The document presents a comparative analysis of solving the unit commitment problem (UCP) of electric power systems using dynamic programming technique. It formulates the UCP considering fuel costs, voltage stability, and imbalance limits. Dynamic programming is described as a conventional algorithm for solving deterministic problems optimally through sequential decision making. The developed algorithm is implemented on 4-unit and 10-unit power systems. Results found the dynamic programming approach provides satisfactory solutions by minimizing total generation costs while meeting operational constraints.
International Journal of Computational Engineering Research (IJCER) is dedicated to protecting personal information and will make every reasonable effort to handle collected information appropriately. All information collected, as well as related requests, will be handled as carefully and efficiently as possible in accordance with IJCER standards for integrity and objectivity.
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit...IJAPEJOURNAL
In this paper an attempt has been made to solve the profit based unit commitment problem (PBUC) using pre-prepared power demand (PPD) table with an artificial bee colony (ABC) algorithm. The PPD-ABC algorithm appears to be a robust and reliable optimization algorithm for the solution of PBUC problem. The profit based unit commitment problem is considered as a stochastic optimization problem in which the objective is to maximize their own profit and the decisions are needed to satisfy the standard operating constraints. The PBUC problem is solved by the proposed methodology in two stages. In the first step, the unit commitment scheduling is performed by considering the pre-prepared power demand (PPD) table and then the problem of fuel cost and revenue function is solved using ABC Algorithm. The PPD table suggests the operator to decide the units to be put into generation there by reducing the complexity of the problem. The proposed approach is demonstrated on 10 units 24 hour and 50 units 24 hour test systems and numerical results are tabulated. Simulation result shows that this approach effectively maximizes the GENCO’s profit than those obtained by other optimizing methods.
Optimal unit commitment of a power plant using particle swarm optimization ap...IJECEIAES
Economic load dispatch among generating units is very important for any power plant. In this work, the economic load dispatch was made at Egbin Thermal Power plant supplying a total load of 600MW using six generating units. In carrying out this study, transmission losses were assumed to be included into the load supplied. Also, three different combinations in the form of 6, 5- and 4-units commitment were considered. In each case, the total load was optimally dispatched between committed generating units using Particle Swarm Optimization (PSO). Similarly, the generation cost for each generating unit was determined. For case 1, the six generators were committed and the generation cost is 2,100,685.069$/h. For case 2, five generators were committed and the generation cost is 2,520,861.947$/h. For case 3, four generators were committed and the generation cost is 3,150,621.685$/h. From all considered cases, it was found that, the minimum generation cost was achieved when all six generating units were committed and a total of 420,178.878$/h was saved.
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMaeijjournal
Solving the unit commitment (UC) problem is one of the most complicated issues in power systems that its
exact solving can be calculated by perfect counting of entire possible compounds of generative units. UC is
equated as a nonlinear optimization with huge size. Purpose of solving this problem is to programming the
optimization of the generative units to minimize the full action cost regarding problem constraints. In this
article, a modified version of ant colony optimization (MACO) is introduced for solving the UC problem in
a power system. ACO algorithm is a powerful optimization method which has the capability of fleeing from
local minimums by performing flexible memory system. The efficiency of proposed method in two power
system containing 4 and 10 generative units is indicated. Comparison of obtained results from the proposed
method with results of the past well-known methods is a proof for suitability of performing the introduced
algorithm in economic input and output of generative units.
International Journal of Computational Engineering Research (IJCER) is dedicated to protecting personal information and will make every reasonable effort to handle collected information appropriately. All information collected, as well as related requests, will be handled as carefully and efficiently as possible in accordance with IJCER standards for integrity and objectivity.
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit...IJAPEJOURNAL
In this paper an attempt has been made to solve the profit based unit commitment problem (PBUC) using pre-prepared power demand (PPD) table with an artificial bee colony (ABC) algorithm. The PPD-ABC algorithm appears to be a robust and reliable optimization algorithm for the solution of PBUC problem. The profit based unit commitment problem is considered as a stochastic optimization problem in which the objective is to maximize their own profit and the decisions are needed to satisfy the standard operating constraints. The PBUC problem is solved by the proposed methodology in two stages. In the first step, the unit commitment scheduling is performed by considering the pre-prepared power demand (PPD) table and then the problem of fuel cost and revenue function is solved using ABC Algorithm. The PPD table suggests the operator to decide the units to be put into generation there by reducing the complexity of the problem. The proposed approach is demonstrated on 10 units 24 hour and 50 units 24 hour test systems and numerical results are tabulated. Simulation result shows that this approach effectively maximizes the GENCO’s profit than those obtained by other optimizing methods.
Optimal unit commitment of a power plant using particle swarm optimization ap...IJECEIAES
Economic load dispatch among generating units is very important for any power plant. In this work, the economic load dispatch was made at Egbin Thermal Power plant supplying a total load of 600MW using six generating units. In carrying out this study, transmission losses were assumed to be included into the load supplied. Also, three different combinations in the form of 6, 5- and 4-units commitment were considered. In each case, the total load was optimally dispatched between committed generating units using Particle Swarm Optimization (PSO). Similarly, the generation cost for each generating unit was determined. For case 1, the six generators were committed and the generation cost is 2,100,685.069$/h. For case 2, five generators were committed and the generation cost is 2,520,861.947$/h. For case 3, four generators were committed and the generation cost is 3,150,621.685$/h. From all considered cases, it was found that, the minimum generation cost was achieved when all six generating units were committed and a total of 420,178.878$/h was saved.
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMaeijjournal
Solving the unit commitment (UC) problem is one of the most complicated issues in power systems that its
exact solving can be calculated by perfect counting of entire possible compounds of generative units. UC is
equated as a nonlinear optimization with huge size. Purpose of solving this problem is to programming the
optimization of the generative units to minimize the full action cost regarding problem constraints. In this
article, a modified version of ant colony optimization (MACO) is introduced for solving the UC problem in
a power system. ACO algorithm is a powerful optimization method which has the capability of fleeing from
local minimums by performing flexible memory system. The efficiency of proposed method in two power
system containing 4 and 10 generative units is indicated. Comparison of obtained results from the proposed
method with results of the past well-known methods is a proof for suitability of performing the introduced
algorithm in economic input and output of generative units.
Design of GCSC Stabilizing Controller for Damping Low Frequency OscillationsIJAEMSJORNAL
This paper presents a systematic procedure for modeling and simulation of a power system equipped with FACTS type Gate Controlled Series Compensator (GCSC) based stabilizer controller. Single Machine Infinite Bus (SMIB) power system was investigated for evaluation of GCSC stabilizing controller for enhancing the overall dynamic system performance. PSO algorithm is employed to compute the optimal parameters of damping controller. Eigenvalues of system under various operating condition and nonlinear time domain simulation is employed to verify the effectiveness and robustness of GCSC stabilizing controller in damping low frequency oscillations (LFO) modes.
Meta-heuristic optimization techniques are important tools to define the optimal solutions for many problems. In this paper, a new advanced artificial intelligence (AI) based direct torque control (DTC) speed drives are optimally designed and implemented in real time to achieve a high performance permanent-magnet synchronous-motor (PMSM) drive. Grey wolf (GW) algorithms are used with the standard PID-based DTC (PIDDTC) and with the DTC with fuzzy logic (FDTC) based speed controllers. DSPACE DS1202 is utilized in the real-time implementation. MATLAB SIMULINK is used to simulate the steady-state (S.S.) and dynamic responses. The overall system is tested at different operating conditions for both simulation and practical work and all results are presented. A comparison between experimental and simulation results is performed and also a comparison between different applied intelligent techniques is introduced.
This work proposes an optimization algorithm to control speed of a permanent magnet synchronous motor (PMSM) during starting and speed reversal of motor, as well as during load disturbance conditions. The objective is to minimize the integral absolute control error of the PMSM shaft speed to achieve fast and accurate speed response under load disturbance and speed reversal conditions. The maximum overshoot, peak time, settling time and rise time of the motor is also minimized to obtain efficient transient speed response. Optimum speed control of PMSM is obtained with the aid of a PID speed controller. Modified Particle Swarm Optimization (MPSO) and Ant Colony Optimization (ACO) techniques has been employed for tuning of the PID speed controller, to determine its gain coefficients (proportional, integral and derivative). Simulation results demonstrate that with use of MPSO and ACO techniques improved control performance of PMSM can be achieved in comparison to the classical Ziegler-Nichols (Z-N) method of PID tuning.
Dynamic Economic Dispatch Assessment Using Particle Swarm Optimization TechniquejournalBEEI
This paper presents the application of particle swarm optimization (PSO) technique for solving the dynamic economic dispatch (DED) problem. The DED is one of the main functions in power system planning in order to obtain optimum power system operation and control. It determines the optimal operation of generating units at every predicted load demands over a certain period of time. The optimum operation of generating units is obtained by referring to the minimum total generation cost while the system is operating within its limits. The DED based PSO technique is tested on a 9-bus system containing of three generator bus, six load bus and twelve transmission lines.
An Adaptive Internal Model for Load Frequency Control using Extreme Learning ...TELKOMNIKA JOURNAL
As an important part of a power system, a load frequency control has to be prepared with a better controller to ensure internal frequency stability. In this paper, an Internal Model Control (IMC) scheme for a Load Frequency Control (LFC) with an adaptive internal model is proposed. The effectiveness of the IMC control has been tested in a three area power system. Results of the simulation show that the proposed IMC with Extreme Learning Machine (ELM) based adaptive model can accurately cover the power system dynamics. Furthermore, the proposed controller can effectively reduce the frequency and mechanical power deviation under disturbances of the power system.
Comparative study of the price penalty factors approaches for Bi-objective di...IJECEIAES
One of the main objectives of electricity dispatch centers is to schedule the operation of available generating units to meet the required load demand at minimum operating cost with minimum emission level caused by fossil-based power plants. Finding the right balance between the fuel cost the green gasemissionsis reffered as Combined Economic and Emission Dispatch (CEED) problem which is one of the important optimization problems related the operationmodern power systems. The Particle Swarm Optimization algorithm (PSO) is a stochastic optimization technique which is inspired from the social learning of birds or fishes. It is exploited to solve CEED problem. This paper examines the impact of six penalty factors like "Min-Max", "Max-Max", "Min-Min", "Max-Min", "Average" and "Common" price penalty factors for solving CEED problem. The Price Penalty Factor for the CEED is the ratio of fuel cost to emission value. This bi-objective dispatch problem is investigated in the Real West Algeria power network consisting of 22 buses with 7 generators. Results prove capability of PSO in solving CEED problem with various penalty factors and it proves that Min-Max price penalty factor provides the best compromise solution in comparison to the other penalty factors.
IMPROVING REAL TIME TASK AND HARNESSING ENERGY USING CSBTS IN VIRTUALIZED CLOUDijcax
Cloud computing provides the facility for the business customers to scale up and down their resource usage
based on needs. This is because of the virtualization technology. The scheduling objectives are to improve
the system’s schedule ability for the real-time tasks and to save energy. To achieve the objectives, we
employed the virtualization technique and rolling-horizon optimization with vertical scheduling operation.
The project considers Cluster Scoring Based Task Scheduling (CSBTS) algorithm which aims to decrease
task’s completion time and the policies for VM’s creation, migration and cancellation are to dynamically
adjust the scale of cloud in a while meets the real-time requirements and to save energy.
IMPROVING REAL TIME TASK AND HARNESSING ENERGY USING CSBTS IN VIRTUALIZED CLOUDijcax
Cloud computing provides the facility for the business customers to scale up and down their resource usage based on needs. This is because of the virtualization technology. The scheduling objectives are to improve the system’s schedule ability for the real-time tasks and to save energy. To achieve the objectives, we employed the virtualization technique and rolling-horizon optimization with vertical scheduling operation.
The project considers Cluster Scoring Based Task Scheduling (CSBTS) algorithm which aims to decrease task’s completion time and the policies for VM’s creation, migration and cancellation are to dynamically adjust the scale of cloud in a while meets the real-time requirements and to save energy.
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...paperpublications3
Abstract: In this paper, an algorithm to solve the optimal unit commitment problem under deregulated environment has been proposed using Particle Swarm Optimization (PSO) intelligent technique accounting economic dispatch constraints. In the present electric power market, where renewable energy power plants have been included in the system, there is a lot of unpredictability in the demand and generation. This paper presents an improved particle swarm optimization algorithm (IPSO) for power system unit commitment with the consideration of various constraints. IPSO is an extension of the standard particle swarm optimization algorithm (PSO) which uses more particles information to control the mutation operation, and is similar to the social society in that a group of leaders could make better decisions. The program was developed in MATLAB and the proposed method implemented on IEEE 14 bus test system.
Security Constrained UCP with Operational and Power Flow ConstraintsIDES Editor
An algorithm to solve security constrained unit
commitment problem (UCP) with both operational and power
flow constraints (PFC) have been proposed to plan a secure
and economical hourly generation schedule. This proposed
algorithm introduces an efficient unit commitment (UC)
approach with PFC that obtains the minimum system
operating cost satisfying both unit and network constraints
when contingencies are included. In the proposed model
repeated optimal power flow for the satisfactory unit
combinations for every line removal under given study period
has been carried out to obtain UC solutions with both unit and
network constraints. The system load demand patterns have
been obtained for the test case systems taking into account of
the hourly load variations at the load buses by adding
Gaussian random noises. In this paper, the proposed
algorithm has been applied to obtain UC solutions for IEEE
30, 118 buses and Indian utility practical systems scheduled
for 24 hours. The algorithm and simulation are carried
through Matlab software and the results obtained are quite
encouraging.
The optimal solution for unit commitment problem using binary hybrid grey wol...IJECEIAES
The aim of this work is to solve the unit commitment (UC) problem in power systems by calculating minimum production cost for the power generation and finding the best distribution of the generation among the units (units scheduling) using binary grey wolf optimizer based on particle swarm optimization (BGWOPSO) algorithm. The minimum production cost calculating is based on using the quadratic programming method and represents the global solution that must be arriving by the BGWOPSO algorithm then appearing units status (on or off). The suggested method was applied on “39 bus IEEE test systems”, the simulation results show the effectiveness of the suggested method over other algorithms in terms of minimizing of production cost and suggesting excellent scheduling of units.
Design of GCSC Stabilizing Controller for Damping Low Frequency OscillationsIJAEMSJORNAL
This paper presents a systematic procedure for modeling and simulation of a power system equipped with FACTS type Gate Controlled Series Compensator (GCSC) based stabilizer controller. Single Machine Infinite Bus (SMIB) power system was investigated for evaluation of GCSC stabilizing controller for enhancing the overall dynamic system performance. PSO algorithm is employed to compute the optimal parameters of damping controller. Eigenvalues of system under various operating condition and nonlinear time domain simulation is employed to verify the effectiveness and robustness of GCSC stabilizing controller in damping low frequency oscillations (LFO) modes.
Meta-heuristic optimization techniques are important tools to define the optimal solutions for many problems. In this paper, a new advanced artificial intelligence (AI) based direct torque control (DTC) speed drives are optimally designed and implemented in real time to achieve a high performance permanent-magnet synchronous-motor (PMSM) drive. Grey wolf (GW) algorithms are used with the standard PID-based DTC (PIDDTC) and with the DTC with fuzzy logic (FDTC) based speed controllers. DSPACE DS1202 is utilized in the real-time implementation. MATLAB SIMULINK is used to simulate the steady-state (S.S.) and dynamic responses. The overall system is tested at different operating conditions for both simulation and practical work and all results are presented. A comparison between experimental and simulation results is performed and also a comparison between different applied intelligent techniques is introduced.
This work proposes an optimization algorithm to control speed of a permanent magnet synchronous motor (PMSM) during starting and speed reversal of motor, as well as during load disturbance conditions. The objective is to minimize the integral absolute control error of the PMSM shaft speed to achieve fast and accurate speed response under load disturbance and speed reversal conditions. The maximum overshoot, peak time, settling time and rise time of the motor is also minimized to obtain efficient transient speed response. Optimum speed control of PMSM is obtained with the aid of a PID speed controller. Modified Particle Swarm Optimization (MPSO) and Ant Colony Optimization (ACO) techniques has been employed for tuning of the PID speed controller, to determine its gain coefficients (proportional, integral and derivative). Simulation results demonstrate that with use of MPSO and ACO techniques improved control performance of PMSM can be achieved in comparison to the classical Ziegler-Nichols (Z-N) method of PID tuning.
Dynamic Economic Dispatch Assessment Using Particle Swarm Optimization TechniquejournalBEEI
This paper presents the application of particle swarm optimization (PSO) technique for solving the dynamic economic dispatch (DED) problem. The DED is one of the main functions in power system planning in order to obtain optimum power system operation and control. It determines the optimal operation of generating units at every predicted load demands over a certain period of time. The optimum operation of generating units is obtained by referring to the minimum total generation cost while the system is operating within its limits. The DED based PSO technique is tested on a 9-bus system containing of three generator bus, six load bus and twelve transmission lines.
An Adaptive Internal Model for Load Frequency Control using Extreme Learning ...TELKOMNIKA JOURNAL
As an important part of a power system, a load frequency control has to be prepared with a better controller to ensure internal frequency stability. In this paper, an Internal Model Control (IMC) scheme for a Load Frequency Control (LFC) with an adaptive internal model is proposed. The effectiveness of the IMC control has been tested in a three area power system. Results of the simulation show that the proposed IMC with Extreme Learning Machine (ELM) based adaptive model can accurately cover the power system dynamics. Furthermore, the proposed controller can effectively reduce the frequency and mechanical power deviation under disturbances of the power system.
Comparative study of the price penalty factors approaches for Bi-objective di...IJECEIAES
One of the main objectives of electricity dispatch centers is to schedule the operation of available generating units to meet the required load demand at minimum operating cost with minimum emission level caused by fossil-based power plants. Finding the right balance between the fuel cost the green gasemissionsis reffered as Combined Economic and Emission Dispatch (CEED) problem which is one of the important optimization problems related the operationmodern power systems. The Particle Swarm Optimization algorithm (PSO) is a stochastic optimization technique which is inspired from the social learning of birds or fishes. It is exploited to solve CEED problem. This paper examines the impact of six penalty factors like "Min-Max", "Max-Max", "Min-Min", "Max-Min", "Average" and "Common" price penalty factors for solving CEED problem. The Price Penalty Factor for the CEED is the ratio of fuel cost to emission value. This bi-objective dispatch problem is investigated in the Real West Algeria power network consisting of 22 buses with 7 generators. Results prove capability of PSO in solving CEED problem with various penalty factors and it proves that Min-Max price penalty factor provides the best compromise solution in comparison to the other penalty factors.
IMPROVING REAL TIME TASK AND HARNESSING ENERGY USING CSBTS IN VIRTUALIZED CLOUDijcax
Cloud computing provides the facility for the business customers to scale up and down their resource usage
based on needs. This is because of the virtualization technology. The scheduling objectives are to improve
the system’s schedule ability for the real-time tasks and to save energy. To achieve the objectives, we
employed the virtualization technique and rolling-horizon optimization with vertical scheduling operation.
The project considers Cluster Scoring Based Task Scheduling (CSBTS) algorithm which aims to decrease
task’s completion time and the policies for VM’s creation, migration and cancellation are to dynamically
adjust the scale of cloud in a while meets the real-time requirements and to save energy.
IMPROVING REAL TIME TASK AND HARNESSING ENERGY USING CSBTS IN VIRTUALIZED CLOUDijcax
Cloud computing provides the facility for the business customers to scale up and down their resource usage based on needs. This is because of the virtualization technology. The scheduling objectives are to improve the system’s schedule ability for the real-time tasks and to save energy. To achieve the objectives, we employed the virtualization technique and rolling-horizon optimization with vertical scheduling operation.
The project considers Cluster Scoring Based Task Scheduling (CSBTS) algorithm which aims to decrease task’s completion time and the policies for VM’s creation, migration and cancellation are to dynamically adjust the scale of cloud in a while meets the real-time requirements and to save energy.
Optimal Unit Commitment Based on Economic Dispatch Using Improved Particle Sw...paperpublications3
Abstract: In this paper, an algorithm to solve the optimal unit commitment problem under deregulated environment has been proposed using Particle Swarm Optimization (PSO) intelligent technique accounting economic dispatch constraints. In the present electric power market, where renewable energy power plants have been included in the system, there is a lot of unpredictability in the demand and generation. This paper presents an improved particle swarm optimization algorithm (IPSO) for power system unit commitment with the consideration of various constraints. IPSO is an extension of the standard particle swarm optimization algorithm (PSO) which uses more particles information to control the mutation operation, and is similar to the social society in that a group of leaders could make better decisions. The program was developed in MATLAB and the proposed method implemented on IEEE 14 bus test system.
Security Constrained UCP with Operational and Power Flow ConstraintsIDES Editor
An algorithm to solve security constrained unit
commitment problem (UCP) with both operational and power
flow constraints (PFC) have been proposed to plan a secure
and economical hourly generation schedule. This proposed
algorithm introduces an efficient unit commitment (UC)
approach with PFC that obtains the minimum system
operating cost satisfying both unit and network constraints
when contingencies are included. In the proposed model
repeated optimal power flow for the satisfactory unit
combinations for every line removal under given study period
has been carried out to obtain UC solutions with both unit and
network constraints. The system load demand patterns have
been obtained for the test case systems taking into account of
the hourly load variations at the load buses by adding
Gaussian random noises. In this paper, the proposed
algorithm has been applied to obtain UC solutions for IEEE
30, 118 buses and Indian utility practical systems scheduled
for 24 hours. The algorithm and simulation are carried
through Matlab software and the results obtained are quite
encouraging.
The optimal solution for unit commitment problem using binary hybrid grey wol...IJECEIAES
The aim of this work is to solve the unit commitment (UC) problem in power systems by calculating minimum production cost for the power generation and finding the best distribution of the generation among the units (units scheduling) using binary grey wolf optimizer based on particle swarm optimization (BGWOPSO) algorithm. The minimum production cost calculating is based on using the quadratic programming method and represents the global solution that must be arriving by the BGWOPSO algorithm then appearing units status (on or off). The suggested method was applied on “39 bus IEEE test systems”, the simulation results show the effectiveness of the suggested method over other algorithms in terms of minimizing of production cost and suggesting excellent scheduling of units.
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineIJAPEJOURNAL
Economic load dispatch (ELD) and Unit Commitment (UC) are significant research applications in power systems that optimize the total production cost of the predicted load demand. The UC problem determines a turn-on and turn-off schedule for a given combination of generating units, thus satisfying a set of dynamic operational constraints. ELD optimizes the operation cost for all scheduled generating units with respect to the load demands of customers. The first phase in this project is to economically schedule the distribution of generating units using Gauss seidal and the second phase is to determine optimal load distribution for the scheduled units using dynamic programming method is applied to select and choose the combination of generating units that commit and de-commit during each hour. These precommitted schedules are optimized by dynamic programming method thus producing a global optimum solution with feasible and effective solution quality, minimal cost and time and higher precision. The effectiveness of the proposed techniques is investigated on two test systems consisting of five generating units and the experiments are carried out using MATLAB R2010b software. Experimental results prove that the proposed method is capable of yielding higher quality solution including mathematical simplicity, fast convergence, diversity maintenance, robustness and scalability for the complex ELD-UC problem.
Reliability Constrained Unit Commitment Considering the Effect of DG and DR P...IJECEIAES
Due to increase in energy prices at peak periods and increase in fuel cost, involving Distributed Generation (DG) and consumption management by Demand Response (DR) will be unavoidable options for optimal system operations. Also, with high penetration of DGs and DR programs into power system operation, the reliability criterion is taken into account as one of the most important concerns of system operators in management of power system. In this paper, a Reliability Constrained Unit Commitment (RCUC) at presence of time-based DR program and DGs integrated with conventional units is proposed and executed to reach a reliable and economic operation. Designated cost function has been minimized considering reliability constraint in prevailing UC formulation. The UC scheduling is accomplished in short-term so that the reliability is maintained in acceptable level. Because of complex nature of RCUC problem and full AC load flow constraints, the hybrid algorithm included Simulated Annealing (SA) and Binary Particle Swarm Optimization (BPSO) has been proposed to optimize the problem. Numerical results demonstrate the effectiveness of the proposed method and considerable efficacy of the time-based DR program in reducing operational costs by implementing it on IEEE-RTS79.
An Improved Particle Swarm Optimization for Proficient Solving of Unit Commit...IDES Editor
This paper presents a new approach to solving the
short-term unit commitment problem using an improved
Particle Swarm Optimization (IPSO). The objective of this
paper is to find the generation scheduling such that the total
operating cost can be minimized, when subjected to a variety
of constraints. This also means that it is desirable to find the
optimal generating unit commitment in the power system for
the next H hours. PSO, which happens to be a Global
Optimization technique for solving Unit Commitment
Problem, operates on a system, which is designed to encode
each unit’s operating schedule with regard to its minimum
up/down time. In this, the unit commitment schedule is coded
as a string of symbols. An initial population of parent
solutions is generated at random. Here, each schedule is
formed by committing all the units according to their initial
status (“flat start”). Here the parents are obtained from a predefined
set of solution’s i.e. each and every solution is adjusted
to meet the requirements. Then, a random decommitment is
carried out with respect to the unit’s minimum down times. A
thermal Power System in India demonstrates the effectiveness
of the proposed approach; extensive studies have also been
performed for different power systems consist of 10, 26, 34
generating units. Numerical results are shown comparing the
cost solutions and computation time obtained by using the
IPSO and other conventional methods like Dynamic
Programming (DP), Legrangian Relaxation (LR) in reaching
proper unit commitment.
Security Constraint Unit Commitment Considering Line and Unit Contingencies-p...IJAPEJOURNAL
This paper presents a new approach for considering all possible contingencies in short-term power system operation. Based on this new approach, both generator and transmission line outages would be modeled in network-based power system analysis. Multi generator and also parallel transmission lines is modeled in this methodology. We also investigate this claim that feasibility and applicability of this approach is much more than the previous analytical methodologies. Security Constrained Unit commitment (SCUC) program which is carried out by Independent System Operator (ISO), is one of the complex problems which would be handled by this approach. In this paper, a DC-Optimal Power Flow (DCOPF) methodology has been implemented by particle swarm optimization technique. The Lagrangian Relaxation technique is based on the derivatives and the PSO is a non- derivative technique. These approaches are effective tools which can be implemented for short-term and long-term power system analysis, especially for economic analysis of restructured power systems. The DCOPF methodology has been considered for LMP calculation in LR, which is not available in PSO techniques. In the other hand, PSO technique may be able to provide the optimal solution, where LR usually getting stuck at a local optimum in a large scale power system. The simulation results show that the presented methods are both satisfactory and consistent with expectation.
This paper proposed the integration of solar energy resources into the conventional unit commitment. The growing concern about the depletion of fossil fuels increased the awareness on the importance of renewable energy resources, as an alternative energy resources in unit commitment operation. However, the present renewable energy resources are intermitted due to unpredicted photovoltaic output. Therefore, Ant Lion Optimizer (ALO) is proposed to solve unit commitment problem in smart grid system with consideration of uncertainties .ALO is inspired by the hunting appliance of ant lions in natural surroundings. A 10-unit system with the constraints, such as power balance, spinning reserve, generation limit, minimum up and down time constraints are considered to prove the effectiveness of the proposed method. The performance of proposed algorithm are compared with the performance of Dynamic Programming (DP). The results show that the integration of solar energy resources in unit commitment scheduling can improve the total operating cost significantly.
International Journal of Engineering Research and Applications (IJERA) is an open access online peer reviewed international journal that publishes research and review articles in the fields of Computer Science, Neural Networks, Electrical Engineering, Software Engineering, Information Technology, Mechanical Engineering, Chemical Engineering, Plastic Engineering, Food Technology, Textile Engineering, Nano Technology & science, Power Electronics, Electronics & Communication Engineering, Computational mathematics, Image processing, Civil Engineering, Structural Engineering, Environmental Engineering, VLSI Testing & Low Power VLSI Design etc.
Operation cost reduction in unit commitment problem using improved quantum bi...IJECEIAES
Unit Commitment (UC) is a nonlinear mixed integer-programming problem. UC used to minimize the operational cost of the generation units in a power system by scheduling some of generators in ON state and the other generators in OFF state according to the total power outputs of generation units, load demand and the constraints of power system. This paper proposes an Improved Quantum Binary Particle Swarm Optimization (IQBPSO) algorithm. The tests have been made on a 10-units simulation system and the results show the improvement in an operation cost reduction after using the proposed algorithm compared with the ordinary Quantum Binary Particle Swarm Optimization (QBPSO) algorithm
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMAEIJjournal2
Solving the unit commitment (UC) problem is one of the most complicated issues in power systems that its
exact solving can be calculated by perfect counting of entire possible compounds of generative units. UC is
equated as a nonlinear optimization with huge size. Purpose of solving this problem is to programming the
optimization of the generative units to minimize the full action cost regarding problem constraints. In this
article, a modified version of ant colony optimization (MACO) is introduced for solving the UC problem in
a power system. ACO algorithm is a powerful optimization method which has the capability of fleeing from
local minimums by performing flexible memory system. The efficiency of proposed method in two power
system containing 4 and 10 generative units is indicated. Comparison of obtained results from the proposed
method with results of the past well-known methods is a proof for suitability of performing the introduced
algorithm in economic input and output of generative units.
A MODIFIED ANT COLONY ALGORITHM FOR SOLVING THE UNIT COMMITMENT PROBLEMAEIJjournal2
Solving the unit commitment (UC) problem is one of the most complicated issues in power systems that its exact solving can be calculated by perfect counting of entire possible compounds of generative units. UC is equated as a nonlinear optimization with huge size. Purpose of solving this problem is to programming the optimization of the generative units to minimize the full action cost regarding problem constraints. In this article, a modified version of ant colony optimization (MACO) is introduced for solving the UC problem in a power system. ACO algorithm is a powerful optimization method which has the capability of fleeing from
local minimums by performing flexible memory system. The efficiency of proposed method in two power system containing 4 and 10 generative units is indicated. Comparison of obtained results from the proposed
method with results of the past well-known methods is a proof for suitability of performing the introduced
algorithm in economic input and output of generative units.
Similar to IRJET-Comparative Analysis of Unit Commitment Problem of Electric Power System using DynamicProgramming Technique (20)
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
CFD analysis is incredibly effective at solving mysteries and improving the performance of complex systems!
Here's a great example: At a large natural gas-fired power plant, where they use waste heat to generate steam and energy, they were puzzled that their boiler wasn't producing as much steam as expected.
R&R and Tetra Engineering Group Inc. were asked to solve the issue with reduced steam production.
An inspection had shown that a significant amount of hot flue gas was bypassing the boiler tubes, where the heat was supposed to be transferred.
R&R Consult conducted a CFD analysis, which revealed that 6.3% of the flue gas was bypassing the boiler tubes without transferring heat. The analysis also showed that the flue gas was instead being directed along the sides of the boiler and between the modules that were supposed to capture the heat. This was the cause of the reduced performance.
Based on our results, Tetra Engineering installed covering plates to reduce the bypass flow. This improved the boiler's performance and increased electricity production.
It is always satisfying when we can help solve complex challenges like this. Do your systems also need a check-up or optimization? Give us a call!
Work done in cooperation with James Malloy and David Moelling from Tetra Engineering.
More examples of our work https://www.r-r-consult.dk/en/cases-en/
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.