Engineering Economics

    November 3, 2004




                       1
Engineering Economy
• It deals with the concepts and techniques
  of analysis useful in evaluating the worth
  of systems, products, and services in
  relation to their costs




                                  2
Engineering Economy
• It is used to answer many different
  questions
  – Which engineering projects are worthwhile?
     • Has the mining or petroleum engineer shown that
       the mineral or oil deposits is worth developing?
  – Which engineering projects should have a
    higher priority?
     • Has the industrial engineer shown which factory
       improvement projects should be funded with the
       available dollars?
  – How should the engineering project be
    designed?
     • Has civil or mechanical engineer chosen the best
       thickness for insulation?           3
Basic Concepts
• Cash flow
• Interest Rate and Time value of money
• Equivalence technique




                                4
Cash Flow
• Engineering projects generally have economic
  consequences that occur over an extended
  period of time
  – For example, if an expensive piece of machinery is
    installed in a plant were brought on credit, the simple
    process of paying for it may take several years
  – The resulting favorable consequences may last as
    long as the equipment performs its useful function
• Each project is described as cash receipts or
  disbursements (expenses) at different points in
  time

                                             5
Categories of Cash Flows
• The expenses and receipts due to
  engineering projects usually fall into one of
  the following categories:
   – First cost: expense to build or to buy and install
   – Operations and maintenance (O&M): annual
     expense, such as electricity, labor, and minor
     repairs
   – Salvage value: receipt at project termination for
     sale or transfer of the equipment (can be a
     salvage cost)
   – Revenues: annual receipts due to sale of products
     or services
   – Overhaul: major capital expenditure that occurs
     during the asset’s life
                                          6
Cash Flow diagrams
• The costs and benefits of engineering
  projects over time are summarized on a cash
  flow diagram (CFD). Specifically, CFD
  illustrates the size, sign, and timing of
  individual cash flows, and forms the basis for
  engineering economic analysis
• A CFD is created by first drawing a
  segmented time-based horizontal line,
  divided into appropriate time unit. Each time
  when there is a cash flow, a vertical arrow is
  added − pointing down for costs and up for
  revenues or benefits. The cost flows are
  drawn to relative scale

                                     7
Drawing a Cash Flow Diagram
• In a cash flow diagram (CFD) the end of period t is
  the same as the beginning of period (t+1)
• Beginning of period cash flows are: rent, lease, and
  insurance payments
• End-of-period cash flows are: O&M, salvages,
  revenues, overhauls
• The choice of time 0 is arbitrary. It can be when a
  project is analyzed, when funding is approved, or
  when construction begins
• One person’s cash outflow (represented as a
  negative value) is another person’s inflow
  (represented as a positive value)
• It is better to show two or more cash flows occurring
  in the same year individually so that there is a clear
  connection from the problem statement to each cash
  flow in the diagram
                                            8
An Example of Cash Flow Diagram
• A man borrowed $1,000 from a bank at 8%
  interest. Two end-of-year payments: at the
  end of the first year, he will repay half of the
  $1000 principal plus the interest that is due.
  At the end of the second year, he will repay
  the remaining half plus the interest for the
  second year.
• Cash flow for this problem is:
   End of year    Cash flow
     0              +$1000
     1              -$580 (-$500 - $80)
     2              -$540 (-$500 - $40)
                                          9
Cash Flow Diagram

$1,000




               1      2

         0


                     $540
              $580




                                 10
Time Value of Money

• Money has value
  – Money can be leased or rented
  – The payment is called interest
  – If you put $100 in a bank at 9% interest for one time
    period you will receive back your original $100 plus $9



           Original amount to be returned = $100
           Interest to be returned = $100 x .09 = $9

                                               11
Compound Interest
• Interest that is computed on the original
  unpaid debt and the unpaid interest
• Compound interest is most commonly
  used in practice
• Total interest earned = In = P (1+i)n - P
  – Where,
     • P – present sum of money
     • i – interest rate
     • n – number of periods (years)

       I2 = $100 x (1+.09)2 - $100 = $18.81
                                              12
Future Value of a Loan With
        Compound Interest
• Amount of money due at the end of a loan
  – F = P(1+i)1(1+i)2…..(1+i)n or F = P (1 + i)n
  – Where,
     • F = future value and P = present value
     • Referring to slide #10, i = 9%, P = $100 and say n=
       2. Determine the value of F.

        F = $100 (1 + .09)2 = $118.81



                                           13
Notation for
    Calculating a Future Value
• Formula:
     F=P(1+i)n is the
     single payment compound amount factor.
• Functional notation:
     F=P(F/P,i,n) F=5000(F/P,6%,10)
• F =P(F/P) which is dimensionally
  correct.
                                 14
Notation for
     Calculating a Present Value
• P=F(1/(1+i))n=F(1+i)-n is the
     single payment present worth factor.
• Functional notation:
     P=F(P/F,i,n) P=5000(P/F,6%,10)
Interpretation of (P/F, i, n): a present sum P,
  given a future sum, F, n interest periods
  hence at an interest rate i per interest
  period
                                     15
Spreadsheet Function
P = PV(i,N,A,F,Type)
F = FV(i,N,A,P,Type)
i = RATE(N,A,P,F,Type,guess)
Where, i = interest rate, N = number of interest
   periods, A = uniform amount, P = present sum
   of money, F = future sum of money, Type = 0
   means end-of-period cash payments, Type =
   1 means beginning-of-period payments,
   guess is a guess value of the interest rate


                                   16
Equivalence
• Relative attractiveness of different
  alternatives can be judged by using the
  technique of equivalence
• We use comparable equivalent values of
  alternatives to judge the relative
  attractiveness of the given alternatives
• Equivalence is dependent on interest rate
• Compound Interest formulas can be
  used to facilitate equivalence
  computations

                                 17
Technique of Equivalence
• Determine a single equivalent value at a
  point in time for plan 1.
• Determine a single equivalent value at a
  point in time for plan 2.
  Both at the same interest rate and at the same time
  point.
  •Judge the relative attractiveness of the
  two alternatives from the comparable
  equivalent values.
                                               18
Engineering Economic Analysis
              Calculation
• Generally involves compound interest
  formulas (factors)
• Compound interest formulas (factors) can
  be evaluated by using one of the three
  methods
  – Interest factor tables
  – Calculator
  – Spreadsheet


                                19
Given the choice of these two plans
    which would you choose?
   Year             Plan 1             Plan 2
    0                                  $5,000
    1               $1,000
    2               $1,000
    3               $1,000
    4               $1,000
    5               $1,000
   Total            $5,000             $5,000
To make a choice the cash flows must be altered
so a comparison may be made.                20
Resolving Cash Flows to Equivalent Present
                    Values


• P = $1,000(P|A,10%,5)
• P = $1,000(3.791) =
  $3,791




• P = $5,000
• Alternative 2 is better
  than alternative 1 since
  alternative 2 has a
  greater present value

                                    21
An Example of Future Value
• Example: If $500 were deposited in a
  bank savings account, how much would
  be in the account three years hence if
  the bank paid 6% interest compounded
  annually?
• Given P = 500, i = 6%, n = 3, use F =
  FV(6%,3,,500,0) = -595.91
• Note that the spreadsheet gives a
  negative number to find equivalent of P.
  If we find P using F = -$595.91, we get
  P = 500.
                                22
An Example of Present Value
• Example 3-5: If you wished to have
  $800 in a savings account at the end of
  four years, and 5% interest we paid
  annually, how much should you put into
  the savings account?
• n = 4, F = $800, i = 5%, P = ?
• P = PV(5%,4,,800,0) = -$658.16
• You should use P = $658.16


                                23
Economic Analysis Methods
• Three commonly used economic analysis
  methods are
• Present Worth Analysis
• Annual Worth Analysis
• Rate of Return Analysis




                              24
Present Worth Analysis
• Steps to do present worth analysis for a
  single alternative (investment)
  – Select a desired value of the return on
    investment (i)
  – Using the compound interest formulas bring
    all benefits and costs to present worth
  – Select the alternative if its net present worth
    (Present worth of benefits – Present worth of
    costs) ≥ 0



                                       25
Present Worth Analysis
• Steps to do present worth analysis for
  selecting a single alternative (investment)
  from among multiple alternatives
  – Step 1: Select a desired value of the return on
    investment (i)
  – Step 2: Using the compound interest formulas
    bring all benefits and costs to present worth
    for each alternative
  – Step 3: Select the alternative with the largest
    net present worth (Present worth of benefits –
    Present worth of costs)
                                      26
Present Worth Analysis
• A construction enterprise is investigating the
  purchase of a new dump truck. Interest rate is
  9%. The cash flow for the dump truck are as
  follows:
• First cost = $50,000, annual operating cost =
  $2000, annual income = $9,000, salvage value
  is $10,000, life = 10 years. Is this investment
  worth undertaking?
• P = $50,000, A = annual net income = $9,000 -
  $2,000 = $7,000, S = 10,000, n = 10.
• Evaluate net present worth = present worth of
  benefits – present worth of costs
                                      27
Present Worth Analysis
• Present worth of benefits = $9,000(P|A,9%,10) =
  $9,000(6.418) = $57,762
• Present worth of costs = $50,000 +
  $2,000(P|A,9%,10) - $10,000(P|F,9%,10)=
  $50,000 + $2,000(6..418) - $10,000(.4224) =
  $58,612
• Net present worth = $57,762 - $58,612 < 0 ⇒ do
  not invest
• What should be the minimum annual benefit for
  making it a worthy of investment at 9% rate of
  return?
                                     28
Present Worth Analysis
• Present worth of benefits = A(P|A,9%,10)
  = A(6.418)
• Present worth of costs = $50,000 +
  $2,000(P|A,9%,10) - $10,000(P|F,9%,10)=
  $50,000 + $2,000(6..418) -
  $10,000(.4224) = $58,612
• A(6.418) = $58,612 ⇒ A = $58,612/6.418
  = $9,312.44


                                29
Cost and Benefit Estimates
• Present and future benefits (income) and
  costs need to be estimated to determine
  the attractiveness (worthiness) of a new
  product investment alternative




                                 30
Annual costs and Income for a Product
• Annual product total cost is the sum of
  annual material, labor, and overhead
  (salaries, taxes, marketing expenses,
  office costs, and related costs), annual
  operating costs (power, maintenance,
  repairs, space costs, and related
  expenses), and annual first cost minus the
  annual salvage value.
• Annual income generated through the
  sales of a product = number of units sold
  annuallyxunit price
                                 31
Rate of Return Analysis
• Single alternative case
• In this method all revenues and costs of
  the alternative are reduced to a single
  percentage number
• This percentage number can be compared
  to other investment returns and interest
  rates inside and outside the organization



                                32
Rate of Return Analysis
• Steps to determine rate of return for a
  single stand-alone investment
  – Step 1: Take the dollar amounts to the same
    point in time using the compound interest
    formulas
  – Step 2: Equate the sum of the revenues to the
    sum of the costs at that point in time and
    solve for i




                                     33
Rate of Return Analysis
• An initial investment of $500 is being
  considered. The revenues from this
  investment are $300 at the end of the first
  year, $300 at the end of the second, and
  $200 at the end of the third. If the desired
  return on investment is 15%, is the project
  acceptable?
• In this example we will take benefits and
  costs to the present time and their present
  values are then equated
                                   34
Rate of Return Analysis
• $500 = $300(P|F, i, n=1) + 300(P|F, i, n=2) +
  $200(P|F, i, n=3)
• Now solve for i using trial and error method
• Try 10%: $500 = ? $272 + $247 + $156 = $669
  (not equal)
• Try 20%: $500 = ? $250 + $208 + $116 = $574
  (not equal)
• Try 30%: $500 = ? $231 + $178 + $91 = $500
  (equal) ⇒ i = 30%
• The desired return on investment is 15%, the
  project returns 30%, so it should be
  implemented
                                     35

More Related Content

What's hot

Importance of engineering economics
Importance of engineering economicsImportance of engineering economics
Importance of engineering economicssohail_azhar
 
Introduction to Engineering economics
Introduction to Engineering economicsIntroduction to Engineering economics
Introduction to Engineering economicsDr. C.V. Suresh Babu
 
Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Shail Nakum
 
Engineering economic importance &amp; application
Engineering economic importance &amp; applicationEngineering economic importance &amp; application
Engineering economic importance &amp; applicationabdus sobhan
 
9. benefit cost analysis
9. benefit cost analysis9. benefit cost analysis
9. benefit cost analysisMohsin Siddique
 
Introduction to Engineering Economics
Introduction to Engineering EconomicsIntroduction to Engineering Economics
Introduction to Engineering EconomicsPrabu U
 
8. Rate of return analysis
8. Rate of return analysis8. Rate of return analysis
8. Rate of return analysisMohsin Siddique
 
Payback timevalue of money and iir
Payback timevalue of money and iirPayback timevalue of money and iir
Payback timevalue of money and iirSubhash Rohit
 
introduction to engineering economy
introduction to engineering economy   introduction to engineering economy
introduction to engineering economy Sebghatullah Karimi
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examplesAbdulaziz AlSuwaidi
 
09 minimum-attractive-rate-of-return
09 minimum-attractive-rate-of-return09 minimum-attractive-rate-of-return
09 minimum-attractive-rate-of-returnEngr muiz raqib
 
Life cycle cost analysis
Life cycle cost analysisLife cycle cost analysis
Life cycle cost analysisAnkur Bansal
 
Methods of depreciation
Methods of depreciationMethods of depreciation
Methods of depreciationAashish Singh
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economyBich Lien Pham
 
Depreciation methods
Depreciation methodsDepreciation methods
Depreciation methodsAmeen San
 

What's hot (20)

Importance of engineering economics
Importance of engineering economicsImportance of engineering economics
Importance of engineering economics
 
Introduction to Engineering economics
Introduction to Engineering economicsIntroduction to Engineering economics
Introduction to Engineering economics
 
Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)
 
Cost estimation techniques
Cost estimation techniquesCost estimation techniques
Cost estimation techniques
 
Engineering economic importance &amp; application
Engineering economic importance &amp; applicationEngineering economic importance &amp; application
Engineering economic importance &amp; application
 
9. benefit cost analysis
9. benefit cost analysis9. benefit cost analysis
9. benefit cost analysis
 
6.2 cash flow - time diagrams
6.2 cash flow - time diagrams6.2 cash flow - time diagrams
6.2 cash flow - time diagrams
 
Introduction to Engineering Economics
Introduction to Engineering EconomicsIntroduction to Engineering Economics
Introduction to Engineering Economics
 
8. Rate of return analysis
8. Rate of return analysis8. Rate of return analysis
8. Rate of return analysis
 
NET PRESENT VALUE (NPV)
NET PRESENT VALUE (NPV)NET PRESENT VALUE (NPV)
NET PRESENT VALUE (NPV)
 
Payback timevalue of money and iir
Payback timevalue of money and iirPayback timevalue of money and iir
Payback timevalue of money and iir
 
introduction to engineering economy
introduction to engineering economy   introduction to engineering economy
introduction to engineering economy
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
 
09 minimum-attractive-rate-of-return
09 minimum-attractive-rate-of-return09 minimum-attractive-rate-of-return
09 minimum-attractive-rate-of-return
 
Life cycle cost analysis
Life cycle cost analysisLife cycle cost analysis
Life cycle cost analysis
 
Methods of depreciation
Methods of depreciationMethods of depreciation
Methods of depreciation
 
Module-4:Introduction to engineering economy,Interest and time value of money...
Module-4:Introduction to engineering economy,Interest and time value of money...Module-4:Introduction to engineering economy,Interest and time value of money...
Module-4:Introduction to engineering economy,Interest and time value of money...
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economy
 
Depreciation methods
Depreciation methodsDepreciation methods
Depreciation methods
 

Similar to Engineering economics

engineering economics presentation1.pptx
engineering economics presentation1.pptxengineering economics presentation1.pptx
engineering economics presentation1.pptxssuser46cd151
 
EngEconPatel03NOV04.ppt
EngEconPatel03NOV04.pptEngEconPatel03NOV04.ppt
EngEconPatel03NOV04.pptAyan Sengupta
 
Engineering economics Slides for Postgraduates
Engineering economics Slides for PostgraduatesEngineering economics Slides for Postgraduates
Engineering economics Slides for Postgraduatesssuser50050d1
 
1 Time Value of Money_.pptx .
1 Time Value of Money_.pptx               .1 Time Value of Money_.pptx               .
1 Time Value of Money_.pptx .Athar739197
 
Инженерийн эдийн засаг №2
Инженерийн эдийн засаг №2Инженерийн эдийн засаг №2
Инженерийн эдийн засаг №2Khatanzorig Enkhjargal
 
Ch1 why engecon_rev2
Ch1 why engecon_rev2Ch1 why engecon_rev2
Ch1 why engecon_rev2Nour Dagher
 
Chapter 2 CFD 2015 civil engineering debre markos university.pptx
Chapter 2 CFD 2015 civil engineering debre markos university.pptxChapter 2 CFD 2015 civil engineering debre markos university.pptx
Chapter 2 CFD 2015 civil engineering debre markos university.pptxHeniyit
 
L3 - With Answers.pdf
L3 - With Answers.pdfL3 - With Answers.pdf
L3 - With Answers.pdfnewton47
 
Lecture 4 Economic Assessment EDIT.pptx
Lecture 4 Economic Assessment EDIT.pptxLecture 4 Economic Assessment EDIT.pptx
Lecture 4 Economic Assessment EDIT.pptxMuhammadZuhdiIbrahim
 
2.8 skill financial analysis
2.8 skill financial analysis2.8 skill financial analysis
2.8 skill financial analysisNigestAbebaw1
 
Future Worth method
Future Worth methodFuture Worth method
Future Worth methodSuhail Ahmed
 
E - ENGINEERING ECONOMICS problems and solutions.pptx
E - ENGINEERING ECONOMICS problems and solutions.pptxE - ENGINEERING ECONOMICS problems and solutions.pptx
E - ENGINEERING ECONOMICS problems and solutions.pptxCarloRemorozaMartine
 
Engineering Economy Costing and Accounting
Engineering Economy Costing and Accounting Engineering Economy Costing and Accounting
Engineering Economy Costing and Accounting Shailesh Dewangan
 

Similar to Engineering economics (20)

1
11
1
 
engineering economics presentation1.pptx
engineering economics presentation1.pptxengineering economics presentation1.pptx
engineering economics presentation1.pptx
 
EngEconPatel03NOV04.ppt
EngEconPatel03NOV04.pptEngEconPatel03NOV04.ppt
EngEconPatel03NOV04.ppt
 
Engineering economics Slides for Postgraduates
Engineering economics Slides for PostgraduatesEngineering economics Slides for Postgraduates
Engineering economics Slides for Postgraduates
 
unit three.pdf
unit three.pdfunit three.pdf
unit three.pdf
 
1 Time Value of Money_.pptx .
1 Time Value of Money_.pptx               .1 Time Value of Money_.pptx               .
1 Time Value of Money_.pptx .
 
Инженерийн эдийн засаг №2
Инженерийн эдийн засаг №2Инженерийн эдийн засаг №2
Инженерийн эдийн засаг №2
 
Ch1 why engecon_rev2
Ch1 why engecon_rev2Ch1 why engecon_rev2
Ch1 why engecon_rev2
 
Module_1.pptx
Module_1.pptxModule_1.pptx
Module_1.pptx
 
Chapter 2 CFD 2015 civil engineering debre markos university.pptx
Chapter 2 CFD 2015 civil engineering debre markos university.pptxChapter 2 CFD 2015 civil engineering debre markos university.pptx
Chapter 2 CFD 2015 civil engineering debre markos university.pptx
 
L3 - With Answers.pdf
L3 - With Answers.pdfL3 - With Answers.pdf
L3 - With Answers.pdf
 
Lecture 4 Economic Assessment EDIT.pptx
Lecture 4 Economic Assessment EDIT.pptxLecture 4 Economic Assessment EDIT.pptx
Lecture 4 Economic Assessment EDIT.pptx
 
2.8 skill financial analysis
2.8 skill financial analysis2.8 skill financial analysis
2.8 skill financial analysis
 
Future Worth method
Future Worth methodFuture Worth method
Future Worth method
 
Investment Settings
Investment SettingsInvestment Settings
Investment Settings
 
E - ENGINEERING ECONOMICS problems and solutions.pptx
E - ENGINEERING ECONOMICS problems and solutions.pptxE - ENGINEERING ECONOMICS problems and solutions.pptx
E - ENGINEERING ECONOMICS problems and solutions.pptx
 
Engineering Economy Costing and Accounting
Engineering Economy Costing and Accounting Engineering Economy Costing and Accounting
Engineering Economy Costing and Accounting
 
Nce603 mod unit3
Nce603 mod unit3Nce603 mod unit3
Nce603 mod unit3
 
Evaluation
EvaluationEvaluation
Evaluation
 
F.M - Chapter 5.pptx
F.M - Chapter 5.pptxF.M - Chapter 5.pptx
F.M - Chapter 5.pptx
 

Recently uploaded

Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...lizamodels9
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 

Recently uploaded (20)

Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 

Engineering economics

  • 1. Engineering Economics November 3, 2004 1
  • 2. Engineering Economy • It deals with the concepts and techniques of analysis useful in evaluating the worth of systems, products, and services in relation to their costs 2
  • 3. Engineering Economy • It is used to answer many different questions – Which engineering projects are worthwhile? • Has the mining or petroleum engineer shown that the mineral or oil deposits is worth developing? – Which engineering projects should have a higher priority? • Has the industrial engineer shown which factory improvement projects should be funded with the available dollars? – How should the engineering project be designed? • Has civil or mechanical engineer chosen the best thickness for insulation? 3
  • 4. Basic Concepts • Cash flow • Interest Rate and Time value of money • Equivalence technique 4
  • 5. Cash Flow • Engineering projects generally have economic consequences that occur over an extended period of time – For example, if an expensive piece of machinery is installed in a plant were brought on credit, the simple process of paying for it may take several years – The resulting favorable consequences may last as long as the equipment performs its useful function • Each project is described as cash receipts or disbursements (expenses) at different points in time 5
  • 6. Categories of Cash Flows • The expenses and receipts due to engineering projects usually fall into one of the following categories: – First cost: expense to build or to buy and install – Operations and maintenance (O&M): annual expense, such as electricity, labor, and minor repairs – Salvage value: receipt at project termination for sale or transfer of the equipment (can be a salvage cost) – Revenues: annual receipts due to sale of products or services – Overhaul: major capital expenditure that occurs during the asset’s life 6
  • 7. Cash Flow diagrams • The costs and benefits of engineering projects over time are summarized on a cash flow diagram (CFD). Specifically, CFD illustrates the size, sign, and timing of individual cash flows, and forms the basis for engineering economic analysis • A CFD is created by first drawing a segmented time-based horizontal line, divided into appropriate time unit. Each time when there is a cash flow, a vertical arrow is added − pointing down for costs and up for revenues or benefits. The cost flows are drawn to relative scale 7
  • 8. Drawing a Cash Flow Diagram • In a cash flow diagram (CFD) the end of period t is the same as the beginning of period (t+1) • Beginning of period cash flows are: rent, lease, and insurance payments • End-of-period cash flows are: O&M, salvages, revenues, overhauls • The choice of time 0 is arbitrary. It can be when a project is analyzed, when funding is approved, or when construction begins • One person’s cash outflow (represented as a negative value) is another person’s inflow (represented as a positive value) • It is better to show two or more cash flows occurring in the same year individually so that there is a clear connection from the problem statement to each cash flow in the diagram 8
  • 9. An Example of Cash Flow Diagram • A man borrowed $1,000 from a bank at 8% interest. Two end-of-year payments: at the end of the first year, he will repay half of the $1000 principal plus the interest that is due. At the end of the second year, he will repay the remaining half plus the interest for the second year. • Cash flow for this problem is: End of year Cash flow 0 +$1000 1 -$580 (-$500 - $80) 2 -$540 (-$500 - $40) 9
  • 10. Cash Flow Diagram $1,000 1 2 0 $540 $580 10
  • 11. Time Value of Money • Money has value – Money can be leased or rented – The payment is called interest – If you put $100 in a bank at 9% interest for one time period you will receive back your original $100 plus $9 Original amount to be returned = $100 Interest to be returned = $100 x .09 = $9 11
  • 12. Compound Interest • Interest that is computed on the original unpaid debt and the unpaid interest • Compound interest is most commonly used in practice • Total interest earned = In = P (1+i)n - P – Where, • P – present sum of money • i – interest rate • n – number of periods (years) I2 = $100 x (1+.09)2 - $100 = $18.81 12
  • 13. Future Value of a Loan With Compound Interest • Amount of money due at the end of a loan – F = P(1+i)1(1+i)2…..(1+i)n or F = P (1 + i)n – Where, • F = future value and P = present value • Referring to slide #10, i = 9%, P = $100 and say n= 2. Determine the value of F. F = $100 (1 + .09)2 = $118.81 13
  • 14. Notation for Calculating a Future Value • Formula: F=P(1+i)n is the single payment compound amount factor. • Functional notation: F=P(F/P,i,n) F=5000(F/P,6%,10) • F =P(F/P) which is dimensionally correct. 14
  • 15. Notation for Calculating a Present Value • P=F(1/(1+i))n=F(1+i)-n is the single payment present worth factor. • Functional notation: P=F(P/F,i,n) P=5000(P/F,6%,10) Interpretation of (P/F, i, n): a present sum P, given a future sum, F, n interest periods hence at an interest rate i per interest period 15
  • 16. Spreadsheet Function P = PV(i,N,A,F,Type) F = FV(i,N,A,P,Type) i = RATE(N,A,P,F,Type,guess) Where, i = interest rate, N = number of interest periods, A = uniform amount, P = present sum of money, F = future sum of money, Type = 0 means end-of-period cash payments, Type = 1 means beginning-of-period payments, guess is a guess value of the interest rate 16
  • 17. Equivalence • Relative attractiveness of different alternatives can be judged by using the technique of equivalence • We use comparable equivalent values of alternatives to judge the relative attractiveness of the given alternatives • Equivalence is dependent on interest rate • Compound Interest formulas can be used to facilitate equivalence computations 17
  • 18. Technique of Equivalence • Determine a single equivalent value at a point in time for plan 1. • Determine a single equivalent value at a point in time for plan 2. Both at the same interest rate and at the same time point. •Judge the relative attractiveness of the two alternatives from the comparable equivalent values. 18
  • 19. Engineering Economic Analysis Calculation • Generally involves compound interest formulas (factors) • Compound interest formulas (factors) can be evaluated by using one of the three methods – Interest factor tables – Calculator – Spreadsheet 19
  • 20. Given the choice of these two plans which would you choose? Year Plan 1 Plan 2 0 $5,000 1 $1,000 2 $1,000 3 $1,000 4 $1,000 5 $1,000 Total $5,000 $5,000 To make a choice the cash flows must be altered so a comparison may be made. 20
  • 21. Resolving Cash Flows to Equivalent Present Values • P = $1,000(P|A,10%,5) • P = $1,000(3.791) = $3,791 • P = $5,000 • Alternative 2 is better than alternative 1 since alternative 2 has a greater present value 21
  • 22. An Example of Future Value • Example: If $500 were deposited in a bank savings account, how much would be in the account three years hence if the bank paid 6% interest compounded annually? • Given P = 500, i = 6%, n = 3, use F = FV(6%,3,,500,0) = -595.91 • Note that the spreadsheet gives a negative number to find equivalent of P. If we find P using F = -$595.91, we get P = 500. 22
  • 23. An Example of Present Value • Example 3-5: If you wished to have $800 in a savings account at the end of four years, and 5% interest we paid annually, how much should you put into the savings account? • n = 4, F = $800, i = 5%, P = ? • P = PV(5%,4,,800,0) = -$658.16 • You should use P = $658.16 23
  • 24. Economic Analysis Methods • Three commonly used economic analysis methods are • Present Worth Analysis • Annual Worth Analysis • Rate of Return Analysis 24
  • 25. Present Worth Analysis • Steps to do present worth analysis for a single alternative (investment) – Select a desired value of the return on investment (i) – Using the compound interest formulas bring all benefits and costs to present worth – Select the alternative if its net present worth (Present worth of benefits – Present worth of costs) ≥ 0 25
  • 26. Present Worth Analysis • Steps to do present worth analysis for selecting a single alternative (investment) from among multiple alternatives – Step 1: Select a desired value of the return on investment (i) – Step 2: Using the compound interest formulas bring all benefits and costs to present worth for each alternative – Step 3: Select the alternative with the largest net present worth (Present worth of benefits – Present worth of costs) 26
  • 27. Present Worth Analysis • A construction enterprise is investigating the purchase of a new dump truck. Interest rate is 9%. The cash flow for the dump truck are as follows: • First cost = $50,000, annual operating cost = $2000, annual income = $9,000, salvage value is $10,000, life = 10 years. Is this investment worth undertaking? • P = $50,000, A = annual net income = $9,000 - $2,000 = $7,000, S = 10,000, n = 10. • Evaluate net present worth = present worth of benefits – present worth of costs 27
  • 28. Present Worth Analysis • Present worth of benefits = $9,000(P|A,9%,10) = $9,000(6.418) = $57,762 • Present worth of costs = $50,000 + $2,000(P|A,9%,10) - $10,000(P|F,9%,10)= $50,000 + $2,000(6..418) - $10,000(.4224) = $58,612 • Net present worth = $57,762 - $58,612 < 0 ⇒ do not invest • What should be the minimum annual benefit for making it a worthy of investment at 9% rate of return? 28
  • 29. Present Worth Analysis • Present worth of benefits = A(P|A,9%,10) = A(6.418) • Present worth of costs = $50,000 + $2,000(P|A,9%,10) - $10,000(P|F,9%,10)= $50,000 + $2,000(6..418) - $10,000(.4224) = $58,612 • A(6.418) = $58,612 ⇒ A = $58,612/6.418 = $9,312.44 29
  • 30. Cost and Benefit Estimates • Present and future benefits (income) and costs need to be estimated to determine the attractiveness (worthiness) of a new product investment alternative 30
  • 31. Annual costs and Income for a Product • Annual product total cost is the sum of annual material, labor, and overhead (salaries, taxes, marketing expenses, office costs, and related costs), annual operating costs (power, maintenance, repairs, space costs, and related expenses), and annual first cost minus the annual salvage value. • Annual income generated through the sales of a product = number of units sold annuallyxunit price 31
  • 32. Rate of Return Analysis • Single alternative case • In this method all revenues and costs of the alternative are reduced to a single percentage number • This percentage number can be compared to other investment returns and interest rates inside and outside the organization 32
  • 33. Rate of Return Analysis • Steps to determine rate of return for a single stand-alone investment – Step 1: Take the dollar amounts to the same point in time using the compound interest formulas – Step 2: Equate the sum of the revenues to the sum of the costs at that point in time and solve for i 33
  • 34. Rate of Return Analysis • An initial investment of $500 is being considered. The revenues from this investment are $300 at the end of the first year, $300 at the end of the second, and $200 at the end of the third. If the desired return on investment is 15%, is the project acceptable? • In this example we will take benefits and costs to the present time and their present values are then equated 34
  • 35. Rate of Return Analysis • $500 = $300(P|F, i, n=1) + 300(P|F, i, n=2) + $200(P|F, i, n=3) • Now solve for i using trial and error method • Try 10%: $500 = ? $272 + $247 + $156 = $669 (not equal) • Try 20%: $500 = ? $250 + $208 + $116 = $574 (not equal) • Try 30%: $500 = ? $231 + $178 + $91 = $500 (equal) ⇒ i = 30% • The desired return on investment is 15%, the project returns 30%, so it should be implemented 35