SlideShare a Scribd company logo
2018 Subway Closures for
TTC System Upgrades
Eglinton Crosstown LRT Project
2
2
• A 19-kilometre route separated from regular traffic
• 10-kilometres underground; 9-kilometres at surface in east
• 15 underground stations and 10 surface stops
• A maintenance and storage facility
• Transit communications system
• Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station
Eglinton LRT Station
Accessible Entrance
Eglinton Station – ProfileView
LRT Lower
Concourse
TTC Subway
Platform
LRT Platform
LRT Upper
Concourse
Eglinton Station - Progress
Completed to Date
 Demolition of the Salvation Army
CommunityChurch
 Demolition of the abandonedTTC bus
depot
 Wet utility relocation at theYonge-
Eglinton intersection
 Toronto Hydro relocation along Redpath
Avenue, DuplexAvenue
 North, east, and west underground
pedestrian tunnel closures
 Shoring at the Salvation Army site
Piling - Nov 2017
Eglinton Station - Progress
Major 2018Work
• Shoring continues for the station
box and main entrance
• Toronto Hydro relocation
• NewTTC Service Building at
Berwick Portal
• Upgrades to subway station
Piling (TTC
Underpinning Piles) –
Feb 2018
Weekend Subway Closures
• Crosstown Project Agreements requiresCTS to make improvements at Eglinton
subway station
• TTC has approved 24 closures in 2018 for this work
– Subway will close 2am Saturday mornings and re-open Monday mornings at 5am
– Closures necessary because CTS must work on and/or needs access to the subway tracks and
Berwick portal
– Work will occur 24 hours a day during the designated weekend closures
• 2018 closures provide benefits toTTC:
– Construction of new subway service building
– Upgrades/improvements to the subway station
• TTC & CTS coordination to limit overall number of Line 1 closures in 2018:
– During 9 of the 24 closures,TTC will undertake states of Good Repair work
– 15 out of the 24 Closures will be strictly from St Clair to Lawrence
Upgrades/Improvements to Subway Station
• During 2018, weekend closures also facilitate upgrades/improvements
to existing subway station:
– Smoke evacuation fans
– New electrical systems
– Improved fire detection systems
– New escalators
• Materials and equipment will be delivered on the subway tracks via the
Berwick portal, necessitating the subway closures
• Additional benefits toTTC/transit users associated with Crosstown
construction:
– Extension of the subway platform by 25 metres
– Upgrading pedestrian tunnels that connect directly to current and future
– development
New Subway Station Service Building
• Building will be located over the subway tracks at the Berwick portal
• Provide improved ventilation and life safety systems for existing subway
• Weekend work February – December 2018
• Weekend activities include excavation, shoring and foundation work
New Subway Station Service Building
• Construction of this building is part of largerTTC plans to upgrade ventilation
systems on Line 1
New Subway Station Service Building
Description of Construction
• Work will occur day and night on each planned subway closure weekend.
• Three basic phases of work planned: micro-piling, pre-cast installation, and material
supply and removal work:
1. Micro-piling phase (May-July)
– Involves the installation of smaller diameter piles within theTTC subway corridor
– Two micro-pile drill rigs, a mobile crane, and a concrete pump will be used continuously
while concrete and steel deliveries will be intermittent. A hydro-vac may be required
occasionally depending on site conditions.
2. Pre-cast Installation (July-August)
– Involves the delivery and installation of pre-fabricated concrete components
– A 500-tonne crane and various hand tools will be used regularly with intermittent
delivery of pre-cast and concrete grout
3. Material Supply and Removal (September-December)
– Parts of Eglinton Station will need to be demolished and re-built. Berwick Portal will be
used as the access point for nighttime work within the station
– Construction equipment could involve concrete trucks, mobile cranes, and bin trucks
Planned 2018 Weekend Subway Closure Schedule
TTC state of good repair closures (9)
UpcomingWorks: May-June
*60% rendering
Activity Anticipated Impacts Anticipated Schedule*
Micro-piling • Overnight work
• Work zones on Berwick Avenue
• Berwick Avenue to close on weekends to
through traffic
• Truck traffic to and from work sites
May 19 at 2am – May 20 at 5am
May 26 at 2am – May 27 at 5am
June 2 at 2am – June 3 at 5am
June 16 at 2am – June 17 at 5am
June 30 at 2am – July 1 at 5am
*Preparatory works and traffic staging may occur outside of these hours
• The following types of equipment will be used throughout the
micro-piling phase of the work (May-June): Hydraulic drill
for micro-piles
250-tonne crane for
pile installation
UpcomingWorks: May-June
Weekday Staging
Weekend Staging
UpcomingWorks: July-August
Activity Anticipated Impacts Anticipated Schedule*
Pre-cast concrete
installation
• Overnight work
• Crane and materials will be placed on
Berwick. Placement and road occupancy
impacts are currently being developed
• Truck traffic to and from work sites
July 7 at 2am – July 8 at 5am
July 14 at 2am – July 15 at 5am
July 21 at 2am – July 22 at 5am
August 11 at 2am – August 12 at 5am
August 18 at 2am – August 19 at 5am
*Preparatory works and traffic staging may occur outside of these hours
500 tonne crane for
pre-cast concrete
installation
500-tonne crane for
pre-cast concrete
installation
Noise Monitoring and Mitigation
• CTS will be assessing sound levels during construction to ensure noise
levels remain within allowable limits and to identify possible mitigation
measures for construction activities.
• Noise mitigation measures already planned include:
– Continuous and proactive noise monitoring from key locations
adjacent the work site
– Acoustic enclosures for pumps and generators
– Broadband backup alarms for equipment
– Environmental awareness training and toolbox talks for contractors
and employees
Stay up to date

More Related Content

What's hot

Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Crosstown TO
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
Crosstown TO
 
Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020
Crosstown TO
 
Leaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 PresentationLeaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 Presentation
Crosstown TO
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021
Crosstown TO
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
Crosstown TO
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020
Crosstown TO
 
Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
Crosstown TO
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
Crosstown TO
 
CLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCLC Eglinton and Mount Pleasant
CLC Eglinton and Mount Pleasant
Crosstown TO
 
Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021
Crosstown TO
 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Crosstown TO
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Crosstown TO
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House Presentation
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Crosstown TO
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Crosstown TO
 

What's hot (20)

Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
 
Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020
 
Leaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 PresentationLeaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 Presentation
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020
 
Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
 
CLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCLC Eglinton and Mount Pleasant
CLC Eglinton and Mount Pleasant
 
Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021
 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House Presentation
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
 

Similar to Public Meeting of Facility Services Building at Eglinton Station - May 2018

Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
Crosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
Crosstown TO
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Crosstown TO
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
Crosstown TO
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House Slides
Crosstown TO
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment Works
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Crosstown TO
 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Crosstown TO
 
Central West Open House
Central West Open HouseCentral West Open House
Central West Open House
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Crosstown TO
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
Crosstown TO
 
Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014
WaterfrontTO
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
Crosstown TO
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
Crosstown TO
 

Similar to Public Meeting of Facility Services Building at Eglinton Station - May 2018 (20)

Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House Slides
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment Works
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Central West Open House
Central West Open HouseCentral West Open House
Central West Open House
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
 
Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014Queens Quay Revitalization Progress Update - May 2014
Queens Quay Revitalization Progress Update - May 2014
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
Crosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
Crosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
Crosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Crosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
Crosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Crosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
Crosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
ILC- UK
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
Saeed Al Dhaheri
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
ukyewh
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
Mohammed325561
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
ahcitycouncil
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
ahcitycouncil
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
ehbuaw
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
ehbuaw
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
Paul Smith
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
ahcitycouncil
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
ARCResearch
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
JSchaus & Associates
 

Recently uploaded (20)

MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
 

Public Meeting of Facility Services Building at Eglinton Station - May 2018

  • 1. 2018 Subway Closures for TTC System Upgrades
  • 2. Eglinton Crosstown LRT Project 2 2 • A 19-kilometre route separated from regular traffic • 10-kilometres underground; 9-kilometres at surface in east • 15 underground stations and 10 surface stops • A maintenance and storage facility • Transit communications system • Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station
  • 4. Eglinton Station – ProfileView LRT Lower Concourse TTC Subway Platform LRT Platform LRT Upper Concourse
  • 5. Eglinton Station - Progress Completed to Date  Demolition of the Salvation Army CommunityChurch  Demolition of the abandonedTTC bus depot  Wet utility relocation at theYonge- Eglinton intersection  Toronto Hydro relocation along Redpath Avenue, DuplexAvenue  North, east, and west underground pedestrian tunnel closures  Shoring at the Salvation Army site Piling - Nov 2017
  • 6. Eglinton Station - Progress Major 2018Work • Shoring continues for the station box and main entrance • Toronto Hydro relocation • NewTTC Service Building at Berwick Portal • Upgrades to subway station Piling (TTC Underpinning Piles) – Feb 2018
  • 7. Weekend Subway Closures • Crosstown Project Agreements requiresCTS to make improvements at Eglinton subway station • TTC has approved 24 closures in 2018 for this work – Subway will close 2am Saturday mornings and re-open Monday mornings at 5am – Closures necessary because CTS must work on and/or needs access to the subway tracks and Berwick portal – Work will occur 24 hours a day during the designated weekend closures • 2018 closures provide benefits toTTC: – Construction of new subway service building – Upgrades/improvements to the subway station • TTC & CTS coordination to limit overall number of Line 1 closures in 2018: – During 9 of the 24 closures,TTC will undertake states of Good Repair work – 15 out of the 24 Closures will be strictly from St Clair to Lawrence
  • 8. Upgrades/Improvements to Subway Station • During 2018, weekend closures also facilitate upgrades/improvements to existing subway station: – Smoke evacuation fans – New electrical systems – Improved fire detection systems – New escalators • Materials and equipment will be delivered on the subway tracks via the Berwick portal, necessitating the subway closures • Additional benefits toTTC/transit users associated with Crosstown construction: – Extension of the subway platform by 25 metres – Upgrading pedestrian tunnels that connect directly to current and future – development
  • 9. New Subway Station Service Building • Building will be located over the subway tracks at the Berwick portal • Provide improved ventilation and life safety systems for existing subway • Weekend work February – December 2018 • Weekend activities include excavation, shoring and foundation work
  • 10. New Subway Station Service Building • Construction of this building is part of largerTTC plans to upgrade ventilation systems on Line 1
  • 11. New Subway Station Service Building
  • 12. Description of Construction • Work will occur day and night on each planned subway closure weekend. • Three basic phases of work planned: micro-piling, pre-cast installation, and material supply and removal work: 1. Micro-piling phase (May-July) – Involves the installation of smaller diameter piles within theTTC subway corridor – Two micro-pile drill rigs, a mobile crane, and a concrete pump will be used continuously while concrete and steel deliveries will be intermittent. A hydro-vac may be required occasionally depending on site conditions. 2. Pre-cast Installation (July-August) – Involves the delivery and installation of pre-fabricated concrete components – A 500-tonne crane and various hand tools will be used regularly with intermittent delivery of pre-cast and concrete grout 3. Material Supply and Removal (September-December) – Parts of Eglinton Station will need to be demolished and re-built. Berwick Portal will be used as the access point for nighttime work within the station – Construction equipment could involve concrete trucks, mobile cranes, and bin trucks
  • 13. Planned 2018 Weekend Subway Closure Schedule TTC state of good repair closures (9)
  • 14. UpcomingWorks: May-June *60% rendering Activity Anticipated Impacts Anticipated Schedule* Micro-piling • Overnight work • Work zones on Berwick Avenue • Berwick Avenue to close on weekends to through traffic • Truck traffic to and from work sites May 19 at 2am – May 20 at 5am May 26 at 2am – May 27 at 5am June 2 at 2am – June 3 at 5am June 16 at 2am – June 17 at 5am June 30 at 2am – July 1 at 5am *Preparatory works and traffic staging may occur outside of these hours • The following types of equipment will be used throughout the micro-piling phase of the work (May-June): Hydraulic drill for micro-piles 250-tonne crane for pile installation
  • 16. UpcomingWorks: July-August Activity Anticipated Impacts Anticipated Schedule* Pre-cast concrete installation • Overnight work • Crane and materials will be placed on Berwick. Placement and road occupancy impacts are currently being developed • Truck traffic to and from work sites July 7 at 2am – July 8 at 5am July 14 at 2am – July 15 at 5am July 21 at 2am – July 22 at 5am August 11 at 2am – August 12 at 5am August 18 at 2am – August 19 at 5am *Preparatory works and traffic staging may occur outside of these hours 500 tonne crane for pre-cast concrete installation 500-tonne crane for pre-cast concrete installation
  • 17. Noise Monitoring and Mitigation • CTS will be assessing sound levels during construction to ensure noise levels remain within allowable limits and to identify possible mitigation measures for construction activities. • Noise mitigation measures already planned include: – Continuous and proactive noise monitoring from key locations adjacent the work site – Acoustic enclosures for pumps and generators – Broadband backup alarms for equipment – Environmental awareness training and toolbox talks for contractors and employees
  • 18. Stay up to date