MINISTER OF EDUCATION YOUTH
AND SPORT
1
INSTITUTE OF TECHNOLOGY OF CAMBODIA
INDUSTRIAL AND MECHANICAL ENGINEERING
THESIS
Title :Water Cooled Chiller System Selection
Student : Mr. SENG Sunhor
Major : Industrial and Mechanical Engineering
Adviser : Mr. UN Amata
Academic year: 2015 – 2016
Outline
2
I. Introduction of Comin Khmere
II. Water Cooled Chiller System
IV. Conclusion
III. Calculation and Selection
I. Introduction
1. Comin Khmer Co. Ltd.,
3
The first MEP Company
Mechanical Electrical Plumbing
Figure2.1. Comin Khmere
 Address: No 8b,
Down Town Road,
Phnom Penh,
4
II. Water Cooled Chiller System
1. Introduction of water cooled chiller system
2. Equipment of Water Cooled Chiller System
5
1. Introduction of water cooled chiller system
 A kind of Air-conditioning system
 It was installed by combined many components
• Chiller
• Pump: Condenser water pump &
: Chilled water pump
• Cooling Tower
• Expansion Tank
6
2. Equipment of Water Cooled Chiller System
 AHU/PHU  FCU
Used for indoor unit
Figure 2.2. Fain coil unitFigure 2.1. Air handing unit
7
• Condenser
• Compressor
• Evaporator
 Components of Chiller
2. Equipment of Water Cooled Chiller System
Figure 2.3. Fain coil unit
8
2. Equipment of Water Cooled Chiller System
 Cooling Tower Pump
Figure 2.4.Pump Figure 2.5.Cooling Tower
9
III. Calculation and Selection
1. Building Load Calculation
2. Cooling Tower
4. Make-Up Tank
3. Pump (CHWP & CDWP)
2. Chiller
10
1. Building Load Calculation
 ACLEDA DATA CENTER BUIDING
It has many kind of rooms
• There are six level; GF, 1F to 4F
and Terrace Floor.
• Data center room
• Office
• UPS room
• Meeting room
11
 Hourly Analysis Program (HAP)
1. Building Load Calculation
Figure 3.1. Hourly Analysis Program
12
1. Building Load Calculation
 FCU Selection from the Catalogs
• Total load in building = 2299kW
 Calculation by HAP
• Total Load = 2357 kW
 Chiller selection
No Description
Cooling Chiller Qty
Duty Standby
Load(kW) kW Total
1 Total load 2357 843.9 4 3 1
Table 3.1. Number of chiller; duty & standby
13Figure.3.2 Chiller Catalog
Cooling Capacity
𝑄 𝑒𝑣𝑎 = 843.9𝑘𝑊
14
2. Cooling Tower
 Net Heat Calculation Qconden𝑠𝑒𝑟; ( kW)
 Water flow rate mw; (kg/s or L/s)
 Inlet and out let temperature in CT ∆T; (℃)
∆𝑇 = TCT en − TC𝑇 out = 37℃ − 32℃ = 5℃
Winput = QH − QL = Qc𝑑 − Qeva
Second law of Thermodynamic
⇒ Qcd = Winput − Qeva (eq.1)
15
Cooling Coefficient of Performance (COPR)
COPR =
Qeva
Winput
⇒ Winput =
Qeva
COPR
(eq.2)
• Qeva =843.9 kW; Cooling Capacity
• Winput: Power input (kW)
COPR ≈5; in water cooled chiller system
2. Cooling Tower
16
Qcd = 𝑚 𝑤 𝑐 𝑝∆𝑇 ⇒ 𝑚 𝑤 =
Qcd
𝑐 𝑝∆𝑇
(eq.3)
 Water flow rate: 𝑚 𝑤;
 𝑐 𝑝=4.179 kJ/kg.K
𝑚 𝑤 =
1012.68
5×4.179
= 48.5 𝑙/𝑠=174.6 𝒎 𝟑
𝒉
(eq.1); => Qcd = Qeva +
Qeva
COPR
= 843.9 +
843.9
5
Qcd = 1012.68 𝑘𝑊
2. Cooling Tower
17
No Description Qcd EWT LWT mw
kW ℃ ℃ m3
h
1 CT-01 1012.68 37 32 174.6
2 CT-01 1012.68 37 32 174.6
3 CT-01 1012.68 37 32 174.6
4 CT-01 1012.68 37 32 174.6
Table 3.1. Cooling selection
Data for selection cooling tower
2. Cooling Tower
18
Cooling tower catalog
Fig 3.3. Cooling tower Catalog
Flow rate
197.9
2230E
2. Cooling Tower
19
2230E
20
 Flow rate; 𝑚 𝑤 and Pressure drop; 𝑃 𝑇𝑜𝑡𝑎𝑙
TCH en ≈ 12 ℃; TCH(out) ≈ 7℃ ; ∆𝑇 = 5℃
Qeva = mwcp∆TCH ; ∆TCH = TCH(en) − TCH out ; eq. 4
mw =
Qeva
cp(TCH(en)−TCH out )
=
843.9
4.179 × 5
mw = 40.4 l/s
3. Chiller Water Pump
21
PTotal=[2L(m)×100% ×400 × 10−3(kPa/m)+FCU(kPa)
+Chiller(kPa)] eq.5
 Estimation method
• Pressure drop that water across chiller is 49.8 kpa
• Pressure drop that water across FCU is 37.6 kpa
• 400 Pa m the maximum pressure drop along pipe
• L = 113m ; pipe length , 100%: Lossing a long fitting
PTotal = 2 × 113 × 2 × 400 × 10−3
kpa +
37.6 kpa + 49.8 kpa ]
𝐏 𝐓𝐨𝐭𝐚𝐥=268.2 kPa
3. Chiller Water Pump
22
 Detail Calculation Method
PTotal= Pt1 (drop by piping) + Pt (drop by fitting) eq.6
Pt1 = Pa × 𝐿 eq.7
• Pa: Pressure drop per meter Pa m
• 𝐿 = 16𝑚; 𝐷 = 150𝑚𝑚; 𝑚 𝑤 = 40.4 𝑙 𝑠
𝑚 𝑤 = 40.4 𝑙 𝑠
260pa
Figure 3.5. pipe sizing
D=150mm
3. Chiller Water Pump
23
⇒ Pt1= 260 × 16 = 4160Pa = 4.16kPa
 Pressure drop by fitting Pt1
• Elbow, Tee; Y-strainer, Flexible
• Valves: Balancing, Butterfly, Motorize, check valve
 Conservation of mass: mw = ρVA eq.8
A =
П𝐷2
4
; eq.8; V =
4×mw
ρПD2 =
4×40.4
1000×3.14×0.152
𝑽 = 𝟐. 𝟑 𝐦/𝐬
• ρ = 1000 𝑘𝑔 𝑚3 ; mass volum of water;
• A: area (𝑚2
); 𝑉: 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 𝑚 𝑠
3. Chiller Water Pump
24
Elbow 90° ⇒ 𝐿 = 5.1𝑚; Pt = 260 × 5.1 = 1326 Pa
⇒ Pt= 260 × 5.1 = 1326 Paeq.7
Fig 3.6. Equivalent length in meters of pipe for 90° Elbows
3. Chiller Water Pump
L=5.1m
25
 Tee
• Tee (300mm to 150mm)
% =
154.53
154.53
= 1 = 100%
The % of water flowing through circled branch
L = n × l eq.9
• n: number of elbow;
• l: equivalent length in meter (m)
3. Chiller Water Pump
26
100%
Flow
condition
n=1.7
Fig 3.7 % of water
3. Chiller Water Pump
27
mw = ρVA ⇒ V =
4 × mw
ρПD2
eq.10
• mw =154.53 l/s D=300mm=0.3m
V =
4 × 154.53
1000 × 3.14 × 0.32
= 2.187 = 2.2 m s
Fig 3.7. 𝑙 = 9.1𝑚 ⇒ L=1.7 ×9.1=15.47
Fig 3. 5 Pt = 120 × 15.47 = 1856.4 Pa
3. Chiller Water Pump
28
Equivalent length in meter of valves; l(m)
Dimension, D=150mm
Accessory Y-strainer Balancing Motorize Flexible Butterfly Check
Length(m) 34 34 1.4 1.4 1.4 18
Table.2. Equivalent length in meter of valves
Y-strainer Pt = 260 × 34 = 8840 Pa
Balancing valve Pt = 260 × 34 = 8840 Pa
Butterfly valve Pt = 260 × 1.4 = 364 Pa
Motorize valve Pt = 260 × 1.4 = 364 Pa
Check valve Pt = 260 × 18 = 4680 Pa
Flexible Pt = 260 × 1.4 = 364 Pa
3. Chiller Water Pump
29
 Summarize total loss in pipe & fitting for the system
• Total discharge pressure drop: Ptotal,1 = 173.8kPa
• Total suction pressure drop: Ptotal,2 = 889kPa
Ptotal = 173808 + 88961 = 262769𝑃𝑎 = 𝟐𝟔𝟐. 𝟖𝐤𝐏𝐚
Comparison
Estimation: Ptoatl = 268.2 kPa Detail: Ptoatl = 262.8 kPa
 Pressure drop total selection: Ptotal = 𝟐𝟕𝟎𝐤𝐏𝐚
Error≈ 2.23%
3. Chiller Water Pump
30
 Chiller water pump Data selection
No Description
Flow
Rate
Pressure
drop
Safety Coeff.
Total Pressure
drop
l/s kPa 20% kPa
1 CHWP-1 40.4 270 1.2 324
2 CHWP-2 40.4 270 1.2 324
3 CHWP-3 40.4 270 1.2 324
4 CHWP-4 40.4 270 1.2 324
Table 3.2. Cooling selection
3. Chiller Water Pump
31
Chilled Water Pumps Schedule
ITEM DESCRIPTION SPECIFIED
1 Ref. CHP-1~4
2 Quantity (set) 4 ( 3 Duty + 1 Standby )
3 System Chilled Water System
4 Location GF Chiller Plant Room
5 Type
End suction or Horizontal
Split Casing
6 Flow Rate (L/s) 40.4
7 Pump Head (m) 32.4
8 Pump Speed (rpm) 1450
9 Pump Efficiency (%) Not Specified
10 Motor Power (kW) 30
11
Power Supply
(Volt/Phase/Hz)
380/3/50
12 Motor - Type TEFC
Table 3.3. chilled water pump schedule
32
 Mass flow rate: mw = 48.5 𝑙 𝑠From: eq.3
 Total Pressure drop: Estimation method
PTotal = 2 × 105 × 2 × 400 × 10−3
kpa
+65 kpa + 38 kpa ]
PTotal=[2L(m)×100% ×400 × 10−3(kPa/m)+CT(kPa)
+H(kPa)] eq.11
• H=3.8m=38kPa Height of CT; L=105m; Loss in CT=65kPa;
100%: loss by fitting; 2: Return and supply pipe
𝐏 𝐓𝐨𝐭𝐚𝐥 = 𝟐𝟕𝟏𝐤𝐏𝐚
3. Condenser water pump
33
 Detail Calculation, we calculate as Chiller water pump
• 𝑇𝑜𝑡𝑎𝑙 𝐶𝐷𝑊𝑆 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑑𝑟𝑜𝑝: Ptotal,1 = 173.2𝐾𝑃𝑎
• 𝑇𝑜𝑡𝑎𝑙 𝐶𝐷𝑊𝑅 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑑𝑟𝑜𝑝: Ptotal,2 = 102.6𝑘𝑃𝑎
Ptotal = 173.2 + 102.6 = 275.8𝑘𝑃𝑎
Ptotal = 𝟐𝟕𝟓. 𝟖 𝐤𝐏𝐚
Comparison
Estimation: Ptoatl = 271 kPa Detail: Ptoatl = 275.8 kPa
 Pressure drop total selection: Ptotal = 𝟐𝟖𝟎𝐤𝐏𝐚
Error≈ 1.74%
3. Condenser water pump
34
No Description
Flowrate Pressure drop Safety Coeff P: total
l/s kPa 20% kPa
1 CHWP-1 48.5 280 1.2 336
2 CHWP-2 48.5 280 1.2 336
3 CHWP-3 48.5 280 1.2 336
4 CHWP-4 48.5 280 1.2 336
3. Chiller Water Pump
Table 3.4. Condenser water pump data selection
35
Condenser Water Pumps Schedule
ITEM DESCRIPTION SPECIFIED
1 Ref. CWP-1~4
2 Quantity (set) 4 ( 3 Duty + 1 Standby )
3 System Condenser Water System
4 Location GF Chiller Plant Room
5 Type
End suction or Horizontal
Split Casing
6 Flow Rate (L/s) 48.5
7 Pump Head (m) 33.6
8 Pump Speed (rpm) 1450
9 Pump Efficiency (%) Not Specified
10 Motor Power (kW) 30
11 Power Supply (Volt/Phase/Hz)380/3/50
12 Motor - Type TEFC
Table 3.5. Condenser water pump schedule
36
4. Make-Up Tank
 Evaporation loss, Drift loss and Blowdown loss
Make up water = Eva. loss + Drift loss + Blowdown loss
 Estimation of make up water calculation
• Evaporation loss=0.85%;
• Drift loss=0.02%;
• Blowdown loss=0.22%
=> Make up water=0.85+0.02+0.22%=1.09%
Water loss in 𝐶𝑇 =
48.5( 𝑙 𝑠)×1.09
100
= 0.53𝑙/𝑠
37
VM = mw × %loss × hours; VM: water volume (𝑚3
)
VM = 48.5 ×
1.09
100
× 2 ℎ = 48.5 × 0.0109 × 2 × 3600
VM = 3806l = 3.8𝑚3
VT = 3.8𝑚3
× 4 = 15.2𝑚3
; 4: number of CT
VT: Volume total
VT = 15.2𝑚3
4. Make-Up Tank
CHILLER
FAN COIL UNIT
AIR HANDLING UNIT
2 WAY VALVE
2 WAY VALVE
FRESH AIR
TEMPERATURE SENSOR
RETURN AIR
SUPPLY AIR
PRESSURE SENSOR
CHECK VALVETEMPERATURE
SENSOR
PRIMARY CHILLED
WATER PUMP
(WITHOUT VSD CONTROL)
THERMOSTAT
25 %
24 °C
10 %
7 °C
23.5 °C
12 °C
COOLING TOWER
CONDENSER
WATER PUMP
TEMPERATURE
SENSOR
37 °C
32 °C
39
 After I finished my thesis
• Calculation
• Selection
V. Conclusion
• Understand about water cooled chiller system
• Concept of designing
40
41

chiller system by Mr.Seng Sunhor

  • 1.
    MINISTER OF EDUCATIONYOUTH AND SPORT 1 INSTITUTE OF TECHNOLOGY OF CAMBODIA INDUSTRIAL AND MECHANICAL ENGINEERING THESIS Title :Water Cooled Chiller System Selection Student : Mr. SENG Sunhor Major : Industrial and Mechanical Engineering Adviser : Mr. UN Amata Academic year: 2015 – 2016
  • 2.
    Outline 2 I. Introduction ofComin Khmere II. Water Cooled Chiller System IV. Conclusion III. Calculation and Selection
  • 3.
    I. Introduction 1. CominKhmer Co. Ltd., 3 The first MEP Company Mechanical Electrical Plumbing Figure2.1. Comin Khmere  Address: No 8b, Down Town Road, Phnom Penh,
  • 4.
    4 II. Water CooledChiller System 1. Introduction of water cooled chiller system 2. Equipment of Water Cooled Chiller System
  • 5.
    5 1. Introduction ofwater cooled chiller system  A kind of Air-conditioning system  It was installed by combined many components • Chiller • Pump: Condenser water pump & : Chilled water pump • Cooling Tower • Expansion Tank
  • 6.
    6 2. Equipment ofWater Cooled Chiller System  AHU/PHU  FCU Used for indoor unit Figure 2.2. Fain coil unitFigure 2.1. Air handing unit
  • 7.
    7 • Condenser • Compressor •Evaporator  Components of Chiller 2. Equipment of Water Cooled Chiller System Figure 2.3. Fain coil unit
  • 8.
    8 2. Equipment ofWater Cooled Chiller System  Cooling Tower Pump Figure 2.4.Pump Figure 2.5.Cooling Tower
  • 9.
    9 III. Calculation andSelection 1. Building Load Calculation 2. Cooling Tower 4. Make-Up Tank 3. Pump (CHWP & CDWP) 2. Chiller
  • 10.
    10 1. Building LoadCalculation  ACLEDA DATA CENTER BUIDING It has many kind of rooms • There are six level; GF, 1F to 4F and Terrace Floor. • Data center room • Office • UPS room • Meeting room
  • 11.
    11  Hourly AnalysisProgram (HAP) 1. Building Load Calculation Figure 3.1. Hourly Analysis Program
  • 12.
    12 1. Building LoadCalculation  FCU Selection from the Catalogs • Total load in building = 2299kW  Calculation by HAP • Total Load = 2357 kW  Chiller selection No Description Cooling Chiller Qty Duty Standby Load(kW) kW Total 1 Total load 2357 843.9 4 3 1 Table 3.1. Number of chiller; duty & standby
  • 13.
    13Figure.3.2 Chiller Catalog CoolingCapacity 𝑄 𝑒𝑣𝑎 = 843.9𝑘𝑊
  • 14.
    14 2. Cooling Tower Net Heat Calculation Qconden𝑠𝑒𝑟; ( kW)  Water flow rate mw; (kg/s or L/s)  Inlet and out let temperature in CT ∆T; (℃) ∆𝑇 = TCT en − TC𝑇 out = 37℃ − 32℃ = 5℃ Winput = QH − QL = Qc𝑑 − Qeva Second law of Thermodynamic ⇒ Qcd = Winput − Qeva (eq.1)
  • 15.
    15 Cooling Coefficient ofPerformance (COPR) COPR = Qeva Winput ⇒ Winput = Qeva COPR (eq.2) • Qeva =843.9 kW; Cooling Capacity • Winput: Power input (kW) COPR ≈5; in water cooled chiller system 2. Cooling Tower
  • 16.
    16 Qcd = 𝑚𝑤 𝑐 𝑝∆𝑇 ⇒ 𝑚 𝑤 = Qcd 𝑐 𝑝∆𝑇 (eq.3)  Water flow rate: 𝑚 𝑤;  𝑐 𝑝=4.179 kJ/kg.K 𝑚 𝑤 = 1012.68 5×4.179 = 48.5 𝑙/𝑠=174.6 𝒎 𝟑 𝒉 (eq.1); => Qcd = Qeva + Qeva COPR = 843.9 + 843.9 5 Qcd = 1012.68 𝑘𝑊 2. Cooling Tower
  • 17.
    17 No Description QcdEWT LWT mw kW ℃ ℃ m3 h 1 CT-01 1012.68 37 32 174.6 2 CT-01 1012.68 37 32 174.6 3 CT-01 1012.68 37 32 174.6 4 CT-01 1012.68 37 32 174.6 Table 3.1. Cooling selection Data for selection cooling tower 2. Cooling Tower
  • 18.
    18 Cooling tower catalog Fig3.3. Cooling tower Catalog Flow rate 197.9 2230E 2. Cooling Tower
  • 19.
  • 20.
    20  Flow rate;𝑚 𝑤 and Pressure drop; 𝑃 𝑇𝑜𝑡𝑎𝑙 TCH en ≈ 12 ℃; TCH(out) ≈ 7℃ ; ∆𝑇 = 5℃ Qeva = mwcp∆TCH ; ∆TCH = TCH(en) − TCH out ; eq. 4 mw = Qeva cp(TCH(en)−TCH out ) = 843.9 4.179 × 5 mw = 40.4 l/s 3. Chiller Water Pump
  • 21.
    21 PTotal=[2L(m)×100% ×400 ×10−3(kPa/m)+FCU(kPa) +Chiller(kPa)] eq.5  Estimation method • Pressure drop that water across chiller is 49.8 kpa • Pressure drop that water across FCU is 37.6 kpa • 400 Pa m the maximum pressure drop along pipe • L = 113m ; pipe length , 100%: Lossing a long fitting PTotal = 2 × 113 × 2 × 400 × 10−3 kpa + 37.6 kpa + 49.8 kpa ] 𝐏 𝐓𝐨𝐭𝐚𝐥=268.2 kPa 3. Chiller Water Pump
  • 22.
    22  Detail CalculationMethod PTotal= Pt1 (drop by piping) + Pt (drop by fitting) eq.6 Pt1 = Pa × 𝐿 eq.7 • Pa: Pressure drop per meter Pa m • 𝐿 = 16𝑚; 𝐷 = 150𝑚𝑚; 𝑚 𝑤 = 40.4 𝑙 𝑠 𝑚 𝑤 = 40.4 𝑙 𝑠 260pa Figure 3.5. pipe sizing D=150mm 3. Chiller Water Pump
  • 23.
    23 ⇒ Pt1= 260× 16 = 4160Pa = 4.16kPa  Pressure drop by fitting Pt1 • Elbow, Tee; Y-strainer, Flexible • Valves: Balancing, Butterfly, Motorize, check valve  Conservation of mass: mw = ρVA eq.8 A = П𝐷2 4 ; eq.8; V = 4×mw ρПD2 = 4×40.4 1000×3.14×0.152 𝑽 = 𝟐. 𝟑 𝐦/𝐬 • ρ = 1000 𝑘𝑔 𝑚3 ; mass volum of water; • A: area (𝑚2 ); 𝑉: 𝑉𝑒𝑙𝑜𝑐𝑖𝑡𝑦 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 𝑚 𝑠 3. Chiller Water Pump
  • 24.
    24 Elbow 90° ⇒𝐿 = 5.1𝑚; Pt = 260 × 5.1 = 1326 Pa ⇒ Pt= 260 × 5.1 = 1326 Paeq.7 Fig 3.6. Equivalent length in meters of pipe for 90° Elbows 3. Chiller Water Pump L=5.1m
  • 25.
    25  Tee • Tee(300mm to 150mm) % = 154.53 154.53 = 1 = 100% The % of water flowing through circled branch L = n × l eq.9 • n: number of elbow; • l: equivalent length in meter (m) 3. Chiller Water Pump
  • 26.
    26 100% Flow condition n=1.7 Fig 3.7 %of water 3. Chiller Water Pump
  • 27.
    27 mw = ρVA⇒ V = 4 × mw ρПD2 eq.10 • mw =154.53 l/s D=300mm=0.3m V = 4 × 154.53 1000 × 3.14 × 0.32 = 2.187 = 2.2 m s Fig 3.7. 𝑙 = 9.1𝑚 ⇒ L=1.7 ×9.1=15.47 Fig 3. 5 Pt = 120 × 15.47 = 1856.4 Pa 3. Chiller Water Pump
  • 28.
    28 Equivalent length inmeter of valves; l(m) Dimension, D=150mm Accessory Y-strainer Balancing Motorize Flexible Butterfly Check Length(m) 34 34 1.4 1.4 1.4 18 Table.2. Equivalent length in meter of valves Y-strainer Pt = 260 × 34 = 8840 Pa Balancing valve Pt = 260 × 34 = 8840 Pa Butterfly valve Pt = 260 × 1.4 = 364 Pa Motorize valve Pt = 260 × 1.4 = 364 Pa Check valve Pt = 260 × 18 = 4680 Pa Flexible Pt = 260 × 1.4 = 364 Pa 3. Chiller Water Pump
  • 29.
    29  Summarize totalloss in pipe & fitting for the system • Total discharge pressure drop: Ptotal,1 = 173.8kPa • Total suction pressure drop: Ptotal,2 = 889kPa Ptotal = 173808 + 88961 = 262769𝑃𝑎 = 𝟐𝟔𝟐. 𝟖𝐤𝐏𝐚 Comparison Estimation: Ptoatl = 268.2 kPa Detail: Ptoatl = 262.8 kPa  Pressure drop total selection: Ptotal = 𝟐𝟕𝟎𝐤𝐏𝐚 Error≈ 2.23% 3. Chiller Water Pump
  • 30.
    30  Chiller waterpump Data selection No Description Flow Rate Pressure drop Safety Coeff. Total Pressure drop l/s kPa 20% kPa 1 CHWP-1 40.4 270 1.2 324 2 CHWP-2 40.4 270 1.2 324 3 CHWP-3 40.4 270 1.2 324 4 CHWP-4 40.4 270 1.2 324 Table 3.2. Cooling selection 3. Chiller Water Pump
  • 31.
    31 Chilled Water PumpsSchedule ITEM DESCRIPTION SPECIFIED 1 Ref. CHP-1~4 2 Quantity (set) 4 ( 3 Duty + 1 Standby ) 3 System Chilled Water System 4 Location GF Chiller Plant Room 5 Type End suction or Horizontal Split Casing 6 Flow Rate (L/s) 40.4 7 Pump Head (m) 32.4 8 Pump Speed (rpm) 1450 9 Pump Efficiency (%) Not Specified 10 Motor Power (kW) 30 11 Power Supply (Volt/Phase/Hz) 380/3/50 12 Motor - Type TEFC Table 3.3. chilled water pump schedule
  • 32.
    32  Mass flowrate: mw = 48.5 𝑙 𝑠From: eq.3  Total Pressure drop: Estimation method PTotal = 2 × 105 × 2 × 400 × 10−3 kpa +65 kpa + 38 kpa ] PTotal=[2L(m)×100% ×400 × 10−3(kPa/m)+CT(kPa) +H(kPa)] eq.11 • H=3.8m=38kPa Height of CT; L=105m; Loss in CT=65kPa; 100%: loss by fitting; 2: Return and supply pipe 𝐏 𝐓𝐨𝐭𝐚𝐥 = 𝟐𝟕𝟏𝐤𝐏𝐚 3. Condenser water pump
  • 33.
    33  Detail Calculation,we calculate as Chiller water pump • 𝑇𝑜𝑡𝑎𝑙 𝐶𝐷𝑊𝑆 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑑𝑟𝑜𝑝: Ptotal,1 = 173.2𝐾𝑃𝑎 • 𝑇𝑜𝑡𝑎𝑙 𝐶𝐷𝑊𝑅 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑑𝑟𝑜𝑝: Ptotal,2 = 102.6𝑘𝑃𝑎 Ptotal = 173.2 + 102.6 = 275.8𝑘𝑃𝑎 Ptotal = 𝟐𝟕𝟓. 𝟖 𝐤𝐏𝐚 Comparison Estimation: Ptoatl = 271 kPa Detail: Ptoatl = 275.8 kPa  Pressure drop total selection: Ptotal = 𝟐𝟖𝟎𝐤𝐏𝐚 Error≈ 1.74% 3. Condenser water pump
  • 34.
    34 No Description Flowrate Pressuredrop Safety Coeff P: total l/s kPa 20% kPa 1 CHWP-1 48.5 280 1.2 336 2 CHWP-2 48.5 280 1.2 336 3 CHWP-3 48.5 280 1.2 336 4 CHWP-4 48.5 280 1.2 336 3. Chiller Water Pump Table 3.4. Condenser water pump data selection
  • 35.
    35 Condenser Water PumpsSchedule ITEM DESCRIPTION SPECIFIED 1 Ref. CWP-1~4 2 Quantity (set) 4 ( 3 Duty + 1 Standby ) 3 System Condenser Water System 4 Location GF Chiller Plant Room 5 Type End suction or Horizontal Split Casing 6 Flow Rate (L/s) 48.5 7 Pump Head (m) 33.6 8 Pump Speed (rpm) 1450 9 Pump Efficiency (%) Not Specified 10 Motor Power (kW) 30 11 Power Supply (Volt/Phase/Hz)380/3/50 12 Motor - Type TEFC Table 3.5. Condenser water pump schedule
  • 36.
    36 4. Make-Up Tank Evaporation loss, Drift loss and Blowdown loss Make up water = Eva. loss + Drift loss + Blowdown loss  Estimation of make up water calculation • Evaporation loss=0.85%; • Drift loss=0.02%; • Blowdown loss=0.22% => Make up water=0.85+0.02+0.22%=1.09% Water loss in 𝐶𝑇 = 48.5( 𝑙 𝑠)×1.09 100 = 0.53𝑙/𝑠
  • 37.
    37 VM = mw× %loss × hours; VM: water volume (𝑚3 ) VM = 48.5 × 1.09 100 × 2 ℎ = 48.5 × 0.0109 × 2 × 3600 VM = 3806l = 3.8𝑚3 VT = 3.8𝑚3 × 4 = 15.2𝑚3 ; 4: number of CT VT: Volume total VT = 15.2𝑚3 4. Make-Up Tank
  • 38.
    CHILLER FAN COIL UNIT AIRHANDLING UNIT 2 WAY VALVE 2 WAY VALVE FRESH AIR TEMPERATURE SENSOR RETURN AIR SUPPLY AIR PRESSURE SENSOR CHECK VALVETEMPERATURE SENSOR PRIMARY CHILLED WATER PUMP (WITHOUT VSD CONTROL) THERMOSTAT 25 % 24 °C 10 % 7 °C 23.5 °C 12 °C COOLING TOWER CONDENSER WATER PUMP TEMPERATURE SENSOR 37 °C 32 °C
  • 39.
    39  After Ifinished my thesis • Calculation • Selection V. Conclusion • Understand about water cooled chiller system • Concept of designing
  • 40.
  • 41.