2. OVERVIEW OF PRESENTATION
Project Overview
Project Status
GMP Development / GMP
Total Project Cost
Project Schedule
Contract Amendment
3. PROJECT OVERVIEW
2016 Facility Program
$28M and 78,000 SF
October 2, 2017
$27.94 Million and 74,815 SF
Council desires a traditional design theme
November 9, 2017
New design concepts reviewed and Council direction provided
January 11, 2018
Approval of current design concept
Approval of project delivery method - Construction Manager at Risk
April 26, 2018
Approval of Vaughn Construction as the Construction Manager at Risk
firm
4. PROJECT STATUS / GMP
PGAL – Design Phase - Design Development 100%
Next Phase: Construction Documents
Vaughn Construction – Pre-Construction Services
Working with PGAL on design review, constructability, material selection and developing the Guaranteed
Maximum Price (GMP)
GMP – The maximum amount the construction portion of the project will cost per Vaughn Construction
They assume liability for construction cost overruns (except for any Owner requested changes)
5. GMP DEVELOPMENT
Vaughn Construction – Develop GMP
Comprehensive review of drawings and specs
Supplemental info from User Group (City Departments and Police Department Staff)
Material and labor take-off / estimating
Trades / Subcontractors provided budget analysis
Constructability and schedule review
Review of material and products
6. GMP
At the time of the Request For Proposals, the amount available for construction was specified as $25,000,000
Vaughn Construction Developed a GMP of $24,833,300
Delta of $166,700
Will be used to cover other Owner related project costs
GMP is within the specified construction budget
Project Budget has 2 parts
Construction Costs (GMP of $24,833,300)
Owner / Below the line Costs
includes design fees
Any item or service not covered by the GMP
The sum of these parts equals the Total Project Cost
7. TOTAL PROJECT COST
2016 Facility Program
$28,000,000
The proposed project budget, as submitted in the FY 2019 budget, is $29,500,000
FY 2016 dollars
Design changes
Project Delay Cost Escalation
Steel Tariffs and increased labor / material costs
Owner related costs not previously accounted for
As we have moved through the budget process, we anticipated the cost would increase and we are accounting for this in the FY 2019
budget.
8. ANTICIPATED PROJECT SCHEDULE
Oct. 8, 2018 – GMP presented for approval (notice to proceed to follow)
Nov. 12, 2018 – Vaughn mobilization / Construction begins
Nov. 16, 2018 – Ground Breaking Ceremony
10am on-site
Feb. 28, 2020 – Vaughn Substantial Completion
March 2, 2020 – Police Department Move-in
March 30, 2020 – Vaughn Final Completion
9. RECOMMENDATIONS
Approve the amendment
to Vaughn Construction’s
contract to include the
GMP of $24,833,300 which
is within the previously
defined construction
budget.