SlideShare a Scribd company logo
1 of 14
Download to read offline
BUILDING 
CONSTRUCTION -III 
 
 
SITE REPORT 
 
 
 
BY- 
KHUSHI GOYAL 
MADHUR BAJAJ 
SHRUTI GARG 
 
 
SITE REPORT 
SITE LOCATION-​ The construction site is strategically located at the borderline of
Puchong and Bukit Jalil (near to Taylor’s Lakeside Campus University), Subang Jaya, Selangor,
Malaysia
 
 
AIM AND OBJECTIVE-
● Understand the basics of the construction process.
● Understand the practical aspect of construction techniques in comparison to the theory
aspect in books and its application on site.
● Exposure to the actual working environment on site including uncertainty circumstances
e.g. weather.
● Ability to communicate with the construction team members on site and to see the
importance of teamwork in the building team.
● Witness the usage of construction equipment on site including mechanical plants.
Explore and identify various types of building materials and technology on site.
● Awareness of the importance of safety on site and understanding of safety problems and
site conditions.
● Recognize the items measurable for sub-structure and reinforced concrete frame works.
SURVEY OF SITE FOR PROPOSED BUILDING- 
Figure 1 and 2 : Wastage found at the site is not properly dealt with. The construction team only
let it flow to the drain.
Figure 1. Figure 2.
Figure 3: A temporary work – office is spotted behind.
Figure 3. Figure 4.
Figure 4: An information board which shows companies that are involved in this project.
Hoarding is used as defence of the site from unauthorized trespassers.
Figure 5: A temporary work – Accommodation for workers is spotted at the corner of site.
Genset is provided as temporary power supply for the workers
Figure 5. Figure 6.
Figure 6: This is a basement construction taken from original ground level. Red and white
plastic line is used to stop lawful visitors from stepping forward.
Figure 7: A temporary staircase that is only fixed into the soil which is very unstable..
Figure 7.
 
 
DESIGN OF SLAB-  
   
 
A slab is a structural element, made of concrete,
that is used to create flat horizontal surfaces such
as floors, roof decks and ceilings.
Slabs are to be designed under the limited state
method by reference
of IS 456:2000.
● Shorter span:= 5.8m
● Longer span:= 7.62m
● Slab has to be designed as Two way slab
● Depth of slab= 120mm
Figure 8- Slab
Figure 9: Reinforcement bars used in the basement slab. This shows the parts that have not
been covered by reinforced concrete.
Figure 9.
Figure 10: Plastic Sheets is used to protect the slab concrete
Figure 10. Figure 11.
Figure 11: Synthetic Fibres is used to prevent concrete loss.
DESIGN OF BEAMS-  
Beams primarily carry vertical gravitational forces. They are
also used to carry horizontal loads (e.g., loads due to an
earthquake or wind or in tension to resist rafter thrust as a tie
beam or (usually) compression as a collar beam)
SPAN = 5.8m (shorter span)
● Height of the wall = 10’-3m
● Beam size = 9”x16”(230x405mm)
● Wall load -1 11.6Kn/m
Figure 12: Beam
DESIGN OF COLUMNS- 
    
● A column is a structural element that transmits, through
compression, the weight of the structure above to other
structural elements below. In other words, a column is
a compression member.
● There are many columns spotted on the basement
slab. Some of it had formwork and reinforcement bars
installed while some are done with reinforced concrete
poured and formwork had also been removed. Each
column is less than 4m2 which means that it weighed
8.5 tonne. (1m2 = 2.2 tonne)
Figure 13: Column
Figure 14: Column that wait for reinforced concrete to be poured
Figure 15: A so called “penimbang” is hung on the column to ensure the formwork of the column
is straight.
Figure 15. Figure 16.
Figure 16: There are many holes on the concrete of columns with pipes installed to stabilize and
strengthen the concrete.
DESIGN OF FOOTING-  
 
● Short side of footing = 1.0 m
● Long side of footing = 1.70 m
● A rectangle footing 1mx1.7m
● Upward soil pressure = 260 KN/m2
● Depth of footing =250 mm
● Reinforcement in longitudinal direction
● Provide 12mm bars at 230 mm c/c
● Reinforcement in shorter direction :- Provide 4 bars of 12mm dia on
either of the central bandwidth
Figure 17.
 
 
 
 
 
DESIGN OF FOUNDATION-
Pile foundation
● Length can be readily varied to suit varying ground conditions.
● It can be installed in very large diameters.
● End enlargement up to two or three diameters are possible in clays.
● Material of piles is not dependent on handling or driving conditions.
● It can be installed in very long lengths.
Figure 18 and 19: Construction of pile cap in the pit excavation. Steel sheet piles are used to
prevent the soil from leaking into the excavation.
Figure 18. Figure 19.
Figure 20: An excavator is spotted while excavating soil.
Figure 20.
Figure 21: This area is where the biggest pile cap among all of the pile caps in the site get
constructed. This pile cap weighed around 85 tonne.
Figure 21. Figure 22.
Figure 22: Bored piles are used at the site to support high buildings that have heavy vertical
load.
OTHER DETAILS AND PHOTOS OF THE SITE-  
Figure 23: Scaffolding is spotted in the site too.
Figure 23. Figure 24.
Figure 24: There are walls around the sides above the slab with formwork and reinforcement
bars installed.
Figure 25: Water stop is installed in the wall to prevent water from entering the basement.
Figure 25. Figure 26.
Figure 26: This photo shows the inner side of formwork of the wall.
Figure 27: The component that is held by the supervisor is used to tie the formwork of walls as
shown in Figure 13.
Figure 27. Figure 28.
Figure 28: 50mm diameter concrete cover is spotted.
Figure 28. Figure 29.
Figure 29: Precast bored piles
Figure 30: 50mm diameter concrete cover is spotted.
 
THANKYOU

More Related Content

Similar to BUILDING CONSTRUCTION SITE REPORT

UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxPraveendubey82
 
CT site visit report
CT site visit report CT site visit report
CT site visit report Yap Xin
 
Mat foundation
Mat foundationMat foundation
Mat foundationshuvo293
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II ReportBolin Loong
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORTWan Nee
 
Pebbles II site report
Pebbles II site reportPebbles II site report
Pebbles II site reportkalyani kadam
 
Field visit report 2019
Field visit report 2019Field visit report 2019
Field visit report 2019Nirob Ahmed
 
U boot beton technology
U boot beton technologyU boot beton technology
U boot beton technologyAmish Raj
 
pdfcookie.com_ppt-on-u-boot-beton-technology.pdf
pdfcookie.com_ppt-on-u-boot-beton-technology.pdfpdfcookie.com_ppt-on-u-boot-beton-technology.pdf
pdfcookie.com_ppt-on-u-boot-beton-technology.pdfAnuKViswam
 
Construction site
Construction siteConstruction site
Construction siteTimun Loh
 
Site report
Site reportSite report
Site reportHuiYik
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1Jing Chuang
 
Lecture2 classification of structures
Lecture2 classification of structuresLecture2 classification of structures
Lecture2 classification of structuresAfroz Khan
 
Site report assignment
Site report assignmentSite report assignment
Site report assignmentSze Ting Kuek
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiJaspreet singh
 

Similar to BUILDING CONSTRUCTION SITE REPORT (20)

UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
 
Mat foundation
Mat foundationMat foundation
Mat foundation
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II Report
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
 
Ayush
AyushAyush
Ayush
 
Pebbles II site report
Pebbles II site reportPebbles II site report
Pebbles II site report
 
Field visit report 2019
Field visit report 2019Field visit report 2019
Field visit report 2019
 
U boot beton technology
U boot beton technologyU boot beton technology
U boot beton technology
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
 
pdfcookie.com_ppt-on-u-boot-beton-technology.pdf
pdfcookie.com_ppt-on-u-boot-beton-technology.pdfpdfcookie.com_ppt-on-u-boot-beton-technology.pdf
pdfcookie.com_ppt-on-u-boot-beton-technology.pdf
 
Construction site
Construction siteConstruction site
Construction site
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
KUY Limeng,e20190482(I4GCI-B)_4.pdf
KUY Limeng,e20190482(I4GCI-B)_4.pdfKUY Limeng,e20190482(I4GCI-B)_4.pdf
KUY Limeng,e20190482(I4GCI-B)_4.pdf
 
Site report
Site reportSite report
Site report
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1
 
Lecture2 classification of structures
Lecture2 classification of structuresLecture2 classification of structures
Lecture2 classification of structures
 
Site report assignment
Site report assignmentSite report assignment
Site report assignment
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 

More from ShrutiGarg261479

hot and cold rolled sections -bms
hot and cold rolled sections -bmshot and cold rolled sections -bms
hot and cold rolled sections -bmsShrutiGarg261479
 
copper as a building material
copper as a building material copper as a building material
copper as a building material ShrutiGarg261479
 
coating of metals and paints -5.pdf
coating of metals and paints -5.pdfcoating of metals and paints -5.pdf
coating of metals and paints -5.pdfShrutiGarg261479
 
building material sciences - accoustical material
building material sciences - accoustical material building material sciences - accoustical material
building material sciences - accoustical material ShrutiGarg261479
 
ALUMINIUM AS A BUILDING MATERIAL
ALUMINIUM AS A BUILDING MATERIALALUMINIUM AS A BUILDING MATERIAL
ALUMINIUM AS A BUILDING MATERIALShrutiGarg261479
 
plastics as building material pdf
plastics as building material pdf plastics as building material pdf
plastics as building material pdf ShrutiGarg261479
 
literature study group 6.pdf
literature study group 6.pdfliterature study group 6.pdf
literature study group 6.pdfShrutiGarg261479
 
31_SHRUTIGARG_LIGHTING_ASSIGNMENT 2.pdf
31_SHRUTIGARG_LIGHTING_ASSIGNMENT 2.pdf31_SHRUTIGARG_LIGHTING_ASSIGNMENT 2.pdf
31_SHRUTIGARG_LIGHTING_ASSIGNMENT 2.pdfShrutiGarg261479
 
Lighting Acoustics Assignment 1.pdf
Lighting Acoustics Assignment 1.pdfLighting Acoustics Assignment 1.pdf
Lighting Acoustics Assignment 1.pdfShrutiGarg261479
 
31_SHRUTIGARG_BC REPORT-2.pdf
31_SHRUTIGARG_BC REPORT-2.pdf31_SHRUTIGARG_BC REPORT-2.pdf
31_SHRUTIGARG_BC REPORT-2.pdfShrutiGarg261479
 
31_SHRUTIGARG_CABINETS_REPORT.docx
31_SHRUTIGARG_CABINETS_REPORT.docx31_SHRUTIGARG_CABINETS_REPORT.docx
31_SHRUTIGARG_CABINETS_REPORT.docxShrutiGarg261479
 
BMS_ASSIGNMENT_SHRUTIGARG (1).pdf
BMS_ASSIGNMENT_SHRUTIGARG (1).pdfBMS_ASSIGNMENT_SHRUTIGARG (1).pdf
BMS_ASSIGNMENT_SHRUTIGARG (1).pdfShrutiGarg261479
 
31_RENZOPIANO_SHRUTIGARG.pdf
31_RENZOPIANO_SHRUTIGARG.pdf31_RENZOPIANO_SHRUTIGARG.pdf
31_RENZOPIANO_SHRUTIGARG.pdfShrutiGarg261479
 

More from ShrutiGarg261479 (15)

BMS_PAINTS.pdf
BMS_PAINTS.pdfBMS_PAINTS.pdf
BMS_PAINTS.pdf
 
hot and cold rolled sections -bms
hot and cold rolled sections -bmshot and cold rolled sections -bms
hot and cold rolled sections -bms
 
copper as a building material
copper as a building material copper as a building material
copper as a building material
 
ARTIFICIALSTONES.pdf
ARTIFICIALSTONES.pdfARTIFICIALSTONES.pdf
ARTIFICIALSTONES.pdf
 
coating of metals and paints -5.pdf
coating of metals and paints -5.pdfcoating of metals and paints -5.pdf
coating of metals and paints -5.pdf
 
building material sciences - accoustical material
building material sciences - accoustical material building material sciences - accoustical material
building material sciences - accoustical material
 
ALUMINIUM AS A BUILDING MATERIAL
ALUMINIUM AS A BUILDING MATERIALALUMINIUM AS A BUILDING MATERIAL
ALUMINIUM AS A BUILDING MATERIAL
 
plastics as building material pdf
plastics as building material pdf plastics as building material pdf
plastics as building material pdf
 
literature study group 6.pdf
literature study group 6.pdfliterature study group 6.pdf
literature study group 6.pdf
 
31_SHRUTIGARG_LIGHTING_ASSIGNMENT 2.pdf
31_SHRUTIGARG_LIGHTING_ASSIGNMENT 2.pdf31_SHRUTIGARG_LIGHTING_ASSIGNMENT 2.pdf
31_SHRUTIGARG_LIGHTING_ASSIGNMENT 2.pdf
 
Lighting Acoustics Assignment 1.pdf
Lighting Acoustics Assignment 1.pdfLighting Acoustics Assignment 1.pdf
Lighting Acoustics Assignment 1.pdf
 
31_SHRUTIGARG_BC REPORT-2.pdf
31_SHRUTIGARG_BC REPORT-2.pdf31_SHRUTIGARG_BC REPORT-2.pdf
31_SHRUTIGARG_BC REPORT-2.pdf
 
31_SHRUTIGARG_CABINETS_REPORT.docx
31_SHRUTIGARG_CABINETS_REPORT.docx31_SHRUTIGARG_CABINETS_REPORT.docx
31_SHRUTIGARG_CABINETS_REPORT.docx
 
BMS_ASSIGNMENT_SHRUTIGARG (1).pdf
BMS_ASSIGNMENT_SHRUTIGARG (1).pdfBMS_ASSIGNMENT_SHRUTIGARG (1).pdf
BMS_ASSIGNMENT_SHRUTIGARG (1).pdf
 
31_RENZOPIANO_SHRUTIGARG.pdf
31_RENZOPIANO_SHRUTIGARG.pdf31_RENZOPIANO_SHRUTIGARG.pdf
31_RENZOPIANO_SHRUTIGARG.pdf
 

Recently uploaded

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 

Recently uploaded (20)

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 

BUILDING CONSTRUCTION SITE REPORT

  • 2. SITE REPORT  SITE LOCATION-​ The construction site is strategically located at the borderline of Puchong and Bukit Jalil (near to Taylor’s Lakeside Campus University), Subang Jaya, Selangor, Malaysia    
  • 3. AIM AND OBJECTIVE- ● Understand the basics of the construction process. ● Understand the practical aspect of construction techniques in comparison to the theory aspect in books and its application on site. ● Exposure to the actual working environment on site including uncertainty circumstances e.g. weather. ● Ability to communicate with the construction team members on site and to see the importance of teamwork in the building team. ● Witness the usage of construction equipment on site including mechanical plants. Explore and identify various types of building materials and technology on site. ● Awareness of the importance of safety on site and understanding of safety problems and site conditions. ● Recognize the items measurable for sub-structure and reinforced concrete frame works. SURVEY OF SITE FOR PROPOSED BUILDING-  Figure 1 and 2 : Wastage found at the site is not properly dealt with. The construction team only let it flow to the drain. Figure 1. Figure 2.
  • 4. Figure 3: A temporary work – office is spotted behind. Figure 3. Figure 4. Figure 4: An information board which shows companies that are involved in this project. Hoarding is used as defence of the site from unauthorized trespassers. Figure 5: A temporary work – Accommodation for workers is spotted at the corner of site. Genset is provided as temporary power supply for the workers Figure 5. Figure 6. Figure 6: This is a basement construction taken from original ground level. Red and white plastic line is used to stop lawful visitors from stepping forward.
  • 5. Figure 7: A temporary staircase that is only fixed into the soil which is very unstable.. Figure 7.     DESIGN OF SLAB-         A slab is a structural element, made of concrete, that is used to create flat horizontal surfaces such as floors, roof decks and ceilings. Slabs are to be designed under the limited state method by reference of IS 456:2000. ● Shorter span:= 5.8m ● Longer span:= 7.62m ● Slab has to be designed as Two way slab ● Depth of slab= 120mm Figure 8- Slab
  • 6. Figure 9: Reinforcement bars used in the basement slab. This shows the parts that have not been covered by reinforced concrete. Figure 9. Figure 10: Plastic Sheets is used to protect the slab concrete Figure 10. Figure 11. Figure 11: Synthetic Fibres is used to prevent concrete loss.
  • 7. DESIGN OF BEAMS-   Beams primarily carry vertical gravitational forces. They are also used to carry horizontal loads (e.g., loads due to an earthquake or wind or in tension to resist rafter thrust as a tie beam or (usually) compression as a collar beam) SPAN = 5.8m (shorter span) ● Height of the wall = 10’-3m ● Beam size = 9”x16”(230x405mm) ● Wall load -1 11.6Kn/m Figure 12: Beam DESIGN OF COLUMNS-       ● A column is a structural element that transmits, through compression, the weight of the structure above to other structural elements below. In other words, a column is a compression member. ● There are many columns spotted on the basement slab. Some of it had formwork and reinforcement bars installed while some are done with reinforced concrete poured and formwork had also been removed. Each column is less than 4m2 which means that it weighed 8.5 tonne. (1m2 = 2.2 tonne) Figure 13: Column
  • 8. Figure 14: Column that wait for reinforced concrete to be poured Figure 15: A so called “penimbang” is hung on the column to ensure the formwork of the column is straight. Figure 15. Figure 16. Figure 16: There are many holes on the concrete of columns with pipes installed to stabilize and strengthen the concrete.
  • 9. DESIGN OF FOOTING-     ● Short side of footing = 1.0 m ● Long side of footing = 1.70 m ● A rectangle footing 1mx1.7m ● Upward soil pressure = 260 KN/m2 ● Depth of footing =250 mm ● Reinforcement in longitudinal direction ● Provide 12mm bars at 230 mm c/c ● Reinforcement in shorter direction :- Provide 4 bars of 12mm dia on either of the central bandwidth Figure 17.           DESIGN OF FOUNDATION- Pile foundation ● Length can be readily varied to suit varying ground conditions. ● It can be installed in very large diameters. ● End enlargement up to two or three diameters are possible in clays. ● Material of piles is not dependent on handling or driving conditions. ● It can be installed in very long lengths.
  • 10. Figure 18 and 19: Construction of pile cap in the pit excavation. Steel sheet piles are used to prevent the soil from leaking into the excavation. Figure 18. Figure 19. Figure 20: An excavator is spotted while excavating soil. Figure 20.
  • 11. Figure 21: This area is where the biggest pile cap among all of the pile caps in the site get constructed. This pile cap weighed around 85 tonne. Figure 21. Figure 22. Figure 22: Bored piles are used at the site to support high buildings that have heavy vertical load.
  • 12. OTHER DETAILS AND PHOTOS OF THE SITE-   Figure 23: Scaffolding is spotted in the site too. Figure 23. Figure 24. Figure 24: There are walls around the sides above the slab with formwork and reinforcement bars installed. Figure 25: Water stop is installed in the wall to prevent water from entering the basement. Figure 25. Figure 26. Figure 26: This photo shows the inner side of formwork of the wall.
  • 13. Figure 27: The component that is held by the supervisor is used to tie the formwork of walls as shown in Figure 13. Figure 27. Figure 28. Figure 28: 50mm diameter concrete cover is spotted. Figure 28. Figure 29. Figure 29: Precast bored piles
  • 14. Figure 30: 50mm diameter concrete cover is spotted.   THANKYOU