This document presents a fuzzy-logic based approach to solve the unit commitment problem in power generation systems. The unit commitment problem aims to determine the optimal on/off schedule of generating units to minimize operating costs while meeting demand and constraints. The proposed approach models key factors like generator load capacity, fuel costs, and startup costs as fuzzy variables. It then uses fuzzy logic techniques to determine a commitment schedule. The approach is demonstrated on a case study of a 4-unit thermal power plant in Turkey. Results are compared to dynamic programming to show the fuzzy logic approach provides preferable solutions with less computational time.