Project Dependencies
DEFINITION, EXAMPLES, AND MORE…
Designed and Developed by https://www.pmbypm.com 1
Agenda
• Definition, differences And Examples
• 4 Types of Dependencies
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM 2
Agenda
• Definition, differences And Examples
• 4 Types of Dependencies
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM 3
Dependency
• Project Dependencies are better characterized as Schedule Dependencies.
• A Project Dependency simply means that one project activity is dependent on
another activity.
• Project Dependency is different from Logical Schedule Relationship.
• Example
• Consider two activities A and B. If Start of B is dependent of Finish of A, it simply
means that B cannot start until A finishes.
• https://www.pmbypm.com/project-dependencies/
• https://www.pmbypm.com/project-network-diagram/
Designed and Developed by https://www.pmbypm.com 4
Assumption vs Dependency
• A factor in the planning process that is considered to be true, real, or certain,
without proof or demonstration is called an Assumption.
• A Dependency is between two activities whereas an assumption is about the
work to be done.
• An assumption can be taken with or without a dependency.
• Example
• Consider a scenario wherein the Project Team needs Approval of Design Artefacts
from the Customer. The project cannot move ahead until this Approval.
• Assumption could be that Approval is likely to come within 2 weeks of submitting the
Design Artefacts.
• All subsequent project activities are dependent on Approval (Customer’s activity).
Designed and Developed by https://www.pmbypm.com 5
Constraint Vs Dependency
• A limiting factor that affects the execution of a project, program, portfolio, or process
is called a Constraint.
• A project constraint could be related to Scope, Schedule, Budget, Quality,
Resources, and Risks.
• Some of the Schedule Constraints can be represented as Project Dependencies.
• Example
• Consider the same scenario as in the example on the previous slide. Project Team needs
Approval of Design Artefacts from the Customer. The project cannot move ahead until this
Approval.
• Project team has a Constraint (limitation). Project team cannot do anything else without
the Customer’s Approval.
• All subsequent project activities are dependent on Approval (Customer’s activity).
Designed and Developed by https://www.pmbypm.com 6
Risks
• Risk is an uncertain event or condition that, if it occurs, has a positive or
negative effect on one or more project objectives.
• A Project Risk can impact Scope, Schedule, Budget, and Quality objectives or
any other project objectives.
• A Project Risk can arise because of a Project Dependency.
• Example
• Consider the same scenario as in the example on the previous slide. Project Team
needs Approval of Design Artefacts from the Customer. The project cannot move
ahead until this Approval.
• Risk could be that Customer may not give approval and hence subsequent project
activities would never start.
Designed and Developed by https://www.pmbypm.com 7
Agenda
• Definition, differences And Examples
• 4 Types of Dependencies
DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM 8
Mandatory
• Mandatory Project Dependencies are those that are legally or contractually
required.
• They are, sometimes, inherent in the nature of the work.
• Mandatory Project Dependencies are also called Hard Logic.
• Example
• Consider two activities A and B. If B has a Mandatory Dependency on A then it means
action on B cannot be performed until Action on A has been completed. E.g.
• A – Requirements Documentation; B – Client Approval
• A – Lay Building Foundation; B – Construct Floor
• A – Build Car Prototype; B – Perform Crash Testing
Designed and Developed by https://www.pmbypm.com 9
Discretionary
Designed and Developed by https://www.pmbypm.com 10
• Discretionary Project Dependencies are defined by the Project Team.
• There could be more than one way to define the sequence between two activities.
• Discretionary Project Dependencies are also called Preferred Logic, Preferential
Logic or Soft Logic.
• Example
• Consider 2 activities A and B. If B has a Discretionary dependency on A then it
means action on B can be performed even before Action on A has been completed.
It can also mean that action on A and B can be independently performed. However,
the Project Team has chosen to make B dependent on A. E.g.
• A – Develop System Module X; B – Develop System Module Y
• A – Furnish Room R; B – Furnish Room S
• A – Book Airline Ticket; B – Buy Insurance
External
• External Project Dependencies are defined between a non-project Activity and
a project activity.
• The non-project activities are done by people who are external to the Project
Team e.g. Client, Vendors or any other external groups.
• Generally the Project Team does not have any control over non-project activities.
• Example
• Consider two activities A and B. B has an External Dependency on A. It means B
is a project activity while A is a non-project activity. E.g.
• A – Client Go-Ahead; B – Initiate Project
• A – Delivery of Equipment; B – Start Development
• A – Approval of Building Plans; B – Start Construction
Designed and Developed by https://www.pmbypm.com 11
Internal
Designed and Developed by https://www.pmbypm.com 12
• Internal Project Dependencies are defined between two project activities.
• The Project Team, usually, has a good control over project activities.
• Example
• Consider 2 activities A and B. B has an Internal Dependency on A. It means both A
and B are project activities that are performed by the Project Team members. There is
no involvement of any external party. E.g.
• A – Develop System; B – Test System
• A – Construct Wall; B – Paint Wall
• A – Assemble Machine; B – Pack Machine
Combination of Project Dependencies
• There are a total of 4 Types of Project Dependencies.
• Two types are applicable at the same time.
• Project Dependency between 2 activities could be any one of the following:
• Mandatory-External
• Discretionary-External
• Mandatory-Internal
• Discretionary-Internal
Designed and Developed by https://www.pmbypm.com 13
Designed and Developed by https://www.pmbypm.com 14
YOUR OPINION IS IMPORTANT TO
US
FOR ANY QUESTIONS OR SUGGESTIONS CONTACT US @
HTTPS://WWW.PMBYPM.COM/CONTACT-PRAVEEN-MALIK/

How To Do Planning Using 4 Types of Project Dependencies?

  • 1.
    Project Dependencies DEFINITION, EXAMPLES,AND MORE… Designed and Developed by https://www.pmbypm.com 1
  • 2.
    Agenda • Definition, differencesAnd Examples • 4 Types of Dependencies DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM 2
  • 3.
    Agenda • Definition, differencesAnd Examples • 4 Types of Dependencies DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM 3
  • 4.
    Dependency • Project Dependenciesare better characterized as Schedule Dependencies. • A Project Dependency simply means that one project activity is dependent on another activity. • Project Dependency is different from Logical Schedule Relationship. • Example • Consider two activities A and B. If Start of B is dependent of Finish of A, it simply means that B cannot start until A finishes. • https://www.pmbypm.com/project-dependencies/ • https://www.pmbypm.com/project-network-diagram/ Designed and Developed by https://www.pmbypm.com 4
  • 5.
    Assumption vs Dependency •A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration is called an Assumption. • A Dependency is between two activities whereas an assumption is about the work to be done. • An assumption can be taken with or without a dependency. • Example • Consider a scenario wherein the Project Team needs Approval of Design Artefacts from the Customer. The project cannot move ahead until this Approval. • Assumption could be that Approval is likely to come within 2 weeks of submitting the Design Artefacts. • All subsequent project activities are dependent on Approval (Customer’s activity). Designed and Developed by https://www.pmbypm.com 5
  • 6.
    Constraint Vs Dependency •A limiting factor that affects the execution of a project, program, portfolio, or process is called a Constraint. • A project constraint could be related to Scope, Schedule, Budget, Quality, Resources, and Risks. • Some of the Schedule Constraints can be represented as Project Dependencies. • Example • Consider the same scenario as in the example on the previous slide. Project Team needs Approval of Design Artefacts from the Customer. The project cannot move ahead until this Approval. • Project team has a Constraint (limitation). Project team cannot do anything else without the Customer’s Approval. • All subsequent project activities are dependent on Approval (Customer’s activity). Designed and Developed by https://www.pmbypm.com 6
  • 7.
    Risks • Risk isan uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives. • A Project Risk can impact Scope, Schedule, Budget, and Quality objectives or any other project objectives. • A Project Risk can arise because of a Project Dependency. • Example • Consider the same scenario as in the example on the previous slide. Project Team needs Approval of Design Artefacts from the Customer. The project cannot move ahead until this Approval. • Risk could be that Customer may not give approval and hence subsequent project activities would never start. Designed and Developed by https://www.pmbypm.com 7
  • 8.
    Agenda • Definition, differencesAnd Examples • 4 Types of Dependencies DESIGNED AND DEVELOPED BY HTTPS://WWW.PMBYPM.COM 8
  • 9.
    Mandatory • Mandatory ProjectDependencies are those that are legally or contractually required. • They are, sometimes, inherent in the nature of the work. • Mandatory Project Dependencies are also called Hard Logic. • Example • Consider two activities A and B. If B has a Mandatory Dependency on A then it means action on B cannot be performed until Action on A has been completed. E.g. • A – Requirements Documentation; B – Client Approval • A – Lay Building Foundation; B – Construct Floor • A – Build Car Prototype; B – Perform Crash Testing Designed and Developed by https://www.pmbypm.com 9
  • 10.
    Discretionary Designed and Developedby https://www.pmbypm.com 10 • Discretionary Project Dependencies are defined by the Project Team. • There could be more than one way to define the sequence between two activities. • Discretionary Project Dependencies are also called Preferred Logic, Preferential Logic or Soft Logic. • Example • Consider 2 activities A and B. If B has a Discretionary dependency on A then it means action on B can be performed even before Action on A has been completed. It can also mean that action on A and B can be independently performed. However, the Project Team has chosen to make B dependent on A. E.g. • A – Develop System Module X; B – Develop System Module Y • A – Furnish Room R; B – Furnish Room S • A – Book Airline Ticket; B – Buy Insurance
  • 11.
    External • External ProjectDependencies are defined between a non-project Activity and a project activity. • The non-project activities are done by people who are external to the Project Team e.g. Client, Vendors or any other external groups. • Generally the Project Team does not have any control over non-project activities. • Example • Consider two activities A and B. B has an External Dependency on A. It means B is a project activity while A is a non-project activity. E.g. • A – Client Go-Ahead; B – Initiate Project • A – Delivery of Equipment; B – Start Development • A – Approval of Building Plans; B – Start Construction Designed and Developed by https://www.pmbypm.com 11
  • 12.
    Internal Designed and Developedby https://www.pmbypm.com 12 • Internal Project Dependencies are defined between two project activities. • The Project Team, usually, has a good control over project activities. • Example • Consider 2 activities A and B. B has an Internal Dependency on A. It means both A and B are project activities that are performed by the Project Team members. There is no involvement of any external party. E.g. • A – Develop System; B – Test System • A – Construct Wall; B – Paint Wall • A – Assemble Machine; B – Pack Machine
  • 13.
    Combination of ProjectDependencies • There are a total of 4 Types of Project Dependencies. • Two types are applicable at the same time. • Project Dependency between 2 activities could be any one of the following: • Mandatory-External • Discretionary-External • Mandatory-Internal • Discretionary-Internal Designed and Developed by https://www.pmbypm.com 13
  • 14.
    Designed and Developedby https://www.pmbypm.com 14 YOUR OPINION IS IMPORTANT TO US FOR ANY QUESTIONS OR SUGGESTIONS CONTACT US @ HTTPS://WWW.PMBYPM.COM/CONTACT-PRAVEEN-MALIK/