SlideShare a Scribd company logo
DETERMINING ESTIMATE
TO COMPLETE
4 SCENARIOS & 3
FORMULAS
AGENDA
• Definition & Explanation
• Calculating ETC
• Example Project
• ETC Formulas
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 2
AGENDA
• Definition & Explanation
• Calculating ETC
• Example Project
• ETC Formulas
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 3
ESTIMATE TO COMPLETE (ETC)
Estimate to Complete or ETC is the expected
cost to finish all the remaining project work.
How much money is needed to complete the
remaining project work?
4DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
PROJECT STATUS
• On Control Date, some work has been completed while some is
remaining.
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 5
COMPLETED REMAINING
TOTAL PROJECT SCOPE/WORK
CALCULATING ETC
• Problem Statement – To Calculate Expected Cost of Remaining Work
(ETC)
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 6
EARNED VALUE
MONETARY VALUE
OF
REMAINING WORK
ORIGINAL PROJECT BUDGET (BAC)
ACTUAL COST/EXPENDITURE ETC
FORECASTED PROJECT BUDGET
?
AGENDA
• Definition & Explanation
• Calculating ETC
• Example Project
• ETC Formulas
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 7
CALCULATING ETC
Is ETC Equivalent to Monetary Value of Remaining Work?
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 8
CALCULATING ETC
Is ETC Equivalent to Monetary Value of Remaining Work?
• No
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 9
CALCULATING ETC
Is ETC Equivalent to Monetary Value of Remaining Work?
• No
• The ETC depends on the Project Team’s efficiency of utilizing the
money
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 10
CALCULATING ETC
Is ETC Equivalent to Monetary Value of Remaining Work?
• No
• The ETC depends on the Project Team’s efficiency of utilizing the
money
• If Efficiency = 1, ETC will be equal to Monetary Value
If Efficiency < 1, ETC will be more than Monetary Value
If Efficiency > 1, ETC will be less than Monetary Value
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 11
Reference –
Basics of Earned Value Analysis
Earned Value Management System Explained in Easy
CALCULATING ETC
12DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
Reference –
Estimate to Complete
ETC = (monetary value of remaining work)/(future projected cost
efficiency)
CALCULATING ETC
 Monetary value of remaining work = monetary value of total work –
monetary value of completed work
 Monetary value of remaining work = BAC – EV
13DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
Reference –
Estimate to Complete
ETC = (monetary value of remaining work)/(future projected cost
efficiency)
CALCULATING ETC
 Monetary value of remaining work = monetary value of total work –
monetary value of completed work
 Monetary value of remaining work = BAC – EV
 In EVM, Cost Efficiency is represented as Cost Performance Index (CPI)
 Let us represent the future projected cost efficiency as CPIp
14DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
Reference –
Estimate to Complete
ETC = (monetary value of remaining work)/(future projected cost
efficiency)
GENERIC ETC EQUATION
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 15
ETC = (BAC – EV) /
CPIp
AGENDA
• Definition & Explanation
• Calculating ETC
• Example Project
• ETC Formulas
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 16
PROJECT PLAN – EXAMPLE
PROJECT
Refer to the example in the previous presentation
(https://www.slideshare.net/pmalik2/101-a-beginners-guide-to-earned-
value-management)
17DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
Project Scope Build 80 Tables
Project Time Estimate (Duration) 5 Days
Cost Estimate Per Table $1000
Project Cost (Budget) $1000*80 = $80000
PROJECT STATUS – EXAMPLE
PROJECT
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 18
Work Completed 35 out of 80 tables
Actual Expenditure $36000 for building 35 tables
Remaining Project Work 45 tables
ETC ?
AGENDA
• Definition & Explanation
• Calculating ETC
• Example Project
• ETC Formulas
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 19
SCENARIO I
• The project team believes that the project’s past performance will
continue to effect the future performance.
• The project would continue to expend money at the current rate.
• The remaining work would be completed at project’s current cost
efficiency.
• Replacing CPIp with CPI, Generic ETC equation becomes
ETC = (BAC – EV) / CPI
20DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
SCENARIO I - CALCULATION
• ETC = ($80000-$35000)/($35000/$36000)
= $46286
• It simply means that the project team will require $46286 to build
the remaining 45 tables.
21DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
SCENARIO II
• The project team believes that the project’s past performance will
not effect the future performance.
• The irregularities of the past would not be repeated in future.
• The remaining work would be completed at project’s 100% cost
efficiency (as per the original estimates).
• Replacing CPIp with 100%, Generic ETC equation becomes
ETC = (BAC – EV)
22DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
SCENARIO II - CALCULATION
• ETC = ($80000-$35000)
= $45000
• It simply means that the project team will require $45000 to build
remaining 45 tables.
23DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
SCENARIO III
• The project team believes that the project’s past performance will
not effect the future performance.
• The team also believes that project would expend money neither at
current rate nor at 100%.
• The remaining work would be completed at new cost efficiency -
CPIp.
• Generic ETC equation becomes formula for the current Scenario
ETC = (BAC – EV) / CPIp
24DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
SCENARIO III - CALCULATION
• Let us assume that the project team determines that future cost
efficiency would be 120% (or 1.2).
• ETC = (80000 – 35000)/1.2
= $37500
• It simply means that the project team will require $37500 to build 45
remaining tables.
25DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
SCENARIO IV
• After analysing the project’s past performance, The project team
believes that the original estimates were not good.
• The cost of remaining work should be re-estimated i.e. ETC should
be determined afresh.
• A fresh ETC can by found by estimating the cost of remaining
(unfinished) work from the Work Breakdown Structure (WBS).
• The project team can re-estimate the cost of remaining work
components (work packages and activities) and then total then total
them Upwards in the WBS to determine a fresh ETC.
• There is no ETC formula for this scenario.
26DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
YOUR OPINION IS
IMPORTANT TO US
For Any Questions Or
Suggestions Contact Us @
https://www.pmbypm.com/c
ontact-praveen-malik/
27DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018

More Related Content

What's hot

Platinum card for agile ev mr4
Platinum card for agile ev mr4Platinum card for agile ev mr4
Platinum card for agile ev mr4
Association for Project Management
 
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of TimeUsing The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
Ahmed Elsayed
 
PPM5D - The BIM Integrated Project Delivery Specialists
PPM5D -  The  BIM Integrated Project Delivery SpecialistsPPM5D -  The  BIM Integrated Project Delivery Specialists
PPM5D - The BIM Integrated Project Delivery Specialists
inistioge
 
ORTEC Case - BAM Infra
ORTEC Case - BAM InfraORTEC Case - BAM Infra
ORTEC Case - BAM Infra
Andrei Pinte
 
What is VICO ?
What is VICO ?What is VICO ?
205540 demonstration of a 10 year, long term project plan
205540 demonstration of a 10 year, long term project plan205540 demonstration of a 10 year, long term project plan
205540 demonstration of a 10 year, long term project plan
p6academy
 
Police Headquarters Guaranteed Maximum Price
Police Headquarters Guaranteed Maximum PricePolice Headquarters Guaranteed Maximum Price
Police Headquarters Guaranteed Maximum Price
City of College Station
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new
uopassignment
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
Essam Lotffy, PMP®, CCP®
 
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
Kuldeep Kumar
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
Abrianto Nugraha
 
Evm Basics
Evm BasicsEvm Basics
Evm Basicsgfbreaux
 
Assignment iii cpm
Assignment iii cpmAssignment iii cpm
Assignment iii cpm
ahsanrabbani
 
Earned value management
Earned value managementEarned value management
Earned value management
Ahmed Gamal
 
EV ِAV PV example
EV ِAV PV exampleEV ِAV PV example
EV ِAV PV example
Mohammed Al_busailiy
 
Building TaxBrain: Numba-enabled Financial Computing on the Web
Building TaxBrain: Numba-enabled Financial Computing on the WebBuilding TaxBrain: Numba-enabled Financial Computing on the Web
Building TaxBrain: Numba-enabled Financial Computing on the Web
talumbau
 
SLOPE intro we have a new project!
SLOPE intro we have a new project!SLOPE intro we have a new project!
SLOPE intro we have a new project!SLOPE Project
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)

What's hot (20)

Platinum card for agile ev mr4
Platinum card for agile ev mr4Platinum card for agile ev mr4
Platinum card for agile ev mr4
 
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of TimeUsing The Earned Value Method To Calculate Project Delays In Terms Of Time
Using The Earned Value Method To Calculate Project Delays In Terms Of Time
 
PPM5D - The BIM Integrated Project Delivery Specialists
PPM5D -  The  BIM Integrated Project Delivery SpecialistsPPM5D -  The  BIM Integrated Project Delivery Specialists
PPM5D - The BIM Integrated Project Delivery Specialists
 
Lesson in fs cpm,cpa
Lesson in fs cpm,cpaLesson in fs cpm,cpa
Lesson in fs cpm,cpa
 
ORTEC Case - BAM Infra
ORTEC Case - BAM InfraORTEC Case - BAM Infra
ORTEC Case - BAM Infra
 
What is VICO ?
What is VICO ?What is VICO ?
What is VICO ?
 
205540 demonstration of a 10 year, long term project plan
205540 demonstration of a 10 year, long term project plan205540 demonstration of a 10 year, long term project plan
205540 demonstration of a 10 year, long term project plan
 
Police Headquarters Guaranteed Maximum Price
Police Headquarters Guaranteed Maximum PricePolice Headquarters Guaranteed Maximum Price
Police Headquarters Guaranteed Maximum Price
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
 
Evm Basics
Evm BasicsEvm Basics
Evm Basics
 
Assignment iii cpm
Assignment iii cpmAssignment iii cpm
Assignment iii cpm
 
Earned value management
Earned value managementEarned value management
Earned value management
 
EV ِAV PV example
EV ِAV PV exampleEV ِAV PV example
EV ِAV PV example
 
june'15
june'15june'15
june'15
 
Building TaxBrain: Numba-enabled Financial Computing on the Web
Building TaxBrain: Numba-enabled Financial Computing on the WebBuilding TaxBrain: Numba-enabled Financial Computing on the Web
Building TaxBrain: Numba-enabled Financial Computing on the Web
 
SLOPE intro we have a new project!
SLOPE intro we have a new project!SLOPE intro we have a new project!
SLOPE intro we have a new project!
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 

Similar to Calculating ETC In 4 Different Scenarios

07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
Dhamo daran
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
Association for Project Management
 
Project Management 3.2 cost
Project Management 3.2 costProject Management 3.2 cost
Project Management 3.2 cost
ElodieDescharmes
 
Agile Estimations in a Traditional World
Agile Estimations in a Traditional WorldAgile Estimations in a Traditional World
Agile Estimations in a Traditional World
ACA IT-Solutions
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptx
AhmedKayed6
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
PMI-Montréal
 
Managing Productivity With Unifier
Managing Productivity With UnifierManaging Productivity With Unifier
Managing Productivity With Unifier
p6academy
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
HuyNguyen657394
 
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdfEVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
RedhaElhuni
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
Association for Project Management
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
Planning & Scheduling - Training
Planning & Scheduling - TrainingPlanning & Scheduling - Training
Planning & Scheduling - TrainingMohammed Feroze
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
Dr Mohamed Elfarran
 
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Shanmukha S. Potti
 
Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14
Integrating cost and schedule in p6  - Oracle Primavera P6 Collaborate 14Integrating cost and schedule in p6  - Oracle Primavera P6 Collaborate 14
Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14
p6academy
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
Qais Ur Rehman Rasooli, PMP
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
B M Shahrier Majumder, PMP, CSM
 

Similar to Calculating ETC In 4 Different Scenarios (20)

07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Project Management 3.2 cost
Project Management 3.2 costProject Management 3.2 cost
Project Management 3.2 cost
 
Agile Estimations in a Traditional World
Agile Estimations in a Traditional WorldAgile Estimations in a Traditional World
Agile Estimations in a Traditional World
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptx
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
 
Managing Productivity With Unifier
Managing Productivity With UnifierManaging Productivity With Unifier
Managing Productivity With Unifier
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
 
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdfEVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Planning & Scheduling - Training
Planning & Scheduling - TrainingPlanning & Scheduling - Training
Planning & Scheduling - Training
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
 
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
 
Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14
Integrating cost and schedule in p6  - Oracle Primavera P6 Collaborate 14Integrating cost and schedule in p6  - Oracle Primavera P6 Collaborate 14
Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
 

More from Praveen Malik, PMP

How To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of RelationshipsHow To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
Praveen Malik, PMP
 
How To Do Planning Using 4 Types of Project Dependencies?
How To Do Planning Using 4 Types of Project Dependencies?How To Do Planning Using 4 Types of Project Dependencies?
How To Do Planning Using 4 Types of Project Dependencies?
Praveen Malik, PMP
 
Successful Project Managers Use These 5 Ways to Represent Project Schedule
Successful Project Managers Use These 5 Ways to Represent Project ScheduleSuccessful Project Managers Use These 5 Ways to Represent Project Schedule
Successful Project Managers Use These 5 Ways to Represent Project Schedule
Praveen Malik, PMP
 
4 Project Estimation Techniques That Can Make You Super Successful
4 Project Estimation Techniques That Can Make You Super Successful4 Project Estimation Techniques That Can Make You Super Successful
4 Project Estimation Techniques That Can Make You Super Successful
Praveen Malik, PMP
 
Ignore Project Scope & WBS At Your Own Peril
Ignore Project Scope & WBS At Your Own PerilIgnore Project Scope & WBS At Your Own Peril
Ignore Project Scope & WBS At Your Own Peril
Praveen Malik, PMP
 
How Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerHow Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project Manager
Praveen Malik, PMP
 

More from Praveen Malik, PMP (6)

How To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of RelationshipsHow To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
 
How To Do Planning Using 4 Types of Project Dependencies?
How To Do Planning Using 4 Types of Project Dependencies?How To Do Planning Using 4 Types of Project Dependencies?
How To Do Planning Using 4 Types of Project Dependencies?
 
Successful Project Managers Use These 5 Ways to Represent Project Schedule
Successful Project Managers Use These 5 Ways to Represent Project ScheduleSuccessful Project Managers Use These 5 Ways to Represent Project Schedule
Successful Project Managers Use These 5 Ways to Represent Project Schedule
 
4 Project Estimation Techniques That Can Make You Super Successful
4 Project Estimation Techniques That Can Make You Super Successful4 Project Estimation Techniques That Can Make You Super Successful
4 Project Estimation Techniques That Can Make You Super Successful
 
Ignore Project Scope & WBS At Your Own Peril
Ignore Project Scope & WBS At Your Own PerilIgnore Project Scope & WBS At Your Own Peril
Ignore Project Scope & WBS At Your Own Peril
 
How Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerHow Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project Manager
 

Recently uploaded

Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
Krisztián Száraz
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
Wasim Ak
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Dr. Vinod Kumar Kanvaria
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
Mohammed Sikander
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
Academy of Science of South Africa
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
Scholarhat
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
chanes7
 

Recently uploaded (20)

Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
 

Calculating ETC In 4 Different Scenarios

  • 1. DETERMINING ESTIMATE TO COMPLETE 4 SCENARIOS & 3 FORMULAS
  • 2. AGENDA • Definition & Explanation • Calculating ETC • Example Project • ETC Formulas DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 2
  • 3. AGENDA • Definition & Explanation • Calculating ETC • Example Project • ETC Formulas DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 3
  • 4. ESTIMATE TO COMPLETE (ETC) Estimate to Complete or ETC is the expected cost to finish all the remaining project work. How much money is needed to complete the remaining project work? 4DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
  • 5. PROJECT STATUS • On Control Date, some work has been completed while some is remaining. DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 5 COMPLETED REMAINING TOTAL PROJECT SCOPE/WORK
  • 6. CALCULATING ETC • Problem Statement – To Calculate Expected Cost of Remaining Work (ETC) DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 6 EARNED VALUE MONETARY VALUE OF REMAINING WORK ORIGINAL PROJECT BUDGET (BAC) ACTUAL COST/EXPENDITURE ETC FORECASTED PROJECT BUDGET ?
  • 7. AGENDA • Definition & Explanation • Calculating ETC • Example Project • ETC Formulas DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 7
  • 8. CALCULATING ETC Is ETC Equivalent to Monetary Value of Remaining Work? DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 8
  • 9. CALCULATING ETC Is ETC Equivalent to Monetary Value of Remaining Work? • No DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 9
  • 10. CALCULATING ETC Is ETC Equivalent to Monetary Value of Remaining Work? • No • The ETC depends on the Project Team’s efficiency of utilizing the money DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 10
  • 11. CALCULATING ETC Is ETC Equivalent to Monetary Value of Remaining Work? • No • The ETC depends on the Project Team’s efficiency of utilizing the money • If Efficiency = 1, ETC will be equal to Monetary Value If Efficiency < 1, ETC will be more than Monetary Value If Efficiency > 1, ETC will be less than Monetary Value DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 11 Reference – Basics of Earned Value Analysis Earned Value Management System Explained in Easy
  • 12. CALCULATING ETC 12DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 Reference – Estimate to Complete ETC = (monetary value of remaining work)/(future projected cost efficiency)
  • 13. CALCULATING ETC  Monetary value of remaining work = monetary value of total work – monetary value of completed work  Monetary value of remaining work = BAC – EV 13DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 Reference – Estimate to Complete ETC = (monetary value of remaining work)/(future projected cost efficiency)
  • 14. CALCULATING ETC  Monetary value of remaining work = monetary value of total work – monetary value of completed work  Monetary value of remaining work = BAC – EV  In EVM, Cost Efficiency is represented as Cost Performance Index (CPI)  Let us represent the future projected cost efficiency as CPIp 14DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 Reference – Estimate to Complete ETC = (monetary value of remaining work)/(future projected cost efficiency)
  • 15. GENERIC ETC EQUATION DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 15 ETC = (BAC – EV) / CPIp
  • 16. AGENDA • Definition & Explanation • Calculating ETC • Example Project • ETC Formulas DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 16
  • 17. PROJECT PLAN – EXAMPLE PROJECT Refer to the example in the previous presentation (https://www.slideshare.net/pmalik2/101-a-beginners-guide-to-earned- value-management) 17DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 Project Scope Build 80 Tables Project Time Estimate (Duration) 5 Days Cost Estimate Per Table $1000 Project Cost (Budget) $1000*80 = $80000
  • 18. PROJECT STATUS – EXAMPLE PROJECT DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 18 Work Completed 35 out of 80 tables Actual Expenditure $36000 for building 35 tables Remaining Project Work 45 tables ETC ?
  • 19. AGENDA • Definition & Explanation • Calculating ETC • Example Project • ETC Formulas DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018 19
  • 20. SCENARIO I • The project team believes that the project’s past performance will continue to effect the future performance. • The project would continue to expend money at the current rate. • The remaining work would be completed at project’s current cost efficiency. • Replacing CPIp with CPI, Generic ETC equation becomes ETC = (BAC – EV) / CPI 20DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
  • 21. SCENARIO I - CALCULATION • ETC = ($80000-$35000)/($35000/$36000) = $46286 • It simply means that the project team will require $46286 to build the remaining 45 tables. 21DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
  • 22. SCENARIO II • The project team believes that the project’s past performance will not effect the future performance. • The irregularities of the past would not be repeated in future. • The remaining work would be completed at project’s 100% cost efficiency (as per the original estimates). • Replacing CPIp with 100%, Generic ETC equation becomes ETC = (BAC – EV) 22DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
  • 23. SCENARIO II - CALCULATION • ETC = ($80000-$35000) = $45000 • It simply means that the project team will require $45000 to build remaining 45 tables. 23DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
  • 24. SCENARIO III • The project team believes that the project’s past performance will not effect the future performance. • The team also believes that project would expend money neither at current rate nor at 100%. • The remaining work would be completed at new cost efficiency - CPIp. • Generic ETC equation becomes formula for the current Scenario ETC = (BAC – EV) / CPIp 24DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
  • 25. SCENARIO III - CALCULATION • Let us assume that the project team determines that future cost efficiency would be 120% (or 1.2). • ETC = (80000 – 35000)/1.2 = $37500 • It simply means that the project team will require $37500 to build 45 remaining tables. 25DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
  • 26. SCENARIO IV • After analysing the project’s past performance, The project team believes that the original estimates were not good. • The cost of remaining work should be re-estimated i.e. ETC should be determined afresh. • A fresh ETC can by found by estimating the cost of remaining (unfinished) work from the Work Breakdown Structure (WBS). • The project team can re-estimate the cost of remaining work components (work packages and activities) and then total then total them Upwards in the WBS to determine a fresh ETC. • There is no ETC formula for this scenario. 26DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018
  • 27. YOUR OPINION IS IMPORTANT TO US For Any Questions Or Suggestions Contact Us @ https://www.pmbypm.com/c ontact-praveen-malik/ 27DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM | COPYRIGHT 2018