SlideShare a Scribd company logo
1 of 12
Download to read offline
EARNED VALUE
ANALYSIS
BY
Prof. Nagesh
Suryawanshi
Advantages
Earned value analysis is the project
management tool that is used to
measure project progress.
 It compares the actual work completed at
any time to the original budget and
schedule.
 It forecasts the final budget and schedule
and analyzes the path to get there.
It gives you the essential early warning
signal that things are going awry (wrong).
2
Terms Used
1.Planned Value (PV)
 Planned Value, also known as Budgeted Cost of
Work Scheduled (BCWS), is defined as the amount
of the task that is supposed to have been
completed.
 It is in monetary terms as a portion of the task
budget.
2.Earned Value (EV)
 Earned Value, also known as Budgeted Cost of Work
Performed (BCWP), is the amount of the task that is
actually complete.
 It is, again, in monetary terms as a portion of the
task budget.
3
3. Actual Cost (AC):
 The Actual Cost, also known as Actual
Cost of Work Performed (ACWP), as you
might guess, is the actual cost of the
work.
 Generally employee hours need to be
converted into a cost, and all project
costs need to be added up, such as the
labour cost, material cost , equipment
cost etc.
4
Indicators
1.Schedule Variance (SV)
 The Schedule Variance represents the schedule status of
the project.
 SV = EV – PV
2.Cost Variance (CV)
 The Cost Variance represents the cost status of the
project.
 CV = EV – AC
 SV and CV are the minimum requirement and work well
for small projects, there are other variables that are
derived from them which you might want to calculate:
5
Other status indicators
 Schedule Performance Index (SPI): The
schedule variance expressed in percentage
terms,
 for example, SPI = 0.8 means the project 20%
behind schedule.
 SPI = EV / PV
 Cost Performance Index (CPI): The cost
variance expressed in percentage terms,
 for example, CPI = 0.9 means the project is 10%
over budget.
 CPI = EV / AC
6
Interpretations
The first two calculations (SV and CV)
give you the basic indicator of project
progress.
A negative value indicates an
undesirable situation.
If the schedule variance (SV) is
negative, you are behind schedule.
If the cost variance (CV) is negative,
you are over budget.
7
:
Interpretation of CPI and SPI
 You interpret CPI results as below:
 CPI less than 1.0 indicates the project is
overspending funds.
 CPI equals 1.0 than the project is on target.
 CPI greater than 1.0 says the project is under
budget.
 You interpret SPI results as below:
 SPI less than 1.0 indicates the project is behind the
schedule
 SPI equals 1.0 than the project is as per schedule .
 SPI greater than 1.0 says the project is ahead the
schedule.
8
Indicators and formulae's
9
Que. It was supposed to complete 5 cubic
meter excavation in eight hrs. Review was taken
after 6 hrs., it was expected to complete 75 %
after 6 hrs. but actually work completed is 60 % .
The actual cost spent to complete the work is
Rs.13,000/- assume the cost require to
excavate one cubic meter per hour is Rs.500.
Calculate the different indices and interpret the
result obtained.
Ans: From the given Data:
Task Excavation budget=5 x 500 x 8= Rs.20,000/-
 PV=75/100 x20,000=15,000/-
 EV=60/100 x 20,000=12,000/-
 AC=Rs.13,000/-
Example
10
 1.CV=EV-PV
 =12000-15000
 = Rs.-3000/-
 2.SV=EV-AC
 =12000-13000
 =Rs. -1000/-
 3.SPI=EV/PV
 =12000/16000
 =0.75
 4.CPI=EV/AC
 =12000/13000
 =0.92
11
Interpretation of results
 First two indicators:
 CV=Cost variance negative it means the
activity excavation is over the budget.
 SV= Schedule variance is also negative
indicates that activity excavation is
behind the schedule.
 Indicators third and fourth:
 SPI is 0.75 (less than 1), indicates that the
excavation is 25 % behind than the
schedule and
 CPI found 0.92(less than 1),indicates its
over budget by 8%.
12

More Related Content

What's hot

Fall 09 Residential Presentation
Fall 09 Residential PresentationFall 09 Residential Presentation
Fall 09 Residential Presentationkneadae
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sumEst
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Valueconstructioninside
 
Construction Spotlight Value
Construction Spotlight ValueConstruction Spotlight Value
Construction Spotlight ValueMatthew Voll
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionAshwiniChaudhari13
 
Estimating and costing contents for polytechnic students
Estimating and costing contents for polytechnic studentsEstimating and costing contents for polytechnic students
Estimating and costing contents for polytechnic studentsAshwiniChaudhari13
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...Tipsographic . com
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budgetharwoodr
 
Evm Basics
Evm BasicsEvm Basics
Evm Basicsgfbreaux
 
AOTB Accounting for Agile
AOTB Accounting for AgileAOTB Accounting for Agile
AOTB Accounting for AgileBrett Ansley
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 RevisionJoyce Wong
 

What's hot (18)

Earned value 01
Earned value 01Earned value 01
Earned value 01
 
Fall 09 Residential Presentation
Fall 09 Residential PresentationFall 09 Residential Presentation
Fall 09 Residential Presentation
 
E.c.v Introduction
E.c.v IntroductionE.c.v Introduction
E.c.v Introduction
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sum
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
 
Construction Spotlight Value
Construction Spotlight ValueConstruction Spotlight Value
Construction Spotlight Value
 
Cs value 2
Cs value 2Cs value 2
Cs value 2
 
New overview
New overviewNew overview
New overview
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Estimating and costing contents for polytechnic students
Estimating and costing contents for polytechnic studentsEstimating and costing contents for polytechnic students
Estimating and costing contents for polytechnic students
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
 
Project managment 6 (a)
Project managment 6 (a)Project managment 6 (a)
Project managment 6 (a)
 
Evm Basics
Evm BasicsEvm Basics
Evm Basics
 
AOTB Accounting for Agile
AOTB Accounting for AgileAOTB Accounting for Agile
AOTB Accounting for Agile
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 Revision
 

Similar to Earned value analysis

Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
What Is Earned Value Analysis
What Is Earned Value AnalysisWhat Is Earned Value Analysis
What Is Earned Value AnalysisSimonRobertson
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Your Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindYour Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindEd Kozak
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updatedFarhana Rehman
 
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN PanigrahiSN Panigrahi, PMP
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptyogeshagrawal84
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examManish Purwar
 
Earned value management
Earned value managementEarned value management
Earned value managementGautam Kumar
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptBetshaTizazu1
 

Similar to Earned value analysis (20)

Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
What Is Earned Value Analysis
What Is Earned Value AnalysisWhat Is Earned Value Analysis
What Is Earned Value Analysis
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Your Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindYour Projects May Be Robbing You Blind
Your Projects May Be Robbing You Blind
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
 
Earned value understanding
Earned value understandingEarned value understanding
Earned value understanding
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.ppt
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Earned value management
Earned value managementEarned value management
Earned value management
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.ppt
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 

Recently uploaded

UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 

Recently uploaded (20)

Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 

Earned value analysis

  • 2. Advantages Earned value analysis is the project management tool that is used to measure project progress.  It compares the actual work completed at any time to the original budget and schedule.  It forecasts the final budget and schedule and analyzes the path to get there. It gives you the essential early warning signal that things are going awry (wrong). 2
  • 3. Terms Used 1.Planned Value (PV)  Planned Value, also known as Budgeted Cost of Work Scheduled (BCWS), is defined as the amount of the task that is supposed to have been completed.  It is in monetary terms as a portion of the task budget. 2.Earned Value (EV)  Earned Value, also known as Budgeted Cost of Work Performed (BCWP), is the amount of the task that is actually complete.  It is, again, in monetary terms as a portion of the task budget. 3
  • 4. 3. Actual Cost (AC):  The Actual Cost, also known as Actual Cost of Work Performed (ACWP), as you might guess, is the actual cost of the work.  Generally employee hours need to be converted into a cost, and all project costs need to be added up, such as the labour cost, material cost , equipment cost etc. 4
  • 5. Indicators 1.Schedule Variance (SV)  The Schedule Variance represents the schedule status of the project.  SV = EV – PV 2.Cost Variance (CV)  The Cost Variance represents the cost status of the project.  CV = EV – AC  SV and CV are the minimum requirement and work well for small projects, there are other variables that are derived from them which you might want to calculate: 5
  • 6. Other status indicators  Schedule Performance Index (SPI): The schedule variance expressed in percentage terms,  for example, SPI = 0.8 means the project 20% behind schedule.  SPI = EV / PV  Cost Performance Index (CPI): The cost variance expressed in percentage terms,  for example, CPI = 0.9 means the project is 10% over budget.  CPI = EV / AC 6
  • 7. Interpretations The first two calculations (SV and CV) give you the basic indicator of project progress. A negative value indicates an undesirable situation. If the schedule variance (SV) is negative, you are behind schedule. If the cost variance (CV) is negative, you are over budget. 7
  • 8. : Interpretation of CPI and SPI  You interpret CPI results as below:  CPI less than 1.0 indicates the project is overspending funds.  CPI equals 1.0 than the project is on target.  CPI greater than 1.0 says the project is under budget.  You interpret SPI results as below:  SPI less than 1.0 indicates the project is behind the schedule  SPI equals 1.0 than the project is as per schedule .  SPI greater than 1.0 says the project is ahead the schedule. 8
  • 10. Que. It was supposed to complete 5 cubic meter excavation in eight hrs. Review was taken after 6 hrs., it was expected to complete 75 % after 6 hrs. but actually work completed is 60 % . The actual cost spent to complete the work is Rs.13,000/- assume the cost require to excavate one cubic meter per hour is Rs.500. Calculate the different indices and interpret the result obtained. Ans: From the given Data: Task Excavation budget=5 x 500 x 8= Rs.20,000/-  PV=75/100 x20,000=15,000/-  EV=60/100 x 20,000=12,000/-  AC=Rs.13,000/- Example 10
  • 11.  1.CV=EV-PV  =12000-15000  = Rs.-3000/-  2.SV=EV-AC  =12000-13000  =Rs. -1000/-  3.SPI=EV/PV  =12000/16000  =0.75  4.CPI=EV/AC  =12000/13000  =0.92 11
  • 12. Interpretation of results  First two indicators:  CV=Cost variance negative it means the activity excavation is over the budget.  SV= Schedule variance is also negative indicates that activity excavation is behind the schedule.  Indicators third and fourth:  SPI is 0.75 (less than 1), indicates that the excavation is 25 % behind than the schedule and  CPI found 0.92(less than 1),indicates its over budget by 8%. 12