SlideShare a Scribd company logo
Present Worth AnalysisPresent Worth Analysis
EGN 3203 Engineering Economics
LO3 – a
5-2
LEARNINGLEARNING OUTCOMESOUTCOMES
1. Formulate Alternatives
2. PW of equal-life alternatives
3. PW of different-life alternatives
4. Future Worth analysis
5. Capitalized Cost analysis
© 2012 by McGraw-Hill All Rights Reserved
Introduction Present WorthIntroduction Present Worth
• A future amount of money converted to its equivalent value now has a
present worth (PW) value
• This present value is always less than that of the actual future cash
flow,
• for any interest rate greater than zero, all P/F factors have a value less
than 1.0. For this reason, present worth values are often referred to
as discounted cash flows (DCF).
• Similarly, the interest rate may be referred to as the discount rate.
Besides PW, equivalent terms frequently used are present value (PV)
and net present value (NPV).
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-3
• Alternatives are developed from project proposals to
accomplish a stated purpose.
• Some projects are economically and technologically
viable, and others are not. Once the viable projects are
defined, it is possible to formulate the alternatives.
• Alternatives are one of two types:
• mutually exclusive or independent.
• Each type is evaluated differently
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-4
Formulating AlternativesFormulating Alternatives
5-5
Formulating AlternativesFormulating Alternatives
Two types of economic proposals
Mutually Exclusive (ME) Alternatives: Only one can be selected;
Compete against each other
Independent Projects: More than one can be selected;
Compete only against DN
© 2012 by McGraw-Hill All Rights Reserved
Do Nothing (DN) – An ME alternative or independent project to
maintain the current approach; no new costs, revenues or savings
5-6
Revenue: Alternatives include estimates of costs
(cash outflows) and revenues (cash inflows)
Two types of cash flow estimates
Cost: Alternatives include only costs; revenues and savings
assumed equal for all alternatives;
also called service alternatives
Formulating AlternativesFormulating Alternatives
© 2012 by McGraw-Hill All Rights Reserved
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-7
5-8
Convert all cash flows to PW using MARR
Precede costs by minus sign; receipts by
plus sign
For mutually exclusive alternatives, select
one with numerically largest PW
For independent projects, select all with PW > 0
PW Analysis of AlternativesPW Analysis of Alternatives
© 2012 by McGraw-Hill All Rights Reserved
For one project, if PW > 0, it is justified
EVALUATION
5-9
Project ID Present Worth
A $30,000
B $12,500
C $-4,000
D $ 2,000
Solution: (a) Select numerically largest PW; alternative A
(b) Select all with PW > 0; projects A, B & D
Selection of Alternatives by PWSelection of Alternatives by PW
© 2012 by McGraw-Hill All Rights Reserved
5-10
Example: PW Evaluation of Equal-Life ME Alts.Example: PW Evaluation of Equal-Life ME Alts.
Alternative X has a first cost of $20,000, an operating cost of $9,000 per year,
and a $5,000 salvage value after 5 years. Alternative Y will cost $35,000
with an operating cost of $4,000 per year and a salvage value of $7,000
after 5 years. At an MARR of 12% per year, which should be selected?
Solution: Find PW at MARR and select numerically larger PW value
PWX = -20,000 - 9000(P/A,12%,5) + 5000(P/F,12%,5)
= -$49,606
PWY = -35,000 - 4000(P/A,12%,5) + 7000(P/F,12%,5)
= -$45,447
Select alternative Y
© 2012 by McGraw-Hill All Rights Reserved
Example: PW Evaluation of Equal-LifeExample: PW Evaluation of Equal-Life
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-11
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-12
Example: PW Evaluation of Equal-LifeExample: PW Evaluation of Equal-Life
• Present worth analysis requires an equal service comparison of alternatives,
that is, the number of years considered must be the same for all alternatives.
• If equal service is not present, shorter-lived alternatives will be favored
based on lower PW of total costs, even though they may not be economically
favorable.
• Fundamentally, there are two ways to use PW analysis to compare
alternatives with unequal life estimates;
• use the least common multiple of lives for each pair of alternatives
• or evaluate over a specific study period (planning horizon),
• In both cases, the PW is calculated at the MARR, and the selection guidelines
of the previous section are applied
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-13
PW of Different-Life AlternativesPW of Different-Life Alternatives
5-14
PW of Different-Life AlternativesPW of Different-Life Alternatives
Must compare alternatives for equal service
(i.e., alternatives must end at the same time)
Two ways to compare equal service:
(The LCM procedure is used unless otherwise specified)
Least common multiple (LCM) of lives
Specified study period
© 2012 by McGraw-Hill All Rights Reserved
Assumptions of LCM approachAssumptions of LCM approach
 Service provided is needed over the LCM or
more years
 Selected alternative can be repeated over
each life cycle of LCM in exactly the same
manner
 Cash flow estimates are the same for each life
cycle (i.e., change in exact accord with the
inflation or deflation rate)
1-15 © 2012 by McGraw-Hill All Rights Reserved
5-16
Example: Different-Life AlternativesExample: Different-Life Alternatives
Compare the machines below using present worth analysis at i = 10% per year
Machine A Machine B
First cost, $
Annual cost, $/year
Salvage value, $
Life, years
20,000 30,000
9000 7000
4000 6000
3 6
Solution:
PWA = -20,000 – 9000(P/A,10%,6) – 16,000(P/F,10%,3) + 4000(P/F,10%,6)
= $-68,961
PWB = -30,000 – 7000(P/A,10%,6) + 6000(P/F,10%,6)
= $-57,100
LCM = 6 years; repurchase A after 3 years
Select alternative B
© 2012 by McGraw-Hill All Rights Reserved
20,000 – 4,000 in
year 3
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-17
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-18
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-19
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-20
PW Evaluation Using a Study PeriodPW Evaluation Using a Study Period
Once a study period is specified, all cash flows after
this time are ignored
Salvage value is the estimated market value at the end
of study period
Short study periods are often defined by management
when business goals are short-term
Study periods are commonly used in equipment
replacement analysis
1-21 © 2012 by McGraw-Hill All Rights Reserved
5-22
Example: Study Period PW EvaluationExample: Study Period PW Evaluation
Compare the alternatives below using present worth analysis at i = 10% per year
and a 3-year study period
Machine A Machine B
First cost, $
Annual cost, $/year
Salvage/market value, $
Life, years
-20,000 -30,000
-9,000 -7,000
4,000 6,000 (after 6 years)
10,000 (after 3 years)
3 6
Solution:
PWA = -20,000 – 9000(P/A,10%,3) + 4000(P/F,10%,3) = $-39,376
PWB = -30,000 – 7000(P/A,10%,3) + 10,000(P/F,10%,3)= $-39,895
Study period = 3 years; disregard all estimates after 3 years
Marginally, select A; different selection than for LCM = 6 years
© 2012 by McGraw-Hill All Rights Reserved
5-23
Future Worth AnalysisFuture Worth Analysis
Must compare alternatives for equal service
(i.e. alternatives must end at the same time)
Two ways to compare equal service:
(The LCM procedure is used unless otherwise specified)
Least common multiple (LCM) of lives
Specified study period
FW exactly like PW analysis, except calculate FW
© 2012 by McGraw-Hill All Rights Reserved
5-24
FW of Different-Life AlternativesFW of Different-Life Alternatives
Compare the machines below using future worth analysis at i = 10% per year
Machine A Machine B
First cost, $
Annual cost, $/year
Salvage value, $
Life, years
-20,000 -30,000
-9000 -7000
4000 6000
3 6
Solution:
FWA = -20,000(F/P,10%,6) – 9000(F/A,10%,6) – 16,000(F/P,10%,3) + 4000
= $-122,168
FWB = -30,000(F/P,10%.6) – 7000(F/A,10%,6) + 6000
= $-101,157
LCM = 6 years; repurchase A after 3 years
Select B (Note: PW and FW methods will always result in same selection)
© 2012 by McGraw-Hill All Rights Reserved
• Capitalized cost (CC) is the present worth of an alternative that will
last “forever.”
• Public sector projects such as bridges, dams, irrigation systems, and
railroads fall into this category, since they have useful lives of 30, 40,
and more years.
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-25
Capitalized Cost (CC) AnalysisCapitalized Cost (CC) Analysis
Capitalized Cost (CC) AnalysisCapitalized Cost (CC) Analysis
5-26
CC refers to the present worth of a project with a very
long life, that is, PW as n becomes infinite
Basic equation is: CC = P = A
i
“A” essentially represents the interest on a perpetual investment
For example, in order to be able to withdraw $50,000 per year forever
at i = 10% per year, the amount of capital required is 50,000/0.10 = $500,000
For finite life alternatives, convert all cash flows into
an A value over one life cycle and then divide by i
© 2012 by McGraw-Hill All Rights Reserved
5-27
Example: Capitalized CostExample: Capitalized Cost
Solution:
Compare the machines shown below on the basis of their
capitalized cost. Use i = 10% per year
Machine 1 Machine 2
First cost,$
Annual cost,$/year
Salvage value, $
Life, years
-20,000 -100,000
-9000 -7000
4000 -----
3 ∞
Convert machine 1 cash flows into A and then divide by i
A1 = -20,000(A/P,10%,3) – 9000 + 4000(A/F,10%,3) = $-15,834
CC1 = -15,834 / 0.10 = $-158,340
CC2 = -100,000 – 7000/ 0.10 = $-170,000
Select machine 1
© 2012 by McGraw-Hill All Rights Reserved
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-28
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-29
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-30
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-31
5-32
Summary of Important PointsSummary of Important Points
PW method converts all cash flows to present value at MARR
PW comparison must always be made for equal service
Alternatives can be mutually exclusive or independent
Cash flow estimates can be for revenue or cost alternatives
Equal service is achieved by using LCM or study period
Capitalized cost is PW of project with infinite life; CC = P = A/i
© 2012 by McGraw-Hill All Rights Reserved

More Related Content

What's hot

Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysisBich Lien Pham
 
7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost methodAli Juma Albahrani
 
Chapter 4 nominal & effective interest rates
Chapter 4   nominal & effective interest ratesChapter 4   nominal & effective interest rates
Chapter 4 nominal & effective interest ratesBich Lien Pham
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
Abdulaziz AlSuwaidi
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysisBich Lien Pham
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on moneyBich Lien Pham
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economyBich Lien Pham
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysisBich Lien Pham
 
Ch5 pw analysis_part1_rev4
Ch5 pw analysis_part1_rev4Ch5 pw analysis_part1_rev4
Ch5 pw analysis_part1_rev4
Nour Dagher
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitationBich Lien Pham
 
Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marrBich Lien Pham
 
Chapter 4 nominal & effective interest rates
Chapter 4   nominal & effective interest ratesChapter 4   nominal & effective interest rates
Chapter 4 nominal & effective interest ratesBich Lien Pham
 
Chapter 6&7 annual worth analysis & ror lo3b
Chapter 6&7  annual worth analysis & ror   lo3bChapter 6&7  annual worth analysis & ror   lo3b
Chapter 6&7 annual worth analysis & ror lo3b
Abdulaziz AlSuwaidi
 
Buku enginering economi edisi ke 7 leland blank
Buku enginering economi edisi ke 7 leland blankBuku enginering economi edisi ke 7 leland blank
Buku enginering economi edisi ke 7 leland blank
Ahmad Muhaimin
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factorsBich Lien Pham
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methodsBich Lien Pham
 
9. benefit cost analysis
9. benefit cost analysis9. benefit cost analysis
9. benefit cost analysis
Mohsin Siddique
 

What's hot (20)

Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysis
 
7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method
 
Chapter 4 nominal & effective interest rates
Chapter 4   nominal & effective interest ratesChapter 4   nominal & effective interest rates
Chapter 4 nominal & effective interest rates
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysis
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on money
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economy
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
Ch5 pw analysis_part1_rev4
Ch5 pw analysis_part1_rev4Ch5 pw analysis_part1_rev4
Ch5 pw analysis_part1_rev4
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitation
 
7.1 present worth method
7.1 present worth method7.1 present worth method
7.1 present worth method
 
Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marr
 
Chapter 4 nominal & effective interest rates
Chapter 4   nominal & effective interest ratesChapter 4   nominal & effective interest rates
Chapter 4 nominal & effective interest rates
 
10 depreciation and depletion
10 depreciation and depletion10 depreciation and depletion
10 depreciation and depletion
 
Chapter 6&7 annual worth analysis & ror lo3b
Chapter 6&7  annual worth analysis & ror   lo3bChapter 6&7  annual worth analysis & ror   lo3b
Chapter 6&7 annual worth analysis & ror lo3b
 
Buku enginering economi edisi ke 7 leland blank
Buku enginering economi edisi ke 7 leland blankBuku enginering economi edisi ke 7 leland blank
Buku enginering economi edisi ke 7 leland blank
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factors
 
Lo 2 b factors
Lo 2 b   factorsLo 2 b   factors
Lo 2 b factors
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methods
 
9. benefit cost analysis
9. benefit cost analysis9. benefit cost analysis
9. benefit cost analysis
 

Viewers also liked

Education systems of australia, china, japan
Education systems of australia, china, japanEducation systems of australia, china, japan
Education systems of australia, china, japanJessa Ariño
 
Engineering Economics Paper solution
Engineering Economics Paper solutionEngineering Economics Paper solution
Engineering Economics Paper solution
Haris Hassan
 
Presentation examples for class 3 value propostion
Presentation examples for class 3 value propostionPresentation examples for class 3 value propostion
Presentation examples for class 3 value propostionStanford University
 
Chapter 6&7 annual worth analysis & ror lo3b
Chapter 6&7  annual worth analysis & ror   lo3bChapter 6&7  annual worth analysis & ror   lo3b
Chapter 6&7 annual worth analysis & ror lo3b
Abdulaziz AlSuwaidi
 
Vave nttf- tech talk
Vave nttf- tech talk Vave nttf- tech talk
Application of VAVE in Cost reduction at Automobile Industry
Application of VAVE in Cost reduction at Automobile IndustryApplication of VAVE in Cost reduction at Automobile Industry
Application of VAVE in Cost reduction at Automobile IndustryVivek Singh
 
Kazanılmış Değer Analizi - Sunu
Kazanılmış Değer Analizi - SunuKazanılmış Değer Analizi - Sunu
Kazanılmış Değer Analizi - Sunu
Yusuf Yıldız
 
Cost Reduction of a product through Value Analysis & Value Engineering
Cost Reduction of a product through Value Analysis & Value EngineeringCost Reduction of a product through Value Analysis & Value Engineering
Cost Reduction of a product through Value Analysis & Value EngineeringQuEST Global
 
Maruti suzuki - Operations Management New Product Launch .
Maruti suzuki - Operations Management New Product Launch .Maruti suzuki - Operations Management New Product Launch .
Maruti suzuki - Operations Management New Product Launch .Prasoon Jadhav
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesBich Lien Pham
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of moneyBich Lien Pham
 
China's education system
China's education systemChina's education system
China's education system
MeRvin Jay Go
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering Economy
Justine Asuncion
 
What is VAVE
What is VAVE What is VAVE
What is VAVE Reff Ren
 
Value Engineering And Value Analysis
Value Engineering And Value AnalysisValue Engineering And Value Analysis
Value Engineering And Value Analysisthombremahesh
 

Viewers also liked (17)

Education systems of australia, china, japan
Education systems of australia, china, japanEducation systems of australia, china, japan
Education systems of australia, china, japan
 
Engineering Economics Paper solution
Engineering Economics Paper solutionEngineering Economics Paper solution
Engineering Economics Paper solution
 
Presentation examples for class 3 value propostion
Presentation examples for class 3 value propostionPresentation examples for class 3 value propostion
Presentation examples for class 3 value propostion
 
Chapter 6&7 annual worth analysis & ror lo3b
Chapter 6&7  annual worth analysis & ror   lo3bChapter 6&7  annual worth analysis & ror   lo3b
Chapter 6&7 annual worth analysis & ror lo3b
 
Vave nttf- tech talk
Vave nttf- tech talk Vave nttf- tech talk
Vave nttf- tech talk
 
Application of VAVE in Cost reduction at Automobile Industry
Application of VAVE in Cost reduction at Automobile IndustryApplication of VAVE in Cost reduction at Automobile Industry
Application of VAVE in Cost reduction at Automobile Industry
 
Kazanılmış Değer Analizi - Sunu
Kazanılmış Değer Analizi - SunuKazanılmış Değer Analizi - Sunu
Kazanılmış Değer Analizi - Sunu
 
Cost Reduction of a product through Value Analysis & Value Engineering
Cost Reduction of a product through Value Analysis & Value EngineeringCost Reduction of a product through Value Analysis & Value Engineering
Cost Reduction of a product through Value Analysis & Value Engineering
 
Maruti suzuki - Operations Management New Product Launch .
Maruti suzuki - Operations Management New Product Launch .Maruti suzuki - Operations Management New Product Launch .
Maruti suzuki - Operations Management New Product Launch .
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest rates
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of money
 
Maruti
MarutiMaruti
Maruti
 
China's education system
China's education systemChina's education system
China's education system
 
Value analysis
Value analysisValue analysis
Value analysis
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering Economy
 
What is VAVE
What is VAVE What is VAVE
What is VAVE
 
Value Engineering And Value Analysis
Value Engineering And Value AnalysisValue Engineering And Value Analysis
Value Engineering And Value Analysis
 

Similar to Chapter 5 present worth analysis -with examples

Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.ppt
Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.pptLeland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.ppt
Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.ppt
ssuser1ba731
 
Method of evaluating alternatives.ppt
Method of evaluating alternatives.pptMethod of evaluating alternatives.ppt
Method of evaluating alternatives.ppt
Jaafar47
 
6 150316005521-conversion-gate01
6 150316005521-conversion-gate016 150316005521-conversion-gate01
6 150316005521-conversion-gate01
abidiqbal55
 
Lo4b (nabil) breakeven analysis
Lo4b (nabil)   breakeven analysisLo4b (nabil)   breakeven analysis
Lo4b (nabil) breakeven analysis
Abdulaziz AlSuwaidi
 
7. annual cash flow analysis
7. annual cash flow analysis7. annual cash flow analysis
7. annual cash flow analysis
Mohsin Siddique
 
7 150316005526-conversion-gate01
7 150316005526-conversion-gate017 150316005526-conversion-gate01
7 150316005526-conversion-gate01
abidiqbal55
 
Lecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdfLecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdf
ssuser5feb82
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysisBich Lien Pham
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysisBich Lien Pham
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternativesBich Lien Pham
 
PRESENT WORTH ANALYSIS.pptx
PRESENT WORTH ANALYSIS.pptxPRESENT WORTH ANALYSIS.pptx
PRESENT WORTH ANALYSIS.pptx
ismailshah64
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysisBich Lien Pham
 
Chap. 6.pptx
Chap. 6.pptxChap. 6.pptx
Chap. 6.pptx
KhuramMaqsood2
 
Capital budgeting ppt@ bec doms on finance
Capital budgeting ppt@ bec doms on financeCapital budgeting ppt@ bec doms on finance
Capital budgeting ppt@ bec doms on finance
Babasab Patil
 
3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf
18010YeashRahman
 
economy Chapter6 2011_by louy Al hami
economy Chapter6 2011_by louy Al hami economy Chapter6 2011_by louy Al hami
economy Chapter6 2011_by louy Al hami
Louy Alhamy
 
Capital budgeting complications
Capital budgeting complications Capital budgeting complications
Capital budgeting complications
Babasab Patil
 
Capital budgeting complications
Capital budgeting complications Capital budgeting complications
Capital budgeting complications
Babasab Patil
 

Similar to Chapter 5 present worth analysis -with examples (20)

Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.ppt
Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.pptLeland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.ppt
Leland_Tarquin_Engineering_Economy_Chapter_6_Annual_Worth_Analysis.ppt
 
Method of evaluating alternatives.ppt
Method of evaluating alternatives.pptMethod of evaluating alternatives.ppt
Method of evaluating alternatives.ppt
 
6 150316005521-conversion-gate01
6 150316005521-conversion-gate016 150316005521-conversion-gate01
6 150316005521-conversion-gate01
 
Lecture blank - 8-9
Lecture  blank - 8-9Lecture  blank - 8-9
Lecture blank - 8-9
 
Lo4b (nabil) breakeven analysis
Lo4b (nabil)   breakeven analysisLo4b (nabil)   breakeven analysis
Lo4b (nabil) breakeven analysis
 
7. annual cash flow analysis
7. annual cash flow analysis7. annual cash flow analysis
7. annual cash flow analysis
 
7 150316005526-conversion-gate01
7 150316005526-conversion-gate017 150316005526-conversion-gate01
7 150316005526-conversion-gate01
 
Lecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdfLecture 3_Economics of Planning.pdf
Lecture 3_Economics of Planning.pdf
 
Lo4a(arif)
Lo4a(arif)Lo4a(arif)
Lo4a(arif)
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternatives
 
PRESENT WORTH ANALYSIS.pptx
PRESENT WORTH ANALYSIS.pptxPRESENT WORTH ANALYSIS.pptx
PRESENT WORTH ANALYSIS.pptx
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
Chap. 6.pptx
Chap. 6.pptxChap. 6.pptx
Chap. 6.pptx
 
Capital budgeting ppt@ bec doms on finance
Capital budgeting ppt@ bec doms on financeCapital budgeting ppt@ bec doms on finance
Capital budgeting ppt@ bec doms on finance
 
3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf
 
economy Chapter6 2011_by louy Al hami
economy Chapter6 2011_by louy Al hami economy Chapter6 2011_by louy Al hami
economy Chapter6 2011_by louy Al hami
 
Capital budgeting complications
Capital budgeting complications Capital budgeting complications
Capital budgeting complications
 
Capital budgeting complications
Capital budgeting complications Capital budgeting complications
Capital budgeting complications
 

More from Abdulaziz AlSuwaidi

Case study questions Engineering Economics
Case study questions Engineering EconomicsCase study questions Engineering Economics
Case study questions Engineering Economics
Abdulaziz AlSuwaidi
 
Lo #5 manufacturing technology (jan 2016)
Lo #5 manufacturing technology (jan  2016)Lo #5 manufacturing technology (jan  2016)
Lo #5 manufacturing technology (jan 2016)
Abdulaziz AlSuwaidi
 
Lo4a benefit cost analysis (nabil)
Lo4a benefit  cost analysis (nabil)Lo4a benefit  cost analysis (nabil)
Lo4a benefit cost analysis (nabil)
Abdulaziz AlSuwaidi
 
Lo #4 manufacturing technology (jan 2016)
Lo #4 manufacturing technology (jan  2016)Lo #4 manufacturing technology (jan  2016)
Lo #4 manufacturing technology (jan 2016)
Abdulaziz AlSuwaidi
 
2. ethical theories part 2 (1)
2.  ethical theories part 2 (1)2.  ethical theories part 2 (1)
2. ethical theories part 2 (1)
Abdulaziz AlSuwaidi
 
1. ethical theories part 1
1. ethical theories part 11. ethical theories part 1
1. ethical theories part 1
Abdulaziz AlSuwaidi
 
Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3
Abdulaziz AlSuwaidi
 
Lo #3b (common)manufacturing technology (jan 2016) part 2
Lo #3b (common)manufacturing technology (jan  2016)   part 2Lo #3b (common)manufacturing technology (jan  2016)   part 2
Lo #3b (common)manufacturing technology (jan 2016) part 2
Abdulaziz AlSuwaidi
 
Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1
Abdulaziz AlSuwaidi
 
lo 2 handout 1 (2) PART 2
 lo 2 handout 1 (2) PART 2 lo 2 handout 1 (2) PART 2
lo 2 handout 1 (2) PART 2
Abdulaziz AlSuwaidi
 
Lo #2 manufacturing process primary secondary part 1
Lo #2 manufacturing process   primary  secondary part 1 Lo #2 manufacturing process   primary  secondary part 1
Lo #2 manufacturing process primary secondary part 1
Abdulaziz AlSuwaidi
 
Lo #1 design factors in manufacturing processes (sept 2015)
Lo #1 design factors in manufacturing processes (sept  2015)Lo #1 design factors in manufacturing processes (sept  2015)
Lo #1 design factors in manufacturing processes (sept 2015)
Abdulaziz AlSuwaidi
 
Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1
Abdulaziz AlSuwaidi
 
Lo 2 a key terminologies
Lo 2 a   key terminologiesLo 2 a   key terminologies
Lo 2 a key terminologies
Abdulaziz AlSuwaidi
 

More from Abdulaziz AlSuwaidi (15)

Case study questions Engineering Economics
Case study questions Engineering EconomicsCase study questions Engineering Economics
Case study questions Engineering Economics
 
Lo #5 manufacturing technology (jan 2016)
Lo #5 manufacturing technology (jan  2016)Lo #5 manufacturing technology (jan  2016)
Lo #5 manufacturing technology (jan 2016)
 
Lo4b(arif)
Lo4b(arif)Lo4b(arif)
Lo4b(arif)
 
Lo4a benefit cost analysis (nabil)
Lo4a benefit  cost analysis (nabil)Lo4a benefit  cost analysis (nabil)
Lo4a benefit cost analysis (nabil)
 
Lo #4 manufacturing technology (jan 2016)
Lo #4 manufacturing technology (jan  2016)Lo #4 manufacturing technology (jan  2016)
Lo #4 manufacturing technology (jan 2016)
 
2. ethical theories part 2 (1)
2.  ethical theories part 2 (1)2.  ethical theories part 2 (1)
2. ethical theories part 2 (1)
 
1. ethical theories part 1
1. ethical theories part 11. ethical theories part 1
1. ethical theories part 1
 
Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3Lo# 3c(common) manufacturing technology part 3
Lo# 3c(common) manufacturing technology part 3
 
Lo #3b (common)manufacturing technology (jan 2016) part 2
Lo #3b (common)manufacturing technology (jan  2016)   part 2Lo #3b (common)manufacturing technology (jan  2016)   part 2
Lo #3b (common)manufacturing technology (jan 2016) part 2
 
Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1Lo# 3a(2033 common) manufacturing technology PART 1
Lo# 3a(2033 common) manufacturing technology PART 1
 
lo 2 handout 1 (2) PART 2
 lo 2 handout 1 (2) PART 2 lo 2 handout 1 (2) PART 2
lo 2 handout 1 (2) PART 2
 
Lo #2 manufacturing process primary secondary part 1
Lo #2 manufacturing process   primary  secondary part 1 Lo #2 manufacturing process   primary  secondary part 1
Lo #2 manufacturing process primary secondary part 1
 
Lo #1 design factors in manufacturing processes (sept 2015)
Lo #1 design factors in manufacturing processes (sept  2015)Lo #1 design factors in manufacturing processes (sept  2015)
Lo #1 design factors in manufacturing processes (sept 2015)
 
Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1Lo # 1 manufacturing process selection design part 1
Lo # 1 manufacturing process selection design part 1
 
Lo 2 a key terminologies
Lo 2 a   key terminologiesLo 2 a   key terminologies
Lo 2 a key terminologies
 

Recently uploaded

Codes n Conventionss copy (2).pptx new new
Codes n Conventionss copy (2).pptx new newCodes n Conventionss copy (2).pptx new new
Codes n Conventionss copy (2).pptx new new
ZackSpencer3
 
2137ad - Characters that live in Merindol and are at the center of main stories
2137ad - Characters that live in Merindol and are at the center of main stories2137ad - Characters that live in Merindol and are at the center of main stories
2137ad - Characters that live in Merindol and are at the center of main stories
luforfor
 
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
taqyed
 
Caffeinated Pitch Bible- developed by Claire Wilson
Caffeinated Pitch Bible- developed by Claire WilsonCaffeinated Pitch Bible- developed by Claire Wilson
Caffeinated Pitch Bible- developed by Claire Wilson
ClaireWilson398082
 
Memory Rental Store - The Ending(Storyboard)
Memory Rental Store - The Ending(Storyboard)Memory Rental Store - The Ending(Storyboard)
Memory Rental Store - The Ending(Storyboard)
SuryaKalyan3
 
CLASS XII- HISTORY-THEME 4-Thinkers, Bes
CLASS XII- HISTORY-THEME 4-Thinkers, BesCLASS XII- HISTORY-THEME 4-Thinkers, Bes
CLASS XII- HISTORY-THEME 4-Thinkers, Bes
aditiyad2020
 
IrishWritersCtrsPersonalEssaysMay29.pptx
IrishWritersCtrsPersonalEssaysMay29.pptxIrishWritersCtrsPersonalEssaysMay29.pptx
IrishWritersCtrsPersonalEssaysMay29.pptx
Aine Greaney Ellrott
 
acting board rough title here lolaaaaaaa
acting board rough title here lolaaaaaaaacting board rough title here lolaaaaaaa
acting board rough title here lolaaaaaaa
angelicafronda7
 
Sundabet | Slot gacor dan terpercaya mudah menang
Sundabet | Slot gacor dan terpercaya mudah menangSundabet | Slot gacor dan terpercaya mudah menang
Sundabet | Slot gacor dan terpercaya mudah menang
Sundabet | Situs Slot gacor dan terpercaya
 
The Legacy of Breton In A New Age by Master Terrance Lindall
The Legacy of Breton In A New Age by Master Terrance LindallThe Legacy of Breton In A New Age by Master Terrance Lindall
The Legacy of Breton In A New Age by Master Terrance Lindall
BBaez1
 
一比一原版UPenn毕业证宾夕法尼亚大学毕业证成绩单如何办理
一比一原版UPenn毕业证宾夕法尼亚大学毕业证成绩单如何办理一比一原版UPenn毕业证宾夕法尼亚大学毕业证成绩单如何办理
一比一原版UPenn毕业证宾夕法尼亚大学毕业证成绩单如何办理
beduwt
 
一比一原版(DU毕业证)迪肯大学毕业证成绩单
一比一原版(DU毕业证)迪肯大学毕业证成绩单一比一原版(DU毕业证)迪肯大学毕业证成绩单
一比一原版(DU毕业证)迪肯大学毕业证成绩单
zvaywau
 
Memory Rental Store - The Chase (Storyboard)
Memory Rental Store - The Chase (Storyboard)Memory Rental Store - The Chase (Storyboard)
Memory Rental Store - The Chase (Storyboard)
SuryaKalyan3
 
thGAP - BAbyss in Moderno!! Transgenic Human Germline Alternatives Project
thGAP - BAbyss in Moderno!!  Transgenic Human Germline Alternatives ProjectthGAP - BAbyss in Moderno!!  Transgenic Human Germline Alternatives Project
thGAP - BAbyss in Moderno!! Transgenic Human Germline Alternatives Project
Marc Dusseiller Dusjagr
 
ART FORMS OF KERALA: TRADITIONAL AND OTHERS
ART FORMS OF KERALA: TRADITIONAL AND OTHERSART FORMS OF KERALA: TRADITIONAL AND OTHERS
ART FORMS OF KERALA: TRADITIONAL AND OTHERS
Sandhya J.Nair
 
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
iraqartsandculture
 
2137ad Merindol Colony Interiors where refugee try to build a seemengly norm...
2137ad  Merindol Colony Interiors where refugee try to build a seemengly norm...2137ad  Merindol Colony Interiors where refugee try to build a seemengly norm...
2137ad Merindol Colony Interiors where refugee try to build a seemengly norm...
luforfor
 
一比一原版(GU毕业证)格里菲斯大学毕业证成绩单
一比一原版(GU毕业证)格里菲斯大学毕业证成绩单一比一原版(GU毕业证)格里菲斯大学毕业证成绩单
一比一原版(GU毕业证)格里菲斯大学毕业证成绩单
zvaywau
 
ashokathegreat project class 12 presentation
ashokathegreat project class 12 presentationashokathegreat project class 12 presentation
ashokathegreat project class 12 presentation
aditiyad2020
 

Recently uploaded (20)

Codes n Conventionss copy (2).pptx new new
Codes n Conventionss copy (2).pptx new newCodes n Conventionss copy (2).pptx new new
Codes n Conventionss copy (2).pptx new new
 
2137ad - Characters that live in Merindol and are at the center of main stories
2137ad - Characters that live in Merindol and are at the center of main stories2137ad - Characters that live in Merindol and are at the center of main stories
2137ad - Characters that live in Merindol and are at the center of main stories
 
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
一比一原版(qut毕业证)昆士兰科技大学毕业证如何办理
 
Caffeinated Pitch Bible- developed by Claire Wilson
Caffeinated Pitch Bible- developed by Claire WilsonCaffeinated Pitch Bible- developed by Claire Wilson
Caffeinated Pitch Bible- developed by Claire Wilson
 
Memory Rental Store - The Ending(Storyboard)
Memory Rental Store - The Ending(Storyboard)Memory Rental Store - The Ending(Storyboard)
Memory Rental Store - The Ending(Storyboard)
 
CLASS XII- HISTORY-THEME 4-Thinkers, Bes
CLASS XII- HISTORY-THEME 4-Thinkers, BesCLASS XII- HISTORY-THEME 4-Thinkers, Bes
CLASS XII- HISTORY-THEME 4-Thinkers, Bes
 
IrishWritersCtrsPersonalEssaysMay29.pptx
IrishWritersCtrsPersonalEssaysMay29.pptxIrishWritersCtrsPersonalEssaysMay29.pptx
IrishWritersCtrsPersonalEssaysMay29.pptx
 
acting board rough title here lolaaaaaaa
acting board rough title here lolaaaaaaaacting board rough title here lolaaaaaaa
acting board rough title here lolaaaaaaa
 
Sundabet | Slot gacor dan terpercaya mudah menang
Sundabet | Slot gacor dan terpercaya mudah menangSundabet | Slot gacor dan terpercaya mudah menang
Sundabet | Slot gacor dan terpercaya mudah menang
 
The Legacy of Breton In A New Age by Master Terrance Lindall
The Legacy of Breton In A New Age by Master Terrance LindallThe Legacy of Breton In A New Age by Master Terrance Lindall
The Legacy of Breton In A New Age by Master Terrance Lindall
 
一比一原版UPenn毕业证宾夕法尼亚大学毕业证成绩单如何办理
一比一原版UPenn毕业证宾夕法尼亚大学毕业证成绩单如何办理一比一原版UPenn毕业证宾夕法尼亚大学毕业证成绩单如何办理
一比一原版UPenn毕业证宾夕法尼亚大学毕业证成绩单如何办理
 
一比一原版(DU毕业证)迪肯大学毕业证成绩单
一比一原版(DU毕业证)迪肯大学毕业证成绩单一比一原版(DU毕业证)迪肯大学毕业证成绩单
一比一原版(DU毕业证)迪肯大学毕业证成绩单
 
Memory Rental Store - The Chase (Storyboard)
Memory Rental Store - The Chase (Storyboard)Memory Rental Store - The Chase (Storyboard)
Memory Rental Store - The Chase (Storyboard)
 
thGAP - BAbyss in Moderno!! Transgenic Human Germline Alternatives Project
thGAP - BAbyss in Moderno!!  Transgenic Human Germline Alternatives ProjectthGAP - BAbyss in Moderno!!  Transgenic Human Germline Alternatives Project
thGAP - BAbyss in Moderno!! Transgenic Human Germline Alternatives Project
 
ART FORMS OF KERALA: TRADITIONAL AND OTHERS
ART FORMS OF KERALA: TRADITIONAL AND OTHERSART FORMS OF KERALA: TRADITIONAL AND OTHERS
ART FORMS OF KERALA: TRADITIONAL AND OTHERS
 
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
The Last Polymath: Muntadher Saleh‎‎‎‎‎‎‎‎‎‎‎‎
 
2137ad Merindol Colony Interiors where refugee try to build a seemengly norm...
2137ad  Merindol Colony Interiors where refugee try to build a seemengly norm...2137ad  Merindol Colony Interiors where refugee try to build a seemengly norm...
2137ad Merindol Colony Interiors where refugee try to build a seemengly norm...
 
一比一原版(GU毕业证)格里菲斯大学毕业证成绩单
一比一原版(GU毕业证)格里菲斯大学毕业证成绩单一比一原版(GU毕业证)格里菲斯大学毕业证成绩单
一比一原版(GU毕业证)格里菲斯大学毕业证成绩单
 
ashokathegreat project class 12 presentation
ashokathegreat project class 12 presentationashokathegreat project class 12 presentation
ashokathegreat project class 12 presentation
 
European Cybersecurity Skills Framework Role Profiles.pdf
European Cybersecurity Skills Framework Role Profiles.pdfEuropean Cybersecurity Skills Framework Role Profiles.pdf
European Cybersecurity Skills Framework Role Profiles.pdf
 

Chapter 5 present worth analysis -with examples

  • 1. Present Worth AnalysisPresent Worth Analysis EGN 3203 Engineering Economics LO3 – a
  • 2. 5-2 LEARNINGLEARNING OUTCOMESOUTCOMES 1. Formulate Alternatives 2. PW of equal-life alternatives 3. PW of different-life alternatives 4. Future Worth analysis 5. Capitalized Cost analysis © 2012 by McGraw-Hill All Rights Reserved
  • 3. Introduction Present WorthIntroduction Present Worth • A future amount of money converted to its equivalent value now has a present worth (PW) value • This present value is always less than that of the actual future cash flow, • for any interest rate greater than zero, all P/F factors have a value less than 1.0. For this reason, present worth values are often referred to as discounted cash flows (DCF). • Similarly, the interest rate may be referred to as the discount rate. Besides PW, equivalent terms frequently used are present value (PV) and net present value (NPV). © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-3
  • 4. • Alternatives are developed from project proposals to accomplish a stated purpose. • Some projects are economically and technologically viable, and others are not. Once the viable projects are defined, it is possible to formulate the alternatives. • Alternatives are one of two types: • mutually exclusive or independent. • Each type is evaluated differently © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-4 Formulating AlternativesFormulating Alternatives
  • 5. 5-5 Formulating AlternativesFormulating Alternatives Two types of economic proposals Mutually Exclusive (ME) Alternatives: Only one can be selected; Compete against each other Independent Projects: More than one can be selected; Compete only against DN © 2012 by McGraw-Hill All Rights Reserved Do Nothing (DN) – An ME alternative or independent project to maintain the current approach; no new costs, revenues or savings
  • 6. 5-6 Revenue: Alternatives include estimates of costs (cash outflows) and revenues (cash inflows) Two types of cash flow estimates Cost: Alternatives include only costs; revenues and savings assumed equal for all alternatives; also called service alternatives Formulating AlternativesFormulating Alternatives © 2012 by McGraw-Hill All Rights Reserved
  • 7. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-7
  • 8. 5-8 Convert all cash flows to PW using MARR Precede costs by minus sign; receipts by plus sign For mutually exclusive alternatives, select one with numerically largest PW For independent projects, select all with PW > 0 PW Analysis of AlternativesPW Analysis of Alternatives © 2012 by McGraw-Hill All Rights Reserved For one project, if PW > 0, it is justified EVALUATION
  • 9. 5-9 Project ID Present Worth A $30,000 B $12,500 C $-4,000 D $ 2,000 Solution: (a) Select numerically largest PW; alternative A (b) Select all with PW > 0; projects A, B & D Selection of Alternatives by PWSelection of Alternatives by PW © 2012 by McGraw-Hill All Rights Reserved
  • 10. 5-10 Example: PW Evaluation of Equal-Life ME Alts.Example: PW Evaluation of Equal-Life ME Alts. Alternative X has a first cost of $20,000, an operating cost of $9,000 per year, and a $5,000 salvage value after 5 years. Alternative Y will cost $35,000 with an operating cost of $4,000 per year and a salvage value of $7,000 after 5 years. At an MARR of 12% per year, which should be selected? Solution: Find PW at MARR and select numerically larger PW value PWX = -20,000 - 9000(P/A,12%,5) + 5000(P/F,12%,5) = -$49,606 PWY = -35,000 - 4000(P/A,12%,5) + 7000(P/F,12%,5) = -$45,447 Select alternative Y © 2012 by McGraw-Hill All Rights Reserved
  • 11. Example: PW Evaluation of Equal-LifeExample: PW Evaluation of Equal-Life © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-11
  • 12. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-12 Example: PW Evaluation of Equal-LifeExample: PW Evaluation of Equal-Life
  • 13. • Present worth analysis requires an equal service comparison of alternatives, that is, the number of years considered must be the same for all alternatives. • If equal service is not present, shorter-lived alternatives will be favored based on lower PW of total costs, even though they may not be economically favorable. • Fundamentally, there are two ways to use PW analysis to compare alternatives with unequal life estimates; • use the least common multiple of lives for each pair of alternatives • or evaluate over a specific study period (planning horizon), • In both cases, the PW is calculated at the MARR, and the selection guidelines of the previous section are applied © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-13 PW of Different-Life AlternativesPW of Different-Life Alternatives
  • 14. 5-14 PW of Different-Life AlternativesPW of Different-Life Alternatives Must compare alternatives for equal service (i.e., alternatives must end at the same time) Two ways to compare equal service: (The LCM procedure is used unless otherwise specified) Least common multiple (LCM) of lives Specified study period © 2012 by McGraw-Hill All Rights Reserved
  • 15. Assumptions of LCM approachAssumptions of LCM approach  Service provided is needed over the LCM or more years  Selected alternative can be repeated over each life cycle of LCM in exactly the same manner  Cash flow estimates are the same for each life cycle (i.e., change in exact accord with the inflation or deflation rate) 1-15 © 2012 by McGraw-Hill All Rights Reserved
  • 16. 5-16 Example: Different-Life AlternativesExample: Different-Life Alternatives Compare the machines below using present worth analysis at i = 10% per year Machine A Machine B First cost, $ Annual cost, $/year Salvage value, $ Life, years 20,000 30,000 9000 7000 4000 6000 3 6 Solution: PWA = -20,000 – 9000(P/A,10%,6) – 16,000(P/F,10%,3) + 4000(P/F,10%,6) = $-68,961 PWB = -30,000 – 7000(P/A,10%,6) + 6000(P/F,10%,6) = $-57,100 LCM = 6 years; repurchase A after 3 years Select alternative B © 2012 by McGraw-Hill All Rights Reserved 20,000 – 4,000 in year 3
  • 17. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-17
  • 18. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-18
  • 19. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-19
  • 20. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-20
  • 21. PW Evaluation Using a Study PeriodPW Evaluation Using a Study Period Once a study period is specified, all cash flows after this time are ignored Salvage value is the estimated market value at the end of study period Short study periods are often defined by management when business goals are short-term Study periods are commonly used in equipment replacement analysis 1-21 © 2012 by McGraw-Hill All Rights Reserved
  • 22. 5-22 Example: Study Period PW EvaluationExample: Study Period PW Evaluation Compare the alternatives below using present worth analysis at i = 10% per year and a 3-year study period Machine A Machine B First cost, $ Annual cost, $/year Salvage/market value, $ Life, years -20,000 -30,000 -9,000 -7,000 4,000 6,000 (after 6 years) 10,000 (after 3 years) 3 6 Solution: PWA = -20,000 – 9000(P/A,10%,3) + 4000(P/F,10%,3) = $-39,376 PWB = -30,000 – 7000(P/A,10%,3) + 10,000(P/F,10%,3)= $-39,895 Study period = 3 years; disregard all estimates after 3 years Marginally, select A; different selection than for LCM = 6 years © 2012 by McGraw-Hill All Rights Reserved
  • 23. 5-23 Future Worth AnalysisFuture Worth Analysis Must compare alternatives for equal service (i.e. alternatives must end at the same time) Two ways to compare equal service: (The LCM procedure is used unless otherwise specified) Least common multiple (LCM) of lives Specified study period FW exactly like PW analysis, except calculate FW © 2012 by McGraw-Hill All Rights Reserved
  • 24. 5-24 FW of Different-Life AlternativesFW of Different-Life Alternatives Compare the machines below using future worth analysis at i = 10% per year Machine A Machine B First cost, $ Annual cost, $/year Salvage value, $ Life, years -20,000 -30,000 -9000 -7000 4000 6000 3 6 Solution: FWA = -20,000(F/P,10%,6) – 9000(F/A,10%,6) – 16,000(F/P,10%,3) + 4000 = $-122,168 FWB = -30,000(F/P,10%.6) – 7000(F/A,10%,6) + 6000 = $-101,157 LCM = 6 years; repurchase A after 3 years Select B (Note: PW and FW methods will always result in same selection) © 2012 by McGraw-Hill All Rights Reserved
  • 25. • Capitalized cost (CC) is the present worth of an alternative that will last “forever.” • Public sector projects such as bridges, dams, irrigation systems, and railroads fall into this category, since they have useful lives of 30, 40, and more years. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-25 Capitalized Cost (CC) AnalysisCapitalized Cost (CC) Analysis
  • 26. Capitalized Cost (CC) AnalysisCapitalized Cost (CC) Analysis 5-26 CC refers to the present worth of a project with a very long life, that is, PW as n becomes infinite Basic equation is: CC = P = A i “A” essentially represents the interest on a perpetual investment For example, in order to be able to withdraw $50,000 per year forever at i = 10% per year, the amount of capital required is 50,000/0.10 = $500,000 For finite life alternatives, convert all cash flows into an A value over one life cycle and then divide by i © 2012 by McGraw-Hill All Rights Reserved
  • 27. 5-27 Example: Capitalized CostExample: Capitalized Cost Solution: Compare the machines shown below on the basis of their capitalized cost. Use i = 10% per year Machine 1 Machine 2 First cost,$ Annual cost,$/year Salvage value, $ Life, years -20,000 -100,000 -9000 -7000 4000 ----- 3 ∞ Convert machine 1 cash flows into A and then divide by i A1 = -20,000(A/P,10%,3) – 9000 + 4000(A/F,10%,3) = $-15,834 CC1 = -15,834 / 0.10 = $-158,340 CC2 = -100,000 – 7000/ 0.10 = $-170,000 Select machine 1 © 2012 by McGraw-Hill All Rights Reserved
  • 28. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-28
  • 29. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-29
  • 30. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-30
  • 31. © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved 1-31
  • 32. 5-32 Summary of Important PointsSummary of Important Points PW method converts all cash flows to present value at MARR PW comparison must always be made for equal service Alternatives can be mutually exclusive or independent Cash flow estimates can be for revenue or cost alternatives Equal service is achieved by using LCM or study period Capitalized cost is PW of project with infinite life; CC = P = A/i © 2012 by McGraw-Hill All Rights Reserved