SlideShare a Scribd company logo
POWER SYSTEM
ANALYSIS
CHAPTER NO # 4
FAULT LOCATION ON POWER SYSTEM
NETWORKS
• If a fault occurs on any section of a power system network it is likely that the intermediate
effect will be to interrupt, the supply to a section of the consumers
• It may be possible to restore the supply by using alternative routes in the network, but this
may in turn mean that the circuit involved become overloaded , resulting in these, too,
becoming faulty.
• It is important that any faults which do arise be located and repaired as quickly as possible
and various techniques have been adopted for this purpose
Fault Resistance
• Under normal conditions there will be a finite resistance between the conductors of a distribution
system & between each conductor and earth due to the fact that the system insulation will not be
perfect, also the current will flow to the earth under working conditions.
• When a fault occurs on the system this insulation resistance will be substantially reduced to such a
value that will permit the flow of large current earth, & in order to locate the position of the fault,
some means of measuring the value of this resistance may be necessary
• It also follows that if this resistance can be monitored continuously , or at least at frequent
intervals, any gradual reduction observed may show that system insulation is beginning to
deteriorate and a fault is about to develop, while a sudden large reduction will indicate that a fault
actually occured
The Murray Loop Test
• Common method to locate a fault to earth
• Requires a presence of a sound conductor between the terminations of the faulty cable, the
faulty conductor being connected to the sound cable at the end remote from that at which the
test is to be made
• The ends of the sound and faulty cables, A and B are then connected at the testing end as
part of a Wheatstone’s bridge
• A Galvanometer with the usual key is connected across AM and a d.c. source is used to supply
the bridge, one end of this source being earthed and therefore in electrical contact with the
fault.
• At balance Resistance of cable between A and F = P
Resistance of cable AD and DF Q
• First assume that the sound and faulty cores have the same cross section a, length l thus
each has the same resistance r per unit length, then if x is the distance of the fault from A we
have and therefore
• Hence if l is known the distance x may be calculated. If the cables are of different cross-
sections and lengths the values for the second cable being r’ and l’ the expression become
• The resistance/length of the cores are inversely proportional to their cross-sectional areas
and therefore:
r x = P
r(2l – x) Q
r x = P
r(l – x) + r’ l’ Q
x = P(l + (r’/r )l’)
P +Q
r = a
r a’
x = 2 l P
P +Q
Fault Localising Bridge
• In order to avoid the necessity for any calculation direct-reading bridges have been developed; one
such being the Raphael bridge
Biavier and Earth Overlap Tests
Voltage Drop Tests
Open Circuits Faults
Induction Method
Location of Overhead Line Faults
• Overhead line faults usually take the form of a broken conductor or a damaged insulator, and since
both of these effects may be observed from the ground the general procedure in the past has been
to send our squad of men to walk along the length of a line and inspect it visually
• For a high voltage line of between 80 -160 km in length which is not common in Britain, the time to
carry out its inspection can be very lengthy and for these cases an improved technique has been
developed which shows that if a voltage pulse travels along a line it will proceed at a definite speed
depending on the line parameters and will be reflected at discontinuities in the line
• This principle is utilized by connecting a pulse generator to the line after a fault has occurred and
transmitting pulse along the line. These are reflected back from the fault to the sending end. The
time taken for this transmission to the fault and back is measured and, knowing the pulse velocity,
this is used to calculate the distance of the fault from the testing end
• This method is not capable of high accuracy but it serves to locate the fault to within a few span
lengths, the actual position then being found by visual inspection as before

More Related Content

What's hot

GATE TURN OFF THYRISTOR
GATE TURN OFF THYRISTORGATE TURN OFF THYRISTOR
GATE TURN OFF THYRISTOR
arulbarathi kandhi
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
Rajashekar Gurrala
 
Islanding
IslandingIslanding
Islanding
Divyang soni
 
Transmission Line Constraints
Transmission Line ConstraintsTransmission Line Constraints
Transmission Line Constraints
Ridwanul Hoque
 
Power system protection
Power system protectionPower system protection
Power system protectionAnu Priya
 
Chapter 3 transmission line performance
Chapter 3  transmission line performanceChapter 3  transmission line performance
Chapter 3 transmission line performance
firaoltemesgen1
 
Underground cables vs overhead lines
Underground cables vs overhead linesUnderground cables vs overhead lines
Underground cables vs overhead lines
ସୁର୍ଯ଼ ପ୍ରତାପ ଭଞ୍ଜ
 
Power electronics devices and their characteristics
Power electronics devices and their characteristicsPower electronics devices and their characteristics
Power electronics devices and their characteristics
KartickJana3
 
Unit 05 Protection of feeders and bus-bars
Unit  05 Protection of feeders and bus-bars Unit  05 Protection of feeders and bus-bars
Unit 05 Protection of feeders and bus-bars
PremanandDesai
 
Hv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generationHv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generation
Asha Anu Kurian
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)
Asha Anu Kurian
 
WIDE AREA MONITORING SYSTEMS(WAMS)
WIDE AREA MONITORING SYSTEMS(WAMS)WIDE AREA MONITORING SYSTEMS(WAMS)
WIDE AREA MONITORING SYSTEMS(WAMS)
Vikram Purohit
 
Power Quality Issues
Power Quality IssuesPower Quality Issues
Power Quality Issues
maneesh001
 
Reliability and clock synchronization
Reliability and clock synchronizationReliability and clock synchronization
Reliability and clock synchronization
Sri Manakula Vinayagar Engineering College
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
Md Irshad Ahmad
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission lines
firaoltemesgen1
 
Power System Analysis!
Power System Analysis!Power System Analysis!
Power System Analysis!
PRABHAHARAN429
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)J. FR
 
Mosfet baising
Mosfet baisingMosfet baising
Mosfet baising
PRAVEENA N G
 

What's hot (20)

GATE TURN OFF THYRISTOR
GATE TURN OFF THYRISTORGATE TURN OFF THYRISTOR
GATE TURN OFF THYRISTOR
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
Islanding
IslandingIslanding
Islanding
 
Transmission Line Constraints
Transmission Line ConstraintsTransmission Line Constraints
Transmission Line Constraints
 
Power system protection
Power system protectionPower system protection
Power system protection
 
Chapter 3 transmission line performance
Chapter 3  transmission line performanceChapter 3  transmission line performance
Chapter 3 transmission line performance
 
Underground cables vs overhead lines
Underground cables vs overhead linesUnderground cables vs overhead lines
Underground cables vs overhead lines
 
Power electronics devices and their characteristics
Power electronics devices and their characteristicsPower electronics devices and their characteristics
Power electronics devices and their characteristics
 
Unit 05 Protection of feeders and bus-bars
Unit  05 Protection of feeders and bus-bars Unit  05 Protection of feeders and bus-bars
Unit 05 Protection of feeders and bus-bars
 
Hv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generationHv module 3 Impulse voltage generation
Hv module 3 Impulse voltage generation
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)
 
WIDE AREA MONITORING SYSTEMS(WAMS)
WIDE AREA MONITORING SYSTEMS(WAMS)WIDE AREA MONITORING SYSTEMS(WAMS)
WIDE AREA MONITORING SYSTEMS(WAMS)
 
Power Quality Issues
Power Quality IssuesPower Quality Issues
Power Quality Issues
 
Reliability and clock synchronization
Reliability and clock synchronizationReliability and clock synchronization
Reliability and clock synchronization
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission lines
 
Power System Analysis!
Power System Analysis!Power System Analysis!
Power System Analysis!
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
 
Mosfet baising
Mosfet baisingMosfet baising
Mosfet baising
 

Similar to Chapter#4

Detection of fault location in underground cable using arduino
Detection of fault location in underground cable using arduinoDetection of fault location in underground cable using arduino
Detection of fault location in underground cable using arduino
Chirag Lakhani
 
Ch14 transmission line. Class 11 cbse ..
Ch14 transmission line. Class 11 cbse ..Ch14 transmission line. Class 11 cbse ..
Ch14 transmission line. Class 11 cbse ..
MukeshSharma132089
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
Asha Anu Kurian
 
Unit 3 SECA1701-microwave measurements.pptx
Unit 3 SECA1701-microwave measurements.pptxUnit 3 SECA1701-microwave measurements.pptx
Unit 3 SECA1701-microwave measurements.pptx
PavanVangapally
 
Resistivity Survey
Resistivity SurveyResistivity Survey
Resistivity Survey
Amit K. Mishra
 
EMI/EMC
EMI/EMC EMI/EMC
EMI/EMC
Abida Zama
 
Decoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike TachickDecoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike Tachick
nacetwincities
 
Resistivity method
Resistivity method Resistivity method
Resistivity method
salahudintanoli
 
Frequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerFrequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformer
Raveendranath Macherla
 
G010144450
G010144450G010144450
G010144450
IOSR Journals
 
Detection and Location of Faults in 11KV Underground Cable by using Continuou...
Detection and Location of Faults in 11KV Underground Cable by using Continuou...Detection and Location of Faults in 11KV Underground Cable by using Continuou...
Detection and Location of Faults in 11KV Underground Cable by using Continuou...
IOSR Journals
 
EE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of CablesEE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of CablesRajesh Ramesh
 
TRANSMISSION LINES and capacity.pptx
TRANSMISSION LINES and capacity.pptxTRANSMISSION LINES and capacity.pptx
TRANSMISSION LINES and capacity.pptx
Satish Pydimarla
 
Technotoy stage 4
Technotoy stage 4Technotoy stage 4
Technotoy stage 4
ralexander1938
 
Technotoy stage 4
Technotoy stage 4Technotoy stage 4
Technotoy stage 4
ralexander1938
 
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
AshaLatha456489
 
Shorted Casing Study - Tim Sievert
Shorted Casing Study - Tim SievertShorted Casing Study - Tim Sievert
Shorted Casing Study - Tim Sievert
nacetwincities
 
presentation.pptx
presentation.pptxpresentation.pptx
presentation.pptx
Aswathymohan53
 
presentation.pptx
presentation.pptxpresentation.pptx
presentation.pptx
Aswathymohan53
 

Similar to Chapter#4 (20)

Detection of fault location in underground cable using arduino
Detection of fault location in underground cable using arduinoDetection of fault location in underground cable using arduino
Detection of fault location in underground cable using arduino
 
Ch14 transmission line. Class 11 cbse ..
Ch14 transmission line. Class 11 cbse ..Ch14 transmission line. Class 11 cbse ..
Ch14 transmission line. Class 11 cbse ..
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
 
Unit 3 SECA1701-microwave measurements.pptx
Unit 3 SECA1701-microwave measurements.pptxUnit 3 SECA1701-microwave measurements.pptx
Unit 3 SECA1701-microwave measurements.pptx
 
Resistivity Survey
Resistivity SurveyResistivity Survey
Resistivity Survey
 
40220140503004
4022014050300440220140503004
40220140503004
 
EMI/EMC
EMI/EMC EMI/EMC
EMI/EMC
 
Decoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike TachickDecoupler Interaction With CP Systems - Mike Tachick
Decoupler Interaction With CP Systems - Mike Tachick
 
Resistivity method
Resistivity method Resistivity method
Resistivity method
 
Frequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformerFrequency response analysis (FRA) of transformer
Frequency response analysis (FRA) of transformer
 
G010144450
G010144450G010144450
G010144450
 
Detection and Location of Faults in 11KV Underground Cable by using Continuou...
Detection and Location of Faults in 11KV Underground Cable by using Continuou...Detection and Location of Faults in 11KV Underground Cable by using Continuou...
Detection and Location of Faults in 11KV Underground Cable by using Continuou...
 
EE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of CablesEE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of Cables
 
TRANSMISSION LINES and capacity.pptx
TRANSMISSION LINES and capacity.pptxTRANSMISSION LINES and capacity.pptx
TRANSMISSION LINES and capacity.pptx
 
Technotoy stage 4
Technotoy stage 4Technotoy stage 4
Technotoy stage 4
 
Technotoy stage 4
Technotoy stage 4Technotoy stage 4
Technotoy stage 4
 
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
 
Shorted Casing Study - Tim Sievert
Shorted Casing Study - Tim SievertShorted Casing Study - Tim Sievert
Shorted Casing Study - Tim Sievert
 
presentation.pptx
presentation.pptxpresentation.pptx
presentation.pptx
 
presentation.pptx
presentation.pptxpresentation.pptx
presentation.pptx
 

More from Syed Muhammad ALi Shah

Chapter # 7
Chapter # 7Chapter # 7
Chapter # 9
Chapter # 9Chapter # 9
Chapter # 6
Chapter # 6Chapter # 6
Chapter # 5
Chapter # 5Chapter # 5
Chapter # 8
Chapter # 8Chapter # 8
Chapter # 4
Chapter # 4Chapter # 4
Chapter # 10
Chapter # 10Chapter # 10
Chapter # 3
Chapter # 3Chapter # 3
Chapter # 2
Chapter # 2Chapter # 2
Chapter # 1
Chapter # 1Chapter # 1
Chapter#18
Chapter#18Chapter#18
Chapter#17
Chapter#17Chapter#17
Chapter#16
Chapter#16Chapter#16
Chapter#15
Chapter#15Chapter#15
Chapter#14
Chapter#14Chapter#14
Chapter#13
Chapter#13Chapter#13
Chapter#14
Chapter#14Chapter#14
Chapter#13
Chapter#13Chapter#13
Chapter#12
Chapter#12Chapter#12

More from Syed Muhammad ALi Shah (20)

Chapter # 7
Chapter # 7Chapter # 7
Chapter # 7
 
Chapter # 9
Chapter # 9Chapter # 9
Chapter # 9
 
Chapter # 6
Chapter # 6Chapter # 6
Chapter # 6
 
Chapter # 5
Chapter # 5Chapter # 5
Chapter # 5
 
Chapter # 8
Chapter # 8Chapter # 8
Chapter # 8
 
Chapter # 4
Chapter # 4Chapter # 4
Chapter # 4
 
Chapter # 10
Chapter # 10Chapter # 10
Chapter # 10
 
Chapter # 3
Chapter # 3Chapter # 3
Chapter # 3
 
Chapter # 2
Chapter # 2Chapter # 2
Chapter # 2
 
Chapter # 1
Chapter # 1Chapter # 1
Chapter # 1
 
Chapter#18
Chapter#18Chapter#18
Chapter#18
 
Chapter#17
Chapter#17Chapter#17
Chapter#17
 
Chapter#16
Chapter#16Chapter#16
Chapter#16
 
Chapter#15
Chapter#15Chapter#15
Chapter#15
 
Chapter#14
Chapter#14Chapter#14
Chapter#14
 
Chapter#13
Chapter#13Chapter#13
Chapter#13
 
Chapter#9
Chapter#9Chapter#9
Chapter#9
 
Chapter#14
Chapter#14Chapter#14
Chapter#14
 
Chapter#13
Chapter#13Chapter#13
Chapter#13
 
Chapter#12
Chapter#12Chapter#12
Chapter#12
 

Recently uploaded

road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

Chapter#4

  • 2. CHAPTER NO # 4 FAULT LOCATION ON POWER SYSTEM NETWORKS
  • 3. • If a fault occurs on any section of a power system network it is likely that the intermediate effect will be to interrupt, the supply to a section of the consumers • It may be possible to restore the supply by using alternative routes in the network, but this may in turn mean that the circuit involved become overloaded , resulting in these, too, becoming faulty. • It is important that any faults which do arise be located and repaired as quickly as possible and various techniques have been adopted for this purpose
  • 4. Fault Resistance • Under normal conditions there will be a finite resistance between the conductors of a distribution system & between each conductor and earth due to the fact that the system insulation will not be perfect, also the current will flow to the earth under working conditions. • When a fault occurs on the system this insulation resistance will be substantially reduced to such a value that will permit the flow of large current earth, & in order to locate the position of the fault, some means of measuring the value of this resistance may be necessary • It also follows that if this resistance can be monitored continuously , or at least at frequent intervals, any gradual reduction observed may show that system insulation is beginning to deteriorate and a fault is about to develop, while a sudden large reduction will indicate that a fault actually occured
  • 5. The Murray Loop Test • Common method to locate a fault to earth • Requires a presence of a sound conductor between the terminations of the faulty cable, the faulty conductor being connected to the sound cable at the end remote from that at which the test is to be made • The ends of the sound and faulty cables, A and B are then connected at the testing end as part of a Wheatstone’s bridge • A Galvanometer with the usual key is connected across AM and a d.c. source is used to supply the bridge, one end of this source being earthed and therefore in electrical contact with the fault. • At balance Resistance of cable between A and F = P Resistance of cable AD and DF Q
  • 6. • First assume that the sound and faulty cores have the same cross section a, length l thus each has the same resistance r per unit length, then if x is the distance of the fault from A we have and therefore • Hence if l is known the distance x may be calculated. If the cables are of different cross- sections and lengths the values for the second cable being r’ and l’ the expression become • The resistance/length of the cores are inversely proportional to their cross-sectional areas and therefore: r x = P r(2l – x) Q r x = P r(l – x) + r’ l’ Q x = P(l + (r’/r )l’) P +Q r = a r a’ x = 2 l P P +Q
  • 7. Fault Localising Bridge • In order to avoid the necessity for any calculation direct-reading bridges have been developed; one such being the Raphael bridge
  • 8. Biavier and Earth Overlap Tests
  • 12. Location of Overhead Line Faults • Overhead line faults usually take the form of a broken conductor or a damaged insulator, and since both of these effects may be observed from the ground the general procedure in the past has been to send our squad of men to walk along the length of a line and inspect it visually • For a high voltage line of between 80 -160 km in length which is not common in Britain, the time to carry out its inspection can be very lengthy and for these cases an improved technique has been developed which shows that if a voltage pulse travels along a line it will proceed at a definite speed depending on the line parameters and will be reflected at discontinuities in the line • This principle is utilized by connecting a pulse generator to the line after a fault has occurred and transmitting pulse along the line. These are reflected back from the fault to the sending end. The time taken for this transmission to the fault and back is measured and, knowing the pulse velocity, this is used to calculate the distance of the fault from the testing end • This method is not capable of high accuracy but it serves to locate the fault to within a few span lengths, the actual position then being found by visual inspection as before

Editor's Notes

  1. FOR HELP VISIT : http://electrical4u.com/blavier-test-murray-loop-test-varley-loop-test/