent
workovers that require tubing retrieval, whereas a VXT is often chosen for
simple reservoirs or when the frequency of tubing retrieval workovers is
low.
 A tree often provides numerous additional functions including chemical
injection points, well intervention means, pressure relief means, monitoring
points such as pressure, temperature, corrosion, erosion, sand detection,
flow rate, flow composition, valve and choke position feedback, and
connection points for devices such as down hole pressure and temperature
transducers.
1.Towns, T. K., Deeken, D. G., Derby, L. M., Exxon Mobil Development
Company, “Diana Subsea Tree Selection and Installation Results in
4,653 Feet of Water” Deep Offshore Technology held in Rio de Janeiro,
Brazil, October 17-19, 2001.
2. Moyer, M.C., Barry, M.D., Tears, N.C., "Hoover-Diana Deepwater
Drilling and Completions", OTC 13081, Offshore Technology
Conference, Houston,, May 2001.
3. Havard Devold," Oil And Gas Production Handbook", An Introduction
to Oil And Production, ABB Oil And Gas, May (2009), Edition 2.0
Oslo,29-32.
4. Oda Ingeborg Stendebakken, NTNU Trondheim, "A reliability study of
a Deepwater Vertical Christmas Tree with attention to XT retrieval
rate", June (2014),11-32.
5. Randy J. Wester and Eric P. Ringle / FMC Energy Systems," Installation
and Work over Time Savings: Key Drivers for Deepwater Tree
Selection" ,OCT 12943, Offshore Technology Conference, May (2001).
Horizontal vertical christmas tree ppt

More Related Content

What's hot

Well completion techniques
Well completion techniquesWell completion techniques
Well completion techniquesvelMurugan260
 
WELLHEAD FOR OIL AND GAS WELL.pptx
WELLHEAD FOR OIL AND GAS WELL.pptxWELLHEAD FOR OIL AND GAS WELL.pptx
WELLHEAD FOR OIL AND GAS WELL.pptxHandaBinAdi
 
Wellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreWellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreMohamed Abdelshafy Abozeima
 
Subsurface safety valves
Subsurface safety valvesSubsurface safety valves
Subsurface safety valvesAkhilesh Maurya
 
Installation procedures of wellhead
Installation procedures of wellheadInstallation procedures of wellhead
Installation procedures of wellheadElsayed Amer
 
WELL COMPLETION, WELL INTERVENTION/ STIMULATION, AND WORKOVER
WELL COMPLETION, WELL INTERVENTION/ STIMULATION, AND WORKOVERWELL COMPLETION, WELL INTERVENTION/ STIMULATION, AND WORKOVER
WELL COMPLETION, WELL INTERVENTION/ STIMULATION, AND WORKOVERAndi Anriansyah
 
1. sequance of well drilling and completion part 1
1. sequance of well drilling and completion part 11. sequance of well drilling and completion part 1
1. sequance of well drilling and completion part 1Elsayed Amer
 
Completion equipment part 1
Completion equipment part 1Completion equipment part 1
Completion equipment part 1Elsayed Amer
 
1. completion sequance
1. completion sequance1. completion sequance
1. completion sequanceElsayed Amer
 
Valves operation and functions complete guide
Valves operation and functions complete guideValves operation and functions complete guide
Valves operation and functions complete guideElsayed Amer
 
Managing Downhole Failures in a Rod Pumped Well
Managing Downhole Failures in a Rod Pumped Well Managing Downhole Failures in a Rod Pumped Well
Managing Downhole Failures in a Rod Pumped Well Ramez Abdalla, M.Sc
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1Elsayed Amer
 
Drilling Problems.pdf
Drilling Problems.pdfDrilling Problems.pdf
Drilling Problems.pdfTinaMarey
 

What's hot (20)

Well completion techniques
Well completion techniquesWell completion techniques
Well completion techniques
 
Wellhead
WellheadWellhead
Wellhead
 
WELLHEAD FOR OIL AND GAS WELL.pptx
WELLHEAD FOR OIL AND GAS WELL.pptxWELLHEAD FOR OIL AND GAS WELL.pptx
WELLHEAD FOR OIL AND GAS WELL.pptx
 
Wellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreWellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and more
 
Tubing string
Tubing stringTubing string
Tubing string
 
Subsurface safety valves
Subsurface safety valvesSubsurface safety valves
Subsurface safety valves
 
Well completion fundamentals
Well completion fundamentalsWell completion fundamentals
Well completion fundamentals
 
Installation procedures of wellhead
Installation procedures of wellheadInstallation procedures of wellhead
Installation procedures of wellhead
 
WELL COMPLETION, WELL INTERVENTION/ STIMULATION, AND WORKOVER
WELL COMPLETION, WELL INTERVENTION/ STIMULATION, AND WORKOVERWELL COMPLETION, WELL INTERVENTION/ STIMULATION, AND WORKOVER
WELL COMPLETION, WELL INTERVENTION/ STIMULATION, AND WORKOVER
 
1. sequance of well drilling and completion part 1
1. sequance of well drilling and completion part 11. sequance of well drilling and completion part 1
1. sequance of well drilling and completion part 1
 
Completion equipment part 1
Completion equipment part 1Completion equipment part 1
Completion equipment part 1
 
well control (1)
 well control (1) well control (1)
well control (1)
 
Well completion and testing
Well completion and testingWell completion and testing
Well completion and testing
 
Production packer
Production packerProduction packer
Production packer
 
1. completion sequance
1. completion sequance1. completion sequance
1. completion sequance
 
Valves operation and functions complete guide
Valves operation and functions complete guideValves operation and functions complete guide
Valves operation and functions complete guide
 
Managing Downhole Failures in a Rod Pumped Well
Managing Downhole Failures in a Rod Pumped Well Managing Downhole Failures in a Rod Pumped Well
Managing Downhole Failures in a Rod Pumped Well
 
Packers GFK
Packers GFKPackers GFK
Packers GFK
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1
 
Drilling Problems.pdf
Drilling Problems.pdfDrilling Problems.pdf
Drilling Problems.pdf
 

Viewers also liked

Manifold design, verification,_and_validation
Manifold design, verification,_and_validationManifold design, verification,_and_validation
Manifold design, verification,_and_validationjpegd
 
[Ajaya kumar gupta]_response_spectrum_method_in_se(book_zz.org)
[Ajaya kumar gupta]_response_spectrum_method_in_se(book_zz.org)[Ajaya kumar gupta]_response_spectrum_method_in_se(book_zz.org)
[Ajaya kumar gupta]_response_spectrum_method_in_se(book_zz.org)Hemant Solanki
 
What subsea control systems low res
What   subsea control systems low resWhat   subsea control systems low res
What subsea control systems low resTomásio Leite
 
Tbi peer2010 05 guidelines for performance based seismic design of tall buil...
Tbi peer2010 05  guidelines for performance based seismic design of tall buil...Tbi peer2010 05  guidelines for performance based seismic design of tall buil...
Tbi peer2010 05 guidelines for performance based seismic design of tall buil...Ramil Artates
 
J Ray Firsts
J Ray FirstsJ Ray Firsts
J Ray FirstsMyLast1
 
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...Cathie Associates
 
ACI Provisions for Seismic Design
ACI Provisions for Seismic Design ACI Provisions for Seismic Design
ACI Provisions for Seismic Design Abdulrahman Salah
 
Advanced blowout and well control robert d. grace
Advanced blowout and well control   robert d. graceAdvanced blowout and well control   robert d. grace
Advanced blowout and well control robert d. graceThần Chết Nụ Hôn
 
Seismic Conceptual Design of Buildings
Seismic Conceptual Design of BuildingsSeismic Conceptual Design of Buildings
Seismic Conceptual Design of BuildingsMohd Danish
 
OIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREE
OIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREEOIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREE
OIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREEPZoneSlide
 
Performance Based Design Presentation By Deepak Bashetty
Performance Based Design Presentation By Deepak BashettyPerformance Based Design Presentation By Deepak Bashetty
Performance Based Design Presentation By Deepak BashettyDeepak Bashetty
 

Viewers also liked (18)

Manifold design, verification,_and_validation
Manifold design, verification,_and_validationManifold design, verification,_and_validation
Manifold design, verification,_and_validation
 
Spar Information
Spar InformationSpar Information
Spar Information
 
[Ajaya kumar gupta]_response_spectrum_method_in_se(book_zz.org)
[Ajaya kumar gupta]_response_spectrum_method_in_se(book_zz.org)[Ajaya kumar gupta]_response_spectrum_method_in_se(book_zz.org)
[Ajaya kumar gupta]_response_spectrum_method_in_se(book_zz.org)
 
What subsea control systems low res
What   subsea control systems low resWhat   subsea control systems low res
What subsea control systems low res
 
Tbi peer2010 05 guidelines for performance based seismic design of tall buil...
Tbi peer2010 05  guidelines for performance based seismic design of tall buil...Tbi peer2010 05  guidelines for performance based seismic design of tall buil...
Tbi peer2010 05 guidelines for performance based seismic design of tall buil...
 
J Ray Firsts
J Ray FirstsJ Ray Firsts
J Ray Firsts
 
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...
Anticipation and Mitigation of Geohazards for Subsea Power Cables (and Pipeli...
 
ACI Provisions for Seismic Design
ACI Provisions for Seismic Design ACI Provisions for Seismic Design
ACI Provisions for Seismic Design
 
Lecture44
Lecture44Lecture44
Lecture44
 
Advanced blowout and well control robert d. grace
Advanced blowout and well control   robert d. graceAdvanced blowout and well control   robert d. grace
Advanced blowout and well control robert d. grace
 
Seismic Conceptual Design of Buildings
Seismic Conceptual Design of BuildingsSeismic Conceptual Design of Buildings
Seismic Conceptual Design of Buildings
 
Spar Platforms
Spar PlatformsSpar Platforms
Spar Platforms
 
Norwegian subsea
Norwegian subseaNorwegian subsea
Norwegian subsea
 
Seismic Design Basics - Superstructure
Seismic Design Basics - SuperstructureSeismic Design Basics - Superstructure
Seismic Design Basics - Superstructure
 
Seismic Design - Introduction
Seismic Design - IntroductionSeismic Design - Introduction
Seismic Design - Introduction
 
OIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREE
OIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREEOIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREE
OIL AND GAS SURFACE WELLHEAD AND CHRISTMAS TREE
 
Performance Based Design Presentation By Deepak Bashetty
Performance Based Design Presentation By Deepak BashettyPerformance Based Design Presentation By Deepak Bashetty
Performance Based Design Presentation By Deepak Bashetty
 
ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8 ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
ETABS manual - Seismic design of steel buildings according to Eurocode 3 & 8
 

Similar to Horizontal vertical christmas tree ppt

Well Complection - Basic-1.pptx
Well Complection - Basic-1.pptxWell Complection - Basic-1.pptx
Well Complection - Basic-1.pptx4twerdefwef
 
Overview of subsea production systems
Overview of subsea production systemsOverview of subsea production systems
Overview of subsea production systemsGiuseppe Moricca
 
Completion equipment .pptx
Completion equipment .pptxCompletion equipment .pptx
Completion equipment .pptxAref12345
 
Valves in Pipelines-December 20150Final
Valves in Pipelines-December 20150FinalValves in Pipelines-December 20150Final
Valves in Pipelines-December 20150Finalgobindkhiani
 
Anchois 1- Oil&Gas Field
Anchois 1- Oil&Gas FieldAnchois 1- Oil&Gas Field
Anchois 1- Oil&Gas FieldJose V.Taboada
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15John Grover
 
Methodology for optimum deepwater safety system selection
Methodology for optimum deepwater safety system selectionMethodology for optimum deepwater safety system selection
Methodology for optimum deepwater safety system selectionamrhaggag
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control systemAmit Nitharwal
 
SPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdfSPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdfJalal Neshat
 
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...John Grover
 
Petro equipment suppliers association credit suisse presentation
Petro equipment suppliers association   credit suisse presentationPetro equipment suppliers association   credit suisse presentation
Petro equipment suppliers association credit suisse presentationgiorgiogarrido6
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailraceRakesh Sunari Magar
 
Stress analysis of storage tank piping - Jeba Anand
Stress analysis of storage tank  piping - Jeba AnandStress analysis of storage tank  piping - Jeba Anand
Stress analysis of storage tank piping - Jeba AnandJeba Anand Nadar
 
Spe26043 (fluid entry)
Spe26043 (fluid entry)Spe26043 (fluid entry)
Spe26043 (fluid entry)Gregg Linville
 
SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)Gregg Linville
 

Similar to Horizontal vertical christmas tree ppt (20)

Well Complection - Basic-1.pptx
Well Complection - Basic-1.pptxWell Complection - Basic-1.pptx
Well Complection - Basic-1.pptx
 
Overview of subsea production systems
Overview of subsea production systemsOverview of subsea production systems
Overview of subsea production systems
 
Completion equipment .pptx
Completion equipment .pptxCompletion equipment .pptx
Completion equipment .pptx
 
Valves in Pipelines-December 20150Final
Valves in Pipelines-December 20150FinalValves in Pipelines-December 20150Final
Valves in Pipelines-December 20150Final
 
Anchois 1- Oil&Gas Field
Anchois 1- Oil&Gas FieldAnchois 1- Oil&Gas Field
Anchois 1- Oil&Gas Field
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
Methodology for optimum deepwater safety system selection
Methodology for optimum deepwater safety system selectionMethodology for optimum deepwater safety system selection
Methodology for optimum deepwater safety system selection
 
Subsea completion and control system
Subsea completion and control systemSubsea completion and control system
Subsea completion and control system
 
Well work over
Well work overWell work over
Well work over
 
SPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdfSPE171748 Surface Safety System for ZADCO (4).pdf
SPE171748 Surface Safety System for ZADCO (4).pdf
 
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
 
Descon Presentation
Descon PresentationDescon Presentation
Descon Presentation
 
Branch connections
Branch connectionsBranch connections
Branch connections
 
Defining Well completion
Defining Well completionDefining Well completion
Defining Well completion
 
Petro equipment suppliers association credit suisse presentation
Petro equipment suppliers association   credit suisse presentationPetro equipment suppliers association   credit suisse presentation
Petro equipment suppliers association credit suisse presentation
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailrace
 
Stress analysis of storage tank piping - Jeba Anand
Stress analysis of storage tank  piping - Jeba AnandStress analysis of storage tank  piping - Jeba Anand
Stress analysis of storage tank piping - Jeba Anand
 
Spe26043 (fluid entry)
Spe26043 (fluid entry)Spe26043 (fluid entry)
Spe26043 (fluid entry)
 
SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)SPE26043 (Fluid Entry)
SPE26043 (Fluid Entry)
 
Final thesis presentation.
Final thesis presentation.Final thesis presentation.
Final thesis presentation.
 

Recently uploaded

mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 

Recently uploaded (20)

mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 

Horizontal vertical christmas tree ppt

  • 1. Submitted by "Mr . AMAR M.GAIKWAD" Under the guidance of " Prof. S.A. Joshi " DEPARTMENT OF PETROLEUM ENGINEERING MAEER'S MAHARASTRA INSTITUTE OF TECHNOLOGY,PUNE UNIVERSITY OF PUNE 2015-2016
  • 2.  What is Christmas tree?  The set of valves, spools & fittings connected to the top of the well to isolate, direct and control the flow wellbore fluids.  The control valves, pressure gauges and chokes assembled at the top of the well to control the flow of oil and gas after the well has been drilled and completed.  The purpose of a production Christmas Tree:  The purpose of an injection Christmas Tree: Fig. Schematic of Wellhead & Christmas Tree
  • 3.  Tubing Hanger  Tubing Head Spool  Tree piping  Flow line connector  Wellhead connector  Valves and fittings  Choke
  • 4.  Safety barrier  Safely stop produced or injected fluid  Injection of chemicals to well or flow line  Allow for control of down hole valves  Allow for electrical signals to down hole gauges  To bleed of excessive pressure from annulus  Regulate fluid flow through a choke  Allow for well intervention
  • 5.  API 6A: Specification for Wellhead and Christmas Tree Equipment.  API 17D: Design and Operation of Subsea Production Systems-Subsea Wellhead and Tree Equipment.  ISO 13628-4: Petroleum and natural gas industries – Design and operation of subsea production systems.  ISO 10423:2009: Petroleum and natural gas industries - Drilling and production equipment - Wellhead and Christmas tree equipment.
  • 6. 1. Vertical Christmas Tree 2. Horizontal Christmas Tree l Christmas Tree Vertical Christmas Tree Horizontal Christmas Tree
  • 7. Horizontal tree Vertical tree  Production master valve (PMV) in horizontal bore  Single, concentric bore  Must pull the production tubing to retrieve the tree  Both barriers fail if the tree is accidentally removed  Designed to take the load from a BOP (increased weight)  Batch-wise completion possible  Tubing hanger is installed in the tree body instead of the wellhead.  The Horizontal tree concept can be further defined as – 1.“Partial Drilling HT” 2.“Full Drilling HT”  Production master valve (PMV) in vertical bore  Dual bore (production + annulus)  Must pull the tree to retrieve the production tubing  Requires landing string to secure well before work over  Primary barrier is maintained if the tree is accidentally removed  Not designed to take the load from a BOP  The vertical tree concept can be further defined as – 1.“Eccentric” production flow is routed eccentrically (dual bore configuration) 2.“Concentric” concentrically (single bore configuration) through the tubing hanger.
  • 8.  The valves are mounted on the lateral sides, allowing for simple well intervention and tubing recovery.  This concept is especially beneficial for wells that need a high number of interventions.  Swab valves are not used in the HXT since they have electrical submersible pumps applications.  The key feature of the HXT is that the tubing hanger is installed in the tree body instead of the wellhead.  This arrangement requires the tree to be installed onto the wellhead before completion of the well.
  • 9. Fig. Partial Drilling HT Fig. Full Drilling HT
  • 10.  Partial Drilling HT:  Diana, Marshall, Madison (ExxonMobil GOM)  Mica (ExxonMobil GOM)  Kizomba (ExxonMobil Angola)  Full Drilling HT:  Dalia (Total Fina Elf – Block 17 Offshore Angola)  Ross (Talisman Energy – North Sea UK)
  • 11.  The master valves are configured above the tubing hanger in the vertical Xmas tree (VXT).  VXT are applied commonly and widely in subsea fields due to their flexibility of installation and operation.  The vertical tree concept can be further defined as –  “Eccentric” production flow is routed eccentrically (dual bore configuration)  “Concentric” concentrically (single bore configuration) through the tubing hanger.
  • 12. Fig. Concentric Mono-bore VTFig. Eccentric Dual Bore VT
  • 13.  Eccentric VT:-  Zinc (ExxonMobil – GOM)  Girossol (Total Fina Elf - Block 17 Offshore Angola)  Balder (ExxonMobil – North Sea Norway)  Blackback (ExxonMobil – Austraila)  Concentric VT:-  Bongo (Shell – Nigeria)  Mensa (BP – GOM)  Crazy Horse (BP – GOM)  Macaroni (Shell – GOM)
  • 14.  The cost of an HXT is much higher than that of a VXT; typically the purchase price of an HXT is five to seven times more.  A VXT is larger and heavier, which should be considered if the installation area of the rig is limited.  Completion of the well is another factor in selecting an HXT or VXT. If the well is completed but the tree has not yet been prepared, a VXT is needed. Or if an HXT is desired, then the well must be completed after installation of the tree.  An HXT is not recommended for use in a gas field because interventions are rarely needed.
  • 15.  For the last 20 years the Horizontal Christmas tree has been the preferred design for deepwater fields, while in recent years the focus in the industry is returning to the conventional Vertical Christmas tree system.  An HXT is applied in complex reservoirs or those needing frequent workovers that require tubing retrieval, whereas a VXT is often chosen for simple reservoirs or when the frequency of tubing retrieval workovers is low.  A tree often provides numerous additional functions including chemical injection points, well intervention means, pressure relief means, monitoring points such as pressure, temperature, corrosion, erosion, sand detection, flow rate, flow composition, valve and choke position feedback, and connection points for devices such as down hole pressure and temperature transducers.
  • 16. 1.Towns, T. K., Deeken, D. G., Derby, L. M., Exxon Mobil Development Company, “Diana Subsea Tree Selection and Installation Results in 4,653 Feet of Water” Deep Offshore Technology held in Rio de Janeiro, Brazil, October 17-19, 2001. 2. Moyer, M.C., Barry, M.D., Tears, N.C., "Hoover-Diana Deepwater Drilling and Completions", OTC 13081, Offshore Technology Conference, Houston,, May 2001. 3. Havard Devold," Oil And Gas Production Handbook", An Introduction to Oil And Production, ABB Oil And Gas, May (2009), Edition 2.0 Oslo,29-32. 4. Oda Ingeborg Stendebakken, NTNU Trondheim, "A reliability study of a Deepwater Vertical Christmas Tree with attention to XT retrieval rate", June (2014),11-32. 5. Randy J. Wester and Eric P. Ringle / FMC Energy Systems," Installation and Work over Time Savings: Key Drivers for Deepwater Tree Selection" ,OCT 12943, Offshore Technology Conference, May (2001).