SlideShare a Scribd company logo
CONCRETE
DAM
ENGINEERING
Components of a Gravity
Dam and their Functions
1/28/2014 1
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
Components of a Gravity
Dam and their Functions
Drainage galleries
Shafts
Overflow section
Non-overflow section
Power house
Energy dissipation works
Outlets
Joints
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
2
Drainage galleries :
A gallery is a small passage in a dam for
providing an access to the interior of the
dam.
The gallery is usually rectangular in shape
with its top and bottom either flat or semi
circular.
For a gallery with its top and bottom flat,
it is necessary that all the corners should
be rounded. The width of gallery generally
varies from 1.5 to 1.8 m. The height of the
gallery in between 2.2 to 2.4 m, so that a
person can easily walk inside it.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
3
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
4
Types of gallery based on
uses :
A Foundation gallery
b. Drainage gallery
c. Inspection gallery
d. Grouting gallery
e. Gate gallery
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
5
Functions of a gallery :
1. To provide drainage of the dam
section.
2. To provide space for equipment
required for drilling holes and
grouting the hole to form a grout
curtain in the foundation.
3. To provide space for header and
return pipes for post cooling of
concrete.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
6
4. A gallery provide an access to the
interior of the dam for inspection
ard maintenance.
5. A Gallery also provides space for
installing various instruments in
the dam to study its structural
behaviour.
6. A gallery can provide space for
the mechanical and electrical
equipment required for the
operation of gates for spillways and
outlets.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
7
2. Shafts :
A shaft is a vertical opening
provided in a dam. Shafts are
required for locating headers of the
post cooling system and for locating
measuring devices.
Shafts are also required for the
movement of elevators and the
hoisting equipment. Sometimes
shafts are constructed inclined to
connect two galleries or the same
gallery at two different elevations
by a staircase or a lift arrangement.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
8
A plumb line shaft is constructed at
the maximum section of the dam to
make observations of the deflection
of the dam under loads.
A plumb bob is suspended by a wire
fixed at the top of the shaft. As the
dam deflects relative to the base,
the plumb bob also moves by the
same amount.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
9
A stilling well shaft is a special
shaft used to record fluctuations of
the water level in the reservoir. The
shaft is connected to the reservoir
at a point below the minimum
reservoir level.
There is a floating mechanism in
the stilling well shaft which records
fluctuations in the water level.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
10
3. overflow Section :
The spillway in a gravity dam is called
overflow section. Spillway is provided
to dispose of surpluswater from the
reservoir to the downstream.
Spillways are provided for all dams as
a safety measure against overtopping
and the consequent damages, and
failure. spillway may be located either
in the middle of the dam or at the end
of the dam near abutment.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
11
Requirements of Spillway :
It must have adequate discharge
capacity.
It must be hydraulically and
structurally safe.
The surface of the spillway must be
erosion resistant.
It should be provided with some
device for the dissipation of excess
energy.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
12
Non-overflow section :
The portion of the gravity dam
other than the spillway is a non-
overflow section, a road is located
on the non-overflow section of the
dam.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
13
Power house :
At the one end of a gravity dam a
power house is located. Water from
the reservoir passes tnrough
penstock and rotates the turbine
provided at power elevations to
produce electricity.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
14
Energy dissipation works :
Water flowing over a spillway has a
very high kinetic energy because of
the conversion of the entire potential
energy to the kinetic energy. If the
water flowing with such a high
velocity is discharged directly into the
channel down stream, serious scour of
the channel may be occur. If the scour
is not properly controlled it may
extend backward and may damage the
spillway and the dam.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
15
The energy dissipation devices can be
broadly classified into two types.
Devices using a hydraulic jump
Devices using a bucket
Following constructions are provided
for energy dissipation :
11 Deflector bucket
1) Sharply upturned bucket
5 End sill with baffles
- Stilling basin,
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
16
7. Outlets :
A major portion of the storage volume
in the reservoir on the upstream of a
dam is below the spillway crest level.
Dam outlets are provided in the body
of the dam or its abutments below the
crest level of the spillways so that the
water can be withdrawn from the
reservoir.
Sluiceways are the special type of
outlets provides in the body of a
concrete gravity dam
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
17
Classification of outlets
based on purpose :
River outlet - discharge water into the
river
Canal outlet - discharge water into the
canal.
Pipe outlet - delivers water into a
closed pipe.
Classification of outlet based on gates :
• Gated outlets
• Ungated outlets
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
18
8. Joints :
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
19
(a) Construction Joints
Construction joints are providedfor ease in
construction of the dam. They also permits
systematic, convenient and economical
construction of the dam. It is usual
practice to place the concrete in a gravity
dam in lifts so as to avoid excessive heat of
hydration of cement.
These are the horizontal joints. The
thickness of each layer of concrete should
not be more than 1.5 m. The thickness of
the first layer of concrete above rock
foundation should not be more than 0.75
m.
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
20
(b) Contraction joints :
Contraction joints are provided to
avoid cracks caused due to
shrinkage of concrete due to
temperature changes.
Contraction joints are of two types :
(i) Transverse joints
(ii) Longitudinal joints
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
21
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
22
1/28/2014
PREPARED BY V.H.KHOKHANI,
ASSISTANT PROFESSOR, DIET
23

More Related Content

What's hot

Canal outlets and modules
Canal outlets and modulesCanal outlets and modules
Canal outlets and modules
bhalinder singh
 
Canal falls and its classification
Canal falls and its classificationCanal falls and its classification
Canal falls and its classification
GNANA PRAKASH
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
RAMPRASAD KUMAWAT
 
Spillway gates
Spillway gatesSpillway gates
Spillway gates
murali mohan
 
Design of gravity dams
Design of gravity damsDesign of gravity dams
Design of gravity dams
VikramKesharwani1
 
Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipator
SAGAR RAUT
 
types of canals
types of canals types of canals
types of canals
number113
 
Types of earth dams
Types of earth damsTypes of earth dams
Types of earth dams
saibabu48
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
Jimit Shah
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
Rajkumar G
 
Gravity dam
Gravity damGravity dam
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage Works
GAURAV. H .TANDON
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
GAURAV. H .TANDON
 
Importance of highway maintenance
Importance of highway maintenanceImportance of highway maintenance
Importance of highway maintenance
Dharmesh Vadher
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
Aaquib ansari
 
Reservior planning
Reservior    planningReservior    planning
Gallery in Concrete Gravity Dam
Gallery in Concrete Gravity DamGallery in Concrete Gravity Dam
Gallery in Concrete Gravity Dam
Manish Khandelwal
 
weir & barrage
weir & barrageweir & barrage
weir & barrage
Raj Daxini
 
Spillways
SpillwaysSpillways
Regulation Works
Regulation WorksRegulation Works
Regulation Works
Malla Reddy University
 

What's hot (20)

Canal outlets and modules
Canal outlets and modulesCanal outlets and modules
Canal outlets and modules
 
Canal falls and its classification
Canal falls and its classificationCanal falls and its classification
Canal falls and its classification
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Spillway gates
Spillway gatesSpillway gates
Spillway gates
 
Design of gravity dams
Design of gravity damsDesign of gravity dams
Design of gravity dams
 
Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipator
 
types of canals
types of canals types of canals
types of canals
 
Types of earth dams
Types of earth damsTypes of earth dams
Types of earth dams
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
 
Gravity dam
Gravity damGravity dam
Gravity dam
 
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage Works
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Importance of highway maintenance
Importance of highway maintenanceImportance of highway maintenance
Importance of highway maintenance
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
 
Reservior planning
Reservior    planningReservior    planning
Reservior planning
 
Gallery in Concrete Gravity Dam
Gallery in Concrete Gravity DamGallery in Concrete Gravity Dam
Gallery in Concrete Gravity Dam
 
weir & barrage
weir & barrageweir & barrage
weir & barrage
 
Spillways
SpillwaysSpillways
Spillways
 
Regulation Works
Regulation WorksRegulation Works
Regulation Works
 

Similar to Gravity dams galleries

HYDROLOGY AND WATER RESOURCE MANAGMENT PPT
HYDROLOGY AND WATER RESOURCE MANAGMENT PPTHYDROLOGY AND WATER RESOURCE MANAGMENT PPT
HYDROLOGY AND WATER RESOURCE MANAGMENT PPT
Kavin Raval
 
5. Conduits, Intake, Power house and Accessories.ppt
5. Conduits, Intake, Power house and Accessories.ppt5. Conduits, Intake, Power house and Accessories.ppt
5. Conduits, Intake, Power house and Accessories.ppt
hussenbelew
 
Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Venkataraju Badanapuri
 
Regulating structure for canal flow
Regulating structure for canal flowRegulating structure for canal flow
Regulating structure for canal flow
Civil engeeneer
 
Hydel Generation and Types Of Turbines
Hydel Generation and Types Of TurbinesHydel Generation and Types Of Turbines
Hydel Generation and Types Of Turbines
Taimoor Muzaffar Gondal
 
Submersible pump 1
Submersible pump 1Submersible pump 1
Submersible pump 1
S SHANKAR RAO
 
Lecture 20 hydro electric power plant
Lecture 20 hydro electric power plantLecture 20 hydro electric power plant
Lecture 20 hydro electric power plant
Swapnil Gadgune
 
Chapter 4 design of hydropower plants.pdf
Chapter 4 design of hydropower plants.pdfChapter 4 design of hydropower plants.pdf
Chapter 4 design of hydropower plants.pdf
tameneaDemissie
 
Hydropower water conveyance systam
Hydropower water conveyance systamHydropower water conveyance systam
Hydropower water conveyance systam
marif tahayy
 
hydro power energy water conveyance system
hydro power energy water conveyance system   hydro power energy water conveyance system
hydro power energy water conveyance system
khabat shekhany
 
Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecture
c3b2a1
 
050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators
Binu Karki
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
Prasad Vejendla
 
Hydrolic Power Plant
Hydrolic Power PlantHydrolic Power Plant
Hydrolic Power Plant
sravanthi computers
 
Elements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSElements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTS
Raju D
 
hydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdfhydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdf
NAVEENM849290
 
RES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptxRES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptx
Engr umar
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailrace
Rakesh Sunari Magar
 
EPE3163_Hydro power stations_Unit2_Lect2.pptx
EPE3163_Hydro power stations_Unit2_Lect2.pptxEPE3163_Hydro power stations_Unit2_Lect2.pptx
EPE3163_Hydro power stations_Unit2_Lect2.pptx
JoseeMusabyimana
 
Malay nces ppt
Malay nces pptMalay nces ppt
Malay nces ppt
9888437802
 

Similar to Gravity dams galleries (20)

HYDROLOGY AND WATER RESOURCE MANAGMENT PPT
HYDROLOGY AND WATER RESOURCE MANAGMENT PPTHYDROLOGY AND WATER RESOURCE MANAGMENT PPT
HYDROLOGY AND WATER RESOURCE MANAGMENT PPT
 
5. Conduits, Intake, Power house and Accessories.ppt
5. Conduits, Intake, Power house and Accessories.ppt5. Conduits, Intake, Power house and Accessories.ppt
5. Conduits, Intake, Power house and Accessories.ppt
 
Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...
 
Regulating structure for canal flow
Regulating structure for canal flowRegulating structure for canal flow
Regulating structure for canal flow
 
Hydel Generation and Types Of Turbines
Hydel Generation and Types Of TurbinesHydel Generation and Types Of Turbines
Hydel Generation and Types Of Turbines
 
Submersible pump 1
Submersible pump 1Submersible pump 1
Submersible pump 1
 
Lecture 20 hydro electric power plant
Lecture 20 hydro electric power plantLecture 20 hydro electric power plant
Lecture 20 hydro electric power plant
 
Chapter 4 design of hydropower plants.pdf
Chapter 4 design of hydropower plants.pdfChapter 4 design of hydropower plants.pdf
Chapter 4 design of hydropower plants.pdf
 
Hydropower water conveyance systam
Hydropower water conveyance systamHydropower water conveyance systam
Hydropower water conveyance systam
 
hydro power energy water conveyance system
hydro power energy water conveyance system   hydro power energy water conveyance system
hydro power energy water conveyance system
 
Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecture
 
050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
 
Hydrolic Power Plant
Hydrolic Power PlantHydrolic Power Plant
Hydrolic Power Plant
 
Elements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSElements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTS
 
hydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdfhydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdf
 
RES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptxRES Lecture 18 Hydro.pptx
RES Lecture 18 Hydro.pptx
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailrace
 
EPE3163_Hydro power stations_Unit2_Lect2.pptx
EPE3163_Hydro power stations_Unit2_Lect2.pptxEPE3163_Hydro power stations_Unit2_Lect2.pptx
EPE3163_Hydro power stations_Unit2_Lect2.pptx
 
Malay nces ppt
Malay nces pptMalay nces ppt
Malay nces ppt
 

More from saibabu48

Design of-steel-structures bhavakkati- by easy engineering.net
Design of-steel-structures bhavakkati- by easy engineering.netDesign of-steel-structures bhavakkati- by easy engineering.net
Design of-steel-structures bhavakkati- by easy engineering.net
saibabu48
 
Sr bolted and welded conviction
Sr bolted and welded convictionSr bolted and welded conviction
Sr bolted and welded conviction
saibabu48
 
Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1
saibabu48
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2
saibabu48
 
Ce 6603-dss-qb
Ce 6603-dss-qbCe 6603-dss-qb
Ce 6603-dss-qb
saibabu48
 
Ce6603 design of steel structures qb
Ce6603 design of steel structures qbCe6603 design of steel structures qb
Ce6603 design of steel structures qb
saibabu48
 
Dss notebook pdf someones
Dss notebook pdf someonesDss notebook pdf someones
Dss notebook pdf someones
saibabu48
 
29 30-31-spillway gatespp20121003
29 30-31-spillway gatespp2012100329 30-31-spillway gatespp20121003
29 30-31-spillway gatespp20121003
saibabu48
 
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate029fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02
saibabu48
 
4 spillways
4 spillways4 spillways
4 spillways
saibabu48
 
Wreii unitv-170917082636
Wreii unitv-170917082636Wreii unitv-170917082636
Wreii unitv-170917082636
saibabu48
 
Unit 4-canal
Unit 4-canalUnit 4-canal
Unit 4-canal
saibabu48
 
Unit 4-canal lining
Unit 4-canal liningUnit 4-canal lining
Unit 4-canal lining
saibabu48
 
Types of spillways
Types of spillwaysTypes of spillways
Types of spillways
saibabu48
 
Types of forces
Types of forcesTypes of forces
Types of forces
saibabu48
 
Sprinkler irrigation
Sprinkler irrigationSprinkler irrigation
Sprinkler irrigation
saibabu48
 
Spillways
SpillwaysSpillways
Spillways
saibabu48
 
Spillways
SpillwaysSpillways
Spillways
saibabu48
 
Spillway
SpillwaySpillway
Spillway
saibabu48
 
Retaing wall
Retaing wallRetaing wall
Retaing wall
saibabu48
 

More from saibabu48 (20)

Design of-steel-structures bhavakkati- by easy engineering.net
Design of-steel-structures bhavakkati- by easy engineering.netDesign of-steel-structures bhavakkati- by easy engineering.net
Design of-steel-structures bhavakkati- by easy engineering.net
 
Sr bolted and welded conviction
Sr bolted and welded convictionSr bolted and welded conviction
Sr bolted and welded conviction
 
Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2
 
Ce 6603-dss-qb
Ce 6603-dss-qbCe 6603-dss-qb
Ce 6603-dss-qb
 
Ce6603 design of steel structures qb
Ce6603 design of steel structures qbCe6603 design of steel structures qb
Ce6603 design of steel structures qb
 
Dss notebook pdf someones
Dss notebook pdf someonesDss notebook pdf someones
Dss notebook pdf someones
 
29 30-31-spillway gatespp20121003
29 30-31-spillway gatespp2012100329 30-31-spillway gatespp20121003
29 30-31-spillway gatespp20121003
 
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate029fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02
9fc1684e e872-4d1a-b54e-254f07c47009-150123191452-conversion-gate02
 
4 spillways
4 spillways4 spillways
4 spillways
 
Wreii unitv-170917082636
Wreii unitv-170917082636Wreii unitv-170917082636
Wreii unitv-170917082636
 
Unit 4-canal
Unit 4-canalUnit 4-canal
Unit 4-canal
 
Unit 4-canal lining
Unit 4-canal liningUnit 4-canal lining
Unit 4-canal lining
 
Types of spillways
Types of spillwaysTypes of spillways
Types of spillways
 
Types of forces
Types of forcesTypes of forces
Types of forces
 
Sprinkler irrigation
Sprinkler irrigationSprinkler irrigation
Sprinkler irrigation
 
Spillways
SpillwaysSpillways
Spillways
 
Spillways
SpillwaysSpillways
Spillways
 
Spillway
SpillwaySpillway
Spillway
 
Retaing wall
Retaing wallRetaing wall
Retaing wall
 

Recently uploaded

一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
introduction to solar energy for engineering.pdf
introduction to solar energy for engineering.pdfintroduction to solar energy for engineering.pdf
introduction to solar energy for engineering.pdf
ravindarpurohit26
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 

Recently uploaded (20)

一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
introduction to solar energy for engineering.pdf
introduction to solar energy for engineering.pdfintroduction to solar energy for engineering.pdf
introduction to solar energy for engineering.pdf
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 

Gravity dams galleries

  • 1. CONCRETE DAM ENGINEERING Components of a Gravity Dam and their Functions 1/28/2014 1 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET
  • 2. Components of a Gravity Dam and their Functions Drainage galleries Shafts Overflow section Non-overflow section Power house Energy dissipation works Outlets Joints 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 2
  • 3. Drainage galleries : A gallery is a small passage in a dam for providing an access to the interior of the dam. The gallery is usually rectangular in shape with its top and bottom either flat or semi circular. For a gallery with its top and bottom flat, it is necessary that all the corners should be rounded. The width of gallery generally varies from 1.5 to 1.8 m. The height of the gallery in between 2.2 to 2.4 m, so that a person can easily walk inside it. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 3
  • 5. Types of gallery based on uses : A Foundation gallery b. Drainage gallery c. Inspection gallery d. Grouting gallery e. Gate gallery 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 5
  • 6. Functions of a gallery : 1. To provide drainage of the dam section. 2. To provide space for equipment required for drilling holes and grouting the hole to form a grout curtain in the foundation. 3. To provide space for header and return pipes for post cooling of concrete. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 6
  • 7. 4. A gallery provide an access to the interior of the dam for inspection ard maintenance. 5. A Gallery also provides space for installing various instruments in the dam to study its structural behaviour. 6. A gallery can provide space for the mechanical and electrical equipment required for the operation of gates for spillways and outlets. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 7
  • 8. 2. Shafts : A shaft is a vertical opening provided in a dam. Shafts are required for locating headers of the post cooling system and for locating measuring devices. Shafts are also required for the movement of elevators and the hoisting equipment. Sometimes shafts are constructed inclined to connect two galleries or the same gallery at two different elevations by a staircase or a lift arrangement. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 8
  • 9. A plumb line shaft is constructed at the maximum section of the dam to make observations of the deflection of the dam under loads. A plumb bob is suspended by a wire fixed at the top of the shaft. As the dam deflects relative to the base, the plumb bob also moves by the same amount. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 9
  • 10. A stilling well shaft is a special shaft used to record fluctuations of the water level in the reservoir. The shaft is connected to the reservoir at a point below the minimum reservoir level. There is a floating mechanism in the stilling well shaft which records fluctuations in the water level. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 10
  • 11. 3. overflow Section : The spillway in a gravity dam is called overflow section. Spillway is provided to dispose of surpluswater from the reservoir to the downstream. Spillways are provided for all dams as a safety measure against overtopping and the consequent damages, and failure. spillway may be located either in the middle of the dam or at the end of the dam near abutment. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 11
  • 12. Requirements of Spillway : It must have adequate discharge capacity. It must be hydraulically and structurally safe. The surface of the spillway must be erosion resistant. It should be provided with some device for the dissipation of excess energy. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 12
  • 13. Non-overflow section : The portion of the gravity dam other than the spillway is a non- overflow section, a road is located on the non-overflow section of the dam. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 13
  • 14. Power house : At the one end of a gravity dam a power house is located. Water from the reservoir passes tnrough penstock and rotates the turbine provided at power elevations to produce electricity. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 14
  • 15. Energy dissipation works : Water flowing over a spillway has a very high kinetic energy because of the conversion of the entire potential energy to the kinetic energy. If the water flowing with such a high velocity is discharged directly into the channel down stream, serious scour of the channel may be occur. If the scour is not properly controlled it may extend backward and may damage the spillway and the dam. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 15
  • 16. The energy dissipation devices can be broadly classified into two types. Devices using a hydraulic jump Devices using a bucket Following constructions are provided for energy dissipation : 11 Deflector bucket 1) Sharply upturned bucket 5 End sill with baffles - Stilling basin, 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 16
  • 17. 7. Outlets : A major portion of the storage volume in the reservoir on the upstream of a dam is below the spillway crest level. Dam outlets are provided in the body of the dam or its abutments below the crest level of the spillways so that the water can be withdrawn from the reservoir. Sluiceways are the special type of outlets provides in the body of a concrete gravity dam 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 17
  • 18. Classification of outlets based on purpose : River outlet - discharge water into the river Canal outlet - discharge water into the canal. Pipe outlet - delivers water into a closed pipe. Classification of outlet based on gates : • Gated outlets • Ungated outlets 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 18
  • 19. 8. Joints : 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 19
  • 20. (a) Construction Joints Construction joints are providedfor ease in construction of the dam. They also permits systematic, convenient and economical construction of the dam. It is usual practice to place the concrete in a gravity dam in lifts so as to avoid excessive heat of hydration of cement. These are the horizontal joints. The thickness of each layer of concrete should not be more than 1.5 m. The thickness of the first layer of concrete above rock foundation should not be more than 0.75 m. 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 20
  • 21. (b) Contraction joints : Contraction joints are provided to avoid cracks caused due to shrinkage of concrete due to temperature changes. Contraction joints are of two types : (i) Transverse joints (ii) Longitudinal joints 1/28/2014 PREPARED BY V.H.KHOKHANI, ASSISTANT PROFESSOR, DIET 21