SlideShare a Scribd company logo
Shahzad Sikandar
Address: 39 Bedford Road, Ilford IG1 1EJ
Mobile: 00447450649671: shahzad_19j@hotmail.com
OVERVIEW:
An experiencedPlanner/DelayAnalystwithwealthofknowledgewithinProgrammedevelopment,control
& Claims,working across various sectors such as Civils, Rail, WaterandPower for both main contractors
and Clients.
Broad experience of Delay Analysis, Construction Planning; Building Tender Programmes; Developing &
Maintaining Contract Programmes, Progress reports, Recovery Programmes, Critical path analysis,
Filtering, Change Control & Maintaining baselines; Milestones tracking; Plan Vs Actual; Resource
analysis and building custom layouts for reporting on earned value etc.
KEY INFORMATION:
 Years of experience – 12 Years
 Nationality – British
 Driving License – UK
 Age – 37 Years
KEY SKILLS:
 Programme Development, Review, Integration & Control
 Earned Value
 Primavera Versions P3, P3e, P6, P6.1, P6.2, P6 R8.2 (Expert)
 ASTA Power Project / MS Project
 Acumen Fuse
 Float Path Analysis
 Resource and cost loading
 Review of Contractor’s Programme
 Claims (Client Side PMA sand Contractor’s Claims Preparation/EOT)
 Delay Analysis (Planned vs Impacted, TIA & Windows Analysis)
 FIDIC
 NEC Contract
 Narrative and Report Writing
 Road Calc (Eagle Point) / AutoCAD
EXPERIENCE BACKGROUND
Gained by working with Contractors and Clients
 Design & Procurement
 Enabling works
 RC Works
 Heavy Civils
 Structural Steel
 Fit-out
 Civils, Mechanical, Electrical and Communications
 Roads and Drainage
CAREER HISTORY:
Employed by David Adamson & Partners Qatar–
April 2014 – Present_________________________________ Senior Planner / Delay Analyst
Working in Parsons Brinkerhoff (PMC) – ASHGHAL LRDP Programme (100 Billion QAR)
 Responsible for advising on the format and content of claims submission to General
Engineering Consultants & Contractors
 Responsible for conducting independent delay analysis of GEC/Contractor’s claims
(EOT/Prolongation)
 Draft narratives for counter claims in defence of contractor extensions of time claims, and
provide advice regarding retrospective analysis for Extension of Time, prolongation
costs, disruption, programme critiques and delay analysis critiques.
 Rationalize baseline and current Programme for multibillion billion pound programme
 Support/work with claims manager in responding to GEC claims submission and provide
independent narrative on time element of claims
 Asses & challenge Contractors impact assessment programmes and narrative
 Carry out independent Time Impact Analysis
 Undertake Programme reviews
Trojan Project Consulting – August 2011 – April 2014 Senior Planner
London Underground / Crossrail – TottenhamCourt Road Rail Station Upgrade (£400
Millions)
 Responsible for detail review of Contractor’s Design, Procurement, Implementation &
Commissioning Programme as per Contract & Works Information and feed observations
into programme response (Programme acceptance/rejection)
 Liaise with Contractor in implementing criteria for project planning and scheduling activities
to suit customer need for Programme control and reporting
 Identify any changes in the period and establish critical path string/s for review with Project
Manager to establish cause and effect of any potential delay
 Suggest mitigation measures and develop recovery programmes and assess mitigation
put forward from the contractor is reasonable
 Monitor / compare site progress against submitted Programme and highlight any disparity
 Assist commercial team for any change assessment
Laing O’Rourke & IMTECH JV– Beckton Sewerage Treatment Project (£145 Million)
 Responsible for development and control of Design, Procurement, Construction and
Commissioning Programme
 Monitor progress and produce regular progress reports & Provided support to engineers
in planning & implementing programmes for work packages
 Working with Project Manager, Project team & Subcontractor to ensure project
programmes are monitored and maintained on a weekly basis
Appraisal and co-ordination of subcontractors’ programmes
Produce phasing diagrams
Identify Risk and Opportunities
 Performing critical path evaluations to ensure targets and objectives are achieved,
highlight any delay and suggest mitigation measures
Provided planning support for commercial submissions such as variations or compensation
events
Preparation of EOT claims
Black & Veatch – Old Whittington WWTW Project (£16 Millions)
 Construct and control fully cost loaded Design, Procurement, Construction and
Commissioning Programme (Clause 31 & 32)
 Setup/ Implement Earned Value and report on performance indicator (Time & cost)
 Analyze critical path and anticipate any delays and suggest mitigation
Appraisal and co-ordination of subcontractors’ programmes.
Generate programme future spend and produce cost profile/reports
London Underground – September 2010 – August 2011 Planner
Various Station Upgrade & Refurbishment Projects (PMO Office)
 Develop Station refurbishment programmes and Capture progress and report into Master
Programme Database (MPD)
 Understand Programme Management framework and code programme in line with
requirement to facilitate Programme reporting for decision making
 Check and Validate Schedules before submission to MPD
 Prepare short term look ahead programme
 Assist senior planner in claims
GallifordTryConstructin Plc UK – April 2006 – September 2010 Planner
Kings Lynn Thermal Hydrolysis Plant (£ 25 Million)
Great Billing Thermal Hydrolysis Plant (£ 30 Million)
Cannock Energy from Waste Plant (£ 20 Million)
 From Tender programme develop fully resourced and cost loaded Design, Procurement,
Construction and Commissioning Programme
 Assist Project Manager in identifying Programme opportunities and highlight any delays
to key milestones and completion dates
 Integrate Subcontract/external Schedule into overall Master Programme
 Carry out Critical path analysis and analyze back log and suggest mitigation measures
 Create what if scenarios
 Generate Cost profile and EV reports
Trojan Engineering & Management Services – April 2003 – August 2003 Planning
Engineer
Right Bank Outfall Drain Project
 Assist in construction planning and scheduling of RBOD (Carrier drain, about 260 km
Long), using Primavera P3 project planner
 Meeting and coordination with client Representative (Mott McDonald’s Pakistan).
 Data collection and compiling for RBOD construction planning and scheduling
 Generating tabular and graphic reports (Including S-Curve, Histogram and Tables)
Ghoury Engineering Company – March 2002 – April 2003 Site
Engineer
Housing Scheme Gulistane-e-Johur
 Part in construction supervision of RCC framed bungalows in Gulistan-e- Johour, Karachi,
Pakistan
Review and detailing of drawings
Part in procurement of materials and labour
Engineering Consultant Intl. Pvt Ltd Karachi Pakistan – August 2001 – March 2002
Junior Engineer
National Highways (N5) Rehabilitation Project
Karachi Northern Bypass Project
 Part in traffic studies for Karachi Northern By Pass project
 Planning and supervision of Various kind of traffic Surveys including O-D Survey,
classified Counts, turning Movement Counts, travel time and delay studies, speed
Surveys
 Assist senior engineer in highway design
 Coordinate diversion of Utilities with local Govt.
 Designing traffic signal layouts
 Cost estimation for ancillary work
 Assist senior engineers in preparing PC-1 forms
EDUCATION:
 2005 MSc, Civil Engineering University of East London, United Kingdom
 2001 B.Eng hons, Civil Engineering - NED University of Engineering & Technology
PROFESSIONAL MEMBERSHIP:
Member Project Management Institute (PMI – USA)
Member Pakistan Engineering Council
Member Institute of Engineers Pakistan
PERSONAL:
 Languages: English, Urdu, Sindhi, Hindi & Punjabi
 Nationality: British
 References available on request

More Related Content

What's hot

Constructability Report Grove 2.0
Constructability Report Grove 2.0Constructability Report Grove 2.0
Constructability Report Grove 2.0Jamal Nelson, CCM
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
ijtsrd
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyRobert Doig
 
Edg resume 06.2016
Edg resume 06.2016Edg resume 06.2016
Edg resume 06.2016
Erwin D. Gibson
 
Detailed LMSS Summary
Detailed LMSS SummaryDetailed LMSS Summary
Detailed LMSS SummaryDan Reagan
 
IRS Sep2016 Vonline
IRS Sep2016 VonlineIRS Sep2016 Vonline
IRS Sep2016 VonlineMahdi Athari
 
Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)Dylan Gonsalves
 
Cv s.sankarasubramanian - senior planning engineer
Cv   s.sankarasubramanian - senior planning engineerCv   s.sankarasubramanian - senior planning engineer
Cv s.sankarasubramanian - senior planning engineer
Sankar Sundaram PMP
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar BeheraTarun Behera
 
DFMC SBAS Receiver Development
DFMC SBAS Receiver DevelopmentDFMC SBAS Receiver Development
DFMC SBAS Receiver Development
The European GNSS Agency (GSA)
 
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo
 
B Nicholls resume 2016-07-17
B Nicholls resume   2016-07-17B Nicholls resume   2016-07-17
B Nicholls resume 2016-07-17
Brian Nicholls
 
Resume - Suzanne Pearce
Resume - Suzanne PearceResume - Suzanne Pearce
Resume - Suzanne PearceSuzanne Pearce
 
Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template
Dr. Mohamed A. El-Reedy
 

What's hot (19)

Constructability Report Grove 2.0
Constructability Report Grove 2.0Constructability Report Grove 2.0
Constructability Report Grove 2.0
 
Vignesh Nagarajan CV
Vignesh Nagarajan CVVignesh Nagarajan CV
Vignesh Nagarajan CV
 
Updated CV
Updated CVUpdated CV
Updated CV
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 Strategy
 
Edg resume 06.2016
Edg resume 06.2016Edg resume 06.2016
Edg resume 06.2016
 
Detailed LMSS Summary
Detailed LMSS SummaryDetailed LMSS Summary
Detailed LMSS Summary
 
IRS Sep2016 Vonline
IRS Sep2016 VonlineIRS Sep2016 Vonline
IRS Sep2016 Vonline
 
Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)Resume_Dylan_Estimator(1)
Resume_Dylan_Estimator(1)
 
Cv s.sankarasubramanian - senior planning engineer
Cv   s.sankarasubramanian - senior planning engineerCv   s.sankarasubramanian - senior planning engineer
Cv s.sankarasubramanian - senior planning engineer
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar Behera
 
DFMC SBAS Receiver Development
DFMC SBAS Receiver DevelopmentDFMC SBAS Receiver Development
DFMC SBAS Receiver Development
 
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
 
B Nicholls resume 2016-07-17
B Nicholls resume   2016-07-17B Nicholls resume   2016-07-17
B Nicholls resume 2016-07-17
 
Resume - Suzanne Pearce
Resume - Suzanne PearceResume - Suzanne Pearce
Resume - Suzanne Pearce
 
eng.ramy
eng.ramy eng.ramy
eng.ramy
 
Dar specific guidelines
Dar specific guidelinesDar specific guidelines
Dar specific guidelines
 
RFP-Test-Design_Psychometrics-2011
RFP-Test-Design_Psychometrics-2011RFP-Test-Design_Psychometrics-2011
RFP-Test-Design_Psychometrics-2011
 
Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template
 

Similar to Shahzad Sikandaruk

kiran Planning sche engineer CV
kiran Planning sche engineer CVkiran Planning sche engineer CV
kiran Planning sche engineer CVkiran kumar Reddy
 
Planning Engineer _CV
Planning Engineer _CVPlanning Engineer _CV
Planning Engineer _CVSajith Nair
 
2017 Updated CV - Essam Harby
2017 Updated  CV - Essam Harby2017 Updated  CV - Essam Harby
2017 Updated CV - Essam HarbyEssam Harby
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerSankar Sundaram PMP
 
Resume-Mubbasher-Railway
Resume-Mubbasher-RailwayResume-Mubbasher-Railway
Resume-Mubbasher-RailwayMubasher Malik
 
Pragnesh Modi_1512010
Pragnesh Modi_1512010Pragnesh Modi_1512010
Pragnesh Modi_1512010Pragnesh Modi
 
Sadeeq Khan_Senior Planning Engineer- Delay Analyst
Sadeeq Khan_Senior Planning Engineer- Delay AnalystSadeeq Khan_Senior Planning Engineer- Delay Analyst
Sadeeq Khan_Senior Planning Engineer- Delay Analyst
Sadeeq Ullah Khan
 
Asad.CV.--Track Inspector..
Asad.CV.--Track Inspector..Asad.CV.--Track Inspector..
Asad.CV.--Track Inspector..muhammadasad ali
 
Asad.CV.--Track Inspector..
Asad.CV.--Track Inspector..Asad.CV.--Track Inspector..
Asad.CV.--Track Inspector..muhammadasad ali
 
Bill resume
Bill resumeBill resume
Bill resume
Awili Bill
 

Similar to Shahzad Sikandaruk (20)

kiran Planning sche engineer CV
kiran Planning sche engineer CVkiran Planning sche engineer CV
kiran Planning sche engineer CV
 
Planning Engineer _CV
Planning Engineer _CVPlanning Engineer _CV
Planning Engineer _CV
 
Keith Kent CV
Keith Kent CVKeith Kent CV
Keith Kent CV
 
Rafeek's CV
Rafeek's CV Rafeek's CV
Rafeek's CV
 
Kiran H K 17-06-2016
Kiran H K 17-06-2016Kiran H K 17-06-2016
Kiran H K 17-06-2016
 
Pugazhenthi Mathuramuthu CV
Pugazhenthi Mathuramuthu CVPugazhenthi Mathuramuthu CV
Pugazhenthi Mathuramuthu CV
 
2017 Updated CV - Essam Harby
2017 Updated  CV - Essam Harby2017 Updated  CV - Essam Harby
2017 Updated CV - Essam Harby
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning Engineer
 
Rao Yagitila CV
Rao Yagitila CVRao Yagitila CV
Rao Yagitila CV
 
Resume-Mubbasher-Railway
Resume-Mubbasher-RailwayResume-Mubbasher-Railway
Resume-Mubbasher-Railway
 
CV - Fakruddin R01
CV - Fakruddin  R01CV - Fakruddin  R01
CV - Fakruddin R01
 
Pragnesh Modi_1512010
Pragnesh Modi_1512010Pragnesh Modi_1512010
Pragnesh Modi_1512010
 
Sadeeq Khan_Senior Planning Engineer- Delay Analyst
Sadeeq Khan_Senior Planning Engineer- Delay AnalystSadeeq Khan_Senior Planning Engineer- Delay Analyst
Sadeeq Khan_Senior Planning Engineer- Delay Analyst
 
Asad.CV.--Track Inspector..
Asad.CV.--Track Inspector..Asad.CV.--Track Inspector..
Asad.CV.--Track Inspector..
 
Asad.CV.--Track Inspector..
Asad.CV.--Track Inspector..Asad.CV.--Track Inspector..
Asad.CV.--Track Inspector..
 
Bill resume
Bill resumeBill resume
Bill resume
 
11 year Exp in Instrumentation Field.
11 year Exp in Instrumentation Field.11 year Exp in Instrumentation Field.
11 year Exp in Instrumentation Field.
 
Esteban Raganit_2016
Esteban Raganit_2016Esteban Raganit_2016
Esteban Raganit_2016
 
JAMES -CV -
JAMES -CV -JAMES -CV -
JAMES -CV -
 
Sajeer mohmamed
Sajeer mohmamedSajeer mohmamed
Sajeer mohmamed
 

Shahzad Sikandaruk

  • 1. Shahzad Sikandar Address: 39 Bedford Road, Ilford IG1 1EJ Mobile: 00447450649671: shahzad_19j@hotmail.com OVERVIEW: An experiencedPlanner/DelayAnalystwithwealthofknowledgewithinProgrammedevelopment,control & Claims,working across various sectors such as Civils, Rail, WaterandPower for both main contractors and Clients. Broad experience of Delay Analysis, Construction Planning; Building Tender Programmes; Developing & Maintaining Contract Programmes, Progress reports, Recovery Programmes, Critical path analysis, Filtering, Change Control & Maintaining baselines; Milestones tracking; Plan Vs Actual; Resource analysis and building custom layouts for reporting on earned value etc. KEY INFORMATION:  Years of experience – 12 Years  Nationality – British  Driving License – UK  Age – 37 Years KEY SKILLS:  Programme Development, Review, Integration & Control  Earned Value  Primavera Versions P3, P3e, P6, P6.1, P6.2, P6 R8.2 (Expert)  ASTA Power Project / MS Project  Acumen Fuse  Float Path Analysis  Resource and cost loading  Review of Contractor’s Programme  Claims (Client Side PMA sand Contractor’s Claims Preparation/EOT)  Delay Analysis (Planned vs Impacted, TIA & Windows Analysis)  FIDIC  NEC Contract  Narrative and Report Writing  Road Calc (Eagle Point) / AutoCAD EXPERIENCE BACKGROUND Gained by working with Contractors and Clients  Design & Procurement  Enabling works  RC Works  Heavy Civils  Structural Steel  Fit-out  Civils, Mechanical, Electrical and Communications  Roads and Drainage CAREER HISTORY: Employed by David Adamson & Partners Qatar– April 2014 – Present_________________________________ Senior Planner / Delay Analyst Working in Parsons Brinkerhoff (PMC) – ASHGHAL LRDP Programme (100 Billion QAR)  Responsible for advising on the format and content of claims submission to General Engineering Consultants & Contractors
  • 2.  Responsible for conducting independent delay analysis of GEC/Contractor’s claims (EOT/Prolongation)  Draft narratives for counter claims in defence of contractor extensions of time claims, and provide advice regarding retrospective analysis for Extension of Time, prolongation costs, disruption, programme critiques and delay analysis critiques.  Rationalize baseline and current Programme for multibillion billion pound programme  Support/work with claims manager in responding to GEC claims submission and provide independent narrative on time element of claims  Asses & challenge Contractors impact assessment programmes and narrative  Carry out independent Time Impact Analysis  Undertake Programme reviews Trojan Project Consulting – August 2011 – April 2014 Senior Planner London Underground / Crossrail – TottenhamCourt Road Rail Station Upgrade (£400 Millions)  Responsible for detail review of Contractor’s Design, Procurement, Implementation & Commissioning Programme as per Contract & Works Information and feed observations into programme response (Programme acceptance/rejection)  Liaise with Contractor in implementing criteria for project planning and scheduling activities to suit customer need for Programme control and reporting  Identify any changes in the period and establish critical path string/s for review with Project Manager to establish cause and effect of any potential delay  Suggest mitigation measures and develop recovery programmes and assess mitigation put forward from the contractor is reasonable  Monitor / compare site progress against submitted Programme and highlight any disparity  Assist commercial team for any change assessment Laing O’Rourke & IMTECH JV– Beckton Sewerage Treatment Project (£145 Million)  Responsible for development and control of Design, Procurement, Construction and Commissioning Programme  Monitor progress and produce regular progress reports & Provided support to engineers in planning & implementing programmes for work packages  Working with Project Manager, Project team & Subcontractor to ensure project programmes are monitored and maintained on a weekly basis Appraisal and co-ordination of subcontractors’ programmes Produce phasing diagrams Identify Risk and Opportunities  Performing critical path evaluations to ensure targets and objectives are achieved, highlight any delay and suggest mitigation measures Provided planning support for commercial submissions such as variations or compensation events Preparation of EOT claims Black & Veatch – Old Whittington WWTW Project (£16 Millions)  Construct and control fully cost loaded Design, Procurement, Construction and Commissioning Programme (Clause 31 & 32)  Setup/ Implement Earned Value and report on performance indicator (Time & cost)  Analyze critical path and anticipate any delays and suggest mitigation Appraisal and co-ordination of subcontractors’ programmes. Generate programme future spend and produce cost profile/reports London Underground – September 2010 – August 2011 Planner Various Station Upgrade & Refurbishment Projects (PMO Office)  Develop Station refurbishment programmes and Capture progress and report into Master Programme Database (MPD)
  • 3.  Understand Programme Management framework and code programme in line with requirement to facilitate Programme reporting for decision making  Check and Validate Schedules before submission to MPD  Prepare short term look ahead programme  Assist senior planner in claims GallifordTryConstructin Plc UK – April 2006 – September 2010 Planner Kings Lynn Thermal Hydrolysis Plant (£ 25 Million) Great Billing Thermal Hydrolysis Plant (£ 30 Million) Cannock Energy from Waste Plant (£ 20 Million)  From Tender programme develop fully resourced and cost loaded Design, Procurement, Construction and Commissioning Programme  Assist Project Manager in identifying Programme opportunities and highlight any delays to key milestones and completion dates  Integrate Subcontract/external Schedule into overall Master Programme  Carry out Critical path analysis and analyze back log and suggest mitigation measures  Create what if scenarios  Generate Cost profile and EV reports Trojan Engineering & Management Services – April 2003 – August 2003 Planning Engineer Right Bank Outfall Drain Project  Assist in construction planning and scheduling of RBOD (Carrier drain, about 260 km Long), using Primavera P3 project planner  Meeting and coordination with client Representative (Mott McDonald’s Pakistan).  Data collection and compiling for RBOD construction planning and scheduling  Generating tabular and graphic reports (Including S-Curve, Histogram and Tables) Ghoury Engineering Company – March 2002 – April 2003 Site Engineer Housing Scheme Gulistane-e-Johur  Part in construction supervision of RCC framed bungalows in Gulistan-e- Johour, Karachi, Pakistan Review and detailing of drawings Part in procurement of materials and labour Engineering Consultant Intl. Pvt Ltd Karachi Pakistan – August 2001 – March 2002 Junior Engineer National Highways (N5) Rehabilitation Project Karachi Northern Bypass Project  Part in traffic studies for Karachi Northern By Pass project  Planning and supervision of Various kind of traffic Surveys including O-D Survey, classified Counts, turning Movement Counts, travel time and delay studies, speed Surveys  Assist senior engineer in highway design  Coordinate diversion of Utilities with local Govt.  Designing traffic signal layouts  Cost estimation for ancillary work  Assist senior engineers in preparing PC-1 forms EDUCATION:
  • 4.  2005 MSc, Civil Engineering University of East London, United Kingdom  2001 B.Eng hons, Civil Engineering - NED University of Engineering & Technology PROFESSIONAL MEMBERSHIP: Member Project Management Institute (PMI – USA) Member Pakistan Engineering Council Member Institute of Engineers Pakistan PERSONAL:  Languages: English, Urdu, Sindhi, Hindi & Punjabi  Nationality: British  References available on request